Period of Performance - 24Z6AQ2.pdf
PDF 480 KB Posted
- Attached to
- FDC SeaTac - Replace Water Heaters
- Solicitation number
- 24Z6AQ2
About this file
This is a memorandum from the Federal Bureau of Prisons Facilities Management establishing the period of performance for contract B&F 24Z6AQ2 to replace water heaters at FDC SeaTac. The memorandum, dated February 13, 2026, is addressed to E. Kramer, the Contracting Officer at FDC SeaTac, from B. J. Halbeisen, Facility Manager at FDC SeaTac.
The total period of performance is 90 calendar days or 12 weeks from time of award to final acceptance. The anticipated timeline breaks down as follows: security clearance (7 calendar days), lead time and mobilization (28 calendar days), scope of work for replacing water heaters per the Statement of Work (28 calendar days), inspections (7 calendar days), de-mobilization (7 calendar days), and contingency (7 calendar days). The 90-day timeframe is designed to accommodate security clearances, material ordering and delivery, removal of old equipment, completion of work, system testing, and demobilization from the work site.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOW - 24Z6AQ2.pdf | ||
| NCIC Form.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of Justice Federal Bureau of Prisons
Facilities Management
Washington, DC 20534
February 13, 2026
MEMORANDUM FOR E. KRAMER, CONTRACTING OFFICER,
FDC SEATAC
FROM: B. J Halbeisen, Facility Manager, FDC SeaTac
SUBJECT: Period of Performance, B&F 24Z6AQ2 Replace Water Heaters
It is anticipated that from the completion of the current contract to testing and acceptance of the project, a performance period of 90 calendar days will be required. The timeframe allotted will allow adequate time for security clearances to be obtained, materials to be ordered and delivered on site, the removal of the old equipment, the work to be completed, system testing to be completed, and demobilization from the work site and the extent or amount of the damage would be difficult to estimate accurately or prove.
The following is an anticipated time frame for this project:
Security Clearance 7 Calendar Days 1 Week Lead Time/Mobilization 28 Calendar Days 4 Weeks Scope of Work Replace Water Heaters Per SOW
28 Calendar Days 4 Weeks
Inspections 7 Calendar Days 1 Week De-Mobilization 7 Calendar Days 1 Week Contingency 7 Calendar Days 1 Week
Total Performance Period: 90 calendar days / 7 days = 12 Weeks
A total of 12 weeks has been allotted from time of award to final acceptance for all work identified in the Statement of Work.
If you have any questions, please contact me at (206)870-1000.