This document is a Performance Work Statement (PWS) for a Blanket Purchase Agreement (BPA) to provide noxious and invasive weed inventory and herbicide application services within the Bureau of Land Management's (BLM) Idaho Falls District. The objective is to inventory and reduce noxious and invasive weeds on BLM-administered lands.

The BPA will have a 5-year period of performance from June 1, 2024 to May 31, 2029. The contractor will be responsible for providing all personnel, equipment, materials, and incidentals necessary to perform the weed inventory and herbicide application. Key requirements include having licensed applicators, maintaining communications with the government, adhering to environmental restrictions, and properly disposing of chemicals. Payment will be made per acre of area sprayed, with procedures for remeasurement if needed. The government will conduct testing to verify uniform coverage and application rates.

View the file

Other files

File Type Posted
IdahoFallsDistrictMap_DRAFT_1.pdf PDF
BPA_-Weed_Inventory_and_Treatment_DRAFT_1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUREAU OF LAND MANAGEMENT – Idaho Falls

Performance Work Statement

Idaho Falls Invasive weed Inventory and Herbicide Application

F-1

1. General: The Idaho Falls District, Bureau of Land Management (BLM) is seeking to award

Blanket Purchase Agreements with one or more contractors to fulfill several different noxious and invasive weed inventory and herbicide application configurations to meet the differing site conditions within the district.

1.1. Description of Services/Introduction: The location of the work sites shall be confined to lands within the boundaries of the Bureau of Land Management (BLM), Idaho Falls

District. The Government is acquiring services for noxious and invasive weed inventory and herbicide application. The Contractor shall furnish all personnel, tools, labor, supervision, equipment, materials, chemicals, supplies, transportation, training, and incidentals necessary to perform the herbicide application in accordance with the specifications provided and the herbicide label(s).

1.2. Objectives: The objective of this service is to inventory and reduce noxious and invasive weeds.

1.3. Scope: The work under this agreement includes inventory of noxious and invasive weed species and application of herbicide on sites within the Idaho Falls District. The

Contractor shall conduct herbicide application procedures safely, while strictly adhering to all guidance and restrictions located within the herbicide label along with the herbicide application restrictions of the State of Idaho. The Contractor shall follow Environmental

Protection Agency (EPA) guidelines for application of herbicides (if applicable). The

Contractor shall provide BLM approved herbicides and adjuvants as specified in the individual orders. Targeted species identified in the orders will be treated at the appropriate biological treatment window to ensure successful control. Control work may involve coverage of broad project areas, seeking out both individual and large patches of targeted noxious weeds for herbicide treatments, or large contiguous areas of invasive plants

1.4. Period of Performance: The Period of Performance will be determined on individual calls within the active agreement period.

Estimated start date: June 1, 2024

Estimated end date: May 31, 2029

1.5. General Information

1.5.1. Hours of Operation: Spraying Operations will be permitted only during daylight hours. The Contractor will be allowed to work seven days per week. Work will not be permitted on Federal holidays, unless authorized by the COR.

1.5.2. Federal Observed Holidays: In addition to any holidays declared by Executive

Orders, the following Federal Legal Holidays are observed: New Year’s Day, Martin

Luther King Jr. Day, President’s Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, Christmas Day.

1.5.3. Place of Performance: The location of the work sites shall be confined to lands within the boundaries of the Idaho Falls Distict. Treatment areas may be located on terrain ranging from flat to steep slopes in areas that may or may not be accessible by motorized vehicles and equipment.

Treatment Area 1 – Salmon Field Office

Treatment Area 2 – Challis Field Office

Treatment Area 3 – Upper Snake Field Office

Treatment Area 4 – Pocatello Field Office

1.5.4. Pre-work Conference: Prior to commencement of work, a meeting may be requested by the Contracting Officer to be attended by the Contractor, the Contracting

Officer's Representative (COR), and the Project Inspector(s). The meeting will be held at the respective Field Office at a time mutually agreeable to the Contractor and the Contracting Officer to discuss the work schedule and to familiarize both parties with the responsibilities of each under this agreement. At this time the Contractor shall provide to the COR a written "work progress plan" that details dates, locations, equipment, and employees to provide for orderly completion of the work within the agreement performance time. This work schedule must be acceptable to the

Government. At a minimum, the schedule must reflect a work progress rate equal to the available amount of agreement performance time.

1.5.5. Invoicing: Invoices shall be submitted through IPP for payment, after services have been performed with supporting invoice on company letterhead and referenced purchase order number. Unit Costs offered must be “All-Inclusive” for materials, labor, transportation, surcharges, fees and services necessary and incidental to noxious and invasive weed inventory and herbicide application. Invoices shall reflect only those costs indicated in the Price Schedule. All expenses relating to maintenance and operation of equipment shall be considered in the all – inclusive pricing. The agreement will be considered completed and payment due when all areas furnished to the Contractor by the Government have been inventoried and sprayed to the standards specified. Test for uniformity will be made at the time of spraying, and final completion of the agreement will be determined by these tests.

1.5.6. Project Boundary Marking: The location and access to the unit(s) will be shown on the vicinity and unit map(s) attached on the respective order. Whether or not the unit boundaries will be identified by flagging, or if it will be up to the contractor to identify and verify boundaries in the field using maps and electronic devices to stay within the unit(s) will be defined at the order level.

1.5.7. Notification of Cessation or Restart of Work: The Contractor will have personnel on project site prior to commencing daily application, during application, and will notify COR or Project Inspector of changing weather conditions. The COR or Project

Inspector will allow Contractor to continue or stop application if weather factors dictate. The Contractor shall stop operation if inclement weather conditions (wind or rain) exceed label recommendations during the spraying operation.

1.5.8. Personnel Requirements: The Contractor must always maintain an adequate work force to ensure timely completion of the work and is responsible for the crew knowing the requirements of the agreement. The crew is also responsible for maintaining a safe working environment following OSHA standards. The

Contractor’s applicators shall hold a current Idaho Professional Applicator License in the Agricultural Pesticide Category. The Government will inspect each applicator for their current Idaho Professional Applicator’s License in the Agricultural Pesticide

Category before work on this agreement.

1.5.8.1. Key Personnel: The following personnel are considered key personnel by the Government: Applicators/pilots and mixing/loading manager must be designated by the Contractor. A Contractor Representative must be on-site always directing work. This person must be fluent in English and will also serve as an on the ground contact person for the COR/PI. Failure to maintain a

Contractor Representative will result in suspension of work until an acceptable on-the-ground Contractor Representative is provided. A maximum of five (5) days will be allowed to produce a qualified Contractor Representative. Failure to do so within five days may result in the Contracting Officer (CO) issuing a

Suspend Work Order. CO and COR must be informed of any changes of

Contractor Representative. The contractor will furnish a legible list of all agreement employees (last name, first name) to the assigned COR. If there are any changes to the list of agreement employees during the life of the agreement a new list will be provided to the COR.

1.5.8.1.1. Applicators: Shall be furnished by the Contractor and shall meet certification requirements of Idaho Regulations for this type of work.

Applicators must hold a current Commercial Agricultural Operating certificate.

1.5.8.1.2. Work Crew: Shall be furnished by the Contractor for handling and mixing the herbicide and loading the equipment. Mixers and Loaders shall hold a Mixer/Loader certification of training. The Contractor shall furnish the necessary qualified mechanics for maintenance of equipment and shall furnish all fuel, oil, and service required for operation of equipment and vehicles.

1.5.9. Camping: Camping on agency-administered lands will only be allowed on site(s) pre-approved by an authorized officer. Camping areas for crews will be identified and surveyed for cultural resources prior to use of that camp location. Some camp sites including designated camp sites have been identified and cleared for use, ask the COR for details. The Contractor shall maintain all camping areas in an orderly and sanitary manner. The ordering and maintenance of portable toilets and dumpsters is the responsibility of the contractor. All fire regulations and restrictions shall be followed.

All garbage and refuse shall be removed from the camp site(s) by the Contractor and disposed of offsite before final payment is made.

1.5.10. Detailed Unit Information: Detailed unit information if available will be provided at the order level.

1.5.11. Risk and Damages: The Contractor shall assume all risks in connection with performance of the agreement and shall be liable for any damages to persons or property in connection with the prosecution of the work, including the applicator or other employees of the Contractor.

F-2

2. Definitions

2.1. Contractor: A supplier or vendor awarded a agreement to provide specific supplies or service to the government. The term used in this agreement refers to the prime.

2.2. Contracting Officer (CO): A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.3.

2.4.

2.5.

2.6.

2.7.

2.8.

2.9.

2.10.

2.11.

2.12.

2.13.

2.14.

Contracting Officer’s Representative (COR): An employee of the U.S. Government appointed by the contracting officer to administer the agreement. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the agreement, does not constitute a change, and has no funding implications.

This individual does NOT have authority to change the terms and conditions of the agreement.

Deliverable: Anything that can be physically delivered but may include non-manufactured things such as meeting minutes or reports.

Equipment: A tangible item that is functionally complete for its intended purpose, durable, nonexpendable, and needed for the performance of a agreement. Equipment is not intended for sale and does not ordinarily lose its identity or become a component part of another article when put into use. Equipment does not include material, real property, special test equipment or special tooling.

Key Personnel: Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a agreement. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal. The prime contractor is responsible for performance of all subcontractors.

Quality Control: All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet agreement requirements.

Subcontractor: One that enters into a agreement with a prime contractor. The Government does not have privity of agreement with the subcontractor.

Active Ingredient: The chemicals in an herbicide which control the targeted noxious weed species.

Adjuvant: An inert material added to an herbicide formulation or tank mix to increase the effectiveness of the active ingredient.

Drift: The movement of airborne particles by air motion or wind away from the intended target area.

Emergence: The act of a germinating seedling breaking through the soil surface.

Endangered Species: Plant or animal species that are in danger of extinction through all or a significant part of their range.

Label: All written, printed, or graphic matter on or attached to pesticide containers as required by law.

2.15. Rate: The amount of active ingredient or acid equivalent applied per unit area or other treatment unit.

2.16. Threatened Species: Plant or animal species that are not in danger of extinction but are likely to be classified as Endangered within the foreseeable future.

2.17. Sensitive Species: Plant or animal species (as designated by the Idaho BLM State

Director) that are managed by the BLM to ensure that agency actions do not contribute to the need to list any species as Threatened or Endangered in the future.

2.18. Noxious weed: A subset of invasive plants that are designated by state and federal laws because they are known to be detrimental to agriculture, commerce, natural resources, and public health.

2.19. Invasive Weed: A plant that is not native to a specific location and has a tendency to cause damage to the environment.

2.20. Infestation: A population of one or more of the subject noxious weeds or invasive plant species.

2.21. Infested Area: An area of land that is occupied by one or more of the subject noxious weeds or invasive plant species. The area of land is defined by drawing a line around the general needed to perform the work identified in these occurring as large patches or contiguous treatment areas. Treatment perimeter of the infestation as a logical treatment unit. May contain areas of land that are not fully occupied by weeds.

2.22. Critical habitat: 1) Specific areas within a species’ habitat that are critical to its life functions; 2) An area designated by USFWS under rule-making as being critical to the needs of a federally listed species, and which then carries special protection and consultation requirements.

2.23. Sensitive areas: Buffers around terrestrial and aquatic areas which provide ecological refugia for or specialized or unique habitats.

2.24. Standard Operating Procedures (SOPs): Management practices that would be followed by the BLM and the Contractor to ensure that risk to human health and the environment from the application of herbicides are minimized to the extent practical.

F-3

3. Government Furnished Property and Services

3.1. The Government will provide work location maps for the site that is to be treated with herbicide.

F-4

4. Contractor -Furnished Items and Services

4.1. Equipment Requirements:

4.1.1. The Contractor shall provide all personal protective equipment (PPE), herbicide application equipment, personnel, supplies, and materials specifications. All tools and equipment must be in good working order without leaks or malfunctions.

4.1.2. The Contractor shall carry spill-prevention equipment to contain and clean-up spills before reaching waterways of critical habitat areas. At a minimum a spill kit should contain barrier cloth material, absorption material, safety eyewear, gloves, and disposal bag.

4.1.3. A first aid kit with portable eyewash shall be required at each work site.

4.1.4. The Contractor shall furnish properly equipped equipment with applicators experienced in applying herbicides in rough featureless terrain. The Contractor shall service and repair their equipment as necessary to maintain satisfactory progress on work. Contractor is responsible for all costs incidental to equipment move-in and move-out associated with the project.

4.1.5. The Contractor shall furnish sufficient equipment to satisfactorily spray the designated areas in the time specified as required in the Detailed Specifications.

Equipment shall be capable of traveling at moderate speed to give proper control and distribution of herbicide. Equipment shall have communications with the

Government by using radio frequencies designated by the Project Inspector.

agreement will not commence until radio communication is established.

4.1.6. The Government will have the option to inspect the Contractor's equipment and work before, during, and after completion of this agreement.

4.1.7. Spray equipment

4.1.7.1. Spray Tanks: Spray solutions of the product shall be mixed, stored and applied using only stainless steel, aluminum, fiberglass, plastic or plastic-lined steel containers.

4.1.7.2. Spray Nozzles: Contractor shall furnish a nozzle type that is designated for the intended application. Refer to the Label for proper nozzles to comply with

Drift Management Section.

4.2. Materials:

4.2.1. Salient Features of herbicide

•Must be registered for use in Idaho by the respective state regulatory agency

•Must be on the BLM’s approved herbicide list

•Supply in 1 or 2.5 gallon containers

4.2.2. Dust Abatement: Any material used for dust abatement, other than water, shall be approved by the COR prior to use.

4.3. APPLICATOR LOGS: One report shall be provided to the Government. The report shall include daily applicator logs. This log or record shall be signed by the applicator operator and turned into the COR upon completion of the agreement via email within 10 business days.

4.4. Herbicide Application:

4.4.1. During application, weather conditions shall be measured hourly by the contractor at the spray site and documented on the Pesticide Application Record (PAR). More frequent measurements shall be taken whenever a weather change appears to have the potential to jeopardize safe application of herbicide on the target area.

4.4.2. Application of chemical herbicides must be accomplished with wind velocities of 10 mph or less in all instances and according to pesticide label. The Contractor shall not use vehicle-based spray equipment in sensitive areas or critical habitats occupied by special status plant or wildlife species when winds are gusty or wind speed exceeds 5 mph.

4.4.3. To reduce drift and volatilization, spraying shall be prohibited when any of the following conditions exist on the spray area.

4.4.3.1. Winds are gusty or velocity exceeds 10 MPH.

4.4.3.2. Rain or imminent rainfall may reduce or will reduce the effectiveness of the chemical being applied.

4.4.3.3. Air turbulence (thermal updrafts) is so great as to seriously affect the normal spray pattern; If applying at wind speeds less than 3 mph, the Contractor shall determine if conditions of temperature inversion exists. No herbicide applications are permitted in areas of temperature inversion or unfavorable atmospheric conditions.

4.4.3.4. Avoid making applications when spray particles may be carried by air currents to areas where sensitive plants are growing.

4.4.4. Wildlife Restrictions: Some sites may have temporary timing restrictions due to the presence of wildlife. The COR/PI may suspend work for up to 2 hours or terminate for the remainder of the day. Contractor will be paid for suspension time. Additionally, sensitive areas may have timing restrictions that prohibit operations outside the hours of 0900 – 1800. These will be disclosed by the government during pre-work meetings.

F-5

5. Specific Tasks

5.1. HERBICIDE APPLICATION: The Contractor shall spray designated areas in conformance with these specifications and the herbicide label. Unless otherwise specified, the Contractor shall furnish chemicals, equipment, labor, supplies, tools, supervision, materials, incidentals, and perform all work necessary to complete herbicide application in accordance with the performance work statement.

5.2. Noxious Weed Inventory: Perform Noxious weed inventory.

F-6

6. Applicable Technical Orders, Specifications, Regulations, Manuals

6.1. Environmental Conditions

6.1.1. Wind: The Contractor shall follow the Label Section on Spray Drift Management -

Wind. Local wind can influence wind patterns. Every applicator should be familiar with local wind patterns and how they affect drift.

6.1.2. Relative Humidity: Refer to the product label when making applications in low relative humidity conditions. Measurements can be obtained from local National

Weather Service.

6.1.3. Site Conditions: No treatment spraying will be allowed if conditions do not meet the label requirements.

6.2. Herbicide Application:

6.2.1. Coverage: The entire surface within the designated boundaries of the project area shall receive uniform coverage with the herbicide except for areas excluded by the

Government. Areas excluded from the spraying operation within the designated boundaries, will not be included in the acreage computed for payment. Any areas not covered by Contractor shall be reapplied or compensated by suitable agreement adjustment, at the option of and at no additional cost to the Government.

6.2.2. Rate of Spraying: Herbicide shall be applied at the application rate per acre according to the work data sheet. For liquid applications, the carrier (water) for the chemical will follow the label limits for ground or aerial application. The carrier

(water) must be clean, free of dirt particles. Ditch water will not be considered clean.

Contractor will be required to demonstrate that they can provide adequate and uniform coverage. Contractor shall furnish mixing equipment, suitable work crew, and perform mixing operation. Spray formulation shall be thoroughly mixed according to the Label and distributed over entire area. Distribution of herbicide shall not vary more than ten percent (10%) above or below the average distribution of herbicide per acre from that specified.

6.2.3. Application Paths: Shall be patterned to secure a uniform distribution of herbicide.

Contractor must ensure that there will be straight and regular paths of application. The

Contractor must keep applications within the perimeter of the Government provided shape file. Irregular paths or areas sprayed outside of the perimeter will result in immediate stoppage of work. Corrective action shall be taken immediately by the

Contractor to insure evenly spaced, straight, and regular application paths and complete coverage of areas included in the spraying job. Avoid overlapping, and no stripping shall be allowed.

6.2.4. Swath Width: Effective swath width shall not exceed the maximum for adequate coverage of supplied application equipment.

6.2.5. Application Height: Herbicide dispenser shall be set at a height to obtain proper distribution and uniform coverage of herbicide on target species. Contractor shall follow Herbicide Label instructions on Spray Drift Management to obtain proper boom height.

6.2.6. Spray Drift Management: The interaction of many equipment and weather-related factors determines the potential for spray drift. The Contractor is responsible for considering all these factors when making application decisions. Avoiding herbicide application drift is the responsibility of the Contractor.

6.2.7. Sprayer Cleanup: Shall be conducted according to the label instructions. Avoiding contamination of the work site is the responsibility of the Contractor.

6.3. Government Testing:

6.3.1. Tests for Uniformity: The Government representative will make tests to determine uniformity of herbicide application. Randomly spaced water sensitive cards or collection trays will be utilized.

6.3.2. Tests for Rate of Application: Rate of application will be determined from test applications and strip tests made prior to commencement and/or during application operations to establish and maintain the desired application setting of the distribution mechanism. Should the Contractor wish to object in any way to the weight recording and/or ground recovery sampling done at any particular time by the Government, the

Contractor shall be present in person or by authorized representative to voice said objections when weight recording and/or ground recovery samplings are done, and to agree upon new records and/or samples at the time, where after the weight recording and ground recovery sampling done by the Government shall be final and binding in the settlement of the agreement.

6.4. MEASUREMENT AND PAYMENT

6.4.1. Method of Measurement:

6.4.1.1. Units: Application of herbicide solution will be measured and paid for by the number of acres sprayed to the nearest whole acre.

6.4.1.2. Measurement: Measurement for payment for spraying will be the actual area, in acres, within the designated boundaries satisfactorily sprayed in conformance with these specifications. Measurement will be made from either physical surveys of the areas or a computer-generated shapefile created in a GPS

Differential Guidance System at the option of Government. The shape file will be used in ArcView for final acreage measurement. Acreages will be computed from horizontal distances as shown on maps at the option of Government.

6.4.1.3. Remeasurement: Remeasurement of the acreage under this agreement will be made upon the written request of the Contractor. The request for remeasurement must be made in writing within 10 calendar days after completion of the work. If remeasurement indicates a difference of not more than 5% from the original measurement, the Contractor shall pay the actual cost of the remeasurement.

Payments will be based on the second measurement where the difference between measurement is more than 5%. Where the difference is less than 5%, the results of the first measurement will be used.

6.4.2. Basis of Payment:

6.4.2.1. Payment: Payment will be made at the unit price per acre specified in the

Bid Schedule which is made a part hereof and shall include the cost of all work described in this paragraph and the Detailed Specifications, including any respraying, if such work is required.

6.5. Safety:

6.5.1. Transportation of Herbicides: The Contractor shall be responsible for the transport of chemical herbicides used to fulfill the specifications of this agreement to the

Contractor’s loading site. The Contractor shall secure herbicide containers in mixing area to prevent spillage. The Contractor shall load and transport herbicide from the pickup point to the work sites and shall be responsible for its protection from loss or damage due to weather, rodents, insects, theft, or any other hazard. Any herbicide damaged or lost while in the custody of the Contractor will be replaced by the

Contractor and actual cost to the Government for replacement will be deducted from payments due the Contractor. All unused herbicides shall be returned to the

Government by the Contractor upon completion of work or termination of the agreement.

6.5.2. Protective Clothing and Equipment for agreement Employees Exposed to Herbicides:

The Contractor shall supply protective clothing and equipment to agreement workers that guarantee minimal exposure throughout the herbicide application process. The

Contractor shall follow all advice on protective clothing and equipment which appears on the herbicide label and/or MSDS documentation. The Contractor shall make available cleanup facilities to agreement employees exposed to herbicides or herbicide-contaminated equipment.

6.5.3. Storage of Herbicides: The Contractor will be responsible for the storage of all chemicals.

6.5.4. Mixing and Application of Herbicides:

6.5.4.1. The Contractor shall mix herbicides in accordance with the proportions listed on the product labels. The Contractor shall provide adequate protective clothing and equipment for agreement employees who mix the herbicides.

6.5.4.2. By law, the application of an herbicide, either directly or through drift, must not expose workers or other people. The Contractor shall be very aware and cautious of any environmental hazard present during herbicide application. Upon completion of herbicide application, the Contractor shall thoroughly clean equipment and dispose of waters, residues, rinses, and unused herbicides only according to EPA and Idaho State regulations. All empty herbicide containers will be tripled rinsed, labels removed, and punctured by the Contractor after mixing. The Contractor shall be responsible for disposal of the empty boxes, labels, and lids. The Contractor shall be responsible for disposal or recycling of the empty containers.

6.5.5. Spills and Accidents: The Contractor shall be responsible if accidents and chemical spills occur. The Contractor shall report immediately spills and accidents to the BLM authorized officers and appropriate local authorities. The Contractor shall provide immediate treatment of contaminated or injured persons and seek professional medical attention when necessary. The Contractor shall control chemical spills quickly and shall secure additional help when the Contractor cannot effectively or safely handle the spill cleanup. Spills will be the responsibility of the Contractor and shall be cleaned up to the satisfaction of the local authorities.

6.5.6. The contractor shall thoroughly wash all vehicles and other equipment to be used on the agreement including the under carriage prior to beginning project work and before moving to another worksite. Washing may be required during the progress of the agreement if the COR suspects that a vehicle has been contaminated with weeds or weed- infected soil. All vehicles, tools, and equipment which are deemed to be potentially contaminated shall be required to be washed in the presence of the

COR/PI.

6.5.7. Buffer strips (no spray areas) shall meet or exceed state-mandated standards for all herbicides applied.

6.5.8. A 100-foot no-spray buffer strip shall be left next to inhabited dwellings unless waived in writing by the resident.

6.5.9. Buffer strips in sensitive areas and critical habitats shall be designated on each site as necessary by the COR as a means to protect special status plant species, wildlife, or other ecological values.

6.5.10. Additional buffer strips may be designated on site by the COR during operations to mitigate environmental risks of herbicide applications.

6.5.11. Sites to be sprayed can be very difficult to locate and their access may require foot travel. The COR will be available to assist the contractor in locating these sites and identifying hazardous conditions. Hazardous conditions include, but are not limited to, rattlesnakes, bees, and ticks.

6.5.12. OHV use would not be allowed on erosive soils, steep slopes, or in areas with wet or muddy soil conditions. OHVs are limited to designated crossings in riparian, wetland, and aquatic systems.

6.5.13. Sensitive, Endangered or Threatened Species (plant or animal) - If sensitive, endangered, or threatened species (plant or animal) are discovered within the treatment the COR shall be notified immediately. The Government may issue a suspend work and/or partially terminate any portion of the work due to discoveries of sensitive, threatened, endangered species or archeological sites during agreement operations.

6.5.14. Candidate I rare plants will be clearly marked in the field. agreement sprayers shall be trained to recognize these areas as no spray zones. When applying herbicides the

Contractor will not treat noxious weeds within twenty five (25) feet of a rare plant if found on flat to nearly flat terrain and 100 feet if found on steep terrain or the rare plant is located within 100 feet down slope of the treatment area.

6.5.15. Bureau Archaeologist may brief the spray contractors o how to recognize cultural resource sightings and to stay clear and report them to the COR.

Technical Exhibits:

Required services table with AQL:

TASK INSPECTION

ITEM

INSPECTION METRIC Acceptable

Quality level

Herbicide application

(Para 5.1.)

Uniform coverage

Comparing applicator logs to original polygon to confirm uniform coverage over the spray area.

95% visual compliance with specs

Noxious Weed

Inventory (Para 5.2)

DELIVERABLE FREQUENCY REFERENCE MEDIUM/FORMAT SUBMIT

TO

Performance/Work

Plan

Once, order level

1.5.4 Pre-work

conference

By email in PDF format or hard copy

COR

Crew Manifest Once, and as needed when crew manifest changes. Order level.

1.5.8 Personnel

Requirements

By email in PDF or scanned or hard copy

COR

Applicator Log Once, order level

4.3 By email in PDF or

scanned or hard copy

COR

Supply Herbicide Once, Order level

4.2.1/5.2 1 or 2.5 gallon containers

COR

Adjuvant Once, Order level

Return as received any remaining

COR

Pesticide

Application Record

(PAR)

24 hours after application of chemical herbicide

By email in PDF or scanned or hard copy.

COR