This is a Performance Work Statement (PWS) for US Mail Delivery Services between Incheon Airport Military Mail Terminal, Busan MMT, and USFK Wide Military Post Offices throughout Korea. The contract is a hybrid Firm-Fixed-Price and Requirement-type contract with FFP task orders, effective for one year (August 1, 2026 – June 30, 2027) with up to four one-year renewal options, following a one-month phase-in period beginning July 1, 2026. The contract is issued by the Department of the Army Materiel Command Army Contracting Command (Solicitation Number W91QVN26RA010).

The contractor must provide personnel, materials, transportation equipment, and supervision for packing/unpacking airline containers, loading/unloading mail, and transporting US mail between terminals and military post offices. Key deliverables include: spotting one 8-ton truck (313 days/year) and one 1-ton truck (52 days/year) at Camp Humphreys; spotting one 8-ton truck (365 days/year) at Osan AB; providing two flatbed trucks (4.5–5 ton) and one 4-ton electric forklift at Incheon MMT; providing two 4-ton electric forklifts (one at each MMT); transporting mail via scheduled delivery routes; packing/unpacking up to 40 airline containers per 8-hour day at Incheon and loading/unloading up to 2,500 mail pieces at Busan; and providing US citizen mail guards for registered mail transport Monday–Friday. The contractor must submit a Quality Control Plan within 10 days of award, a Staffing and Equipment Plan within 7 days of contract start, vehicle maintenance certificates within 5 days of award, and monthly worker schedules to the Contracting Officer's Representative. Contractor qualifications include minimum two years of freight transportation experience, valid ROK government business and transportation licenses, a Contract Manager with English proficiency (TOEIC 450+ or TOEIC Speaking 100+), licensed cargo and forklift drivers, and vehicles not exceeding 10 years of age throughout the contract period.

View the file

Other files

File Type Posted
Solicitation Amendment W91QVN26RA0100002 SF 30.pdf PDF
Attachment A ELIN List Revised 6 Apr 2026.xlsx XLSX spreadsheet
Solicitation Amendment W91QVN26RA0100001 SF 30.pdf PDF
Local Clauses.docx DOCX document
Solicitation W91QVN26RA010.pdf PDF
Attachment B Route Schedule.xlsx XLSX spreadsheet
Attachment A ELIN List.xlsx XLSX spreadsheet
Performance Work Statement.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

US Mail Delivery Services between Incheon Airport Military Mail Terminal (MMT), Busan MMT, And USFK Wide Military Post Offices (MPO)

PART 1 GENERAL INFORMATION

1. GENERAL: This is a contract to provide US mail delivery services between the Incheon Airport Military Mail Terminal (MMT), Busan MMT, and USFK Wide Military Post Offices (MPO) as specified by the US Government. The Government will not exercise any supervision or control over the contract service providers performing the services herein.

1.1 Description of Services/Introduction: The Contractor shall provide personnel, materials, transportation equipment, tools, and supervision necessary to the performance of packing/unpacking airline containers, loading/unloading mail, and transporting US mail delivery services between Incheon Airport MMT, and Busan MMT, and MPOs throughout Korea as specified by the US Government.

1.2 Background: This contract is designed to transport US mail between Incheon Airport MMT, Busan MMT, and MPOs; packing/unpacking airline containers, loading/unloading mail, and transporting US mail delivery services for USFK.

1.3 Objectives: The contractor shall protect the US Government property (US Mail) from any damage or loss when loading/unloading and transporting the US Government property (US Mail) between Incheon Airport MMT, Busan MMT, and USFK Wide MPOs.

1.4 Period of Performance: The effective period of this contract is a one year performance period and may be renewed yearly (with up to four (4) one (1) year extensions) from the date of award.

Phase-in Period:1 Jul 2026 – 31 Jul 2026
Base Period:1 Aug 2026 – 30 Jun 2027
1st Option Period:1 Jul 2027 – 30 Jun 2028
2nd Option Period:1 Jul 2028 – 30 Jun 2029
3rd Option Period:1 Jul 2029 – 30 Jun 2030
4th Option Period:1 Jul 2030 – 30 Jun 2031

1.5 Place of Performance: The work to be performed under this contract will be performed throughout Korea.

1.6 Type of Contract: This is a hybrid of Firm-Fixed-Price (FFP) and Requirement-type contract with a FFP task orders.

1.7. Quality Control Plan: The Contractor shall meet the minimum quality standards.

1.7.1. Service Quality: The Contractor shall conduct this inspection to ensure that all prescribed services are provided in such manner as required by PART 5 of these specifications, including conduct of the Contractor’s employees. Drivers and mechanics may be tested or questioned by the Contracting Officer or their authorized representatives at any time to verify qualifications such as driver’s license, past performance, driving record, knowledge of route, etc.

1.7.1.1 The Quality Control Program is the means by which the contractor assures that their work complies with the requirement of the contract. The contractor is responsible for quality control to ensure services are performed in accordance with this PWS. The contractor shall develop and maintain an effective Quality Control Program to identify, prevent, and ensure non-recurrence of defective services. The Quality Control Plan (QCP) shall be submitted within ten (10) calendar days after the contract is awarded to the Contracting Officer (KO) and the Contracting Officer’s Representative (COR) and shall be updated thereafter to maintain an effective and efficient quality control program.

1.7.1.2 The Quality Control Plan (QCP) shall include: The name(s) and qualification(s) of the contractor's quality control representative(s) and clearly defined authority of these personnel under the contractor's organization. The names of the individuals performing quality control and the extent of their authority shall be in the form of an organizational chart.

1.7.1.3. All of the following elements shall be provided in the quality control plan (QCP):

1.7.1.3.1. A description of the inspection system to cover all services. The description shall include specifics as to the areas to be inspected on scheduled and unscheduled basis, the performance standard, the contractor’s employee who will perform the quality control and the frequency of inspection. The contractor shall use the format below to measure each line item in the Performance Requirements Summary (PRS) table. See example below.

Objective
Performance Standard
Contractor Performance

Standard

Performance Threshold
What/Data Source
How/ Method of Assessment
Calculation
What level of
What level of
What are
How are you
How will you
performance
performance is
you going
going to
determine if
is required to
required to meet
to inspect?
inspect? see
the AQL and
meet the
the
drop down list
Standard are
Performance
Performance

being

Objective or
Objective or

achieved?

Task?
Task?

1.7.1.3.2. A description of the methods to be used to identify and prevent defects in the quality of service performed.

1.7.1.3.3. A description of the records to be kept to document inspections and corrective or preventive actions taken.

1.7.1.3.4. A description of what contractor action will be taken if quality control problems are found and a method of identifying deficiencies in the quality of services performed before the level or performance becomes unacceptable.

1.7.1.3.5. A description of the training plan for its employees i.e. Safety, Security, Packing/unpacking airline containers, Emergency Responses, etc.

1.7.1.4. The records of quality control inspection, to include items identified in paragraph 1.7.2, shall be kept and made available to the Government throughout the contract performance period and for the period after contract completion until final settlement of any claims under this contract.

1.7.2. Equipment Qualification: The Contractor shall perform inspections and maintenance on all trucks prior to reporting for service each day in order to ensure that all trucks provided under the terms of this contract are in good operating condition and meet safety requirements as listed in PART 6, Applicable Publications in this PWS. Prior to placement of truck(s) at the loading point, the Contractor shall correct all deficiencies noted during the inspection. The contractor shall ensure that the trucks meet the following minimum safety standards:

a. Fuel supply, oil level, water and/or anti-freeze in radiator and all tires pressure including the spare tire.

b. Brake system is fully functional, both foot brakes and hand brakes.

c. Trucks are equipped with heater/air conditioning, charged batteries, horn, windshield wipers, lights, reflectors, tire chains, fire-extinguishers, and wheel chock blocks and all equipment are fully functional.

d. The interior of the cargo compartment must be clean, free of clutter and in a condition to protect the mail loaded from being damaged.

e. Vehicles shall conform to postal regulations as stated in DoDI 4525.09 Military Postal Service, Section 3.5. “Security”.

f. All vehicles used to transport mail from/to MPOs: The vehicles shall have a closed body cargo area, with access permitted only by lockable double doors. Wing-body type trucks are not permitted except for those specified in para 4.1.2 and 5.2.1.1. No side doors allowed on cargo area of vehicle. Each door shall have bolts welded on both sides. Doors, locks, and bolts shall conform to postal standards. All hinges on doors shall be inside the compartment, no portion of the hinge shall be exposed to the outside. Door hasps shall fit U.S. General Services Administration (GSA) approved locks and U.S. Postal Service (USPS) numbered seals to secure US mail. The Government postal personnel will attach both USPS numbered seals and GSA approved locks to vehicles.

g. A USPS numbered seal is mandatory for all shipments. A tin band seal (PS Item O-817A or C) shall be affixed to the secured doors to maintain integrity of shipment. The Government will attach this seal.

h. Tires. Front tires will have at least 1/4 in. tread and the rear tires will have at least 3/16 in tread remaining. Vehicles will have serviceable spare tires. Snow chains are required to meet USFK Road condition restrictions.

1.8. Quality Assurance Surveillance Plan (QASP): The U.S. Government reserves the right to perform any of the inspections set forth in these specifications where such inspections are deemed necessary to assure services and equipment furnished conform to prescribed requirements specified by this PWS.

1.8.1. Shipping Officer (MMT/MPO Supervisor) Inspection: The shipping officer may inspect truck(s) furnished by the Contractor prior to loading to ascertain the suitability for loading of mail. This includes the mechanical condition of the truck(s) and the presence of necessary equipment, or installation thereof, as specified herein.

1.8.2. Right to Reject. The shipping officer (MMT/MPO Supervisor) has the right to reject any truck that they consider not meeting vehicle requirements specified herein. In the event any truck is rejected, the Contractor shall correct the defects noted or replace the truck with one that meets the specified standards within 2 hours.

1.9. Safety:

1.9.1. Safety Plan - The contractor shall develop and furnish a safety plan to be given to the KO and COR for approval within 60 calendar days of beginning of Phase-In. General safety requirements can be found in Occupational Safety and Health Standards and Safety and Health Requirements Manual (E385-1-1) with applicable attachments, figures and tables, and Korea Occupational Safety and Health Agency (KOSHA) as reference tools. All safety and health requirements shall be complied with during the contractor’s activities pertaining to this contract.

1.9.2. The contractor’s safety plan is to prevent accidents and preserve the life and health of contractor and Government personnel who perform under this contract. The contractor is responsible for ensuring that all work performed under this contract is accomplished in accordance with all safety requirements. The contractor shall maintain an accurate record of each accident which occurs pursuant or incidental to work performed under this contract.

1.9.3. The contractor shall furnish tools to perform daily task during this contract. All contractor equipment used in and around the AFH area shall meet all standard practice safety and noise level requirements and shall be always in a safe operating condition. All contractor equipment shall be subject to safety inspections by the COR at any time during the performance of this contract. Any defective equipment shall be either repaired or removed from the work site.

1.9.4. The contractor shall exercise mandatory safety precautions as necessary to prevent and eliminate safety hazards of personnel, material and equipment. The contractor shall take all safety measures; as specified in EM- 385-1-1, General Safety and Health Requirements, USFK Safety Program and all ROK Safety and Health Regulations and Requirements.

1.9.5. The Government assumes no liability for damages to the property of the contractor or for personal injuries, disabilities, or death to the contractor or the contractor’s employees or to any other person.

1.9.6. Vehicle Safety - The Contractor shall take all necessary measures to ensure safe operation of trucks transporting U.S. Government mail and being operated on U.S. military installations under the terms of this contract. The safe operation shall include the maintaining of trucks in good operational and safe condition, driving, loading/unloading, and protection of mail from damage, loss and inclement weather.

1.9.6.1. Regulations: All safety measures mentioned above shall be in conformance with applicable safety and traffic rules and regulations of the ROK Government.

1.9.6.2. The Contractor shall submit one copy of each vehicle maintenance and inspection certificate for each vehicles performing service under this contract and Vehicles Maintenance Annual Plan to the Contracting Officer and the COR within five (5) calendar days after award of the contract. The Contractor shall furnish a copy of each certificate yearly, on the beginning of each option year, and when applying for new vehicle passes. These certificates shall be updated immediately upon completion of each inspection in accordance with Engineer Manual (EM) 385-1-1, Safety and Health Requirements Manual Section 18, and ROK Highway Traffic Laws and other applicable regulations of both US and ROK Government.

1.10. Hours of Operations:

1.10.1. Hours of Operation: The Contractor shall perform the work from Sunday through Saturday, for those hours specified in the Attachment A, ELIN List and Attachment B, Route Schedules. The contractor shall provide two (2) round trips on 24 December to include Sunday.

1.10.2. Holidays: US mail delivery is required on US and ROK Government legal holidays.

1.11. Contractor Qualification:

1.11.1. Prime Contractor’s Prior Experience. The Contractor shall have a minimum two (2) years of experience within the last seven (7) years in general cargo and airline cargo delivery/transporting services and to move/transport and pack/unpack airline cargo containers/pallets. The experience of a subcontractor cannot be substituted for the prime contractor’s experience.

1.11.2. Prime Contractor’s Business Permission Certificates: The Contractor shall possess a current and valid Business Registration (사업자등록증), Freight Transportation Business Permission Certificate (화물자동차운송사업허가증), and Freight Transportation Forwarder Business Permission Certificate (화물자동차운송사업주선업허가증) issued by ROK Government authorities. The business permission certificates of a subcontractor cannot be substituted for the prime contractor’s business permission certificates.

1.11.3. Contract Manager: The Contractor shall provide a Contract Manager with a minimum two (2) years of experience within the last seven (7) years in freight transport operations and services where the cargo was of a sensitive nature, delivered on a strict time schedule and protected from pilferage and damage. Additionally, the contract manager must have experience with operations involving packing/unpacking and movement of airline containers. The Contract Manager shall be able to speak, read, write, and converse in English. The Contract Manager’s resume shall provide one of the two (2) following criteria: 1) Test of English for International Communication (TOEIC) score 450 or higher; OR 2) TOEIC Speaking Test score 100 or higher. Within the first thirty (30) calendar days of employment, the COR shall evaluate and report to the KO if the employee meets minimum English proficiency level. Personnel who fail to meet minimum English-language requirements will be determined as non-responsible by the KO. KO will request new personnel for the position who meets the English requirement.

1.11.3.1 Before removing, replacing, or diverting a Contract Manager, the Contractor shall:

(1) Notify the Contracting Officer/COR 14 calendar days in advance;

(2) Submit justification (including proposed substitutions with resumes of equal qualifications stated in this paragraph) in sufficient detail to permit evaluation of the impact on this contract;

(3) Obtain the Contracting Officer’s written approval. Notwithstanding the foregoing, if the Contractor deems immediate removal or suspension of any member of its management team is necessary to fulfill its obligation to maintain satisfactory standards of employee competency, conduct, and integrity under the clause at 48 CFR 970.5203–3, Contractor's Organization, the Contractor may remove or suspend such person at once, although the Contractor shall notify the Contracting Officer prior to or concurrently with such action.

(4) The Contract Manager may, with the consent of the contracting parties, be amended from time to time during the course of the contract to add or delete personnel so long as the aforementioned items are addressed.

1.11.4. Cargo Truck Drivers: The contractor shall provide Cargo Truck Drivers who have a minimum two (2) years of experience within the last seven (7) years in freight transport operations and services. In addition, the drivers must possess Freight Transportation Operator Licenses (화물운송종사자격증) issued by ROK Government authorities.

1.11.5. Forklift Drivers: The contractor shall provide Forklift Drivers who have a minimum two (2) years of experience within the last seven (7) years in freight transport operations and services. In addition, the drivers must possess Forklift Driver Licenses (지게차 운전기능사) issued by ROK Government authorities.

1.11.6. Vehicle Registration: The contractor shall submit certified copies of each vehicle’s (vehicle registration certificate) containing license plate number, vehicle manufacturer, and Model year. Throughout the entire contract period (up to 5 years), all vehicles used to perform the contract must not exceed ten (10) years of age. If any vehicle is replaced during the contract period, the replacement vehicle must also be no more than ten (10) years old at the time of replacement.

1.12. Staffing and Equipment Plan and List: The Contractor shall submit the staffing and equipment plan that includes a finalized list of all workers (truck drivers, mail guards, forklift drivers, and packing/unpacking service workers), trucks, and forklifts, including labor mix and labor quantities to be used for each ELIN as specified in the Attachment A, no later than 7 days after the start of contract and each option year. Failure to submit the required information within this specified timeframe may impact the contractor’s monthly and annual performance reports. The Staffing and Equipment Plan shall also include the organizational structure (manning charts), personnel qualifications, the replacement plan, backup staffing plan, and retention plan.

1.13. Phase In Period: During the 30-day Phase-In period, the contractor shall complete all preparation and transition activities, including conducting required training, inspecting vehicles, submitting required documentation, and coordinating with the Government. No mail delivery services are required during this period.

PART 2 DEFINITIONS & ACRONYMS

2. DEFINITIONS AND ACRONYMS:

2.1. DEFINITIONS: As used throughout this contract, the following terms have the meaning as set forth below:

2.1.1. Commitment – Action by the Ordering Officer of the Military Mail Terminal (MMT) requiring the Contractor to arrange and prepare transportation services as specified for the US Government. Commitment may be made orally and later confirmed in writing. A commitment will be made no later than 1600 hours on the day prior to operation.

2.1.2. Loading – Physical movement of mail from a general location onto or into a mode of transportation.

2.1.3. Unloading – Physical movement of mail from one mode of transportation to a general location exclusive of another mode.

2.1.4. Truck – A motor vehicle provided by the Contractor under the terms of this contract which is suitable for hauling the US mail as specified in the PWS, PART 4.

2.1.5. US Government Bill of Lading (GBL) – USFK Form 79-3EK is a serially numbered, bilingual, accountable document. This document is required for the procurement of transportation services under Contract Line Items (CLINs) of the contract.

2.1.6. Military Mail Terminal (MMT) – A sub-element of the Postal Operations Detachment (POD), acting as a field control team which is responsible for the commitment, coordination and supervision of all transportation activities within its assigned area. The POD commands and supervises assigned MMT under the direction of the Chief, Postal Operations.

2.1.7. Mail Manifest – DD Form 1372 is used to document mail shipped and received by postal agencies in accordance with Military Postal Service Procedures Manual (MPM). This form is furnished upon completion of each delivery so that the Contractor can use it as evidence of transportation services rendered pursuant to this contract. This form is also used to support the Contractor’s request for issuance of GBL.

2.1.8. Consignee - The recipient (unit, depot, or person) to whom mail is addressed or consigned for final delivery and the activity that receives the shipment.

2.1.9. Consignor - The individual, unit, or activity that request shipment of the mail.

2.2. ACRONYMS:

ACORAlternate Contracting Officer's Representative
AFARSArmy Federal Acquisition Regulation Supplement
ARArmy Regulation
CCEContracting Center of Excellence
CFRCode of Federal Regulations
CONUSContinental United States (excludes Alaska and Hawaii)
CORContracting Officer Representative
COTRContracting Officer's Technical Representative
COTSCommercial Off the Shelf
DADepartment of the Army
DD250Department of Defense Form 250 (Receiving Report)
DD254Department of Defense Contract Security Requirement List
DFARSDefense Federal Acquisition Regulation Supplement
DMDCDefense Manpower Data Center
DODDepartment of Defense
FARFederal Acquisition Regulation
HIPAAHealth Insurance Portability and Accountability Act of 1996
KOContracting Officer
OCIOrganizational Conflict of Interest
OCONUSOutside Continental United States (includes Alaska and Hawaii) ODCOther Direct Costs
PIPOPhase In/Phase Out
POCPoint of Contact
PRSPerformance Requirements Summary
PWSPerformance Work Statement
QAQuality Assurance
QAPQuality Assurance Program
QASPQuality Assurance Surveillance Plan
QCQuality Control
QCPQuality Control Plan
TETechnical Exhibit

PART 3

GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

3. GOVERNMENT FURNISHED ITEMS AND SERVICES:

With the exception of GSA approved locks and USPS numbered seals, the Government will provide no other property.

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:

4.1. Firm Fixed Price Portion:

4.1.1. The Contractor shall spot one (1) 8 ton truck, 313 days per year (Mon thru Sat), and one (1) 1 ton, 52 days per year (Sun) at Camp Humphreys. And the contractor shall also spot one (1) 8 ton truck, 365 days (Mon thru Sun) at Osan AB.

4.1.2. The Contractor shall transport mail between Incheon MMT, Cargo Terminal A, and Terminal C in Incheon Airport. The Contractor shall provide this service with two (2) trucks (Flat bed type, Size: 4.5 or 5 ton) and one (1) 4 Ton electric forklift at Incheon MMT.

4.2. Requirement Portion:

4.2.1. The contractor shall transport mail IAW delivery service schedules. This service will be ordered on as- required basis to transport mail and covered by a US Government Bill of Lading (GBL).

4.2.2. Type of Truck (s) Required for Mail Deliveries. Truck(s) provided by the Contractor for the purpose of mail delivery service shall be a truck designed for hauling of US Mail. The cargo compartment must be so constructed with metal body and lockable from outside to protect mail from pilferage and weather. The door of the cargo compartment shall be so designed that a lock and seal can be affixed by the US Government to the latch handle of the door to the vehicle in the closed position to maintain the integrity of the shipment. Cargo area may not have any side doors and flooring must be sealed to protect mail from pilferage and weather. The cab of the truck(s) must have sufficient space to allow one U.S. mail guard to ride with the driver and accompany the mail shipment.

4.2.3. The Contractor shall pack and load, unload mail into airline cargo containers 7 days per week at Incheon MMT and into airline cargo truck at Busan MMT. The contractor shall be capable of packing, unpacking, and moving airline containers as specified in Attachment A. ELIN List. The Contractor shall provide this service with two (2) 4 Ton electric forklifts: one (1) positioned at Incheon MMT and one (1) at Busan MMT.

4.2.4. The contractor shall provide U.S. citizen mail guard in each truck that is transporting Registered mail through- out Korea, Monday thru Friday excluding U.S. Holidays, IAW Military Postal Service Procedures Manual (MPM) Section 23.2.e. The U.S. mail guards are required to have physical capability to lift parcels and sacks weighing up to 70 pounds.

4.2.5. The contractor shall unpack boat mail pallets 1 day or 2 days per week. The contractor shall be capable of unpacking, unloading, and movement of boat mail pallets as specified in Attachment A. ELIN List.

4.2.6. The contractor shall provide U.S. citizen mail guards under the CLIN E0002BA thru BT except the followings; (a) U.S. Holidays, (b) MPO Closed. Note: The contractor takes full responsibility in ensuring that the U.S. citizen employed by the company is properly registered to work in South Korea.

4.2.7. The Military Mail Terminal manager will provide registered mail handling procedures training to all U.S. citizen mail guards under this Contract. Loss or damaged registered mail is on the responsibility of the contractor, if it causes of lack of safeguarding the mail and failure to maintain accountability by US Mail Guard.

PART 5 SPECIFIC TASKS

5. SPECIFIC TASKS:

5.1. Commitment of Services:

5.1.1. Commitment for services under this contract shall be made not later than 1600 hours on the day prior to required services. Commitment of the Contractor’s trucking services shall be made by the duly appointed Ordering Officer. It is the responsibility of the Contractor to ensure that only commitments made by the Ordering Officer are honored. The Postal Operations Detachment (POD) shall issue the commitment through email correspondence. The Contractor shall acknowledge receipt of the commitment through the same email system. If necessary, the commitment may be orally made and later confirmed in writing.

5.1.2. Cancellation of services under CLINs shall be made not later than 1600 hours on the day prior to the scheduled delivery service. Cancellation shall be made by the Ordering Officer. It is the responsibility of the Contractor to ensure that cancellations are only made by the Ordering Officer. Cancellations will be made orally and confirmed in writing within 24 hours.

5.2. Performance Procedures for Mail Deliveries:

5.2.1. Type of Truck(s) Required: Truck(s) provided by the Contractor for the purpose of mail delivery service shall be a truck designed for hauling of US Mail. The cargo compartment must be so constructed with metal closed body and lockable from outside to protect mail from pilferage and weather. The door of the trucks shall be so designed that a seal and lock can be affixed by the US Government to the latch handle of the door of the vehicle in the closed position to maintain the integrity and security of the shipment. Cargo area may not have any side doors and flooring must be sealed to protect mail from pilferage and weather. The cab of the truck(s) must have sufficient space to allow one US mail guard to ride with the driver and accompany the mail shipment.

5.2.1.1. All contractor trucks in the performance of this contract shall be in good and safe working condition. Trucks that do not meet the stated minimum cargo capacity as outlined in Attachment A. ELIN list, are not authorized for use in the execution of the contract. Failure to meet the cargo capacity requirement may impact the contractor’s monthly and annual performance reports.

5.2.1.2. In addition to providing trucks for mail delivery services to locations specified in Attachment B, US Mail Route Schedule, Contractor shall provide two (2) trucks designed for carrying airline cargo containers between the Joint Military Mail Terminal (JMMT) and cargo terminals. The trucks must have the capability to carry the airline containers/pallets described in Paragraph 5.6. The cargo compartment shall be Flat Bed and size be

4.5 ton or 5 ton. Bed Type trucks must be so constructed with metal body and when containers/pallets are loaded on the trucks they will be covered by a tarp to protect mail from weather/pilferage. The cab of the truck(s) must have sufficient space to allow one mail guard to ride with the driver and accompany the mail shipment. Mail container/pallet delivery services will be conducted as specified in Attachment A ELIN List.

5.2.1.3 The Contractor shall provide two (2) 4 ton electric forklifts to load and unload airline containers from Contractor trucks, as well as movement of airline containers/pallets and boat mail pallets, one at Incheon MMT and the other at Busan MMT. The contractor must have operational forklifts with the capability to load/unload containers non-stop during scheduled MMTs mail-call operating hours, 8 hours per day.

5.2.1.4 The contractor shall provide certificates of all vehicles showing those vehicles meet the operational and safety standards for both ROK and US Government and shall provide evidence of insurance coverage within five (5) calendar days after the contract is awarded to the Contracting Officer and the COR and yearly thereafter at the beginning of each option year, and when applying for new vehicle passes.

5.2.1.5. The Contractor shall make one (1) additional 5‑ton truck each at the Incheon MMT and the Busan MMT available for immediate deployment as a replacement vehicle in the event of a vehicle accident, mechanical failure, scheduled or unscheduled maintenance, or any other condition that renders a primary truck unavailable. Continuous on-site stationing of the replacement trucks is not required. During any maintenance, inspection, or repair of a primary truck, the Contractor shall use the additional truck as the replacement vehicle without exception. Under no circumstances shall a truck carrying U.S. mail be taken to a maintenance facility or removed from service while loaded with mail.

5.2.2. Report for service: Trucks shall report to the military postal agency at the point of origin as specified in the schedule at U.S. Mail Delivery Route Schedules, for services under ELIN List. The estimated time of departure (ETD) and estimated time of arrival (ETA) indicated in U.S. Mail Delivery Route Schedules may be changed at no additional cost to the Government and without need for formal modification of the contract, providing that notice of the change is given to the Contractor not later than 1600 hours, on the day prior to the required service.

5.2.3. When a truck is transporting US mail, extreme care shall be exercised to ensure that the doors of the cargo compartment will close securely and will not come open during transit. Vehicles with door latches worn so that doors will not securely close, shall not be used to transport mail.

5.2.4. When a truck is ordered for US mail delivery services, it will be used exclusively for transporting US mail. The truck shall be routed via Military postal activities as specified by the commitment, and under the surveillance of accompanying US mail guards.

5.2.5. Completed Trip: Upon completion of deliveries, the Contractor shall prepare a list of truck/trips for each delivery route, which shall be supported by the originals of DD Form 1372. The Contractor shall submit the original copy of DD Form 1372 with supporting documents by 1300 hours of each day to the Postal Supervisor at the Military Mail Terminals.

5.2.6. Accountability of Mail: Once the cargo compartment is locked and sealed by the shipping postal facility, the Contractor is responsible for mail accountability. The contractor shall validate all seals and locks and submit the original signed copy of DD Form 1372 to the Postal Supervisor of the Military Mail Terminal. The contractor shall also submit the signed Postal Form 3854-A when it is generated by the shipping postal facility.

5.3. Marking of Vehicles: All trucks utilized by the Contractor pursuant to this contract shall be marked with the following information:

a. Name of firm in English (abbreviation is acceptable).

b. Cargo hauling capacity of the truck in tons and cubic feet.

c. Identification of mail being transported; i.e., “US MAIL - DO NOT DELAY”. The marking may be a plate (metal or wooden) which can be securely placed on the front inside window of trucks.

5.4. Loading and Unloading from the Contractor’s truck(s): Requires the cooperation between the US Government and Contractor personnel.

5.4.1. The U.S. Government is responsible for the loading and unloading of mail on and off the Contractor’s truck(s) which includes the proper sequencing of mail for multi stop routes; does not include trucks transporting mail between the Incheon MMT and cargo terminal.

5.4.2. Contractor is responsible for ensuring the load is correctly balanced and the truck is not overloaded, and all safety standards are met.

5.5. Packing/Unpacking and Loading/Unloading Airline Containers and Trucks: Contractor personnel shall load and unload mail into and out of airline cargo containers/trucks up to 8 hours a day, 7 days per week at both MMTs. Contractor personnel are expected to pack/unpack up to 40 airline containers per 8-hour work day at Incheon MMT and load/unload up to 2500 mail pieces at Busan MMT, as specified in Attachment A ELIN List. Airline containers, as specified in paragraph 5.6, must be packed in compliance with airline standards. Unpacking airline containers must meet the guidance of the Military Mail Terminal Operations provided by the MMT supervisor. All mail loading and unloading operations involving airline cargo trucks must comply with the guidance of the Military Mail Terminal Operations provided by the MMT supervisor.

5.5.1 Boat Mail Pallets: Contractor personnel shall unpack and unload boat mail pallets during scheduled MMT mail-call operating hours. Contractor personnel are expected to unload up to 20 pallets per week at Incheon MMT, and up to 15 pallets per week at Busan MMT. Boat mail pallets are specified in paragraph 5.6.

5.5.2 The Contractor shall provide sufficient qualified manpower to conduct the daily operations as outlined in paragraph 5.5 - 5.5.1. The Contractor shall ensure that staffing levels are adequate at all times to complete all daily mail processing, packing/unpacking, and loading/unloading requirements without delay or interruption. Under no circumstances shall a shortage of personnel result in incomplete mail handling operations or impact the timely processing of U.S. mail.

5.5.3 Contractor personnel shall ensure that mail pieces are placed onto the conveyor-belts with spacing that meets the Government-specified requirement to prevent excessive conveyor load and to ensure proper X‑ray screening operations. The Contractor is responsible for determining the methods necessary to achieve the required spacing.

5.6. Container, Pallet, and Mail piece Sizes: Contractors must have executed procedures used to move/transport and pack/unpack the following sized containers/pallets.

Container

No.
Type
Max Cap
Inch/Cm Size
1
LD3
1,588 Kg
60.4 x 61.5 x 64/153.4 x 156.2 x 162.5
2
LD6
3,175 Kg
60.4 x 125 x 64/153.4 x 317.5 x 162.5
3
DL9
6,033 Kg
88 x 125 x 64/223/5 x 317.5 x 162.5
4
GM1
6,804 Kg
96 x 125 x 118/243.8 x 317.5 x 299.7

Pallet

1
88”
6,804 Kg
88 x 125/223/5 x 317.5
2
96”
6,804 Kg
96 x 125/243.8 x 317.5

Boat Mail Pallet

907 Kg
48 x 40 x 60

Mail Piece

35 Kg
USPS/APO/FPO/DPO mail

5.7. Transportation Documentation And Distribution: The following documents shall be used in ordering of services, certifications, and distribution.

5.7.1. Trip Document. U.S. mail shipper at point of origin shall issue DD Form 1372, Mail Manifest, covering mail shipment consigned to the next stop. Military Post Offices (MPOs) at intermediate stops shall do the same. These forms shall be presented to the receiving postal agency upon arrival and the signature of the receiver shall be obtained in the block provided thereon. Upon completion of each trip, the original shall be used as supporting document for issuance of GBL under each ELIN in accordance with USFK Reg 55-37. These forms serve as verification of actual truck trips and stops made enroute. The Contractor shall ensure that DD Form 1372 is signed in blocks #21 thru 25.

FORM NO.
ISSUED BY
COPY NO
DISTRIBUTION
DD Form 1372
MMT/Shipping Post Office
1. Original

2. Copy

MMT

Shipping Post Office

3. Copy
Contractor
USFK Form 79-3EK
Designated MMT/COR
1. Original
Contractor to support invoice

(GBL)

2. Copy
POD

(Electronic Version)

3. Copy
Origin MMT

5.8. U.S. Mail Delivery Route Schedules:

5.8.1 Trucks need to be spotted for loading at both MMT docks at Incheon and Busan at 1300 hours each day and will be used for US mail until the following day at the termination of each run as shown in each ELIN #. The trucks will be staged at the dock from 1300 hours until 0400 hours. The driver of each truck is needed from 0400 (except as noted in specific ELIN #) each morning until the termination of their ELIN #.

5.8.2. In addition to providing trucks for mail delivery services to locations specified in Attachment B, US Mail Route Schedule, Contractor shall provide two (2) trucks designed for carrying airline cargo containers/pallets at Incheon MMT. The trucks must have the capability to carry the airline containers/pallets described in Para 5.6 and meet 5.2.1 specifications.

5.8.3. Mail delivery route schedules by Exhibit Line Items (ELIN) are separately attached. (Attachment B, US Mail Delivery Route Schedules)

5.8.4. Contractor is responsible for providing COR with all workers names and working schedule monthly to include U.S. Mail Guards, no later than seven (7) calendar days before the first of the month. Contractor shall provide daily report of all workers and working schedule to the supervisor(s) of both MMTs, no later than 1300 hours each day prior to the following day.

PART 6 APPLICABLE PUBLICATIONS

6. APPLICABLE DOCUMENTS:

The following documents form a part of this Performance Work Statement and will be in effect on the date of Request for Proposals.

USFK Regulation 55-37, Transportation and Travel - Korea Traffic Management

Mileage Distance Table (2008), published by the 25th Transportation Battalion (25th TB), Unit #15181, APO AP 96218-5181, in effect at the time of commitment of services.

DoDI 4525.09 Military Postal Service Military Postal Service Procedures Manual (MPM) AR 385, Army Safety Program AR 385-55, Prevention of Motor Vehicle Accidents

PART 7 ANTITERRORISM/OPERATIONS SECURITY (AT/OPSEC)

1. AT Level I training. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. All contractor employees, to include subcontractor employees, requiring access Army installations, facilities and controlled access areas shall complete AT Level I awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee to the COR or to the contracting officer, if a COR is not assigned, within 30 days after completion of training by all employees and subcontractor personnel. AT level I awareness training is available at the following website: http://jko.jten.mil

2. Access and general protection/security policy and procedures. This standard language is for contractor employees with an area of performance within Army controlled installation, facility, or area. Contractor and all associated sub- contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204- 9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

3. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

4. iWATCH Training. This standard language is for contractor employees with an area of performance within an Army controlled installation, facility or area. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.

5. For contracts that require OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.

6. For Contract Requiring Performance or Delivery in a Foreign Country. DFARS Clause 252.225-7043, Antiterrorism/Force Protection for Defense Contractors Outside the US. The clause shall be used in solicitations and contracts that require performance or delivery in a foreign country. This clause applies to both contingencies and non-contingency support. The key AT requirement is for non-local national contractor personnel to comply with theater clearance requirements and allows the combatant commander to exercise oversight to ensure the contractor’s compliance with combatant commander and subordinate task force commander policies and directives.

PART 8

CONTRACT REQUIREMENT DELIVERY LIST (CDRL)

Deliverable & PWS Section
Frequency
Acceptable Quality Threshold
# of Copies & Medium

/Format

Submit To
Remedy of Failure
Staffing and Equipment Plan and List 1.12
No later than 7 days after the start of contract and each option year.
100%
1 Copy
COR
See para 1.12
Quality Control Plan, 1.7.
Within ten (10) days after contract is

awarded

90%
1 Copy
COR & KO
Resubmit within 2

calendar days

Vehicle Maintenance and Inspection Certificate and vehicles Maintenance Annual Plan 1.9.3.

Within five (5) days after contract award and yearly thereafter at beginning of each option year, and when applying for new vehicle passes.

90%
1 Copy
COR
Resubmit within 5 calendar days
Evidence of insurance coverage 5.2.1.4
Within five (5) days after contract award and yearly thereafter at beginning of each option year, and when applying for

new vehicle passes

90%
1 Copy
COR
Resubmit within 5 calendar days

DD Form 1372 with supporting documents, 5.2.5

By 1300 hours of each day
90%
1 Copy
MMT
Resubmit within 30

minutes

Workers names and working schedule 5.8.4
-Monthly, no later than seven (7) days before the first of the month

-Daily, no later than 1300 hour each day prior to the following day.

90%
1 Copy
-COR

-MMT

Resubmit within 1 calendar day

PART 9

PERFORMANCE REQUIREMETNS SUMMARY (PRS)

The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Requirement
PWS

Para

Standard
Acceptable Quality Threshold
Method of Surveillance
Correction / Remedy

The records of quality control inspection, to include items identified in paragraph 1.7.2, shall be kept and made available to the Government throughout the contract performance period

1.7.1.4.
All records of Quality Control inspection shall be kept and made available to the Government.
100%
Periodic Inspection
Resubmit within 5 calendar days
The contractor shall provide U.S. citizen mail guard in each truck that is transporting Registered mail through- out Korea, Monday thru Friday excluding U.S. Holidays, IAW MPM Section 23.2.e.
4.2.3
U.S. citizen guards provided for each delivery of Registered mail.
100%
Periodic Inspection/Postal Supervisor Feedback
Shall be 100% or Contract Non Conformance will result and a Corrective Action Request (CAR) Issued.
Type of Truck(s) Required
5.2.1.

The correct type and quantity of trucks and electronic forklifts are provided.

90%
Periodic Inspection
Repair, Refurbish or replace truck(s)

within 2 hours.

Truck(s) Report for Service
5.2.2.
Trucks report to MMT at the point of origin as specified in the route schedule for

services.

90%
Periodic Inspection/Postal Supervisor Feedback
Repair, Refurbish or replace truck(s) within 2 hours.

Doors of the cargo compartment securely close

5.2.3
All cargo doors close securely.
100%
Periodic Inspection/Postal Supervisor Feedback
No remedy has to

be 100% or results in failure.

DD Form 1372 with supporting documents
5.2.5
Contractor submits DD Form 1372 with

supporting documents to the MMT.

90%
Periodic Inspection/Postal Supervisor Feedback
On-the-spot training/correction.
Accountability of mail
5.2.6
Contractor verifies that the cargo compartment of the truck is locked and sealed, and the Contractor is responsible for mail

accountability.

100%
Periodic Inspection/Postal Supervisor Feedback
Contractor should be responsible for reimbursements of stolen/lost mail.
Marking of Vehicles
5.3
Marking as listed under Para 5.3
90%
Periodic Inspection
Provide a sample of marking to the COR for approval prior to marking.
Loading/unloading operations
5.4
Contractor shall ensure load balancing and compliance with safety standards. Loading/unloading of mail on and off the contractor’s trucks with sufficient/qualified personnel.
100%
Periodic Inspection/ Postal Supervisor Feedback
On-the-spot training/ correction. Corrective Action Request (CAR) Issued.
Packing/Unpacking and Loading/Unloading Airline Containers and Trucks
5.5 – 5.5.2
Contractor personnel shall pack/unpack and load/unload from airline containers/trucks in compliance with standards established by airlines and the MMT guidance with sufficient/ qualified manpower.
100%
Periodic Inspection/ Postal Supervisor Feedback
On-the-spot training/correction. Corrective Action Request (CAR) Issued.
Mail spacing on conveyor-belts
5.5.3
Contractor personnel shall ensure that mail pieces are placed onto the conveyor-belts with spacing that meets the Government-specified requirement.
90%
Periodic Inspection/ Postal Supervisor Feedback
On-the-spot training/correction. Corrective Action Request (CAR) Issued.

PART 10 ATTACHMENT/TECHNICAL EXHIBIT LISTING

10. Attachment/Technical Exhibit List:

10.1. Attachment A - ELIN List

10.2. Attachment B – Route Schedule