Install 30 ton A/C for the fourth bay in the Greenhouse
Solicitation number
12405B22Q0221
Issued by

View the file

Other files

File Type Posted
RFI Questions answered.docx DOCX document
Davis Bacon Wage Determination.pdf PDF
12405B22Q0221.pdf PDF
IMG_0131.JPG JPG image
IMG_0134.JPG JPG image
Wage Determination.pdf PDF
IMG_0136.JPG JPG image
IMG_0137.JPG JPG image
New AHU for Greenhouse Drawings2.pdf PDF
Clauses and Provisions.docx DOCX document
IMG_0132.JPG JPG image
IMG_0135.JPG JPG image
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

US Department of Agriculture (USDA)

Performance Work Statement

Contents

Project Title3
General Information3
1.0 Background and Purpose3
2.0 Definitions3
Contractor Requirements3
3.0 Technical Requirements / Tasks3
4.0 Deliverable / Schedule3
5.0 Government Furnished4
6.0 Travel4
7.0 Contractor’s Key Personnel4
8.0 Security Requirements4
9.0 Data Rights4
10.0 Section 508 - Electronic and Information Technology Standards4
11.0 Performance Requirement Measures4
Attachment5

Project Title Install A/C for the fourth bay in the Greenhouse for cooling and heating

General Information

1.0 Background and Purpose

Install A/C for the 4th bay in the New Greenhouse where corn will be grown year around. The optimum temperature should be 80-85 degrees F. Outside temp in summer will be around 105 deg F and in cooler months it can dip to low 30s deg F.

2.0 Definitions

N/A

Contractor Requirements

3.0 Technical Requirements / Tasks

The AC should maintain temp from 78-80 degrees F for the fourth bay (700 sq ft) in the greenhouse for successfully growing corn year around. The following specifications apply:

The packaged A/C Unit should be 2-speed belt-driven with cooling capacity of at least 290,000 Btu (using refrigerant R-410-A) and gas heating with at least 320,000 Btu. The AC should be powered by volts/Ph/HZ - 208/3/60. The whole unit should be mounted on a weather proof slab (14” x 14”) and mounted on vibration -free galvanized steel frame. Ducts should be extended into bay -4 for uniform dispersal of cold/hot air. Control mechanisms are available at the Headhouse (MicroGrow control)

All components should be American-made and compliant to industry standards.

4.0 Deliverable / Schedule

All written deliverables shall be phrased in layperson language.

· AC should be procured installed within 60-90 days from the date of acceptance of the contract.

· AC will be controlled by the MicroGrow controller in the headhouse. For technical reasons, this will be handled separately.

· Reporting Requirements: The contractor is required to provide written progress reports {biweekly} for the period of installation and completion {not beyond 90 days).

Key Deliverables

Item No.
Deliverable
Objective
Due
1
Procure and Install AC for the 4th bay in the New Greenhouse
For growing corn year around. See statement of work
No later than 60 business days after contract award
2
Bi-Weekly Status Report
Report documenting tasks & issues weekly.
Weekly, every Friday, by 3:00 PM EDST until the contract expires

5.0 Government Furnished

Access to government site will be provided. The contract awardee will be working with Ponchartrain Partners – in house contractors who maintain the building, greenhouse and the surroundings.

6.0 Travel

N/A

7.0 Contractor’s Key Personnel

Not known until the contract is awarded

8.0 Security Requirements

Register with the Administrative Office for access to the greenhouse. Inform The Research Leader Dr. Rajasekaran in advance of the commencement of work.

9.0 Data Rights

N/A

10.0 Section 508 - Electronic and Information Technology Standards N/A

11.0 Performance Requirement Measures

Performance Objective
Required Task or Deliverable
Performance Standard
Method of Surveillance
Positive/Negative Incentive

% for NOT meeting the Task

Install an AC for the fourth bay and the duct work.
When connected to the controller board in the headhouse, the AC should perform without shaking, flaws and should maintain a temperature of 78-80 degrees F. Outside temp will be around 105 F in summer and can dip into low 30s in winter
The controller board will be set up to operate the AC and will allow a difference of 2-3 degrees F from the set temperature.
The MicroGrow controller will be operated by the users in the FFS Unit and also by the building Engineer.
Should be under warranty for at least one year. Extension is also preferred..

Insert Performance Requirement Measures Here

Attachment None. For the AC specs please see PWS. Additional information can be provided by the building engineer or by Dr. K. Rajasekaran image1.png