PCS ADDENDUM 1 STES Pre-K Modular Q & A.pdf
PDF 146 KB Posted
- Attached to
- PCS Pre-K Modular Classroom
- Solicitation number
- 225-205-MNT-003
- Issued by
- Pitt County, North Carolina
About this file
This is an Addendum document from Pender County Schools containing questions and answers related to a Pre-K Modular Classroom construction project. The document addresses 25 technical questions about construction specifications, including clarification that students may be present on campus briefly during a summer learning program, though the district will attempt to reassign the program and keep all students clear of the construction area for safety reasons.
The document specifies several key requirements including: poured concrete footings are required per building inspector requirements, LED lighting will be used instead of T-8, Bard units with dehumidification capability are required for HVAC, IT wiring will be handled by the school district, and the fire alarm must be tied into the main school system. The project requires Davis Bacon wages, minimal grading with soil deposits allowed onsite, a full-time project manager, and contractor responsibility for final grading and seeding. Electrical contractors must schedule a site visit to assess service adequacy and coordinate with Duke Energy if needed. The school district will handle parking lot painting and the covered walkway separately, while landscaping is not required for this project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Pender County Schools - STES Pre-K Modular RFP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM 1:Can you confirm if students will be present on campus during the period of construction/completion of the RFP scope of work?
Please see the list of questions that have been asked. The responses from Pender County Schools are highlighted in red.
1. Will you provide an approved full Civil Engineering plan?
At this time, the plan that is attached is all that is available. If more information is required, please schedule a site visit.
2. Are poured concrete footings required?
Yes, that is the Pender County Building Inspectors requirement.
3. Has a soil test been done for the site?
No, assume 3000 PSI.
4. The building floor plan shows quite a lot of J-Boxes on the drawings then the specifications. Do we go by the drawing?
Yes, please follow the drawings
5. In the restrooms, do you want Corlon Flooring in lieu of vinyl?
Yes
6. In the rest of the building, do you want Congoleum flooring that is installed at the factory and the seams area finished onsite? This doesn’t require a tile bar.
Yes. This is owner preferred.
7. In lieu of the 4 legged plastic mop sink, would you like to replace it with a Terrazzo mop sink?
No. The standard 4 legged mop sink will suffice.
8. Interior lights – Do you want LED in lieu of T-8?
LED
9. The HVAC will require dehumidifiers.
Yes. Include Bard units with dehumidification capability
10. Is the IT wiring to be the responsibility of the school district?
Yes. The school district will handle the IT wiring.
11. Is the fire alarm to be a standalone or is it to be joined into the main school
System?
Tied into the main school.
12. Is the crosswalk to be stripped?
The school district will handle any parking lot painting.
13. Is the covered walkway to be included?
No. That will be handled separately.
14. Is landscaping required for the site?
No.
15. If there is no soil report, can we assume the compaction is 3,000 PSI?
Yes.
16. Is there an existing electrical service?
Please have your electrical contractor schedule a site visit to see what is in place to determine if the service is adequate for the needs of the project. If it is determined that the existing service is not enough, they must contact Duke Energy to discuss.
17. If the electrical single or double phase?
Please see Question 16.
18. Who will be doing the hook-up to existing utilities?
Yes.
19. Does this project require Davis Bacon wage?
Yes.
20. Will any grading be required?
Minimal.
21. Can we deposit soils onsite?
Yes. A site will be selected..
22. What is the size of the electrical panel?
Please see question 16.
23. Who will be doing the final grading and seeding?
That will be the selected contractors responsibility.
24. Are you requiring a full time project manager onsite?
Yes.
25. Can you confirm if students will be present on campus during the period of construction/completion of the RFP scope of work?
Students may be on campus for a brief period of time there is a summer learning opportunity. The District will try to reassign the program if possible. All traffic and students will be kept clear of the construction area for safety reasons.