This is a Statement of Work (SOW) for PC-12 hangar support requirements in support of NASA's QUARC laser communications campaign at Cleveland Hopkins International Airport (KCLE), Cleveland, Ohio.

NASA's Support Aircraft and Maintenance Operations (SAMO) fleet requires contractor-provided facilities, utilities, and support services to enable safe, continuous, and efficient PC-12 aircraft ground and flight operations during the QUARC mission from September 2, 2026 through January 31, 2027. The contractor must provide a secure hangar with minimum dimensions of 75 feet wide, 20 feet high, and 80 feet deep, equipped with an operational fire suppression system. Additional facility requirements include 625 square feet of secure office space with four desks and chairs, 250 square feet of secure office/storage space for aircraft components and parts, 625 square feet of storage space for NASA tools, and 500 square feet of Ground Support Equipment (GSE) storage space, all located near the aircraft parking area. The contractor must provide 208 VAC building power to support 600 amps at 28 VDC via NASA-provided equipment, high-speed commercial internet connectivity, diesel fuel for ground and support equipment, coordinate refueling operations with estimated consumption of 1,500 gallons weekly during flight phase (mid-September through mid-December 2026, potentially extending to January 2027), provide personnel badging and flightline access coordination, and furnish five non-reserved parking spaces for daily use. Approximately 5-8 personnel will be onsite each day. September services will be purchased via Government Purchase Card, with the base Purchase Order covering October 1 through December 31, 2026, and an option to extend through January 31, 2027. All work must comply with applicable airport regulations, safety requirements, and NASA coordination requirements.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

PC-12 HANGAR SUPPORT REQUIREMENTS

IN SUPPORT OF

QUARC DEPLOYMENT

AUGUST 2026

1. INTRODUCTION/BACKGROUND

The National Aeronautics and Space Administration (NASA) Support Aircraft and Maintenance Operations (SAMO) aircraft fleet are utilized as support aircraft and potentially as test beds for variety of experiments. The fleet operates out of Armstrong Flight Research Center (AFRC).

NASA intends to conduct the QUARC laser communications campaign starting in August 2026. To support this campaign, NASA requires contractor-provided hangar facilities, utilities, and support at Cleveland Hopkins International Airport (KCLE), Cleveland, Ohio. The purpose of this effort is to ensure safe, continuous, and efficient PC-12 ground and flight operations in support of the QUARC mission objectives.

2. OBJECTIVE AND SCOPE OF CONTRACT

The Contractor shall provide all facilities and utilities necessary to support PC-12 aircraft ground and flight operations during the QUARC laser communications campaign. The scope includes hangar access, servicing utilities, secure office and storage space, internet connectivity, fuel support for ground equipment, and personnel access coordination. Approximately, 5-8 people will be onsite each day.

The Contractor shall perform all work in accordance with applicable airport regulations, safety requirements, and NASA coordination requirements.

3. DESCRIPTION OF TASKS AND TECHNICAL REQUIREMENTS

3.1 Coordinate location and access to PC-12 for refueling operations. Estimated fuel consumption is 1500 gallons per week, once we enter flight phase (mid-September through mid-December 2026), possibly extending into January 2027

3.2 Provide 208 VAC building power in order to provide 600 amps at 28 VDC via NASA provided GFE (Horbart Model Power Master ADV 45 KVA Model

45SX200).

3.3 Provide secure office space (625 square feet minimum) with four desks/tables and chairs near aircraft parking location. Inside the hanger is adequate

3.4 Provide secure office/storage space (250 square feet minimum) (Store A/C parts & payload components)

3.5 Provide secure hangar with operational fire suppression system (door opening: 75 feet wide minimum, height: 20 feet minimum, depth: 80 feet minimum) for aircraft storage. Aircraft will always remain towable.

3.6 Provide storage space for NASA tools (625 square feet minimum) near aircraft parking location.

3.7 Provide access to high-speed commercial internet to support operations and instrument team data transfer

3.8 Provide diesel fuel for aircraft ground and support equipment.

3.9 Provide Ground Support Equipment (GSE) storage space (500 square feet minimum) near aircraft parking location.

3.10 Provide personnel access to hangar and flightline – to include, but not limited to badging, gate codes, etc.

3.11 Provide non-reserved car parking spaces for up to 5 vehicles near hangar daily during period of performance.

4. PLACE OF PERFORMANCE

The required place of performance is Cleveland Hopkins International Airport (KCLE), Cleveland, Ohio.

5. PERIOD OF PEFORMANCE

The estimated period of performance is September 2, 2026 through January 31, 2027.

Hangar services for September will be purchased using a Government Purchase Card. The base Purchase Order will cover October 1 through December 31, 2026, with an option to extend performance through January 31, 2027.

File details come from the government source that posted it. Updated .