Questions and Answers - Call for Solution for AdvM Composite Printer June 24 2026.xlsx
XLSX spreadsheet 10 KB Posted
- Attached to
- Call for Solution - Composite Print Capability
- Solicitation number
- PANRSA26P0000037193
About this file
This is a Questions and Answers document for the Call for Solution - Composite Print Capability solicitation issued by the Army Contracting Command - Redstone Arsenal on behalf of the U.S. Army Aviation and Missile Command (AMCOM).
The document addresses technical specifications regarding facility electrical infrastructure requirements for the Advanced Manufacturing (AdvM) composite printer installation at Corpus Christi Army Depot (CCAD). Specifically, it clarifies that the Government Standard Utility (USG) can provide either 208V three-phase or 120V single-phase power within 25 feet of the equipment's installation location. Vendors are responsible for providing their own transformer if alternative voltages (such as 230V or 240V) are required. The Q&A document indicates that proposals must include all required ancillary equipment, including post-processing systems and facility transformers necessary for power requirements. The associated Call for Solution seeks innovative solutions for Advanced Manufacturing composite print capability to address critical readiness gaps in aviation maintenance operations and enable CCAD to rapidly fabricate qualified parts, tools, jigs, fixtures, and ground support equipment. The Phase 1 question submission deadline was June 24, 2026, at 12:00 PM Central Daylight Time.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Call for Solutions - Composite Printer.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AdvM Composite Print Capability
| Question # | Category | Question | Answer | |
| 1 | Technical Specifications | Per the proposal requirements, proposals shall include the following: | ||
| • | All required ancillary equipment to include but not limited to post processing systems | |||
| • | Facility transformers for power requirements. |
1. Does the current facility electrical infrastructure support the installation of this machine and if so, what is the distance between the current panel and the installation area? (For example, within 25 ft or such) USG provides either 208V, 3 phase or 120V single phase within 25 feet of the equipment’s home. The vendor shall provide a transformer if some other voltage is required (ie 230V or 240V).