PWS Batch Treatment Support Structure.pdf

PDF 692 KB Posted

Attached to
Sources Sought for Batch Waste Treatment Support Structure at CCAD
Solicitation number
PANRSA-24-P-0000-002530
Issued by

About this file

This document is a performance work statement for a federal contract to provide design, fabrication, and installation services for a batch waste treatment support structure at Corpus Christi Army Depot. The contractor will design a support structure that meets the specified performance criteria, remove the existing structure, fabricate a new structure according to the design and specifications, and install the new structure. The period of performance is two calendar weeks. The contractor must adhere to safety, security, fire, and environmental requirements and complete the work in conformance with the performance standards and acceptance procedures defined in the attachments, which include technical specifications for the support structure.

View the file

Other files

File Type Posted
SOW Support Structure.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

FOR

ACCF PIT LINING SYSTEM

PART 1

GENERAL INFORMATION

1.0 GENERAL: This is a non-personal services contract to provide a pit lining system for the containment pit in the chemical booth of the Advanced Corrosion Control Facility (ACCF).The Government will not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.1 Scope: The Contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, supervision, quality control, and other items and non-personal services necessary to apply a pit lining system as defined in this PWS, except for those items specified as government furnished. The Contractor shall perform to the standards of this contract.

1.2 Background: The ACCF chemical booth will be used for the application of trivalent chromium and nonchromated conversion coatings on airframe structures. However, during the initial construction of the ACCF, a chemical resistant lining system was not included in the building design for the containment pit in the chemical booth. This pit is constructed from concrete which will be degraded if corrosive chemicals are allowed to come in contact over an extended period of time. The chemistry employed for conversion coatings contains fluorotitanic acid or chromium sulfate and the chemistry is applied to airframes at a pH range of 2.6 to 4.0. A chemical resistant lining system is required to prevent damage to the concrete in the containment pit.

1.3 Description of Services: The Contractor will install a pit lining system for the ACCF facility as specified by section 5.0 Requirements of this PWS.

1.4 Period of Performance (POP): The POP shall be two calendar weeks. The POP will be defined in the contract document.

1.5 Quality Control (QC): Not applicable.

1.6 Quality Assurance (QA): The Government will evaluate the Contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).

1.7 Recognized Holidays: The Contractor shall not perform services on these days:

New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Independence Day Christmas Day Juneteenth

1.8 Hours of Operation: The Contractor shall provide services between the hours of 0800 and 1630 Monday thru Thursday, except on US Holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. For other than firm fixed price contracts, the Contractor shall not be reimbursed when the Government facility is closed for the above reasons. The Contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed.

CCAD may schedule a “compressed work schedule” during various times of the year. The Contracting Officer may authorize a “compressed work schedule” for Contractor operations during a planned CCAD “compressed work schedule”. The Contracting Officer will inform the Contractor of any planned CCAD “compressed work schedule” at least 7 calendar days prior to the change via email or memorandum.

1.9 Place of Performance: Performance for work under this contract shall be at the conversion coating bay of Building 1882 (ACCF), Corpus Christi Army Depot.

1.10 Safety Requirements: The Contractor shall follow CCAD Safety requirements which are provided in Part 7.3, Attachment 3 of this document.

1.11 Fire Protection Requirements: The Contractor shall follow NAS Corpus Christi Fire Protection requirements which are provided in Part 7.4, Attachment 4 of this document.

1.12 Environmental Requirements: The Contractor shall follow CCAD Environmental requirements which are provided in Part 7.5, Attachment 5 of this document.

1.13 Security Requirements: The Contractor shall follow CCAD Security requirements which are provided in Part 7.6, Attachment 6 of this document.

1.14 Conservation of Utilities: The Contractor shall instruct employees in utilities conservation practices. The Contractor shall operate under conditions that preclude the waste of utilities which include turning off the water faucets or valves after using the required amount.

1.15 Contracting Officer Representative (COR): The COR will be identified by a separate letter. The COR monitors all technical aspects of the contract and assists in contract administration. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.

1.16 Contractor Travel: Contractor shall travel to Corpus Christi Army Depot during the performance of this contract to provide services as detailed in this PWS. The Contractor shall be authorized travel expenses consistent with the provisions of FAR 31.205-46 and the limitation of funds specified in this contract. All travel requires COR recommendation for approval and authorization by the KO prior to travel arrangements being made.

PART 2

DEFINITIONS & ACRONYMS

2.0 DEFINITIONS AND ACRONYMS:

2.1 Definitions:

2.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or services to the Government. The term used in this contract refers to the prime.

2.1.2 CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and/or terminate contracts, and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.

2.1.3 CONTRACTING OFFICER’S REPRESENTATIVE (COR). An employee of the U.S. Government designated by the KO to monitor Contractor performance. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4 DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the

PWS.

2.1.5 DELIVERABLE. Anything that can be physically delivered and includes non-manufactured items such as meeting minutes or reports.

2.1.6 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.8 QUALITY ASSURANCE. The Government procedures to verify that services being performed by the Contractor are performed according to the acceptable standards.

2.1.9 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of Contractor performance.

2.1.10 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.11 SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.1.12 WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.13 WORK WEEK. Monday through Thursday, unless specified otherwise.

2.2 Acronyms:

ACCF Advanced Corrosion Control Facility ACOR Alternate Contracting Officer’s Representative AFARS Army Federal Acquisition Regulation Supplement AR Army Regulation CCAD Corpus Christi Army Depot CFR Code of Federal Regulations CONUS Continental United States (excludes Alaska and Hawaii) COR Contracting Officer’s Representative COTR Contracting Officer’s Technical Representative COTS Commercial-Off-the-Shelf DA Department of the Army DD250 Department of Defense Form 250 Receiving Report DD254 Department of Defense Form 254 Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DOD Department of Defense ECMRA Enterprise Contractor Manpower Reporting Application FAR Federal Acquisition Regulation FSC Federal Service Code GFP Government Furnished Property HIPAA Health Insurance Portability and Accountability Act of 1996 HMI Human-Machine Interface KO Contracting Officer OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) ODC Other Direct Costs PIPO Phase In/Phase Out PMB Plastic Media Blast POC Point of Contact POP Period of Performance PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program TE Technical Exhibit UIC Unit Identification Code WAWF Wide Area Workflow

PART 3

GOVERNMENT FURNISHED PROPERTY, EQUIPMENT AND SERVICES

3.0 GOVERNMENT FURNISHED ITEMS AND SERVICES:

3.1 Facilities: The Government will provide access to and the necessary workspace to perform the tasks as outlined in the PWS.

3.2 Equipment: Not applicable.

3.3 Materials: Not applicable.

3.4 Services: Not applicable.

3.5 Utilities: The Government will provide all utilities available in the facility for the Contractor’s use in the performance of this contract. The Contractor shall instruct employees in utilities conservation practices. The Contractor shall be responsible for operating under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount to accomplish cleaning vehicles and equipment.

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4.0 CONTRACTOR FURNISHED ITEMS AND RESPONSBILITIES:

4.1 General: Except for those items specifically stated to be Government-Furnished in paragraph 3.0, the Contractor shall furnish everything required to perform these services as indicated in paragraph 1.1.

4.2 Secret Facility Clearance: Not applicable.

4.3 Materials/Equipment

4.3.1 Materials: The Contractor shall provide all materials necessary to perform these services as indicated in paragraph 1.1.

4.3.2 Equipment: The Contractor shall provide all equipment necessary to perform these services as indicated in paragraph 1.1.

PART 5

SPECIFIC TASKS

5.0 REQUIREMENTS:

5.1 Basic Services: The Contractor shall install new lining system for containment pit in conformance to the specification in 5.2.

5.2 Task/Requirement:

5.2.1 Approximately 7,000 square feet of concrete surface will be coated with a chemically resistant lining system supplied by the Contractor. Specifically, this lining system must be resistant to fluorotitanic acid and chromium sulfate and must withstand a pH range of 2.6 to 4.0 in continuous service. Actual area of concrete surface to be coated will be determined by the Contractor based on field measurements during preparation for lining installation.

5.2.2 Concrete surfaces must be prepared sufficiently to allow for bonding of the lining system to the concrete.

Preparation of concrete surfaces can include degreasing, power washing, abrasive blasting, and other methods for ensuring cleanliness and proper roughness of concrete surfaces. Contractor shall select proper preparation methods for the lining system to be installed.

5.2.3 Contractor shall fill all cracks, holes, and other surface imperfections in concrete that can interfere with the integrity of the lining system.

5.3 Inspection and Acceptance:

5.3.1 Inspection and acceptance shall be performed at CCAD by the Contracting Officer’s Representative (COR).

5.3.2 Final acceptance of the services, equipment, materials, documentation and procedures called for in this Performance Work Statement (PWS) will be performed by the Contracting Officer based upon the inspection and recommendation of the COR.

5.4 Contractor Manpower Reporting (CMR):

5.4.1 The Office of the Assistant Secretary of the Army (Manpower & Reserve Affairs) operates and maintains a secure Army data collection site where the Contractor shall report ALL Contractor manpower (including subcontractor manpower) required for performance of this contract. The Contractor shall completely fill in all the information in the format using the following web address https://Contractormanpower.army.pentagon.mil. The required information includes: (1) Contracting Office, KO, Contracting Officer’s Technical Representative (COTR) or also known as the Contracting Officer’s Representative (COR); (2) Contract number, including task and delivery order number; (3) Beginning and ending dates covered by reporting period; (4) Contractor's name, address, phone number, e-mail address, identity of Contractor employee entering data; (5) Estimated direct labor hours (including sub-Contractors);

(6) Estimated direct labor dollars paid this reporting period (including sub-Contractors); (7) Total payments (including sub-Contractors); (8) Predominant Federal Service Code (FSC) reflecting services provided by Contractor (and separate predominant FSC for each sub-Contractor if different); (9) Estimated data collection cost; (10) Organizational title associated with the Unit Identification Code (UIC) for the Army Requiring Activity (the Army Requiring Activity is responsible for providing the Contractor with its UIC for the purposes of reporting this information); (11) Locations where Contractor and sub-Contractors perform the work (specified by zip code in the United States and nearest city, country, when in an overseas location, using standardized nomenclature provided on website); (12) Presence of deployment or contingency contract language; and (13) Number of Contractor and sub- Contractor employees deployed in theater this reporting period (by country). As part of its submission, the Contractor shall provide the estimated total cost (if any) incurred to comply with this reporting requirement. Reporting period shall be the period of performance not to exceed 12 months ending September 30 of each government fiscal year and must be reported by 31 October of each calendar year. Contractors may use a direct XML data transfer to the database server or fill in the fields on the website. The XML direct transfer is a format for transferring files from a Contractor’s system to the secure website without the need for separate data entries for each required data element at the website.

The specific formats for the XML direct transfer may be downloaded from the website.

PART 6

APPLICABLE PUBLICATIONS

6.0 APPLICABLE PUBLICATIONS:

6.1 The Contractor shall abide by all applicable regulations, publications, manuals, and local policies and procedures listed below:

Line Item Publication Mandatory or

Advisory Website

1 Security Requirements Mandatory 7.0 ATTACHMENT LIST

2 Safety Requirements Mandatory 7.0 ATTACHMENT LIST

3 CCAD Reg. 385.30 CCAD Safety Program Mandatory Copy available from COR

4 Fire Protection Requirements Mandatory 7.0 ATTACHMENT LIST

5 Environmental Requirements Mandatory 7.0 ATTACHMENT LIST

PART 7

ATTACHMENTS

7.0 ATTACHMENT LIST:

7.1 Attachment 1: Technical Exhibit 1: Performance Requirements Summary

7.2 Attachment 2: Technical Exhibit 2: Deliverables Schedule

7.3 Attachment 3: Safety Requirements

7.4 Attachment 4: Fire Protection Requirements

7.5 Attachment 5: Environmental Requirements

7.6 Attachment 6: Security Requirements

ATTACHMENT 1 / TECHNICAL EXHIBIT 1

Performance Requirements Summary

This Performance Requirements Summary includes performance standards. The Government will use these standards to determine Contractor performance and shall compare Contractor performance to the Acceptable Quality Level

(AQL).

PWS Paragraph Task Performance Standard Acceptable Quality Levels (AQL)

Surveillance Method / By Whom

1.10, 1.11, 1.12 and 1.13

Adherence to CCAD regulations (Safety, security, fire and environmental).

Adherence to CCAD regulations.

100% Inspection by COR.

5.2.1 Application of lining system to pit floor.

Continuous lining that will provide long term protection to concrete floor.

100% Inspection by COR.

5.2.2 and 5.2.3

Surface preparation of pit floor prior to application of lining system.

Clean adherent surface that will provide maximum adhesion of lining system to concrete floor.

100% Inspection by COR.

5.3.1 and 5.3.2 Inspection and Acceptance

Final Acceptance of services I.A.W. this PWS

100% Inspection by COR.

ATTACHMENT 2 / TECHNICAL EXHIBIT 2

Deliverables Schedule

Deliverable Frequency Number of Copies

Medium/Format Submit To

Detailed project schedule that outlines tasks and completion dates for project.

One week prior to commencing project.

One.

E-mail.

steven.e.churchman.civ@army.mil

Site specific safety plan to be reviewed by CCAD Safety Office.

Two weeks prior to commencing project.

One E-mail. steven.e.churchman.civ@army.mil

Product Data Sheet that summarizes the performance and technical characteristics of the liner system.

Upon contract award.

One E-mail steven.e.churchman.civ@army.mil

Safety Data Sheet in compliance with

29 CFR

1910.1200(g) for the liner system.

Upon contract award.

One E-mail

ATTACHMENT 3 / Safety Requirements

A. A Safety and Health Plan is required prior to the contractor starting work. The contractor shall submit a Safety and Health Plan not less than 5 days before starting physical on-site work at CCAD. The government will review the contractor’s proposed Safety and Health Plan, and the contractor shall promptly resolve any comments arising from government review. When requested by the contracting officer, DoD qualified safety and health personnel may participate in the government review of the contractor’s proposed Safety and Health Plan. Upon the contracting officer’s determination that the government’s comments (if any) have been satisfactorily resolved, the government shall approve the Safety and Health Plan in writing, and the approved Safety and Health Plan will be considered part of this contract.

Unless approved in writing by the contracting officer, the contractor shall not perform physical on-site work at the government installation/facility prior to approval of the Safety and Health Plan.

B. The contractor bears sole responsibility for compliance at all times with Federal, state, and municipal safety and health laws, regulations, and standards that apply to the work performed under this contract, including the Occupational Safety and Health Act. The contractor shall take all reasonable steps and precautions to maintain compliance with applicable regulations/ requirements, prevent accidents, and preserve the health and safety of contractor and government personnel performing or in any way coming in contact with the performance of the work required by this contract. The contractor shall also take additional immediate actions/precautions as requested by the contracting officer when the contracting officer determines that such measures are necessary for safety and health purposes. Contractor/subcontractor supervisors shall monitor worksites and operations daily to ensure safe working conditions and continuing compliance.

Hazardous or noncompliant conditions identified by the contracting officer shall be promptly corrected, and corrective action(s) taken shall be reported in writing to the contracting officer within 5 days of the contracting officer’s notification to the contractor. In cases of serious and/or recurring hazards/noncompliance, the contracting officer may stop the work in question pending correction of the hazardous/noncompliant condition, and/or order the removal of the involved contractor/subcontractor employees from the government installation/ facility. In such cases, the contractor will not be granted a cost adjustment nor an extension of time due to the work stoppage or employee removal action. Failure of the contractor to effectively resolve serious and/or recurring hazards or noncompliance may result in termination of the contract.

C. Contractor Safety Brief. Contractors will attend and provide contractor safety briefing to be scheduled and hosted by contracting officer representative with all stakeholders present (Safety, IH, Fire department, industrial hygiene, affected shop supervisors, etc.) prior to start of the contract.

D. Personal Protective Equipment (PPE). The Contractor personnel shall utilize the proper PPE where appropriate including head, eye, hand, foot, respiratory, and hearing protection suitable for the contracted work based on hazard analysis. All required PPE shall be maintained serviceable and worn properly when required. The Contractor Safety and Health Plan shall clearly identify the work areas requiring PPE and the type of PPE required. Unserviceable PPE shall be removed from service and properly disposed. The PPE utilized shall comply with all applicable American National Safety Institute (ANSI) and OSHA standards. Training of employees on the proper use of PPE shall be an integral part of the Contractor Safety and Occupational Health Training Program. The minimum PPE requirements required for all contractor, including sub-contractor personnel entering CCAD Industrial areas shall include but not limited to:

E. High impact safety glasses with side shields that meet or exceed ANSI Z87.1-2015, American National Standard for Occupational and Educational Personal Eye and Face Protection Devices.

F. Hearing protection in the form of plugs or muffs shall be worn by all who are exposed to high noise activities/operations that produce noise levels in excess of 85 decibels. Bldg. 340 is a hazardous noise area and contractor personnel must be provided and wear appropriate hearing protection.

G. Hard hats shall be worn that comply ANSI Z89.1-2014, Industrial Head Protection, and shall be worn by all workers when overhead hazards exists or areas designated as Hard Hat Working Zones. Bldg. 340 is not normally a hard hat hazard area but some overhead work is anticipated during this project.

H. Gloves of the proper type shall be worn by persons involved in activities that expose the hands to cuts, abrasions, punctures, burns and chemical irritants.

I. The Contractor will ensure contractor employees, including subcontractors, who enter industrial areas wear compression-type protective footwear with slip-resistant soles meeting ASTM F2413, Specification for Performance Requirements for Protective Footwear.

J. The Contractor is responsible for assessing and determining what PPE is required to be worn by contract personnel to include subcontractors fulfilling the contracted service. OSHA 29 CFR 1910.1026 provides recommended engineering and housekeeping and good hygiene practices.

K. Compliance with Licenses and Certifications Requirements. Contractor shall obtain and maintain all licenses and certifications required by federal, state, and local safety and occupational health, environmental laws and regulations necessary to adhere to the specifications of this contract.

L. Welding, Cutting and Brazing Requirements. Contractor will obtain a written permit from NAS Fire and Emergency Services before conducting any operation involving fires, open flame devices, burning , welding , cutting or other spark producing activities near flammable or combustible material ( to include dust). Additionally, any hot work will require the Contracting Officer Representative to schedule a synchronization meeting with stakeholders prior to execution to address stakeholders’ concerns associated with the operation. See Appendix IV for additional information.

M. Electrical Equipment Safety. The Contractor shall ensure all electrical and electronic equipment use and maintenance is IAW CCADR 385-97, Electrical Safety Program. GFCIs will be used where power outlets are required in damp or wet locations and within 6 feet (ft) (1.83 m)) of a water source. GFCIs are required for power outlets where live maintenance work is performed on cord- and plug-connected equipment. Job-made extension cords are prohibited.

Only purchased, National recognized testing laboratory approved extensions cords are acceptable when used with a GFCI outlet or portable GFCI device. Energized work will not be conducted unless it is determined that de-energization is not possible. An Energized Electrical Work Permit (EEWP) must be completed and energized work must be authorized by the AHJ prior to commencement.

N. Hazard Communication. The contractor is responsible for providing and documenting hazard communication briefing to contractor personnel to include subcontractors IAW 29 CFR 1910.1026.(i).

ATTACHMENT 4 / Fire Protection Requirements

A. Fire Protection Requirements and Plans

A.1 ATTENTION CONTRACTOR: Ensure that you and your subcontractors read and abide by this guide. All contractors and subcontractors are under the jurisdiction of the station Commanding Officer. Contractor shall comply with all pertinent provisions of the latest version of U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1,UFGS-01 35 26 and NFPA 241 Standard for Safeguarding Construction, Alteration, and Demolition Operations. Structures in the course of construction, alteration, or demolition, including those in underground locations a fire safety plan will be required. Essential items to be emphasized include the following:

• Good housekeeping

• On-site security if necessary

• Installation of new fire protection systems as construction progresses

• Preservation of existing systems during demolition

• Development of a prefire plan may be required

• Rapid communication

• Consideration of special hazards resulting from previous occupancies

• Protection of existing structures and equipment from exposure fires resulting from construction, alteration, and demolition operations

• Fire alarm and fire protection system changes/additions/acceptance testing must be witnessed and approved by personnel from Naval Air Station Corpus Christi Fire Prevention Branch.

Please contact the Fire Department Inspection Branch if you have any questions at 961-3369.

A.2 FIRES: All fires, chemical spills, and other emergencies shall be reported to the fire department, even fires that have been put out.

A.3 PHONES: Fire, Police, Ambulance (911)

A.4 Hot work permits are issued by the Fire Prevention Inspectors please call 961-4983. Provide- Name of person doing the work, time of the request and Location. The permit request needs to be submitted no earlier than 24 hours before the work is to be performed. If permit is needed less than 24 hours before work begins, you will need to stop by Building 7- Inspection office. Note: There may be a delay in issuance of a permit if the request is less than 24 hours before the work is to be performed.

A.5 Permits are issued on a daily basis only, and from start of work until finished. Permits are required for all hot work and before entering hangars. Hot work includes welding, cutting. Soldering/ brazing, tar pots, blow torches, etc.

B. Fire General Information

B.1 Prior to opening , using, securing, or testing any fire equipment, fire system, piping, panel, alarm system, hydrant, or any fire protection related item the Contracting Officer's Representative (COR) and or Government Representative must be notified before work shall begin.

B.2 No smoking is strictly enforced in designated areas.

B.3 Contractors must follow good housekeeping practices. Flammable and combustible materials shall be removed from construction site and shall be maintained in lay down area.

B.4 The fire department does not perform gas free inspection. Contractor shall provide own inspection; however, gas free documentation must be presented to the fire inspector.

B.5 Contractor/ subcontractor shall not perform any maintenance (i.e., changing oil) on company equipment aboard

NAS.

B.6 Fifteen minutes prior to the end of the work day, a foreman or supervisor shall conduct a walk-through inspection to ensure that there are no fire hazards left overnight.

B.7 Contractor shall ensure that subcontractors are informed and abide by fire regulations.

B.8 The fire department shall be notified 24 hours prior to the commencement and closure of asbestos removal operations.

C. Equipment

C.1 Only compression fittings allowed on high pressure hoses, no threaded type allowed.

C.2 Only gauge type regulators allowed on tar pots.

C.3 All electrical equipment must be UL approved.

C.4 No splices on extension cords.

C.5 Check -valve back flow valves required on welding equipment

C.6 Spring loaded, metal, noncombustible fuel containers required.

C.7 Fire extinguishers of at least-10lb ABC type required

C.8 Welders must have fire blankets. Regulators are required on all high-pressure cylinders.

ATTACHMENT 5 / Environmental Requirements

A. Compliance with Environmental Laws and Regulations: Contractor shall comply with all applicable federal, state, and local environmental laws, statutes, regulations, executive orders, permits, Army regulations (with supplements), as well as Major Subordinate Command (MSC) and installation regulations and policies. Contractor shall immediately report any conflicts between applicable federal, state, local environmental laws, statutes, executive orders, and provisions of Army Regulation 200-1, and any specifications within this contract to the Contracting Officer Representative (COR), as well as to the Chief of the Environmental Programs Compliance Division (EPCD).

B. Compliance with Green Procurement Requirements: Contractor shall follow Federal EPA Comprehensive Procurement guidelines (www.epa.gov/cpg) and Army Contracting Command Quick Guide (https://acc.aep.army.mil/accapps/ACCMAP/Documents/Quick-Guide-for-Sustainable-Procurement.docx) for acquisition of building materials and products and select materials that have a long life cycle; the least toxic materials;

recyclable materials; materials that are resource-efficient; recovered materials; bio-based materials; materials with the maximum recycled content; materials harvested on a sustained yield basis; and products causing the least pollution during their manufacture, use, and reuse, to the extent possible. No acutely toxic materials, polychlorinated biphenyls (PCBs), formaldehyde, asbestos containing materials, asbestos compounds, or fragile or brittle materials, shall be procured or furnished unless specifically approved by the procuring activity. No Class 1 ozone depleting compounds (ODCs) or equipment requiring such substances, even if contained in a closed looped system, shall be procured or furnished for use at government installations. No Class 2 ODCs or equipment requiring such substances shall be procured or furnished for use unless specifically approved in writing by the procuring activity.

C. Compliance with License and Certification Requirements and local permits and approvals: Contractor shall obtain all licenses and certifications required by Federal, State, and Local environmental laws and regulations necessary and ensure such licenses and certifications remain current throughout the duration of the contracted work to adhere to the specifications of this contract The Contractor shall submit all plans, notifications, reports, submittal documents, and fees required by Federal, State, and Local environmental laws and regulations to the appropriate Federal, State, and Local authority or agency as necessary to adhere to the specifications of this contract. All required licenses and certifications required by Federal, State, and Local environmental laws or regulations shall be considered a contract deliverable upon award. It is the responsibility of the Contractor to identify and obtain all of the installations' required permits and approvals prior to commencement of any of the work specified under this contract and to meet all stipulated conditions and requirements at all times while performing any work. Contractor shall abide by all local and installation requirements and provide a site-specific environmental plan as part of the deliverables. Appropriate and detailed notification shall be provided by the Contractor to the Chief of the EPCD prior to excavating or conducting any kind of hot work anywhere on the installation where the work is to be performed.

D. Notification of Federal and State Regulators: Contractor shall immediately notify the Chief of the EPCD and the COR, or their designated backups in their absence, of the arrival on site of any Federal, State, or DoD environmental regulator or enforcement agent or the receipt of any correspondence from a Federal or State environmental agency.

E. Inspections of Work Sites: Contractor shall submit to potential Federal, State, Army and installation work site environmental regulatory inspections and/or investigations into noncompliance, and fully cooperate with such inspections/investigations by providing the appropriate records and documentation. Environmental regulatory agencies are authorized by law to inspect any work site for environmental compliance with regulatory requirements. The inspection will only require the work site environmental officer, or supervisor/manager to answer questions and/or escort the inspector to specific work site areas with the potential to affect environmental quality. If an inspection is conducted, it will not stop or disrupt ongoing contract activities, except, if the Contractor is requested by the regulatory inspector, the Contractor shall correct any regulatory problems during the inspection to the extent possible. Any regulatory inspections and their outcomes shall be communicated to the COR and to the Chief of the EPCD or their appointed backups. Typical environmental work site inspections are conducted in less than 30 minutes with an approximate frequency of one inspection every two months. More frequent inspections may be required at the installation level and some may also require a close-out inspection prior to the Contractor vacating the work site.

Inspections will focus on hazardous material management, solid and hazardous waste disposal, Pollution Prevention (P2), air quality, and waste water management, to include storm water requirements. Contractor shall obtain the Environmental Compliance Checklist from the EPCD at the start of the contract performance period.

F. Reporting Noncompliance: Contractor shall immediately report any nonconformance or noncompliance with applicable Federal, State or Local environmental laws, Army and installation environmental regulations or policies, as well as any actions taken to address and correct the noncompliance, to the COR and Chief of the EPCD, or their appointed backups in their absence.

G. Verification of National Environmental Policy Act Documents: Where applicable, the Contractor shall obtain from the COR or Chief of the EPCD, of project NEPA documentation. These documents include but are not limited to a Categorical Exclusion, and NEPA checklist for this project. , H. Conformance with Environmental Management System: Contractor shall adhere to the guidelines stipulated by CCAD's Environmental Management System (EMS) during the performance of the contracted work and shall take the necessary actions to identify, monitor, and control those contract operations and activities that pose a risk of contamination, or can negatively impact the natural or human environment.

I. Generation of Solid Waste: Contractor shall remove from the installation and dispose of all solid waste that is generated through their contracted work, and which cannot be recycled, to an approved and permitted off-post disposal facility.

I.(a). Submit in writing the quantities of waste removed and quantities recycled to the Chief of the EPCD or designee on a monthly basis and at the expiration of the contract. The submittal shall include the date of disposal/recycling, the disposal/recycling facility, the types of material disposed/recycled and each of the quantities of materials disposed of and recycled by weight.

I.(b). The Contractor shall establish a program to promote cost-effective waste reduction in all operations and facilities covered by the contract. This includes collection, separation, and processing products or other materials recovered from solid waste streams for use in the form of raw materials.

I.(c). The Contractor shall make maximum effort to reduce and prevent waste and comply with Executive Order 13693 and the installation's waste management requirements. Upon completion of the contracted work, the Contractor shall conduct final clean-up of the work site, containerize any debris, and haul it away for appropriate disposal at no additional cost to the government. The COR or an Environmental Advocate shall be contacted for approval of the final clean-up work.

J. Generation of Hazardous Waste: Contractor shall abide by the guidelines stipulated in NASCC's Hazardous Waste Management Plan and shall assign all hazardous waste management responsibilities to the appointed ECD. Contractor shall contact the Chief of the EPCD to obtain technical assistance from the installation's Environmental Director who will assist the ECD with achieving and maintaining compliance with hazardous waste storage and disposal requirements.

The EPCD will provide hazardous waste drums for the Contractor to containerize hazardous waste generated through the contracted work. Where liquid hazardous waste is to be stored, the Contractor shall provide appropriate secondary containment and ensure containers are properly bonded and grounded where the chemical waste requires it. In addition, the Contractor shall be responsible for maintaining an appropriate spill response and control kit at all times. All spills are reportable and shall be coordinated with the COR and the Chief of the EPCD. Contractor shall accumulate hazardous waste prior to disposal shipment in a satellite accumulation point at or near the point of generation or in a less-than-90-day site, in accordance with Federal, State, Army, and installation regulations or policies. The Government is responsible for removal of all hazardous waste. Contractor shall contact the EPCD Chief for assistance. The Contractor shall provide a 24-hour notification to the Chief of the EPCD or designee that hazardous waste containers are ready for pick up and turn in by the EPCD. The EPCD will remove and dispose of manifested hazardous waste generated by contract activities from the installation to an approved, off-post, permitted hazardous waste disposal facility. The Contractor shall coordinate appropriately with the COR and the Chief of the EPCD the management of all hazardous waste to include profiling and final disposal. The Contractor shall perform a daily walk-through to ensure all hazardous material and all hazardous waste is properly secured and segregated by compatibility. Contractor shall reference section E of this appendix to ensure compliance with Federal, State and local laws and regulations.

K. Use of Hazardous Materials: Contractor shall contact the Chief of the EPCD to obtain technical assistance from the installation's Environmental Director who will assist the Contractor with achieving and maintaining compliance with hazardous materials management guidelines, to include requesting and obtaining an Approved Chemical List (ACL), labeling, storage, secondary containment, issue, use, and disposal requirements. Contractor shall submit to the COR or Chief of the EPCD a hazardous material inventory for any materials to be used in the performance of the contracted work. Where required by the Chief of the EPCD, the Contractor shall coordinate turn in and check out of all hazardous materials with a Hazardous Distribution Supply Center (HDSC) on a daily basis. The hazardous material inventory will be submitted 30 days prior to commencement of work for contracts that exceed 180 consecutive days and 15 days prior to commencement of work for contracts requiring under 180 days of consecutive work. The inventory list shall contain the hazardous material type and maximum quantities of materials anticipated to be used and stored on-site. The hazardous material shall be properly identified and labeled to include any applicable identification number, such as National Stock Number or Special Item Number and include any applicable hazardous materials management guidelines found on CCAD Regulation 200-16 and all applicable hazardous communication (hazcom) requirements or as required by the installation. Contractor shall ensure all hazardous materials are properly secured and segregated by compatibility and kept under his or her control at all times. No expired hazardous materials shall be used or stored at the installation.

Where applicable, and prior to bringing or removing hazardous materials on, at, or from the facilities where the contracted work is to be performed, the Contractor shall submit copies, preferably in electronic form, of Global Harmonization System (GHS) compliant Safety Data Sheets (SDSs) for all hazardous materials used and stored on-site during performance of the contract. Contractor shall not supply or deliver any hazardous materials or chemicals to an AMC installation that are listed on EPA toxic chemical list without prior written approval from Chief of the EPCD.

During the performance of the contracted work, the Contractor shall ensure that hazardous material containers remain under the control of the user at all times and that containers are properly closed when the material is not in use. The Contractor shall not bring into a government installation any non-approved hazardous materials for use in the performance of their work. Where liquid materials are to be stored, the Contractor shall provide appropriate secondary containment and ensure containers are properly bonded and grounded where the chemical material requires it. In addition, the Contractor shall be responsible for maintaining an appropriate spill control kit at all times. All spills are reportable and shall be coordinated with the COR and the Chief of the EPCD. The Contractor shall, upon completion of each day’s work, clean, remove, and properly containerize or dispose of any resultant hazardous waste generated by the work performed under this contract, where required by the installation. Upon completion of the contracted work, the Contractor shall conduct final clean-up of the work site, containerize any hazardous material/waste debris, and coordinate with the EPCD for pick up and turn in for disposal. Any unused hazardous material and any non-ozone depleting substances or refrigerants brought in by the Contractor shall be recovered and removed from the installation by the Contractor prior to vacating the work site. The COR or an Environmental Advocate shall be contacted for approval of the final clean-up work.

L. Prevention of Storm Water Pollution: The Contractor shall perform, track, participate, implement, and comply with storm water pollution prevention minimum control measures, protocols, and best management practices (BMP) and ensure that water quality standards are not violated in accordance with all regulations and policies as they apply to the State Pollutant Discharge Elimination System general permit requirements and any of the installation's guidelines.

this project requires minimal digging outside. However, during any excavation, Best Management Practices to prevent storm water pollution are required in accordance with the Navy’s Stormwater Pollution Prevention Plan (SWPPP). The project falls under the Texas General Construction Permit (TX150000) but does not require a site specific SWPP because disturbance will be less than one acre. • The Contractor shall control all pollutants, including waste materials and demolition debris that occur onsite and shall be handled and disposed of in a manner that does not cause contamination of storm water. Good housekeeping and preventative measures shall be taken at all times to ensure that the site will be kept clean, well-organized, and free of debris. All spills are reportable and shall be coordinated with the COR and the Chief of the EPCD. No discharges to the stormwater system or wastewater systems are allowed without explicit approval from the COR and the Chief of the EPCD.

M. Protection of Work Site Resources: Contractor shall confine all activities to areas defined by the drawings and specifications. Prior to the beginning of any work, the Contractor shall identify any land resources to be preserved within the work area. Except in areas indicated on the drawings or specified to be cleared, the Contractor shall not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, grasses, topsoil, and landforms. The Contractor shall provide effective protection for land and vegetative resources at all times. Prior to site clearing and grubbing, or any sort of outdoor construction activity, the Contractor shall coordinate harvesting of saleable timber with the Chief of the EPCD. Contractor shall notify the Chief of the EPCD if any trees are required to be disposed or removed. The Contractor is not authorized to remove or dispose of any tree greater than 6 inches in diameter unless permission has been granted in writing by the Chief of the EPCD.

N. Prevention of Spills: The Contractor shall follow NASCC's Spill Prevention, Control, and Counter Measure (SPCC) Plan and reference the Corpus Christi Army Depot's (CCAD's) Spill Prevention Control and Countermeasures Plan (SPCCP) and Installation Spill Contingency Plan (ISCP) if transporting, processing, storing, or in any way managing hazardous waste, hazardous material, petroleum-oils-lubricants, or other restricted items. The Contractor shall ensure secondary containment is in place any time liquid materials are stored on-site and shall provide his or her own spill response supplies and have them readily available at each work site. In case of a spill, the person in control of the spill site, or their designated representative, shall take appropriate action to protect workers and bystanders; contain the spill (if it can be done safely); secure the spill site; restrict ignition sources; and immediately contact the installation Fire and Emergency Services (Fire Department), the COR and the Chief of the EPCD. Contractors storing 1,320 gallons or more of any oil-based product in an aboveground storage tank at a construction site shall follow NASCC's SPCC Plan. The Contractor shall immediately respond to actual emergencies and accidents, prevent or mitigate associated adverse environmental impacts, and contact the installation's Fire and Emergencies Services.

P. Corrective Action for Noncompliance: Contractor shall take immediate corrective action when given a verbal or written notice of environmental noncompliance or nonconformance by the COR or the Chief of the EPCD. Failure or refusal by the Contractor to comply promptly may be grounds for the Contracting Officer to invoke the appropriate contractual remedies. This may cause all or part of the work to be stopped immediately until satisfactory corrective action has been taken by the Contractor.

Q. Mercury: Mercury is prohibited, unless specified otherwise, with the exception of mercury vapor lamps and fluorescent lamps. Dumping of mercury-containing materials and devices such as mercury vapor lamps, fluorescent lamps, and mercury switches in rubbish containers is prohibited. Contractors shall remove any mercury vapor lamps, fluorescent lamps or mercury containing switches without breaking, pack them to prevent breakage, and transport them out of the activity in an unbroken condition for disposal as directed by COR or the Chief of the EPCD. The Contractor shall immediately report any instances of breakage or mercury spillage to the Chief of the EPCD and the Contracting Officer. The Contractor shall contact the EPCD any time there is a need for cleanup of a mercury spill area resulting from any work under this contract.

R. Universal Waste / e-Waste Management: Universal waste including, but not limited to, some mercury containing building products such as fluorescent lamps, mercury vapor lamps, high pressure sodium lamps, CRTs, batteries, aerosol paint containers, electrical equipment containing PCBs, and consumed electronic devices, shall be managed in accordance with applicable environmental law and installation instructions. The Contractor shall coordinate the management of these types of waste with the COR and the Chief of the EPCD.

S. Pollution Prevention / Hazardous Waste Minimization: The Contractor shall implement practices that reduce, eliminate, or prevent pollution at the source and make a conscious effort to minimize the use of hazardous materials and the generation of hazardous waste. Contractor shall consult with the EPCD for suggestions and to obtain a copy of the installation's pollution prevention/hazardous waste minimization plan for use as reference material to reduce environmental impacts generated through their work.

ATTACHMENT 6 / Security Requirements

CAO: April 2019

ADDITIONAL SECURITY REQUIREMENTS FOR CONTRACTS PERFORMED AT CORPUS CHRISTI

ARMY DEPOT

Place these security requirements in all Statement of Works (SOW’s) and Performance Work Statements (PWS’s) for contracts performed at Corpus Christi Army Depot (CCAD).

*******************…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .