JR3 RFI Questions and Answers_7 Dec 23.docx
DOCX document 24 KB Posted
- Attached to
- Joint Reduced Range Rocket
- Solicitation number
- PANRSA23P0000016158
About this file
This document provides questions and answers related to a Request for Information solicitation number PANRSA23P0000016158 from the Department of the Army Materiel Command Contracting Command Redstone Arsenal for a Joint Reduced Range Rocket. The solicitation seeks either a free flight or guided rocket with a desired range of 7.5 to 15 kilometers and accuracy of no more than 30 meters from targeted point. Offerors are asked to address challenges and capabilities related to firing above populated areas as part of system performance in their Technical Information Paper. Questions and answers clarify that integration with AFATDS is not required, that an initial or follow on capability for a flash/bang/smoke warhead is desirable, and that offerors should identify field or production reload requirements as part of their human factors assessment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| JR3 RFI Questions and Answers_Rev 01_12 Dec 23.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Notice ID: PANRSA23P0000016158 7 December 2023 Request for Information: Joint Reduced Range Rocket
Questions and Answers
1. Paragraph II 6. Please clarify if the request is for a Free Flight Rocket or a Guided Rocket (The dispersion of a FF rocket C.E.P fired to 15km is more than 150m)? The Request for Information does not presuppose a recommended solution. Offerors can provide either Free flight, trajectory correct, or both. Paragraph II.4 identifies the desired range impact minimum (7.5 to 8km) and maximum (15 km) If the requirement is for a Guided Rocket, is the required accuracy 30m max.? Paragraph II.6 identifies that accuracy should be between “no less than 25-30m of targeted point” and no more than “2km fire support safety distance from impact”
2. Paragraph II 10. Who is responsible for the integration of the munition with the AFADTS? This RFI does not require the offeror to integrate with the Army Field Artillery Tactical Data System (AFATDS). Paragraph II.5 identifies the requirement to “be capable of integrating with the current Ml142/M270 SW suite”
3. Paragraph II 11. Is the requested warhead at the first stage inert? Paragraph II.11 identifies “The ability to see a flash/bang/smoke as an initial or follow on increment/update is desirable”. This can be in the initial increment or identified as a follow on capability.
4. Paragraph II 12. Is there a requirement to enable firing above populated area? Paragraph II.12 identifies that the munition “Should be cleared to fire over all personnel and man-made structures within all launcher exclusion areas.” Offerors should address challenges/capability to firing above populated areas as part of their assessment of system performance (Paragraph III.2) in their Technical Information Paper.
5. Paragraph II 13. At what level is the reloading expected; field or production? Offerors should identify as part of their Technical Information Paper, the Human Factors (Paragraph III.8) for either field or production reload requirements.