- Replace Doors at OMS and Training Bldg/Paint OMS Ceiling; Farrell, PA Federal contract opportunity
- Solicitation number
- W15QKN-20-Q-5363
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| PA027-Farrell-A2-CSS 17022-SOW-Replace doors at OMS and Training Bldg.docx | DOCX document | |
| PA027-Farrell-A2-CSS 17022-Farrell Motor Pool Door.jpg | JPG image | |
| PA027 Farrell A2 CSS 5003 SOW Paint OMS ceilings V4 10 25 2019.DOCX | DOCX document | |
| PA027 Farrell A2 CSS 5003 Floor Plan Paint OMS Ceilings .pdf | ||
| PA027 Farrell A2 CSS 5003 SOO Paint OMS ceilings 10 25 2019.DOCX | DOCX document | |
| PA027 Farrell A2 CSS 5003 Pictures Paint the OMS ceiling and convert the tool storage room int.pptx | PPTX presentation |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Objectives
99th Readiness Division Directorate of Public Works Fort Dix, New Jersey 08640
The Statement of Objectives (SOO) identifies the broad, basic, top-level objectives of an acquisition/procurement.
| Date: |
| June 6, 2019 |
| Title: |
| PA027- Replacement of Doors – Training Center and Motor Pool |
| CSS# |
| 17022 |
| RFOS: |
| Scott Kawski |
| Center: |
| PA027 - Pendel-Caminiti USARC |
| Field Eng. Tech.: |
| John Daley |
| Address: |
| 950 Sharon New Castle Rd., Farrell, PA 16121 |
| AFOS: |
| Cindy Croyle |
| BLDG MGR: |
| John Cidila |
| Other POC: |
| Gary Shadowens |
Other POC:
1. Overall Objective:
Replace 2 man doors and 1 hazmat door on the Motor Pool Building. Covert 2 single office doors to Dutch doors with shelves. Convert one double and one single door in supply with Dutch doors.
2. General Requirements:
Replace doors, frames, hardware and thresh holds
3. Impact of Deficiency:
Doors are all rusting through and Dutch doors are request for supplies
4. Rough Estimate(s):
35,000
5. Expected Results of Completed Project:
New Doors
6. Attachments:
Picture image1.png image2.png