PA_Prevailing_Wage_Rates-_Ft_Pitt.pdf
PDF 22 KB Posted
- Attached to
- Fort Pitt Park Mine Stabilization
- Solicitation number
- 2026-IFB-194
- Issued by
- Allegheny County, Philadelphia City, Pennsylvania
About this file
This is a Prevailing Wage Rates document from the Commonwealth of Pennsylvania applicable to the Fort Pitt Park Mine Stabilization project in Pittsburgh. The document establishes the mandatory wage rates that must be paid to workers on this public works project conducted by the City of Pittsburgh Office of Management and Budget on behalf of the Department of Public Works. The prevailing wage rates specified in this document apply to all construction and related labor performed on the mine stabilization work and must be adhered to by all bidders and contractors awarded work under this solicitation.
The prevailing wage rates are determined by the Pennsylvania Department of Labor and Industry and represent the minimum compensation required for various classifications of workers involved in construction activities. These rates ensure that workers on publicly funded projects receive standardized, competitive wages across different trade classifications including general laborers, skilled trades, and specialized positions. All bidders responding to the Fort Pitt Park Mine Stabilization solicitation must incorporate these established wage rates into their cost proposals and maintain compliance throughout project execution.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Name: Fort Pitt Park Mine Stabilization
General Description: The City of Pittsburgh Office of Management and Budget, on behalf of the Department of Public Works, is soliciting bids from qualified firms for Fort Pitt Park Mine Stabilization.
Project Locality City of Pittsburgh
Awarding Agency: City of Pittsburgh
Contract Award Date: 10/9/2026
Serial Number: 26-08261
Project Classification: Heavy/Highway
Determination Date: 9/14/2026
Assigned Field Office: Pittsburgh
Field Office Phone Number: (412)565-5300
Toll Free Phone Number: (877)504-8354
Project County: Allegheny County
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Commonwealth of Pennsylvania Department of Labor & Industry Report Date: 9/14/2026 Page 1 of 5
Project: 26-08261 - Building Effective Date
Expiration Date
Hourly Rate Fringe Benefits
Total
Asbestos & Insulation Workers 8/1/2025 $45.10 $30.31 $75.41
Boilermakers 6/1/2016 $40.90 $27.61 $68.51
Bricklayer 12/1/2025 $42.00 $26.59 $68.59
Bricklayer 6/1/2026 $42.65 $26.94 $69.59
Carpenters - Piledriver/Welder 1/1/2025 $43.38 $22.72 $66.10
Carpenters - Piledriver/Welder 1/1/2026 $44.63 $23.47 $68.10
Carpenters, Drywall Hangers, Framers, Instrument Men, Lathers, Soft Floor Layers
6/1/2026 $42.11 $23.36 $65.47
Carpenters, Drywall Hangers, Framers, Instrument Men, Lathers, Soft Floor Layers
6/1/2027 $43.26 $24.35 $67.61
Carpenters, Drywall Hangers, Framers, Instrument Men, Lathers, Soft Floor Layers
6/1/2028 $44.45 $25.19 $69.64
Carpenters, Drywall Hangers, Framers, Instrument Men, Lathers, Soft Floor Layers
6/1/2029 $45.72 $26.01 $71.73
Cement Masons 6/1/2025 $35.52 $25.64 $61.16
Cement Masons 6/1/2026 $36.02 $26.14 $62.16
Drywall Finisher 6/1/2025 $35.16 $25.98 $61.14
Drywall Finisher 6/1/2026 $36.59 $27.30 $63.89
Electricians & Telecommunications Installation Technician
12/27/2024 $50.86 $32.69 $83.55
Electricians & Telecommunications Installation Technician
12/26/2025 $53.11 $33.72 $86.83
Elevator Constructor 1/1/2025 $61.07 $40.05 $101.12
Elevator Constructor 1/1/2026 $63.71 $40.89 $104.60
Glazier 9/1/2024 $37.06 $31.89 $68.95
Glazier 9/1/2025 $38.70 $33.75 $72.45
Iron Workers 6/1/2025 $41.50 $37.36 $78.86
Iron Workers 6/1/2026 $43.50 $37.91 $81.41
Laborers (Class 01 - See notes) 1/1/2025 $27.32 $19.96 $47.28
Laborers (Class 01 - See notes) 1/1/2026 $27.82 $20.46 $48.28
Laborers (Class 02 - See notes) 1/1/2025 $27.47 $19.96 $47.43
Laborers (Class 02 - See notes) 1/1/2026 $27.97 $20.46 $48.43
Laborers (Class 03 - See notes) 1/1/2025 $30.47 $19.96 $50.43
Laborers (Class 03 - See notes) 1/1/2026 $30.97 $20.46 $51.43
Landscape Laborer (Skilled) 1/1/2025 $25.79 $18.78 $44.57
Landscape Laborer (Skilled) 1/1/2026 $26.79 $19.03 $45.82
Landscape Laborer (Tractor Operator) 1/1/2025 $26.09 $18.78 $44.87
Landscape Laborer (Tractor Operator) 1/1/2026 $27.09 $19.03 $46.12
Landscape Laborer 1/1/2025 $25.37 $18.78 $44.15
Landscape Laborer 1/1/2026 $26.37 $19.03 $45.40
Millwright 6/1/2020 $41.68 $20.32 $62.00
Operators (Class 01 - see notes) 6/1/2025 $42.72 $24.79 $67.51
Operators (Class 01 - see notes) 6/1/2026 $43.74 $25.29 $69.03
Operators (Class 02 -see notes) 6/1/2025 $36.67 $24.79 $61.46
Operators (Class 02 -see notes) 6/1/2026 $37.67 $25.29 $62.96
Operators (Class 03 - See notes) 6/1/2025 $33.88 $24.79 $58.67
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Report Date: 9/14/2026 Page 2 of 5
Project: 26-08261 - Building Effective
Expiration Date
Hourly Rate Fringe Benefits
Total
Operators (Class 03 - See notes) 6/1/2026 $34.88 $25.29 $60.17
Painters Class 6 (see notes) 6/1/2025 $34.16 $25.81 $59.97
Painters Class 6 (see notes) 6/1/2026 $35.26 $26.51 $61.77
Piledrivers 1/1/2026 $43.13 $23.47 $66.60
Plasterers 6/1/2024 $33.14 $21.04 $54.18
Plasterers 6/1/2026 $34.59 $22.59 $57.18 plumber 6/1/2026 $58.05 $25.87 $83.92 plumber 6/1/2027 $61.15 $25.87 $87.02
Pointers, Caulkers, Cleaners 12/1/2025 $41.50 $22.50 $64.00
Pointers, Caulkers, Cleaners 6/1/2026 $42.20 $22.80 $65.00
Roofers 12/1/2025 $41.21 $21.46 $62.67
Roofers 6/1/2026 $42.00 $23.17 $65.17
Sheet Metal Workers 7/1/2025 $45.00 $35.16 $80.16
Sheet Metal Workers 7/1/2026 $46.75 $36.61 $83.36
Sign Makers and Hangars 7/15/2025 $33.48 $26.41 $59.89
Sign Makers and Hangars 7/15/2026 $36.38 $25.01 $61.39
Sprinklerfitters 1/1/2026 $46.14 $28.30 $74.44
Sprinklerfitters 7/1/2026 $48.64 $28.30 $76.94
Steamfitters 6/1/2025 $50.20 $31.02 $81.22
Steamfitters 6/1/2026 $53.05 $31.27 $84.32
Stone Masons 12/1/2025 $44.10 $25.22 $69.32
Stone Masons 6/1/2026 $44.70 $25.62 $70.32
Terrazzo Finisher 12/1/2025 $42.75 $19.51 $62.26
Terrazzo Finisher 6/1/2026 $43.82 $19.94 $63.76
Terrazzo Mechanics 12/1/2025 $42.15 $21.76 $63.91
Terrazzo Mechanics 6/1/2026 $43.22 $22.19 $65.41
Tile Finisher 12/1/2025 $33.99 $18.71 $52.70
Tile Finisher 6/1/2026 $34.82 $18.98 $53.80
Tile Setter 12/1/2025 $40.80 $23.25 $64.05
Tile Setter 6/1/2026 $41.66 $23.49 $65.15
Truckdriver class 1(see notes) 1/1/2025 $36.43 $23.21 $59.64
Truckdriver class 1(see notes) 1/1/2026 $37.93 $23.71 $61.64
Truckdriver class 2 (see notes) 1/1/2025 $36.89 $23.52 $60.41
Truckdriver class 2 (see notes) 1/1/2026 $38.39 $24.02 $62.41
Window Film / Tint Installer 10/1/2019 $25.00 $2.63 $27.63
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Report Date: 9/14/2026 Page 3 of 5
Project: 26-08261 - Heavy/Highway Effective
Expiration Date
Hourly Rate Fringe Benefits
Total
Carpenter 1/1/2026 $42.60 $22.84 $65.44
Carpenter Welder 1/1/2025 $42.85 $22.09 $64.94
Carpenter Welder 1/1/2026 $44.10 $22.84 $66.94
Carpenters - Piledriver/Welder 1/1/2025 $43.38 $22.72 $66.10
Carpenters - Piledriver/Welder 1/1/2026 $44.63 $23.47 $68.10
Cement Finishers 1/1/2024 $35.14 $26.30 $61.44
Cement Finishers 1/1/2025 $35.94 $27.50 $63.44
Cement Masons 1/1/2020 $32.84 $21.10 $53.94
Electric Lineman 6/3/2024 $53.97 $31.05 $85.02
Electric Lineman 6/2/2025 $57.10 $31.63 $88.73
Electricians & Telecommunications Installation Technician
12/26/2025 $54.16 $32.69 $86.85
Iron Workers (Bridge, Structural Steel, Ornamental, Precast, Reinforcing)
6/1/2025 $41.50 $37.36 $78.86
Iron Workers (Bridge, Structural Steel, Ornamental, Precast, Reinforcing)
6/1/2026 $43.50 $37.91 $81.41
Laborers (Class 01 - See notes) 1/1/2025 $33.70 $26.00 $59.70
Laborers (Class 01 - See notes) 1/1/2026 $34.70 $27.00 $61.70
Laborers (Class 02 - See notes) 1/1/2025 $33.86 $26.00 $59.86
Laborers (Class 02 - See notes) 1/1/2026 $34.86 $27.00 $61.86
Laborers (Class 03 - See notes) 1/1/2025 $34.25 $26.00 $60.25
Laborers (Class 03 - See notes) 1/1/2026 $35.25 $27.00 $62.25
Laborers (Class 04 - See notes) 1/1/2025 $34.70 $26.00 $60.70
Laborers (Class 04 - See notes) 1/1/2026 $35.70 $27.00 $62.70
Laborers (Class 05 - See notes) 1/1/2025 $35.11 $26.00 $61.11
Laborers (Class 05 - See notes) 1/1/2026 $36.11 $27.00 $63.11
Laborers (Class 06 - See notes) 1/1/2025 $31.95 $26.00 $57.95
Laborers (Class 06 - See notes) 1/1/2026 $32.95 $27.00 $59.95
Laborers (Class 07 - See notes) 1/1/2025 $34.70 $26.00 $60.70
Laborers (Class 07 - See notes) 1/1/2026 $35.70 $27.00 $62.70
Laborers (Class 08 - See notes) 1/1/2025 $36.20 $26.00 $62.20
Laborers (Class 08 - See notes) 1/1/2026 $37.20 $27.00 $64.20
Millwright 6/1/2025 $49.72 $23.72 $73.44
Operators (Class 01 - see notes) 1/1/2025 $40.39 $24.23 $64.62
Operators (Class 01 - see notes) 1/1/2026 $41.96 $24.66 $66.62
Operators (Class 02 -see notes) 1/1/2025 $40.13 $24.23 $64.36
Operators (Class 02 -see notes) 1/1/2026 $41.70 $24.66 $66.36
Operators (Class 03 - See notes) 1/1/2025 $36.48 $24.23 $60.71
Operators (Class 03 - See notes) 1/1/2026 $38.05 $24.66 $62.71
Operators (Class 04 - See notes) 1/1/2025 $36.02 $24.23 $60.25
Operators (Class 04 - See notes) 1/1/2026 $37.59 $24.66 $62.25
Operators (Class 05 - See notes) 1/1/2025 $35.77 $24.23 $60.00
Operators (Class 05 - See notes) 1/1/2026 $37.34 $24.66 $62.00
Operators Class 1-A 1/1/2025 $43.39 $24.23 $67.62
Operators Class 1-A 1/1/2026 $44.96 $24.66 $69.62
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Report Date: 9/14/2026 Page 4 of 5
Project: 26-08261 - Heavy/Highway Effective
Expiration Date
Hourly Rate Fringe Benefits
Total
Operators Class 1-B 1/1/2025 $42.39 $24.23 $66.62
Operators Class 1-B 1/1/2026 $43.96 $24.66 $68.62
Painters Class 1 (see notes) 6/1/2022 $34.45 $22.82 $57.27
Painters Class 2 (see notes) 6/1/2025 $40.36 $25.81 $66.17
Painters Class 2 (see notes) 6/1/2026 $41.66 $26.51 $68.17
Painters Class 3 (see notes) 6/1/2025 $43.68 $25.81 $69.49
Painters Class 3 (see notes) 6/1/2026 $45.08 $26.51 $71.59
Painters Class 4 (see notes) 6/1/2019 $28.20 $20.06 $48.26
Painters Class 5 (see notes) 6/1/2019 $22.91 $20.06 $42.97
Pile Driver Divers (Building, Heavy, Highway) 1/1/2025 $62.82 $22.72 $85.54
Pile Driver Divers (Building, Heavy, Highway) 1/1/2026 $64.70 $23.47 $88.17
Piledrivers 1/1/2025 $41.88 $22.72 $64.60
Piledrivers 1/1/2026 $43.13 $23.47 $66.60
Steamfitters (Heavy and Highway - Gas Distribution) 5/1/2022 $48.43 $40.28 $88.71
Truckdriver class 1(see notes) 1/1/2026 $37.93 $23.71 $61.64
Truckdriver class 2 (see notes) 1/1/2026 $38.39 $24.02 $62.41
BUREAU OF LABOR LAW COMPLIANCE
PREVAILING WAGES PROJECT RATES
Report Date: 9/14/2026 Page 5 of 5
File details come from the government source that posted it. Updated .