About this file
This is a Public Water Supply Permit issued by the Pennsylvania Department of Environmental Protection (DEP), Bureau of Safe Drinking Water, to the Pennsylvania Department of Transportation for the operation of water supply facilities at the I-70 Warfordsburg Westbound Welcome Center in Bethel Township, Fulton County. The permit (No. 2924505) authorizes construction and operation of a groundwater-based system including well pump replacement, pressure tanks, ion exchange softening, cartridge filtration, reverse osmosis treatment, acid neutralization, and sodium hypochlorite disinfection. The project is known as the I-70 Warfordsburg Westbound Welcome Center: Well Pump Replacement & Water Treatment Upgrades. The approved pumping rate for Well B is 27 gallons per minute, with maximum instantaneous flow rates specified for each treatment component: 22.8 gpm for ion exchange softening, 11.1 gpm for cartridge filtration and acid neutralization, and 20 gpm for the disinfection contact tank. The permit was issued on January 28, 2025.
The permit establishes eight special conditions governing facility operations and maintenance. Key operational requirements include submission of a Certificate of Construction upon project completion, proper disinfection and coliform testing before operation begins, weekly monitoring of free chlorine residuals and total dissolved solids concentrations, quarterly sampling for iron and manganese analysis, and maintenance of equipment logs, water quality complaint logs, and chemical usage records on site for minimum five-year retention periods. All chemicals must meet NSF standards, and acid neutralizer media must be replaced every 6 to 12 months. Critically, the permittee must retain a properly certified drinking water operator at all times, with a requirement to employ a replacement operator within 10 days if the current operator's contract is terminated. No deviations from approved plans and specifications affecting treatment processes or water quality may be made without written Department approval.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
3900-PM-BSDW0043 Rev. 7/2023 COMMONWEALTH OF PENNSYLVANIA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
BUREAU OF SAFE DRINKING WATER
PUBLIC WATER SUPPLY PERMIT
No. 2924505
A. PERMITTEE: (Name and Address)
Pennsylvania Department of Transportation
400 North Street, 6th Floor
Harrisburg, PA 17105
B. PROJECT/PLANT LOCATION
PWS ID No. 4290805
Municipality Bethel Township
County Fulton County
C. THIS PERMIT APPROVES FOR: 1. CONSTRUCTION 2. OPERATION OF FACILITIES
AS INDICATED BELOW: Approved Under Construction Permit No.
Source Facilities/Treatment BVRB
Groundwater Impoundment General Corrosion Control Bottled Water System
Purchased Groundwater Clarification Corrosion Control for lead/copper Bulk Water Hauling System
Surface Water Filtration Disinfection Vended Water System
Purchased Surface Water Iron and Manganese Treatment Pump Station(s) Retail Water Facility
Ion Exchange Reverse Osmosis
Fluoridation Finished Water Storage
Distribution Facility Other Well pump replacement, pressure tanks
KNOWN AS: I-70 Warfordsburg Westbound Welcome Center: Well Pump Replacement & Water Treatment
Upgrades
LIMIT OF AUTHORIZATION
YOU ARE HEREBY AUTHORIZED TO CONSTRUCT OR OPERATE, AS INDICATED ABOVE, PROVIDED THAT
FAILURE TO COMPLY WITH CHAPTER 109, OF THE RULES AND REGULATIONS OF THE DEPARTMENT OF
ENVIRONMENTAL PROTECTION OR THE TERMS OR CONDITIONS OF THIS PERMIT SHALL VOID THE AUTHORITY
GIVEN TO THE PERMITTEE BY THE ISSUANCE OF THE PERMIT.
THE PLANS, SPECIFICATIONS, REPORTS AND SUPPORTING DOCUMENTS SUBMITTED AS PART OF THE PERMIT
APPLICATION BECOME PART OF THE PERMIT.
NO DEVIATIONS FROM APPROVED PLANS OR SPECIFICATIONS AFFECTING THE TREATMENT PROCESS OR
QUALITY OF WATERS SHALL BE MADE WITHOUT WRITTEN APPROVAL FROM THE DEPARTMENT.
THIS PERMIT IS ISSUED BY THE DEPARTMENT OF ENVIRONMENTAL PROTECTION UNDER THE AUTHORITY OF
THE PENNSYLVANIA SAFE DRINKING WATER ACT, THE ACT OF MAY 1, 1984 (P.L. 206, NO. 43). OPERATION
SHALL COMPLY WITH THE PROVISIONS OF CHAPTER 109 ADOPTED UNDER THE AUTHORITY IN SECTIONS 4
AND 6(e) OF THE PENNSYLVANIA SAFE DRINKING WATER ACT.
THIS PERMIT IS SUBJECT TO THE ATTACHED SPECIAL CONDITIONS 1 through 8 .
PERMIT ISSUED DEPARTMENT OF ENVIRONMENTAL PROTECTION
Date: January 28, 2025 By: Joseph M. Mattucci Joseph M. Mattucci, Program Manager
Safe Drinking Water Program - Southcentral Regional Office
January 28, 2025
SAFE DRINKING WATER PROGRAM
Pennsylvania Department of Transportation
I-70 Warfordsburg Westbound Welcome Center
Public Water Supply Permit No. 2924505
Page 1 Bethel Township
Fulton County
This permit is issued subject to all Department of Environmental Protection Rules and Regulations now in force and the following Special Conditions:
1. Upon completion of construction in accordance with the approved plans and specifications, the permittee shall submit the Certificate of Construction to the Department. Certification shall state that the work was completed in accordance with the approved plans and specifications and shall be signed by the professional engineer or other person responsible for the work. Certification shall include that adequate operation and maintenance information for the approved facilities is available, on site, for use by the public water system’s personnel.
2. Prior to issuance of an Operation Permit, the facilities shall be properly disinfected in accordance with 25 PA Code, Chapter 109.711 of the Safe Drinking Water regulations and by the American
Water Works Association (AWWA). The facilities shall be tested for coliform bacteria in accordance with AWWA standards. The samples shall be analyzed by a Department-accredited laboratory. Copies of the satisfactory microbiological test results shall be submitted with the
Certificate of Construction.
3. The approved pumping rate of Well B is 27 gallons per minute (gpm).
4. Ion Exchange Softening:
A. The maximum instantaneous flow rate through the treatment system shall not exceed 22.8 gpm.
B. Salt used in the softener shall be NSF Standard 60 certified.
5. TDS Removal:
A. No more than 51% of the total system flow shall bypass the TDS treatment.
B. Cartridge Filters:
1. The maximum instantaneous flow rate through the treatment system shall not exceed 11.1 gpm.
2. The cartridge filter shall be replaced by an ANSI/NSF Standard 61 certified cartridge filter.
C. Reverse Osmosis:
1. The permittee shall collect and analyze samples for total dissolve solids (TDS) concentrations from the raw water of Well B and finished water at Entry Point No. 101 at least weekly. The samples shall be analyzed by a Department accredited laboratory or by a properly certified operator using an appropriate calibrated field analytical test kit. A non-certified operator may also utilize an appropriate calibrated field analytical test kit, provided the analysis is conducted in accordance with standard operating procedures approved by the properly certified operator. These results shall be recorded on the monthly operating report.
January 28, 2025
SAFE DRINKING WATER PROGRAM
Pennsylvania Department of Transportation
I-70 Warfordsburg Westbound Welcome Center
Public Water Supply Permit No. 2924505
Page 2 Bethel Township
Fulton County
2. The permittee shall collect finished water samples from Entry Point No.101 once per calendar year quarter. The samples shall be analyzed by a Department accredited laboratory for iron and manganese and reported to the Department.
D. Acid Neutralizer:
1. The maximum instantaneous flow rate through the treatment system shall not exceed 11.1 gpm.
2. The acid neutralizer media shall be replaced by CSI NE10 pH neutralizing media only.
3. The acid neutralizer media shall be replaced at least every 6 months to 12 months (per CSI’s recommendations).
6. Sodium Hypochlorite Disinfection:
A. The maximum instantaneous flow rate through the contact tank shall not exceed 20 gpm and the minimum water level in Tank No. 2 shall not be less than 230 gallons (9” water level) in order to maintain a minimum of 20 minutes of disinfection contact time for Entry Point No. 101.
B. Sodium Hypochlorite used in the treatment system shall be NSF Standard 60 certified.
C. The Public Water System shall be monitored weekly for free chlorine at the entry point. Records of chlorine residual monitoring shall be kept onsite for a minimum of five years and made available to the Department upon request.
D. A water quality complaint log, equipment maintenance records, and chemical usage log shall be maintained onsite. These logs and records shall include the amount (gallons per day or inches per day) and mixing ratio of sodium hypochlorite fed daily.
7. An equipment maintenance log shall be maintained onsite. Records shall be kept for a minimum of five years and shall be made available to the Department upon request.
8. The permittee shall retain the services of a properly certified water operator for the public water system. In the event permittee terminates the contract of the properly certified operator, they shall employ a new, properly certified operator within 10 days.