GOGA_Marine_Drive_Bid_Schedule.pdf

PDF 150 KB Posted

Attached to
GOGA - FORT POINT MARINE DRIVE ROAD REHAB
Solicitation number
P16PS01710
Issued by

About this file

P06 - Solicitation Bid Pricing Scheduel

View the file

Other files

File Type Posted
Sol_P16PS01710_Amd_000002.pdf PDF
Sol_P16PS01710_Amd_000001.pdf PDF
GOGA_Marine_Drive_Specs_Final_5-6-16.pdf PDF
Subcontractor_Reference.docx DOCX document
Past_Performance_Quesionnaire.docx DOCX document
DB_CA29.pdf PDF
GOGA_Marine_Drive_Specs_Final_5-6-16.pdf PDF
Relevant_Prior_Experience.docx DOCX document
SF_24_Bid_Bond.pdf PDF
Fort_Point_Marine_Drive_Plan_Final_Stamped.pdf PDF
Sol_P16PS01710.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT LINE

ITEM NUMBER

(CLIN)

CONTRACT LINE ITEM (CLI) TITLE QUANTITY

UNIT OF

MEASURE

UNIT PRICE TOTAL PRICE

Mobilization/Demobilization & UPPP BMP's

1 Lump Sum $0.00

2 Traffic Control 1 Lump Sum $0.00

Marine Drive Cold Mill and Asphalt Overlay

5,950 SY $0.00

Replace Missing and Damaged Wheel Stops

75 Each $0.00

Signage, Striping, and Pavement Markings

1 Lump Sum $0.00

Removal of Existing Fort Point Striping and Pavement Markings

1 Lump Sum $0.00

$0.00

Bid Option A Drainage Channel Rehabilitation, Storm Drain Cleaning & CCTV Inspection

1 Lump Sum $0.00

CONTRACT PRICE SCHEDULE

TOTAL BASE PRICE (Contract Line Item Number 1 through 6)

SOLICITATION NUMBER: P16PS01710

PARK PMIS: GOGA PMIS 173200

DEVELOPED AREA: Fort Point PROJECT TITLE: Fort Point Road Rehabilitation Project

Notice: Refer to FAR Clause 52.217 5, Evaluation of Options, as prescribed in FAR 17. Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items and all option line items. Failure to do so may render the proposal unacceptable. On lump sum line items, provide the total price only. For all unit priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars. The Government reserves the right to award any or no options at or after the time of award.

At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the date of award. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgment of the Contracting Officer to offer the best value to the Government.

In addition to the offer that conforms to the solicitation documents, offerors are encouraged to submit alternate proposals that will result in cost savings to the Government. Such proposals shall clearly identity why the acceptance of the alternate proposal would be advantageous to the Government, see FAR Clause 52.215 1, Instructions to Offerors Competitive Acquisition Alternate II and DSC 36 Clause (Instructions for Submission of Offers and Other Information) in Section L of the Solicitation.