Text version
Solicitation Number – P16PS00832
VAFO Remediation
Remediation for the Asbestos Release Site Remedial Action at Valley Forge National Historical Park, Upper Merion Township, Montgomery County, PA
Attachment 6:
Section 01 2700
Definition of Contract Line Items April 15, 2016
012700- 1
DEFINITION OF CONTRACT LINE ITEMS
VAFO Remediation April 15, 2016
P16PS00832
SECTION 01 2700 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins. Specific details regarding activities to be completed for each contract line item are described in the Implementation of Supplemental Remedial Design for the Asbestos Release Site Remedial Action Performance Work Statement and the Supplemental Remedial Design (RD) Report, Volumes 1 through 4.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 1: Prepare Project Deliverables.
1. This item consists of preparing a draft and final Remedial Action Work Plan (RAWP) prior to the initiation of any on-site remedial activities and a close-out report at the completion of work. The RAWP shall provide all of the elements to be followed during implementation of the supplemental remedial action including the technical approach, project organization (including personnel), communication, reporting, remedial schedule, and subcontractor management. In addition the RAWP shall include the following specific plans as detailed in the PWS:
• Site Management Plan
• Contractor Health and Safety Plan
• Quality Assurance Project Plan
• Construction Quality Assurance Plan
• Contaminated Soil Excavation and Handling Plan
• Waste Characterization and Disposal Plan
• Transportation and Disposal Plan
• Decontamination Plan
• Planting and Restoration Plan
This item also includes preparation of a close-out report at the completion of work that fully documents and substantiates the work performed; results of all air monitoring; clean fill documentation; waste manifests; record drawings (as-built drawings) and a certification by a licensed Professional Engineer of the completion of the work.
2. No measurement of quantities will be made.
B. Contract Line Item No. 2: Site Preparation/Remediation/Restoration-MAR - AOC.
1. This item consists of all activities related to the site preparation/remediation and restoration of the Maintenance Area Ruins (MAR) Area of Concern (AOC), as detailed
012700- 2
DEFINITION OF CONTRACT LINE ITEMS
VAFO Remediation April 15, 2016
P16PS00832
in the PWS and Supplemental RD Report.
C. Contract Line Item No. 3: Site Preparation/Remediation/Restoration- FKP - AOC.
restoration of the Former Keene Plant (FKP) AOC, as detailed in the PWS and Supplemental RD Report.
D. Contract Line Item No. 4: Site Preparation/Remediation/Restoration-HB - AOC.
restoration of the Historic Bridge (HB) AOC, as detailed in the PWS and Supplemental RD Report.
E. Contract Line Item No. 5: Site Preparation/Remediation/Restoration- SAQ- AOC.
restoration of the Small Additional Quarry (SAQ) AOC, as detailed in the PWS and Supplemental RD Report.
F. Contract Line Item No. 6: Site Preparation/Remediation/Restoration-WCRS - AOC.
restoration of the Waste Channel Railbed South (WCRS) AOC, as detailed in the PWS and Supplemental RD Report.
G. Contract Line Item No. 7: Removal of Brown Vinyl Fencing and Signage
1. This item consists of removal of existing brown vinyl fencing (“flex fence”) and warning signage installed by NPS around portions of the site (see Supplemental RD Report, Volume 1, Section 4.7 and Figure 4-12).
H. Contract Line Item No. 8: Monitoring Well Closure
1. This item consists of performing all activities related to closure of eight monitoring wells installed on the site (see Supplemental RD Report, Volume 1, Section 4.8 and Appendix B).
END OF SECTION 012700
| Attachment 6 |
| Solicitation Number – P16PS00832 |
| VAFO Remediation |
| Remediation for the Asbestos Release Site Remedial Action |
| at Valley Forge National Historical Park, |
| Upper Merion Township, Montgomery County, PA |
| Attachment 6: |
| Section 01 2700 |
| Definition of Contract Line Items |
| April 15, 2016 |
Apr 26 VAFO Section 01 2700 Definition of Contract Line Items 4 15 2016