This document outlines the scope of work for a federal construction contract to replace the roof at the Fort Detrick VA Medical Center in Frederick, Maryland. The Department of Veterans Affairs is seeking a contractor to remove the existing ballast, EPDM and roof insulation. The selected contractor will then install new energy star roof insulation and thermoplastic polyolefin sheet roofing with a minimum 30-year warranty. Additional work includes removing and reinstalling the lightening protection, metal coping, gutters and downspouts as necessary. The rooftop air conditioning unit must be removed and reinstalled to allow for roof replacement. Bidders should note the solicitation number 36C24522B0007 and project number 613-22-138 for reference. The goal of this project is to provide an upgraded TPO roof to replace the existing leaking roof at the Fort Detrick VA Medical Center facility.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work
Fort Detrick CBOC
Project Number: 613-22-138
Contractor shall furnish all labor, tools, material, equipment, supplies and supervision necessary for Roof replacement as shown on the attached drawing at
Fort Detrick MD CBOC in accordance with VA specifications and drawings.
1. Overview:
1.1 Government Agency Department and Address:
Martinsburg Va Medical Center-VISN 5 -Martinsburg WV
1.2 Project title, Number and Location:
Project Title – Fort Detrick Roof replacement.
Location- 1433 Porter ST. Fredrick MD, 21702
Project Number- 613-22-138
A. This project will engage a Contractor to re move existing Ballast, EPDM and roof Insulation. Install Energy Star Roof Insulation and Thermoplastic
Polyolefin
(TPO) White in color sheet roofing, adhered or Mechanically Fastened to existing roof Decking.
B. Items of work to include but not limited:
1. Remove existing Ballast, EPDM, and Roof Insulation to Existing Steel decking.
2. Remove all Debris from site.
3. Replace existing insulation with an Energy Star Taper design by supplier to route all water to existing drains.
4. Remove and reinstall existing Lightening Protection.
5. Remove and reinstall existing Coping metal.
6. Remove and reinstall existing Gutters and Downspout as needed.
7. Install an Energy Star Thermoplastic Polyolefin (TPO) white in color sheet roofing with a minimum of a 30year Warranty
8. Install walkway pads per Specs.
9. Roof top (AHU) Air Condition Unit (Per Drawings and Spec) will need removed prior to demo; Existing unit will need to be installed at a later date. This portion of the project will need to be Scheduled with the VA
COR.
10. AHU during the install should be mounted on existing roof pavers with addition TPO slip welded in place underneath the pavers.
11. A Penetration pocket for the AHU Line sets to be installed during new work.
12. Contractor to have a Stand by AHU to condition the IT closet prior to proceeding with removing the Roof top AHU.