P09-Final Specs 882 PGS-589A7-23-315 Fluoroscope .pdf
PDF 23 MB Posted
- Solicitation number
- 36C25525R0092
About this file
This document is a comprehensive specification file for site preparation for a Fluoroscope installation at the Robert J. Dole VA Medical Center in Wichita, Kansas. The project (VA Project #589A7-23-315) involves detailed technical specifications across multiple construction divisions, including architectural, structural, mechanical, electrical, and finish work required to prepare the site for a new fluoroscope room (Rooms 153D-1 and 153E-1).
Key specifications include non-structural metal framing, gypsum board installation, resilient flooring with heat-welded seams, acoustical ceiling systems, wall protection, painting, and specialized accessories. The specifications outline precise requirements for materials, installation methods, and quality standards, with a focus on sustainable construction practices. The project involves modifications to an existing medical facility, including installing new flooring, wall finishes, electrical systems, and preparing the space to accommodate medical imaging equipment. The specifications emphasize attention to detail in surface preparation, material selection, and installation techniques to ensure a high-quality medical facility environment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site Visit Attendance Roster.pdf | ||
| 36C25525R0092 0002.docx | DOCX document | |
| Prepopsal Conference Agenda.pdf | ||
| 36C25525R0092 0001.pdf | ||
| P09- Final DRAWINGS 56 PGS - Fluoroscope.pdf | ||
| 36C25525R0092_1.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
06-01-24
SITE PREPERATION FOR FLUOROSCOPE
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
SECTION NO DIVISION AND SECTION TITLES DATE
VOLUME 1 (Divisions 00 14)
DIVISION 00 - SPECIAL SECTIONS
00 01 10 Table of Contents, Volume 1,2 06-24 00 01 15 List of Drawing Sheets 05-20
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 11-21 01 32 16.15 Project Schedules (Small Projects Design/Bid/Build 01-24 01 33 23 Shop Drawings, Product Data, and Samples 11-23 01 35 26 Safety Requirements 05-24 01 42 19 Reference Standards 11-20 01 45 00 Quality Control 02-21 01 45 29 Testing Laboratory Services 11-18 01 45 35 Special Inspections 06-21 01 57 19 Temporary Environmental Controls 01-21 01 58 16 Temporary Interior Signage 07-15 01 74 19 Construction Waste Management 04-22 01 81 13 Sustainable Construction Requirements 10-17 01 91 00 General Commissioning Requirements 04-22
DIVISION 02 EXISTING CONDITIONS
02 41 00 Demolition 08-17
DIVISION 03 CONCRETE (NOT USED)
DIVISION 04 MASONRY (NOT USED)
DIVISION 05 METALS
05 50 00 Metal Fabrications 08-18
DIVISION 06 WOOD, PLASTICS AND COMPOSITES
06 20 00 Finish Carpentry 01-21
00 01 10-2
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 84 00 Firestopping 01-21 07 92 00 Joint Sealants 04-22
DIVISION 08 - OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-21 08 14 00 Interior Wood Doors 01-21 08 17 10 Integrated Door Assemblies 01-21 08 31 13 Access Doors and Frames 04-22 08 71 00 Door Hardware 03-24 08 71 13 Automatic Door Operators 01-21 08 71 13.11 Low Energy Power Assist Door Operators 01-21 08 80 00 Glazing 01-21 08 90 00 Louvers and Vents 01-21
DIVISION 09 FINISHES
09 05 16 Subsurface Preparation for Floor Finishes 01-21 09 06 00 Schedule for Finishes 01-21 09 22 16 Non-Structural Metal Framing 06-18 09 29 00 Gypsum Board 04-20 09 51 00 Acoustical Ceilings 12-18 09 65 13 Resilient Base and Accessories 01-21 09 65 16 Resilient Sheet Flooring 06-22 09 65 19 Resilient Tile Flooring 05-18 09 91 00 Painting 01-21
DIVISION 10 SPECIALTIES
10 26 00 Wall and Door Protection 01-21 10 28 00 Toilet, Bath, and Laundry Accessories 01-21
DIVISION 11 EQUIPMENT
11 73 00 Ceiling Mounted Patient Lift System 08-20
DIVISION 12 FURNISHINGS
12 32 00 Manufactured Wood Casework 01-21
DIVISION 13 - SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non-Structural
Components 01-21
13 49 00 Radiation Protection 01-21
00 01 10-3
DIVISION 14 CONVEYING EQUIPMENT (NOT USED)
VOLUME 2 (Divisions 21 48)
DIVISION 21- FIRE SUPPRESSION
21 13 13 Wet-Pipe Sprinkler Systems 06-15
DIVISION 22 PLUMBING
22 05 11 Common Work Results for Plumbing 01-23 22 05 23 General-Duty Valves for Plumbing Piping 09-20 22 07 11 Plumbing Insulation 09-19 22 08 00 Commissioning of Plumbing Systems 11-16 22 11 00 Facility Water Distribution 05-21 22 13 00 Facility Sanitary and Vent Piping 09-20 22 40 00 Plumbing Fixtures 05-24
DIVISION 23 HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 03-23 23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment 03-23
23 05 93 Testing, Adjusting, and Balancing for HVAC 03-23 23 07 11 HVAC and Boiler Plant Insulation 02-20 23 08 00 Commissioning of HVAC Systems 03-23 23 31 00 HVAC Ducts and Casings 03-23 23 37 00 Air Outlets and Inlets 03-23
DIVISION 25 INTEGRATED AUTOMATION (Not Used)
DIVISION 26 ELECTRICAL
26 05 11 Requirements for Electrical Installations 11-22 26 05 19 Low-Voltage Electrical Power Conductors and Cables 11-22 26 05 26 Grounding and Bonding for Electrical Systems 11-22 26 05 33 Raceway and Boxes for Electrical Systems 11-22 26 05 36.26 Wireways for Radiology Equipment 11-22 26 05 73 Overcurrent Protective Device Coordination Study 11-22 26 08 00 Commissioning of Electrical Systems 11-22 26 09 23 Lighting Controls 11-22 26 27 26 Wiring Devices 11-22 26 51 00 Interior Lighting 03-24
DIVISION 27 COMMUNICATIONS
27 05 11 Requirements for Communications Installations 09-19
00 01 10-4
27 05 26i Grounding and Bonding for Communications Systems 06-15 27 05 33i Conduits and BackBoxes for Communications Systems 12-22 27 08 00 Commissioning of Communications Systems 11-16 27 15 00 Communications Structured Cabling 01-16
DIVISION 31 EARTHWORK (NOT USED)
DIVISION 32 EXTERIOR IMPROVEMENTS (NOT USED)
DIVISION 33 UTILITIES
DIVISION 34 TRANSPORTATION (NOT USED)
DIVISION 48 Electrical Power Generation (NOT USED)
05-01-20
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS
VA Project #589A7-23-315
00 01 15 - 1
SECTION 00 01 15
LIST OF DRAWING SHEETS
The drawings listed below accompanying this specification form a part of the contract.
Drawing No. Title
ARCHITECTURAL
GI001 COVER SHEET
GI002 INDEX OF DRAWINGS
GI101 FIRST FLOOR - LIFE SAFETY
AG001 ARCHITECTURAL ABBREVIATIONS, LEGENDS AND NOTES
AD101 FIRST FLOOR DEMOLITION PLAN
AE101 FIRST FLOOR FLOOR PLAN
AC101 FIRST FLOOR REFLECTED CEILING PLAN
AE401 SECTIONS
AE701 DOOR AND FRAME TYPES, DETAILS AND DOOR SCHEDULE
AE801 PARTITION TYPES
AE802 PATITION DETAILS
AE902 CASEWORK ELEVATIONS
AE905 INTERIOR ELEVATIONS
IN101 FIRST FLOOR INTERIOR FLOOR FINISH PLAN AND
SCHEDULE
QH101 FIRST FLOOR EQUIPMENT PLAN
STRUCTURAL
SE101 STRUCTURAL PLAN
FIRE PROTECTION
FG101 FIRE SUPRESSION SYMBOLS LEGEND AND GENERAL
NOTES
FD101 FIRST FLOOR FIRE SUPPRESSION DEMOLITION PLAN
FP101 FIRST FLOOR FIRE SUPPRESSION PLAN
HEATING, VENTILATING, AIR
MG101 MECHANICAL SYMBOLS LEGEND AND GENERAL NOTES
MD101 FIRST FLOOR MECHANICAL DEMOLITION PLAN
05-01-20
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS
VA Project #589A7-23-315
00 01 15 - 2
MH101 FIRST FLOOR MECHANICAL PLAN
M-701 MECHANICAL SCHEDULES AND DETAILS
PLUMBING
PG101 PLUMBING SYMBOLS LEGEND AND GENERAL NOTES
PD101 FIRST FLOOR PLUMBING DEMOLITION PLAN
PL101 FIRST FLOOR PLUMBING PLAN
P-701 PLUMBING SCHEDULES AND DETAILS
ELECTRICAL
EG101 ELECTRICAL SYMBOLS LEGEND AND GENERAL NOTES
ED101 ELECTRICAL DEMOLITION PLAN
EL101 FIRST FLOOR LIGHTING PLAN
EP101 FIRST FLOOR POWER PLAN
E501 ELECTRICAL DETAILS
- - - END - - -
a) b) c) d) e) f) g) h) i) j) k) l) m) n) o) p)
Warranty Tags
Type of product/material
Model number
Serial number
Contract number
Warranty period from/to
Construction Contractor
Address
Telephone number
Warranty Contact
Address
Telephone number
Warranty response time priority code
01-01-24
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 32 16.15 - 1
SECTION 01 32 16.15
PROJECT SCHEDULES
(SMALL PROJECTS DESIGN/BID/BUILD)
PART 1- GENERAL
1.1 DESCRIPTION:
A. The Contractor shall develop a Critical Path Method (CPM) plan and schedule demonstrating fulfillment of the contract requirements
(Project Schedule), and shall keep the Project Schedule up-to-date in accordance with the requirements of this section and shall utilize the plan for scheduling, coordinating and monitoring work under this contract (including all activities of subcontractors, equipment vendors and suppliers). Conventional Critical Path Method (CPM) technique shall be utilized to satisfy both time and cost applications.
1.2 CONTRACTOR'S REPRESENTATIVE:
A. The Contractor shall designate an authorized representative responsible for the Project Schedule including preparation, review and progress reporting with and to the Contracting Officer's Representative (COR).
B. The Contractor's representative shall have direct project control and complete authority to act on behalf of the Contractor in fulfilling the requirements of this specification section.
C.
project schedule within their organization or to engage the services of an outside consultant. If an outside scheduling consultant is utilized, Section 1.3 of this specification will apply.
1.3 CONTRACTOR'S CONSULTANT:
A. The Contractor shall submit a qualification proposal to the COR, within
10 days of bid acceptance. The qualification proposal shall include:
1. The name and address of the proposed consultant.
2. Information to show that the proposed consultant has the qualifications to meet the requirements specified in the preceding paragraph.
3. A representative sample of prior construction projects, which the proposed consultant has performed complete project scheduling services. These representative samples shall be of similar size and scope.
B. The Contracting Officer has the right to approve or disapprove the proposed consultant, and will notify the Contractor of the VA decision
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 32 16.15 - 2 within seven calendar days from receipt of the qualification proposal.
In case of disapproval, the Contractor shall resubmit another consultant within 10 calendar days for renewed consideration. The
Contractor shall have their scheduling consultant approved prior to submitting any schedule for approval.
1.4 COMPUTER PRODUCED SCHEDULES
A. The contractor shall provide monthly, to the Department of Veterans
Affairs (VA), all computer-produced time/cost schedules and reports generated from monthly project updates. This monthly computer service will include: three copies of up to five different reports (inclusive of all pages) available within the user defined reports of the scheduling software approved by the Contracting Officer; a hard copy listing of all project schedule changes, and associated data, made at the update and an electronic file of this data; and the resulting monthly updated schedule in PDM format. These must be submitted with the signed look ahead report. The COR shall identify the five different report formats that the contractor shall provide.
B. The contractor shall be responsible for the correctness and timeliness of the computer-produced reports. The Contractor shall also responsible for the accurate and timely submittal of the updated project schedule and all CPM data necessary to produce the computer reports and payment request that is specified.
C. The VA will report errors in computer-produced reports to the reports. The Contractor shall reprocess the computer-produced reports and associated diskette(s), when requested by the Co representative, to correct errors which affect the payment and schedule for the project.
1.5 THE COMPLETE PROJECT SCHEDULE SUBMITTAL
A. Within 45 calendar days after receipt of Notice to Proceed, the
Contractor shall submit for the Contracting Officer's review; three blue line copies of the interim schedule on sheets of paper 765 x 1070 mm (30 x 42 inches) and an electronic file in the previously approved
CPM schedule program. The submittal shall also include three copies of a computer-produced activity/event ID schedule showing project duration; phase completion dates; and other data, including event cost.
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 32 16.15 - 3
Each activity/event on the computer-produced schedule shall contain as a minimum, but not limited to, activity/event ID, activity/event description, duration, budget amount, early start date, early finish date, late start date, late finish date and total float. Work activity/event relationships shall be restricted to finish-to-start or start-to-start without lead or lag constraints. Activity/event date constraints, not required by the contract, will not be accepted unless submitted to and approved by the Contracting Officer. The contractor shall make a separate written detailed request to the Contracting
Officer identifying these date constraints and secure the Contracting diagram. The Con
Schedule shall not excuse the contractor of this requirement. Logic events (non-work) will be permitted where necessary to reflect proper logic among work events, but must have zero duration. The complete working schedule shall reflect the Contractor's approach to scheduling the complete project. The final Project Schedule in its original form shall contain no contract changes or delays which may have been incurred during the final network diagram development period and shall reflect the entire contract duration as defined in the bid documents.
These changes/delays shall be entered at the first update after the final Project Schedule has been approved. The Contractor should provide their requests for time and supporting time extension analysis for contract time as a result of contract changes/delays, after this update, and in accordance with Article, ADJUSTMENT OF CONTRACT
COMPLETION.
B. Within 30 calendar days after receipt of the complete project interim
Project Schedule and the complete final Project Schedule, the
Contracting Officer or his representative, will do one or both of the following:
1. Notify the Contractor concerning his actions, opinions, and objections.
2. A meeting with the Contractor at or near the job site for joint review, correction or adjustment of the proposed plan will be scheduled if required. Within 14 calendar days after the joint review, the Contractor shall revise and shall submit three blue line copies of the revised Project Schedule, three copies of the revised
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 32 16.15 - 4 computer-produced activity/event ID schedule and a revised electronic file as specified by the Contracting Officer. The revised submission will be reviewed by the Contracting Officer and, if found to be as previously agreed upon, will be approved.
C. The approved baseline schedule and the computer-produced schedule(s) generated there from shall constitute the approved baseline schedule until subsequently revised in accordance with the requirements of this section.
D. The Complete Project Schedule shall contain a sufficient amount of work activities/events to appropriately describe the entire work including all phases, sub-phases or other sequences of work, tasks/subtasks, as required.
1.6 WORK ACTIVITY/EVENT COST DATA
A. The Contractor shall cost load all work activities/events except procurement activities. The cumulative amount of all cost loaded work activities/events (including alternates) shall equal the total contract price. Prorate overhead, profit and general conditions on all work activities/events for the entire project length. The contractor shall generate from this information cash flow curves indicating graphically the total percentage of work activity/event dollar value scheduled to be in place on early finish, late finish. These cash flow curves will be used by the Contracting Officer to assist him in determining approval or disapproval of the cost loading. Negative work activity/event cost data will not be acceptable, except on VA issued contract changes.
B. The Contractor shall cost load work activities/events for guarantee period services, test, balance and adjust various systems in accordance with the provisions in Article, FAR 52.232 5 (PAYMENT UNDER
FIXED-PRICE CONSTRUCTION CONTRACTS) and VAAR 852.232 Article 71
Including NAS-CPM for (PAYMENTS UNDER FIXED PRICE CONSTRUCTION).
C. In accordance with FAR 52.236 1 (PERFORMANCE OF WORK BY THE
CONTRACTOR), the Contractor shall submit, simultaneously with the cost per work activity/event of the construction schedule required by this
Section, a responsibility code for all activities/events of the project for which the Contractor's forces will perform the work.
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 32 16.15 - 5
D. The Contractor shall cost load work activities/events for all BID ITEMS including ASBESTOS ABATEMENT. The sum of each BID ITEM work shall equal the value of the bid item in the Contractors' bid.
1.7 PROJECT SCHEDULE REQUIREMENTS
A. Show on the project schedule the sequence of work activities/events required for complete performance of all items of work. The Contractor
Shall:
1. Show activities/events as:
a. Contractor's time required for submittal of shop drawings, templates, fabrication, delivery and similar pre-construction work.
b. Contracting Officer's and Architect-Engineer's review and approval of shop drawings, equipment schedules, samples, template, or similar items.
c. Interruption of VA Facilities utilities, delivery of Government furnished equipment, and rough-in drawings, project phasing and any other specification requirements.
d. Test, balance and adjust various systems and pieces of equipment, maintenance and operation manuals, instructions and preventive maintenance tasks.
e. VA inspection and acceptance activity/event with a minimum duration of five work days at the end of each phase and immediately preceding any VA move activity/event required by the contract phasing for that phase.
2. Show not only the activities/events for actual construction work for each trade category of the project, but also trade relationships to indicate the movement of trades from one area, floor, or building, to another area, floor, or building, for at least five trades who are performing major work under this contract.
3. Break up the work into activities/events of a duration no longer than 20 work days each or one reporting period, except as to non-construction activities/events (i.e., procurement of materials, delivery of equipment, concrete and asphalt curing) and any other activities/events for which the COR may approve the showing of a longer duration. The duration for VA approval of any required submittal, shop drawing, or other submittals will not be less than
20 work days.
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 32 16.15 - 6
4. Describe work activities/events clearly, so the work is readily identifiable for assessment of completion. Activities/events labeled
"start," "continue," or "completion," are not specific and will not be allowed. Lead and lag time activities will not be acceptable.
5. The schedule shall be generally numbered in such a way to reflect either discipline, phase or location of the work.
B. The Contractor shall submit the following supporting data in addition to the project schedule:
1. The appropriate project calendar including working days and holidays.
2. The planned number of shifts per day.
3. The number of hours per shift.
Failure of the Contractor to include this data shall delay the review of the submittal until the Contracting Officer is in receipt of the missing data.
C. To the extent that the Project Schedule or any revised Project Schedule shows anything not jointly agreed upon, it shall not be deemed to have been approved by the COR. Failure to include any element of work required for the performance of this contract shall not excuse the
Contractor from completing all work required within any applicable completion date of each phase regardless of the CO
Project Schedule.
D. Compact Disk Requirements and CPM Activity/Event Record Specifications:
Submit to the VA an electronic file(s) containing one file of the data required to produce a schedule, reflecting all the activities/events of the complete project schedule being submitted.
1.8 PAYMENT TO THE CONTRACTOR:
A. Monthly, the contractor shall submit an application and certificate for payment using VA Form 10-6001a reflecting updated schedule activities and cost data in accordance with the provisions of the following
Article, PAYMENT AND PROGRESS REPORTING, as the basis upon which progress payments will be made pursuant to Article, FAR 52.232 5
(PAYMENT UNDER FIXED-PRICE CONSTRUCTION CONTRACTS) and VAAR 852.232
Article 71 Including NAS-CPM for (PAYMENTS UNDER FIXED PRICE
CONSTRUCTION). The Contractor shall be entitled to a monthly progress payment upon approval of estimates as determined from the currently approved updated project schedule. Monthly payment requests shall
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 32 16.15 - 7 include: a listing of all agreed upon project schedule changes and associated data; and an electronic file (s) of the resulting monthly updated schedule.
B.
contingent, among other factors, on the submittal of a satisfactory monthly update of the project schedule.
1.9 PAYMENT AND PROGRESS REPORTING
A. Monthly schedule update meetings will be held on dates mutually agreed to by the COR and the Contractor. Contractor and their CPM consultant
(if applicable) shall attend all monthly schedule update meetings. The
Contractor shall accurately update the Project Schedule and all other data required and provide this information to the COR three work days in advance of the schedule update meeting. Job progress will be reviewed to verify:
1. Actual start and/or finish dates for updated/completed activities/events.
2. Remaining duration for each activity/event started, or scheduled to start, but not completed.
3. Logic, time and cost data for change orders, and supplemental agreements that are to be incorporated into the Project Schedule.
4. Changes in activity/event sequence and/or duration which have been made, pursuant to the provisions of following Article, ADJUSTMENT OF
CONTRACT COMPLETION.
5. Completion percentage for all completed and partially completed activities/events.
6. Logic and duration revisions required by this section of the specifications.
7. Activity/event duration and percent complete shall be updated independently.
B. After completion of the joint review, the contractor shall generate an updated computer-produced calendar-dated schedule and supply the the Article, COMPUTER PRODUCED SCHEDULES, specified.
C.
representative or scheduling consultant shall rerun all current period contract change(s) against the prior approved monthly project schedule.
The analysis shall only include original workday durations and schedule
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 32 16.15 - 8 logic agreed upon by the contractor and COR for the contract change(s).
When there is a disagreement on logic and/or durations, the Contractor shall use the schedule logic and/or durations provided and approved by the COR. After each rerun update, the resulting electronic project schedule data file shall be appropriately identified and submitted to the VA in accordance to the requirements listed in articles 1.4 and
1.7. This electronic submission is separate from the regular monthly project schedule update requirements and shall be submitted to the COR within fourteen (14) calendar days of completing the regular schedule update. Before inserting the contract changes durations, care must be taken to ensure that only the original durations will be used for the analysis, not the reported durations after progress. In addition, once the final network diagram is approved, the contractor must recreate all manual progress payment updates on this approved network diagram and associated reruns for contract changes in each of these update periods as outlined above for regular update periods. This will require detailed record keeping for each of the manual progress payment updates.
D. Following approval of the CPM schedule, the VA, the General Contractor, its approved CPM Consultant, RE office representatives, and all subcontractors needed, as determined by the SRE, shall meet to discuss the monthly updated schedule. The main emphasis shall be to address work activities to avoid slippage of project schedule and to identify any necessary actions required to maintain project schedule during the reporting period. The Government representatives and the Contractor should conclude the meeting with a clear understanding of those work and administrative actions necessary to maintain project schedule status during the reporting period. This schedule coordination meeting will occur after each monthly project schedule update meeting utilizing the resulting schedule reports from that schedule update. If the project is behind schedule, discussions should include ways to prevent further slippage as well as ways to improve the project schedule status, when appropriate.
1.10 RESPONSIBILITY FOR COMPLETION
A. If it becomes apparent from the current revised monthly progress schedule that phasing or contract completion dates will not be met, the
Contractor shall execute some or all of the following remedial actions:
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 32 16.15 - 9
1. Increase construction manpower in such quantities and crafts as necessary to eliminate the backlog of work.
2. Increase the number of working hours per shift, shifts per working day, working days per week, the amount of construction equipment, or any combination of the foregoing to eliminate the backlog of work.
3. Reschedule the work in conformance with the specification requirements.
B. Prior to proceeding with any of the above actions, the Contractor shall notify and obtain approval from the COR for the proposed schedule changes. If such actions are approved, the representative schedule revisions shall be incorporated by the Contractor into the Project
Schedule before the next update, at no additional cost to the
Government.
1.11 CHANGES TO THE SCHEDULE
A. Within 30 calendar days after VA acceptance and approval of any updated project schedule, the Contractor shall submit a revised electronic file
(s) and a list of any activity/event changes including predecessors and successors for any of the following reasons:
1. Delay in completion of any activity/event or group of activities/events, which may be involved with contract changes, strikes, unusual weather, and other delays will not relieve the
Contractor from the requirements specified unless the conditions are shown on the CPM as the direct cause for delaying the project beyond the acceptable limits.
2. Delays in submittals, or deliveries, or work stoppage are encountered which make rescheduling of the work necessary.
3. The schedule does not represent the actual prosecution and progress of the project.
4. When there is, or has been, a substantial revision to the activity/event costs regardless of the cause for these revisions.
B. CPM revisions made under this paragraph which affect the previously approved computer-produced schedules for Government furnished equipment, vacating of areas by the VA Facility, contract phase(s) and sub phase(s), utilities furnished by the Government to the Contractor, or any other previously contracted item, shall be furnished in writing to the Contracting Officer for approval.
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 32 16.15 - 10
C. Contracting Officer's approval for the revised project schedule and all relevant data is contingent upon compliance with all other paragraphs of this section and any other previous agreements by the Contracting
Officer or the VA representative.
D. The cost of revisions to the project schedule resulting from contract changes will be included in the proposal for changes in work as specified in FAR 52.243 4 (Changes, and will be based on the complexity of the revision or contract change, man hours expended in analyzing the change, and the total cost of the change.
E. The cost of revisions to the Project Schedule not resulting from contract changes is the responsibility of the Contractor.
1.12 ADJUSTMENT OF CONTRACT COMPLETION
A. The contract completion time will be adjusted only for causes specified in this contract. Request for an extension of the contract completion date by the Contractor shall be supported with a justification, CPM data and supporting evidence as the COR may deem necessary for determination as to whether or not the Contractor is entitled to an extension of time under the provisions of the contract. Submission of proof based on revised activity/event logic, durations (in work days) and costs is obligatory to any approvals. The schedule must clearly display that the Contractor has used, in full, all the float time available for the work involved in this request. The Contracting
Officer's determination as to the total number of days of contract extension will be based upon the current computer-produced calendar-dated schedule for the time period in question and all other relevant information.
B. Actual delays in activities/events which, according to the computer- produced calendar-dated schedule, do not affect the extended and predicted contract completion dates shown by the critical path in the network, will not be the basis for a change to the contract completion date. The Contracting Officer will within a reasonable time after receipt of such justification and supporting evidence, review the facts and advise the Contractor in writing of the Contracting Officer's decision.
C. The Contractor shall submit each request for a change in the contract completion date to the Contracting Officer in accordance with the provisions specified under FAR 52.243 4 (Changes). The Contractor
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 32 16.15 - 11 shall include, as a part of each change order proposal, a sketch showing all CPM logic revisions, duration (in work days) changes, and cost changes, for work in question and its relationship to other activities on the approved network diagram.
D. All delays due to non-
STRIKES, and similar non-work activities/events shall be analyzed on a month by month basis.
- - - E N D - - -
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS
01 32 16.15 - 12
(This page is left blank intentionally)
11-01-23
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 33 23 - 1
SECTION 01 33 23
SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES
PART 1 GENERAL
1.1 DESCRIPTION
A. This specification defines the general requirements and procedures for submittals. A submittal is information submitted for VA review to establish compliance with the contract documents.
B. Detailed submittal requirements are found in the technical sections of the contract specifications. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective technical specifications at no additional cost to the government.
C. VA approval of a submittal does not relieve the Contractor of the responsibility for any error which may exist. The Contractor is responsible for fully complying with all contract requirements and the satisfactory construction of all work, including the need to check, confirm, and coordinate the work of all subcontractors for the project.
Non-compliant material incorporated in the work will be removed and
1.2 DEFINITIONS
A. Preconstruction Submittals: Submittals which are required prior to issuing contract notice to proceed or starting construction. For example, Certificates of insurance; Surety bonds; Site-specific safety plan; Construction progress schedule; Schedule of values; Submittal register; List of proposed subcontractors.
B. Shop Drawings: Drawings, diagrams, and schedules specifically prepared to illustrate some portion of the work. Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be integrated and coordinated.
C. Product Data: Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions, and brochures, which describe and illustrate size, physical appearance, and other characteristics of materials, systems, or equipment for some portion of the work. Samples of warranty language when the contract requires extended product warranties.
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 33 23 - 2
D. Samples: Physical examples of materials, equipment, or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged. Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project. Field samples and mock-ups constructed to establish standards by which the ensuing work can be judged.
E. Design Data: Calculations, mix designs, analyses, or other data pertaining to a part of work.
F. Test Reports: Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work. Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
G. Certificates: Document required of Contractor, or of a manufacturer, supplier, installer, or subcontractor through Contractor. The purpose is to document procedures, acceptability of methods, or personnel qualifications for a portion of the work.
H. Manufacturer's Instructions: Pre-printed material describing installation of a product, system, or material, including special notices and MSDS concerning impedances, hazards, and safety precautions.
I. Manufacturer's Field Reports: Documentation of the testing and verification actions taken by manufacturer's representative at the job site on a portion of the work, during or after installation, to confirm compliance with manufacturer's standards or instructions. The documentation must indicate whether the material, product, or system has passed or failed the test.
J. Operation and Maintenance Data: Manufacturer data that is required to operate, maintain, troubleshoot, and repair equipment, including manufacturer's help, parts list, and product line documentation. This data shall be incorporated in an operations and maintenance manual.
K. Closeout Submittals: Documentation necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a phase of construction on a multi-phase contract.
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 33 23 - 3
1.3 SUBMITTAL REGISTER
A. The submittal register will list items of equipment and materials for which he contract documents but which have been omitted from the submittal register.
B. The submittal register will serve as a scheduling document for submittals and will be used to control submittal actions throughout the contract period.
C. The VA will provide a blank submittal register in electronic format.
Thereafter, the Contractor shall fill in the blank register with the required submittals as documented in the project spec. The Contractor shall track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the VA.
D. The Contractor shall update the submittal register as submittal actions occur and maintain the submittal register at the project site until final acceptance of all work by Contracting Officer.
E. The Contractor shall submit formal monthly updates to the submittal register in electronic format. Each monthly update shall document actual submission and approval dates for each submittal.
1.4 SUBMITTAL SCHEDULING
A. Submittals are to be scheduled, submitted, reviewed, and approved prior to the acquisition of the material or equipment.
B. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow time for potential resubmittal.
C. No delay costs or time extensions will be allowed for time lost in late submittals or resubmittals.
D. All submittals are required to be approved prior to the start of the specified work activity.
1.5 SUBMITTAL PREPARATION
A. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
B. Collect required data for each specific material, product, unit of work, or system into a single submittal. Prominently mark choices, options, and portions applicable to the submittal. Partial submittals will not be accepted for expedition of construction effort. Submittal will be returned without review if incomplete.
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 33 23 - 4
C. If available product data is incomplete, provide Contractor-prepared documentation to supplement product data and satisfy submittal requirements.
D. All irrelevant or unnecessary data shall be removed from the submittal to facilitate accuracy and timely processing. Submittals that contain the excessive amount of irrelevant or unnecessary data will be returned without review.
E. Provide a transmittal form for each submittal with the following information:
1. Project title, location and number.
2. Construction contract number.
3. Date of the drawings and revisions.
4. Name, address, and telephone number of subcontractor, supplier, manufacturer, and any other subcontractor associated with the submittal.
5. List paragraph number of the specification section and sheet number of the contract drawings by which the submittal is required.
6. When a resubmission, add alphabetic suffix on submittal description.
For example, submittal 18 would become 18A, to indicate resubmission.
7. Product identification and location in project.
F. The Contractor is responsible for reviewing and certifying that all submittals are in compliance with contract requirements before submitting for VA review. Proposed deviations from the contract requirements are to be clearly identified. All deviations submitted must include a side by side comparison of item being proposed against item specified. Failure to point out deviations will result in the VA requiring removal and replacement of such work at the Contractor's expense.
G. Stamp, sign, and date each submittal transmittal form indicating action taken.
H. Stamp used by the Contractor on the submittal transmittal form to certify that the submittal meets contract requirements is to be similar to the following:
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 33 23 - 5
| CONTRACTOR |
| (Firm Name) |
| Approved |
| Approved with corrections as noted on submittal data and/or |
| attached sheets(s) |
| SIGNATURE: |
| TITLE: |
| DATE: |
1.6 SUBMITTAL FORMAT AND TRANSMISSION
A. Provide submittals in electronic format, with the exception of material samples. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer.
B. Compile the electronic submittal file as a single, complete document.
Name the electronic submittal file specifically according to its contents.
C. Electronic files must be of sufficient quality that all information is legible. Generate PDF files from original documents so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required.
D. E-mail electronic submittal documents smaller than 5MB in size to e-mail addresses as directed by the Contracting Officer.
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 33 23 - 6
E. Provide electronic documents over 5MB through an electronic FTP file sharing system. Confirm that the electronic FTP file sharing system can be accessed from the VA computer network. The Contractor is responsible for setting up, providing, and maintaining the electronic
FTP file sharing system for the construction contract period of performance.
F. Provide hard copies of submittals when requested by the Contracting
Officer. Up to 3 additional hard copies of any submittal may be requested at the discretion of the Contracting Officer, at no additional cost to the VA.
1.7 SAMPLES
A. Submit two sets of physical samples showing range of variation, for each required item.
B. Where samples are specified for selection of color, finish, pattern, or texture, submit the full set of available choices for the material or product specified.
C. When color, texture, or pattern is specified by naming a particular manufacturer and style, include one sample of that manufacturer and style, for comparison.
D. Before submitting samples, the Contractor is to ensure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.
E. The VA reserves the right to disapprove any material or equipment which previously has proven unsatisfactory in service.
F. Physical samples supplied maybe requested back for use in the project after reviewed and approved.
1.8 OPERATION AND MAINTENANCE DATA
A. Submit data specified for a given item within 30 calendar days after the item is delivered to the contract site.
B. In the event the Contractor fails to deliver O&M Data within the time limits specified, the Contracting Officer may withhold from progress payments 50 percent of the price of the item with which such O&M Data are applicable.
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 33 23 - 7
1.9 TEST REPORTS
COR may require specific test after work has been installed or completed which could require contractor to repair test area at no additional cost to contract.
1.10 VA REVIEW OF SUBMITTALS AND RFIS
A. The VA will review all submittals for compliance with the technical requirements of the contract documents. The Architect-Engineer for this project will assist the VA in reviewing all submittals and determining contractual compliance. Review will be only for conformance with the applicable codes, standards and contract requirements.
B. Period of review for submittals begins when the VA COR receives submittal from the Contractor.
C. Period of review for each resubmittal is the same as for initial submittal.
D. VA review period is 15 business days for submittals.
E. VA review period is 10 business days for RFIs.
F. The VA will return submittals to the Contractor with the following notations:
1. "Approved": authorizes the Contractor to proceed with the work covered.
2. "Approved as noted": authorizes the Contractor to proceed with the work covered provided the Contractor incorporates the noted comments and makes the noted corrections.
3. "Disapproved, revise and resubmit": indicates noncompliance with the contract requirements or that submittal is incomplete. Resubmit with appropriate changes and corrections. No work shall proceed for this item until resubmittal is approved.
4. "Not reviewed": indicates submittal does not have evidence of being reviewed and approved by Contractor or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals after taking appropriate action.
1.11 APPROVED SUBMITTALS
A. The VA approval of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing, and other information are satisfactory.
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 33 23 - 8
B. VA approval of a submittal does not relieve the Contractor of the responsibility for any error which may exist. The Contractor is responsible for fully complying with all contract requirements and the satisfactory construction of all work, including the need to check, confirm, and coordinate the work of all subcontractors for the project.
Non-compliant material incorporated in the work will be removed and
C. After submittals have been approved, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
D. Retain a copy of all approved submittals at project site, including approved samples.
1.12 WITHHOLDING OF PAYMENT
Payment for materials incorporated in the work will not be made if required approvals have not been obtained.
01 35 26 - 1
01 35 26 - 2
01 35 26 - 3
01 35 26 - 4
01 35 26 - 5
01 35 26 - 6
01 35 26 - 7
01 35 26 - 8
01 35 26 - 9
01 35 26 - 10
01 35 26 - 11
01 35 26 - 12
01 35 26 - 13
01 35 26 - 14
01 35 26 - 15
01 35 26 - 16
01 35 26 - 17
01 35 26 - 18
01 35 26 - 19
01 35 26 - 20
01 35 26 - 21
01 35 26 - 22
01 35 26 - 23
01 35 26 - 24
01 35 26 - 25
01 35 26 - 26
01 35 26 - 27
01 35 26 - 28
01 35 26 - 29
01 35 26 - 30
01 35 26 - 31
01 35 26 - 32
01 35 26 - 33
01 35 26 - 34
01 35 26 - 35
01 35 26 - 36
01 35 26 - 37
01 35 26 - 38
01 35 26 - 39
01 35 26 - 40
01 35 26 - 41
02-01-21
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 45 00 - 1
SECTION 01 45 00
QUALITY CONTROL
PART 1 - GENERAL
1.1 DESCRIPTION
This section specifies requirements for Contractor Quality Control
(CQC) for Design-Bid-Build (DBB) or Design-Build (DB) construction projects. This section can be used for both project types.
1.2 APPLICABLE PUBLICATIONS
A. The publication listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
B. ASTM International (ASTM)
1. D3740 - (2012a) Minimum Requirements for Agencies Engaged in the
Testing and/or Inspection of Soil and Rock as Used in Engineering
Design and Construction
2. E329 - (2014a) Standard Specification for Agencies Engaged in the
Testing and/or Inspection of Materials Used in Construction
1.3 SUBMITTALS
Government approval is required for all submittals. CQC inspection reports shall be submitted under this Specification section and follow the [Applicable CQC Control Phase (Preparatory, Initial, or Follow-
Up)]: [Applicable Specification section] naming convention.
1. Preconstruction Submittals
a. Interim CQC Plan
b. CQC Plan
c. Additional Requirements for Design Quality Control (DQC) Plan
2. Design Data
a. Discipline-Specific Checklists
b. Design Quality Control
3. Test Reports
a. Verification Statement
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 45 00 - 2
PART 2 PRODUCTS NOT USED
PART 3 - EXECUTION
3.1 GENERAL REQUIREMENTS
Establish and maintain an effective quality control (QC) system. that
. QC consists of plans, procedures, and organization necessary to produce an end product which complies with the Contract requirements. The QC system covers all design and construction operations, both onsite and offsite, and be keyed to the proposed design and construction sequence. The project superintendent will be held responsible for the quality of work and is subject to removal by the Contracting Office or Authorized designee for non-compliance with the quality requirements specified in the Contract. In this context the highest level manager responsible for the overall construction activities at the site, including quality and production is the project superintendent. The project superintendent maintains a physical presence at the site at all times and is responsible for all construction and related activities at the site, except as otherwise acceptable to the Contracting Officer.
3.2 CQC PLAN:
A. Submit the CQC Plan no later than 15days after receipt of Notice to
Proceed (NTP) proposed to implement the requirements of the FAR Clause consider an Interim CQC Plan for the first 15 days of operation, which must be accepted within 20 business days of NTP. Design and/or construction will be permitted to begin only after acceptance of the CQC
Plan or acceptance of an Interim plan applicable to the particular feature of work to be started. Work outside of the accepted Interim CQC
Plan will not be permitted to begin until acceptance of a CQC Plan or another Interim CQC Plan containing the additional work scope is accepted.
B. Content of the CQC Plan: Include, as a minimum, the following to cover all design and construction operations, both onsite and offsite, including work by subcontractors, designers of record consultants, architects/engineers (A/E), fabricators, suppliers, and purchasing agents:
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 45 00 - 3
1. A description of the QC organization, including a chart showing lines of authority and acknowledgement that the CQC staff will implement the three phase control system for all aspects of the work specified. Include a CQC System Manager that reports to the project superintendent.
2. The name, qualifications (in resume format) duties, responsibilities, and authorities of each person assigned a CQC function.
3. A copy of the letter to the CQC System Manager signed by an authorized official of the firm which describes the responsibilities and delegates sufficient authorities to adequately perform the functions of the CQC System Manager, including authority to stop work which is not in compliance with the Contract. Letters of direction to all other various quality control representatives outlining duties, authorities, and responsibilities will be issued by the CQC System Manager. Furnish copies of these letters to the
Contracting Officer or Authorized designee.
4. Procedures for scheduling, reviewing, certifying, and managing submittals including those of subcontractors, designers of record, agents. These procedures must be in accordance with Section 01 33 23
Shop Drawings, Product Data, and Samples.
5. Control, verification, and acceptance of testing procedures for each specific test to include the test name, specification paragraph requiring test, feature of work to be tested, test frequency, and person responsible for each test. (Laboratory facilities approved by the Contracting Officer or Authorized designee are required to be used)
6. Procedures for tracking Preparatory, Initial, and Follow-Up control phases and control, verification, and acceptance tests including documentation.
7. Procedures for tracking design and construction deficiencies from identification through acceptable corrective action. Establish verification procedures that identified deficiencies have been corrected.
8. Reporting procedures, including proposed reporting formats.
Robert J. Dole VA Medical Center, 5500 Kellogg, Wichita, KS VA Project #589A7-23-315
01 45 00 - 4
9. A list of the definable features of work. A definable feature of work is a task which is separate and distinct from other tasks has separate control requirements, and is identified by different trades or disciplines, or it is work by the same trade in a different environment.
This is the start of the file's text. The full file is on GovTribe.