P09 - Final Drawings.pdf

PDF 5 MB Posted

Attached to
Z2DA--CORRECT ELECTRICAL DEFICIENCIES PN:589A4-23-104 Federal contract opportunity
Solicitation number
36C25524R0106
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 15

About this file

This document appears to be a set of construction drawings and specifications related to a federal contract opportunity to correct electrical deficiencies at the Harry S Truman VA Medical Center in Columbia, Missouri. The project scope includes replacing multiple automatic transfer switches (ATS), distribution switchboards, transformers, and supporting electrical infrastructure. Key details include:

The solicitation number is 36C25524R0106 and the project number is 589A4-23-104. The procuring agency is the Department of Veterans Affairs Veterans Health Administration. The project involves fully sprinklered 100% construction documents to correct electrical deficiencies at the facility. New equipment includes four ATS units, four distribution switchboards, and five 1500 kVA pad-mounted transformers. The drawings provide one-line diagrams, floor plans, and details for the electrical demolition and new work. Deduct alternates are included for potential reductions in scope.

View the file

Other files for this federal contract opportunity

Other files attached to Z2DA--CORRECT ELECTRICAL DEFICIENCIES PN:589A4-23-104, newest first.
File Type Posted
36C25524R0106 0002.docx DOCX document
261219.pdf PDF
PRE-BID site walk through sign in list.pdf PDF
36C25524R0106 0001.docx DOCX document
Revised 01 33 23 1Aug24.pdf PDF
ATTENDANCE ROSTER PRE-BID Meeting.xlsx XLSX spreadsheet
36C25524R0106.docx DOCX document
P09 - Final Specifications - Revised 03JUL24.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

100% CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

10360 Ellison Circle Omaha, NE 68134 Phone: 402.991.5520 www.specializedeng.com

SES Project : 23133

A u to d e s k D o c s /2

.0

V A

C o lu m b ia

M

O

C o rr e c t E le c tr ic a l D e fi c ie n c ie s /5

A

-2

-1

.E

.R

.r v t

/1

/2

:1

:4

P

M

G00

COVER SHEET

Introba

6 S Old Orchard Ave Suit 285

Saint Louis, MO 63119

800.404.7677

CORRECT ELECTRICAL

DEFICIENCIES, HARRY S TRUMAN

VAMC

800 Hospital Drive, Columbia, MO 65201

589A4-23-104

05/17/2024 AEA AEA

CORRECT ELECTRICAL

DEFICIENCIES, HARRY S

TRUMAN VAMC

PROJECT NAME:

800 Hospital Drive, Columbia, MO 65201

SITE ADDRESS:

VA PROJECT NUMBER:

589A4-23-104

VICINITY MAP: SITE MAP:

Revisions: Date:

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

100% CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

10360 Ellison Circle Omaha, NE 68134 Phone: 402.991.5520 www.specializedeng.com

SES Project : 23133

A u to d e s k D o c s /2

.0

V A

C o lu m b ia

M

O

C o rr e c t E le c tr ic a l D e fi c ie n c ie s /5

A

-2

-1

.E

.R

.r v t

/1

/2

:1

:4

P

M

G01

SHEET INDEX

Introba

6 S Old Orchard Ave Suit 285

Saint Louis, MO 63119

800.404.7677

CORRECT ELECTRICAL

DEFICIENCIES, HARRY S TRUMAN

VAMC

800 Hospital Drive, Columbia, MO 65201

589A4-23-104

05/17/2024 AEA AEA

SHEET INDEX

Sheet Number Sheet Name

G00 COVER SHEET

G01 SHEET INDEX

E00 ELECTRICAL SYMBOLS AND ABBREVIATIONS

ED10 B1 EQUIPMENT ATS ONE-LINE DIAGRAM DEMOLITION

ED11 B1 CRITICAL ATS ONE-LINE DIAGRAM DEMOLITION

ED12 B1 LIFE SAFETY ATS ONE-LINE DIAGRAM DEMOLITION

ED13 ACA & CHILLER HOUSE ATS ONE-LINE DIAGRAM DEMOLITION

ED14 TRANSFORMER ONE-LINE DIAGRAM DEMOLITION

ED50 ENLARGED ELECTRICAL DEMOLITION PLANS - BASEMENT

ED51 ENLARGED ELECTRICAL DEMOLITION PLANS - BASEMENT

E10 B1 EQUIPMENT ATS ONE-LINE DIAGRAM NEW WORK

E11 B1 CRITICAL ATS ONE-LINE DIAGRAM NEW WORK

E12 B1 LIFE SAFETY ATS ONE-LINE DIAGRAM NEW WORK

E13 ACA & CHILLER ATS ONE-LINE DIAGRAM NEW WORK

E14 TRANSFORMER ONE-LINE DIAGRAM NEW WORK

E15 BRANCH CIRCUIT CORRECTION ONE-LINE DIAGRAMS

E30 PARTIAL PIPE BASEMENT PLAN - MAIN HOSPITAL

E31 PARTIAL PIPE BASEMENT PLAN - OR SUITE

E32 PARTIAL BASEMENT PLAN - MAIN HOSPITAL

E33 PARTIAL BASEMENT PLAN - ACA BUILDING

E34 PARTIAL BASEMENT PLAN - OR SUITE AND WAREHOUSE

E35 PARTIAL FIRST FLOOR PLAN - MAIN HOSPITAL

E36 PARTIAL FIRST FLOOR PLAN - ACA BUILDING

E37 PARTIAL FIRST FLOOR PLAN - OR SUITE

E38 PARTIAL SECOND FLOOR PLAN - MAIN HOSPITAL

E39 PARTIAL SECOND FLOOR PLAN - ACA BUILDING

E40 OVERALL THIRD FLOOR PLAN - MAIN HOSPITAL

E41 OVERALL THIRD FLOOR PLAN - ACA BUILDING

E42 OVERALL FOURTH FLOOR PLAN - MAIN HOSPITAL

E43 OVERALL FIFTH FLOOR PLAN - MAIN HOSPITAL

E44 OVERALL SIXTH FLOOR PLAN - MAIN HOSPITAL

E45 OVERALL PENTHOUSE FLOOR PLAN - MAIN HOSPITAL

E46 OVERALL CHILLER HOUSE - FIRST FLOOR PLAN

E47 PARKING GARAGE ELECTRICAL PLAN

E50 ENLARGED ELECTRICAL PLANS-BASEMENT

E51 ENLARGED ELECTRICAL PLANS-BASEMENT

E52 ENLARGED ELECTRICAL PLANS-BASEMENT

E53 ENLARGED ELECTRICAL PLANS-BASEMENT

E54 ENLARGED ELECTRICAL PLANS-FIRST FLOOR

E55 ENLARGED ELECTRICAL PLANS-FIRST FLOOR

E56 ENLARGED ELECTRICAL PLANS-FIRST FLOOR

E57 ENLARGED ELECTRICAL PLANS-SECOND FLOOR

E58 ENLARGED ELECTRICAL PLANS-SECOND FLOOR

E59 ENLARGED ELECTRICAL PLANS-SECOND FLOOR

E60 ENLARGED ELECTRICAL PLANS-THIRD FLOOR

E61 ENLARGED ELECTRICAL PLANS-FOURTH FLOOR

E62 ENLARGED ELECTRICAL PLANS-FIFTH FLOOR

E63 ENLARGED ELECTRICAL PLANS-SIXTH FLOOR

E70 ELECTRICAL DETAILS

E71 ELECTRICAL SCHEDULES

E72 ELECTRICAL SCHEDULES

E73 ELECTRICAL SCHEDULES

E74 ELECTRICAL SCHEDULES

E75 ELECTRICAL SCHEDULES

Grand total: 54

ELECTRICAL ABBREVIATIONS

ABBREVIATION DESCRIPTION

REFER TO OTHER SCHEDULES AND NOTES FOR ADDITIONAL ABBREVIATIONS.

MOUNTING HEIGHT TO CENTERLINE (ABOVE FINISHED FLOOR)

AMPERE

AMPERE FRAME

ABOVE FINISHED FLOOR

ALUMINUM

AMPERE TRIP

CONDUIT

CIRCUIT BREAKER

CORRELATED COLOR TEMPERATURE

COPPER

DATA (WHEN APPLIED TO COMMUNICATIONS OUTLET)

DEMO (WHEN APPLIED TO EXISTING/DEMO ITEMS)

EXISTING

ELECTRICALLY OPERATED

ENERGY REDUCING MAINTENANCE SWITCH

FUSE

FULL LOAD AMPS

GROUND FAULT CIRCUIT INTERRUPTER

GROUND FAULT ALARM

GROUND FAULT PROTECTION

HORSEPOWER

KILOAMPERE INTERRUPTING CAPACITY

KILOVOLT AMPERE

KILOWATT

MAXIMUM

MINIMUM CIRCUIT AMPS

MAIN CIRCUIT BREAKER

MINIMUM

MAIN LUGS ONLY

MANUALLY OPERATED

NORMALLY CLOSED

NON-FUSED

NOT IN CONTRACT

NORMALLY OPEN

POLES

PARTIAL

RELOCATE

SHORT CIRCUIT CURRENT RATING

SURGE PROTECTIVE DEVICE

SHUNT TRIP

TYPICAL

UNLESS NOTED OTHERWISE

VOICE

WALL PHONE

WIRE

WEATHER RESISTANT

TRANSFORMER

ZONE SELECTIVE INTERLOCKING

A

AF

AFF

AL

AT

C

CB

CCT

CU

D

D

E

EO

ERMS

F

FLA

G, GFCI

GFA

GFP

HP

KAIC

KVA

KW

MAX

MCA

MCB

MIN

MLO

MO

NC

NF

NIC

NO

P

PART

R

SCCR

SPD

ST

TYP

UNO

V

W

W

WR

XFMR

ZSI

A. FOR ALL CONDUIT AND OTHER ITEMS PENETRATING A FIRE RATED WALL, PROVIDE UL LISTED THROUGH PENETRATION FIRE STOPPING SYSTEM THAT IS SPECIFIC TO THE WALL CONSTRUCTION ASSEMBLY AND COMPLIANT WITH ASTM E814. INSTALL SYSTEM IN STRICT COMPLIANCE WITH THE FIRE STOPPING MANUFACTURER’S U.L. APPROVED DETAIL. WHERE EXISTING WALLS ARE BEING UPGRADED TO FIRE RATED WALLS OR THE FIRE RATING IS BEING MODIFIED, PROVIDE U.L. LISTED THROUGH PENETRATION FIRE

STOPPING SYSTEM FOR ALL NEW AND EXISTING PENETRATIONS.

B. ANY ITEMS DAMAGED BY THE CONTRACTOR SHALL BE REPLACED BY THE CONTRACTOR, AT NO ADDITIONAL

COST TO THE OWNER.

C. THE SELECTED EQUIPMENT AIC RATINGS ARE BASED ON THE IMPEDANCES FOR CONDUCTORS AND TRANSFORMERS USED IN THE CALCULATIONS. IF DIFFERENT EQUIPMENT OR DIFFERENT CONFIGURATIONS

ARE SELECTED FOR INSTALLATION, THE CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING

ADEQUATELY RATED EQUIPMENT THAT MEETS APPLICABLE SELECTIVE COORDINATION GOALS AND

PROVIDES SIMILAR INCIDENT ENERGY RISK OF ARC FLASH HAZARDS.

D. PROVIDE AN INSULATED CONTINUOUS COPPER CONDUCTOR, NOT SMALLER THAN #10, TO BOND ALL

NORMAL AND ESSENTIAL ELECTRICAL SYSTEM PANELBOARDS TOGETHER THAT SERVE THE SAME

INDIVIDUAL PATIENT VICINITY AS DEFINED IN NEC 517.14.

E. PROVIDE ADDITIONAL SUPPORTS AS REQUIRED TO INDEPENDENTLY SUPPORT ALL EXISTING TO REMAIN

CABLING.

F. NEW TRANSFORMER GROUNDING CONDUCTORS SHALL BE ROUTED WITHIN METALLIC CONDUIT TO THE GROUNDING ELECTRODE SYSTEM AND SHALL CONNECT TO THE METALLIC CONDUIT WITH GROUNDING

BUSHINGS ON BOTH ENDS.

G. NEW PANELBOARD INSTALLATION SHALL INCLUDE EXTERNAL WIREWAYS ABOVE TEH PANEL. ALL HOMERUN CONDUITS AT PANEL/WIREWAY TERMINATION SHALL BE MARKER-LABELED INDICATING BRANCH CIRCUIT

NUMBERS CONTAINED WITHIN EACH CONDUIT.

H. PROVIDE CIRCUIT BREAKER LOCK ACCESSORIES ON ALL SOURCE CIRCUIT BREAKERS SERVING

TRANSFORMERS TO ACCOMMODATE LOCK-OUT OF TRANSFORMER PRIMARY SOURCES.

I. EXISTING MOTOR CONTROL CENTERS: TRACE EXISTING BRANCH CIRCUITS TO VERIFY EQUIPMENT SERVED.

PROVIDE NEW PERMANENT LABELING OF MOTOR CONTROL CENTER AND EACH INDIVIDUAL UNIT/BUCKET.

LABEL SHALL IDENTIFY EQUIPMENT SERVED AND DESCRIPTION OF EQUIPMENT LOCATION. PAINT OVER EXISTING MARKER-APPLIED LABELING AFTER CIRCUIT DESCRIPTIONS ARE VERIFIED. PROVIDE MIMIC-BUS

LABELING OF THE EXISTING MCC WITH RAISED PHENOLIC PLASTIC.

J. NEW TRANSFORMERS SHALL BE SUSPENDED FROM STRUCTURE ABOVE AND ANCHORED THROUGH

VIBRATION ISOLATORS. GROUND TRANSFORMER SECONDARY NEURTAL CONDUCTORS PER

REQUIREMENTS.

(GENERAL NOTES SHALL APPLY TO ALL SHEETS)

ELECTRICAL GENERAL NOTES:

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

100% CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

10360 Ellison Circle Omaha, NE 68134 Phone: 402.991.5520 www.specializedeng.com

SES Project : 23133

A u to d e s k D o c s /2

.0

V A

C o lu m b ia

M

O

C o rr e c t E le c tr ic a l D e fi c ie n c ie s /5

A

-2

-1

.E

.R

.r v t

/1

/2

:3

:1

A

M

E00

ELECTRICAL SYMBOLS AND

ABBREVIATIONSIntroba

6 S Old Orchard Ave Suit 285

Saint Louis, MO 63119

800.404.7677

CORRECT ELECTRICAL

DEFICIENCIES, HARRY S TRUMAN

VAMC

800 Hospital Drive, Columbia, MO 65201

589A4-23-104

05/17/2024 AEA CTB

ELECTRICAL EQUIPMENT

SYMBOLS

PLAN SYMBOL NAME

AUTOMATIC TRANSFER SWITCH

DISTRIBUTION PANEL

ENCLOSED CIRCUIT BREAKER -

SURFACE

ENCLOSED DISCONNECT

SWITCH - FUSED

ENCLOSED DISCONNECT

SWITCH - NON-FUSED

GENERATOR

PANELBOARD - RECESSED

PANELBOARD - SURFACE

SWITCHBOARD

TRANSFORMER - DRY TYPE

TRANSFORMER - OIL FILLED

VARIABLE FREQUENCY DRIVE

ONE LINE SYMBOL

PLAN SYMBOL NAME

CONTINUATION

ENCLOSED CIRCUIT BREAKER

GROUND BAR

GROUNDING ELECTRODE

PANEL BOARD

SURGE PROTECTIVE DEVICE

SWITCHBOARD/SWITCHGEAR

TRANSFORMER

L

E N

L

E N

SPD

STEAM

GENERATOR

D P B

IC

U V Q

M C C P J V Q

M C C P J V Q

L P J V Q

T B D D .0 V Q

ATS-EQ2

1600A-3P

480V-3ɸ-3W

BYPASS

ISOLATION

ATS-EQ

1600A-3P

480V-3~-3W

BYPASS ISOLATION

NA 110A NA NA 23A

(1)#4/0 G. 3-1/2"C.

(5)SETS OF (3)#500,

FOR CONT.

SEE SHEET

ED11

EQ2

PULLBOX

150AF

100AT

3P

100AT

3P

100AF

600AT

3P

600AF

600AT

3P

600AF

300AT

3P

400AF

45AT

3P

60AF

800AT

3P

800AF

C H

C H

C H

MCCB-BB7.6-480VQ

TB-H14-120VQ

SQUARE D

EE112T3HCU

150° RISE

3.8% Z

XFMR

TB-D08.9-120VQ

DPB-H14-480VQ, GE SPECTRA SERIES,

1600A 480V-3ɸ-3W 65KAIC

(3)#1,(1)#4G,1"C.

400AF

400AT

400AP

600AF

250AP

M C C M V Q

LPB-H14-120VQ

SQUARE D NQ442L2C

25KAIC

225A MCB

TO DPB-Ja14-277VN, 3-B

TO CIRCUIT BREAKER IN PARALLELING SWITCHGEAR EGB-F14-277CG

480∆-208Y/120V

EX MCCB-G14-480VQR

800A, 480V, 3∅, 3W

GE EVOLUTION SERIES E900

CAT# 0859X0928M01

EX MCCB-G14-480VQF

800A, 480V, 3∅, 3W

GE EVOLUTION SERIES E900

CAT# 0859X0928M02

(2)SETS OF (3)#350

(1)#1/0 G. 3"C.

(5)SETS OF (3)#500

(1)#1/0 G. 3"C.(5)SETS OF (3)#500

(1)#4/0 G. 3"C.

TO CIRCUIT BREAKER IN PARALLELING SWITCHGEAR EGB-F14-277CG

250AT

LSILSI

400AF

250AT

250AP

LSI

400AF

300AT

300AP

LSI

150AF

100AT

100AP

LSI

400AF

400AT

400AP

LSI

400AF

400AT

400AP

LSI

400AF

200AT

200AP

LSI

600AF

600AT

600AP

LSI

600AF

600AT

600AP

LSI

NA 80A NA

120A 77A

DPB-DD8.9-277VQ, 1600A, 480Y/277V, 3∅, 4W, 25KAIC

(5)SETS OF (3)#500,

(1)#4/0 G. 3-1/2"C.

TO DPB-Ja14-277VN, 6-C

MAIN HOSPITAL

(5)SETS OF (3)#500

(1)#1/0 G. 3"C.

NORMAL SWITCHGEAR

MAIN HOSPITAL

NORMAL SWITCHGEAR

G013

D020

D022 D022

D022

D022

D022 D022

6 6 6 6 6 6

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

100% CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

10360 Ellison Circle Omaha, NE 68134 Phone: 402.991.5520 www.specializedeng.com

SES Project : 23133

A u to d e s k D o c s /2

.0

V A

C o lu m b ia

M

O

C o rr e c t E le c tr ic a l D e fi c ie n c ie s /5

A

-2

-1

.E

.R

.r v t

/1

/2

:4

:4

P

M

ED10

B1 EQUIPMENT ATS ONE-LINE

DIAGRAM DEMOLITIONIntroba

6 S Old Orchard Ave Suit 285

Saint Louis, MO 63119

800.404.7677

CORRECT ELECTRICAL

DEFICIENCIES, HARRY S TRUMAN

VAMC

800 Hospital Drive, Columbia, MO 65201

589A4-23-104

05/17/2024

SHEET NOTES:

1. DISCONNECT AND REMOVE EXISTING ATS. PULL BACK AND PREPARE

SUPPLY AND LOAD FEEDERS FOR RECONNECTION TO NEW ATS.

2. INTERCEPT EXISTING FEEDER FROM PARALLELING SWITCHGEAR EGB-

F14-277VG. PREPARE EXISTING CONDUITS FOR EXTENSION TO NEW

ATS-EQ1AND ATS-EQ3 LOCATIONS AND REMOVE CABLES. REFER TO

NEW WORK PLAN FOR MORE INFORMATION.

3. DEMOLISH NORMAL POWER FEEDER FROM ATS TO NORMAL

SWITCHGEAR.

4. REMOVE ATS-EQ2 PULLBOX. CUT AND PULL BACK CABLES WITH

ENOUGH LENGTH TO TERMINATE ON NEW DISTRIBUTION

SWITCHBOARD DPB-G13-480VQ. TRIM CONDUITS AS NEEDED. REFER

TO NEW WORK PLAN FOR MORE INFORMATION.

5. REMOVE EXISTING FEEDER AND AUTOMATIC TRANSFER SWITCH ATS-

EQ TO EXISTING DISTRIBUTION SWITCHBOARD DPB-H14-480VQ.

PREPARE EXISTING FEEDER FOR EXTENSION/RECONNECTION TO NEW

DEVICE. REFER TO NEW WORK PLAN FOR MORE INFORMATION.

6. DISCONNECT AND RELOCATE EXISTING LOADS TO NEW DISTRIBUTION

SWITCHBOARD DPB-G14-277VQ AND DPB-G13-277VQ TO MAKE ROOM

FOR MODIFICATIONS TO EXISTING SWITCHBOARD. REFER TO NEW

WORK PLAN FOR MORE INFORMATION.

NO SCALEED10

ATS DEMO B1 EQUIPMENT1

1. ATS-EQ2 SYSTEM:

a. RELOCATE TRANSFORMER TB-G13-120VN AND PANELBOARD LPB-

G13-120VN.

b. PREPARE ATS EQ2 SYSTEM REPLACEMENT AS MUCH AS POSSIBLE.

c. INTERCEPT TWO SETS OF THE FIVE SETS OF LOAD SIDE FEEDER

CONDUITS IN PIPE BASEMENT BELOW ATS-EQ2 PULLBOX. PULL

CABLES OUT WITH ENOUGH CABLE LENGTH FOR FINAL

TERMINATIONS BACK INTO NEW SWITCHBOARD DPB-G13-277VQ.

d. PROVIDE TEMPORARY CABLES FROM CRITICAL POWER CAM LOCK

BOX TO LOCATION OF CABLE INTERCEPT BELOW BASEMENT AND

SPLICE CABLES.

e. SET CAMLOCK BOX CIRCUIT BREAKER TO MAX 800AMPS SETTING.

f. DISCONNECT THE OTHER 3 SETS OF CABLES AT SWITCHBOARD

DPB-DD8.9-277VQ FROM ATS-EQ2 AND MAKE SAFE.

g. CONFIRM ALL CABLES IN ATS-EQ2 PULL BOX ARE NO LONGER

ENERGIZED AND SAFE TO WORK ON AND SWITCHBOARD DPB-

DD8.9-277VQ IS ENERGIZED FROM ATS-C4.

h. REMOVE ATS-EQ2 PULL BOX.

i. REPLACE ATS-EQ2 AND INSTALL NEW SWITCHBOARD DPB-

B13-277VQ, CAMLOCK BOX DPB-G13-277VQ, CABLES AND CONDUIT.

j. IF CABLE INTERCEPT CANNOT MAINTAIN CABLE LENGTH WITHOUT

SPLICES IN A MANOR THAT FINAL TERMINATIONS AND CABLE

LENGTHS REACH NEW SWITCHBOARD, PROVIDE TWO NEW SETS

OF CABLES FROM DPB-DD8.9-277VQ MATCHING EXISTING.

k. EXTEND 2 SETS OF CONDUITS FROM CABLE INTERCEPT OR DPB-

DD8.9-277VQ TO SWITCHBOARD. DISCONNECT TEMPORARY

CABLES AND COMPLETE ALL FIVE SETS OF CABLE TERMINATIONS

AT NEW SWITCHBOARD.

l. COMPLETE REMAINING INSTALLATION INCLUDING REMOVAL OF

TEMPORARY CABLES LABELING AND CLEAN UP.

GENERAL:

A. ANY POWER OUTAGE FOR EQUIPMENT SAFETY POWER SYSTEM

SHALL HAVE METHOD OF PROCEDURE SUBMITTED 8 WEEKS

BEFORE EXPECTED WORK BEGINS FOR THE OUTAGE. INCLUDE

METERED LOAD OF POWER TO CONFIRM TEMPORARY POWER WILL

BE ADEQUATE.

B. PREPARE ALL FEEDERS, SWITCHBOARDS AND JUNCTION BOXES

THAT DO NOT REQUIRE A POWER OUTAGE PRIOR TO STARTING

WORK.

C. SIZING FOR TEMPORARY CABLES AND EQUIPMENT SHALL MATCH

EXISTING CABLES AND EQUIPMENT THAT REQUIRES TEMPORARY

POWER.

D. REPLACE ONE ATS AND ASSOCIATED SWITCHBOARDS AT A TIME.

DURING POWER OUTAGE, ONLY THE TIME TO TRANSFER AND

EQUIPMENT POWER SINGLE FEEDER AT A TIME SHOULD TAKE

PLACE. NO ASSUMPTION SHOULD BE MADE THAT COMBINING

MULTIPLE FEEDER REPLACEMENTS IN A SINGLE TIME PERIOD IS

ALLOWED. MULTIPLE FEEDER REPLACEMENTS MAY ONLY BE

ALLOWED IF METHOD OF PROCEDURE (MOP) IS APPROVED.

Revisions: Date:

1. DEDUCT 4: REMOVE SCOPE OF WORK FOR REPLACEMENT AND

ASSOCIATED WORK FOR THE REPLACEMENT OF ATS-EQ1, ATS-EQ2,

ATS-EQ3, AND ATS-EQ4 INCLUDING ATS METERING, SUPPLY AND LOAD

FEEDERS, SWITCHBOARDS DPB-G13-277VQ, DPB-H14-277VQ, DPB-

G14-277VQ, DPB-J13-277VQ, AND CAMLOCK BOX FOR DEDUCT

ALTERNATE 4. NOTE, THIS MEANS ALL WORK SHOWN ON THIS SHEET.

SHEET DEDUCT GENERAL NOTES:

BUILDING ONE EQUIPMENT POWER

ATS'S PHASING:

M

E N

L

E NN

L

E

L

E N M

GEN

GEN

M

ATS-C3

600A-4P

480V

BYPASS

ISOLATION

S P A C E

ATS-C1

GE-ZENITH

600A-4 POLE

480Y/277V -3ɸ-4W

BYPASS ISOLATION

SOLID GROUND

DS-C2

800A 600V

FERRAZ

SHAWMUH

800AF

DS-DPB-J4-480VC

800A 600V

FUSTRON

FRN-R-35

DPB-G13-277VC, (DP-CRITICAL-2), 480Y/277V-3 ɸ-4W, 800A BUS 25KAIC, 87.5KVA PEAK LOAD

250AF

150AT

3P

250AF

150AT

3P3P

400AF

300AT

3P

60AF

40AT

3P

60AF

50AT150AT

3P

150AF

150AT

3P

250AF

100AT

3P

250AF

150AT

3P

150AF60AF

60AT

3P

250AF

150AT

3P

60AT

60AF

DP-CRITICAL 1, GE-SPECTRA SERIES, 480Y/277V-3~-4W,

600A BUS 65KAIC

3P

300AT

400AF

3P

175AT

250AF

3P

100AT

100AF

3P

225AT

250AF

3P

ATS-C2

GE-ZENITH

800A-4 POLE

480Y/277V-3

BYPASS ISOLATION

SOLID GROUND

FOR CONT.

SEE SHEET

ED12

FOR CONT.

SEE SHEET

ED10

100A 3P3P

100A

DPB-G14-480VC, 600A,

(DP-CRITICAL 3)

3P 400A

3P 225A

SPARE SPARE

(2)SETS OF (4)#350

(1)#1 G. 3"C.

800AF

800AT

3P

G3G2

1600AF

1600AT

3P

1600AF

1600AT

3P

G1

MASTER

CONTROL

1600AF

1600AT

3P

1600AT

1600AF

3P

1600AF

1600AT

3P

800AF

800AT

3P

600AF

600AT

3P

1200AF

800AT

3P

400AF

3P

200AT

480Y/277V-

1250KW

3P

600AF

3P

400AF

200AT

480Y/277V-

1250KW

2000A2000A2000A4000A

S P A C E

2000A

600AF

600AT

3P

600AF

600AT

3P

S P A R E

3P

150AF

125AT

2000A2000A2000A

(4) SETS OF (4)#600, (1)#4/0G, 4"C

GENERATOR

CONNECTION

CABINET

1600A BUS DUCT

S P A C E3P

1600AF

1600AT1

A

F E E D E R

BUS DUCT

MAIN

ATS-EQ ATS-EQ2ATS-ELATS-LSATS-C2ATS-GENATS-C1ATS-C3

600AT

ATS-FPATS-C4

800AF

400AT

3P

S P A C E

S P A R E

800AF

800AT

3P

S P A C E

400AF

200AT

3P

S P A R E

800AF

800AT

3P

800AF

400AT

3P

150AF

125AT

3P

S P A R E

2000A 2000A 1600A 1600A 1600A

S P A R E

ATS-C4D

P B C

V N

V N

I-0

ATS-C3

I-0

LP

B G N

P

LB

G

LP

,5

A

TS

M C C

LT-1

ST-.4

TS

C

LT-1

LTd-3

ST-8

STd-1

P P B .5

TS

B

V N

V N

LP

,2

800AF

400AT

3P

LT-1

LTd-3

ST-8

STd-1

800AF

400AT

3P

LT-1

LTd-3

ST-4

STd-1

400AF

200AT

3P

LT-1

LTd-1

ST-4

STd-1 LT-1

LTd-3

ST-9

STd-1

800AF

300AT

3P

LT-1

LTd-3

ST-6

STd-1

800AF

600AT

3P

1600AF

1600AT

3P

LT-1

LTd-4

STPU-2

STd-1

400AF

400AT

3P

LT-1

LTd-1

ST-1

STd-1

800AF

400AT

3P

LT-1

LTd-3

ST-5

STd-1

800AF

800AT

3P

LT-1

LTd-3

ST-4

STd-1

800AF

800AT

3P

LT-1

LTd-3

ST-4

STd-1

LT-1

LTd-3

ST-6

STd-1

800AF

400AT

3P

GFs-.02 GFd-1

I-5 GFs-.02 GFd-4

I-2 GFs-.02

GFd-1 I-5

ATS-C4

1600A.4P 480Y/277V 3∅, 4W

BYPASS

ISOLATION

800A

GE SKLB

SRPK

800/800

800A

GE SKLB

SRPK

800/800

800AF

600AT

3P

200AF

200AT

3P

250A 3P

250A 3P

DPB-H15-480VC, 1600A, 3∅, 4W, 480/277

(5) SETS OF (4)#500,

(1)#4/0 G. 3-1.2"C.

S P A R E

S P A R E

S P A R E

LP

E V C

D P B L4 V C

TS

L4 V C

D P B L4 .4 V C

D P J9 V C

LP

J9 V C

D P B .3

V N

D P C

D P L4 .3

P P E a

E

LE

V A

TO

R

M N

(2) SETS OF

(4)#350,(1)#1G,2 1/2"C

M E D

A

IR

M E D

V A C

P U M P

V A C

P U M P

2P P B J V C

L P J V C

L P M V C

P P B N V C

X F M R

T B G V C

L P B H V C

L P B C V C

X F M R

T F V C

CABLE

TOP

BOX

T X E V C

O L D

C A T H

L A B

M D P

P P B L V C

D P B J V N

X F M R

T F V C K V A

600A PLUG-IN

BUSDUCT-CRITICAL

SPACE

400AF

SPACE

600AF

3P

800AT

1200AF

3P

200AT

3P

400AF600AF

3P

600AT

600AF

600AT

DPB-J4-480VC, 480Y/277V-3ɸ-4W 800A BUS 65KAIC

3P

250A

HJD65K

3P

250A

HJD65K

3P

30A

3P

200A

C T R M

B

C T R M

B

G A R A G E

E L E C

R M

E

100A

3P

50A

3P

300A

3P

HJD65K

250A

3P

HJD65K

100A

3P

X F M R

L O C A T E D

IN

A

U P S

800A-3P

HDML65K

S P A R E

S P A R E

50A

3P

HJD65K

300A

3P

HJD65K

C T

R M

B M

P P B P V C

P P B H b V C

L P H V C

TS-E4-120VC

DSS-E4-120VC

TO ATS GEN

T B P V C

T B L

K V A

TO 3-B, 2000AF,

1600AT, 3P, MAIN

HOSPITAL NORMAL

SWITCHGEAR

DPB-H14-277VN, 1600A, 480V, 3∅, 4W, 65KAIC

(1)#1/0 G. 3-1/2""C.

(2)SETS OF (4)#500,

DPB-Ha13-277VN, 2000A BUS

TO ATS-EQ EMERGENCY FEED SIDE

TO ATS-EQ2 EMERGENCY FEED SIDE

TO ATS-LS EMERGENCY FEED SIDE

TO ATS-LS NORMAL SIDE

TO ATS-EL EMERGENCY FEED SIDE

TO ATS-EL NORMAL FEED SIDE

480Y/277V-

3∅-4W

PARALLELING SWITCHGEAR, EGB-F14-277VG,

5000A BUS, 480Y/277V, 3∅, 4W

3P

1600AF

---AT

SPARE

3P

1600AF

---AT

SPARE

3P

1600AF

---AT

SPARE

(1)#1/0 G. 3-1/2"C.

(2)SETS OF (4)#500,

(1)#1/0 G. 3"C.

(2)SETS OF (4)#350,

(1)#1/0 G. 3-1/2"C.

(2)SETS OF (4)#500,

(1)#1/0 G. 3"C.

(2)SETS OF (4)#350,

(2)SETS OF (4)#350, (1)#1/0 G. 3"C.

(2)SETS OF (3)#350, (1)#1/0 G. 3"C.

(5)SETS OF (4)#500, (1)#1/0 G. 3-1/2""C.

(5)SETS OF (3)#500, (1)#4/0 G. 3"C.

(5)SETS OF (4)#500, (1)#4/0 G. 3"C.

(2)SETS OF (4)#350,

(1)#1 G. 3"C.

(2)SETS OF (4)#350,

(1)#1/0 G. 3"C. (2)SETS OF (4)#350,

(1)#1/0 G. 3"C.

(1)#1 G. 3"C.

(2)SETS OF (4)#350,

D022B

D022B

D020

D022

D020

D020

D020

D022 D022

D020 D020

D022 D022

D023 D023

D022C

3 3

1 1

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

100% CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

10360 Ellison Circle Omaha, NE 68134 Phone: 402.991.5520 www.specializedeng.com

SES Project : 23133

A u to d e s k D o c s /2

.0

V A

C o lu m b ia

M

O

C o rr e c t E le c tr ic a l D e fi c ie n c ie s /5

A

-2

-1

.E

.R

.r v t

/1

/2

:4

:4

P

M

ED11

B1 CRITICAL ATS ONE-LINE

DIAGRAM DEMOLITIONIntroba

6 S Old Orchard Ave Suit 285

Saint Louis, MO 63119

800.404.7677

CORRECT ELECTRICAL

DEFICIENCIES, HARRY S TRUMAN

VAMC

800 Hospital Drive, Columbia, MO 65201

589A4-23-104

05/17/2024

SHEET NOTES:

1. DISCONNECT AND REMOVE EXISTING ATS. PREPARE EXISTING

INCOMING FEEDERS FOR RECONNECTION TO NEW ATS.

2. DISCONNECT AND REMOVE EXISTING 800A DISCONNECT SWITCH.

REMOVE INCOMING AND OUTGOING FEEDERS. SALVAGE BELOW SLAB

CONDUIT FOR REUSE. REFER TO NEW WORK PLAN FOR MORE

INFORMATION.

3. DISCONNECT AND REMOVE EXISTING SWITCHBOARD. DISCONNECT

AND PREPARE EXISTING BRANCH CIRCUITING FOR RECONNECTION TO

NEW SWITCHBOARD. REFER TO NEW WORK PLAN FOR MORE

INFORMATION.

4. REMOVE EXISTING FEEDER FROM DEMOLISHED 800A DISCONNECT

SWITCH TO BELOW PIPE BASEMENT. PREPARE EXISTING CONDUIT AND

WIRE FOR RECONNECTION/EXTENSION. REFER TO NEW WORK PLAN

FOR MORE INFORMATION.

5. DEMOLISH EXISTING FEEDER FROM EXISTING ATS-C4 TO EXISTING

DISTRIBUTION SWITCHBOARD DPB-H15-480VC. REFER TO NEW WORK

PLAN FOR MORE INFORMATION.

6. DEMOLISH EXISTING FEEDER FROM EXISTING ATS-C2 TO EXISTING

DISCONNECTS TO EXISTING DISTRIBUTION PANELBOARD DPB-

G13-277VC. REFER TO NEW WORK PLAN FOR MORE INFORMATION.

7. REMOVE EXISTING FEEDERS.

NO SCALEED11

ATS DEMO B1 CRITICAL1

GENERAL:

A. ANY POWER OUTAGE FOR CRITICAL POWER SYSTEM SHALL HAVE

METHOD OF PROCEDURE (MOP) SUBMITTED 8 WEEKS BEFORE

EXPECTED WORK BEGINS FOR THE OUTAGE. INCLUDE METERED

LOAD OF POWER TO CONFIRM TEMPORARY POWER WILL BE

ADEQUATE.

B. PREPARE ALL FEEDERS, SWITCHBOARDS AND JUNCTION BOXES

THAT DO NOT REQUIRE A POWER OUTAGE PRIOR TO STARTING

WORK.

C. SIZING FOR TEMPORARY CABLES AND EQUIPMENT SHALL MATCH

EXISTING CABLES AND EQUIPMENT THAT REQUIRES TEMPORARY

POWER.

D. REPLACE ONE ATS AND ASSOCIATED SWITCHBOARDS AT A TIME.

E. DURING POWER OUTAGE, ONLY THE TIME TO TRANSFER A LIFE

SAFETY POWER SINGLE FEEDER AT A TIME SHOULD TAKE PLACE.

NO ASSUMPTION SHOULD BE MADE THAT COMBINING MULTIPLE

FEEDER REPLACEMENTS IN A SINGLE TIME PERIOD IS ALLOWED.

MULTIPLE FEEDER REPLACEMENTS MAY ONLY BE ALLOWED IF

METHOD OF PROCEDURE (MOP) IS APPROVED.

1. ATS-C4 SYSTEM:

a. COMPLETE INSTALLATION OF CRITICAL POWER CAM LOCK BOX

DPB-H15-277VC EXCEPT FOR FINAL TERMINATIONS TO

SWITCHBOARD DPB-H15-277VC.

b. PROVIDE COMPLETE TEMPORARY POWER ATS SYSTEM INCLUDING

800ATS, TEMPORARY NORMAL SUPPLY CONDUCTORS FROM DPB-

HA13-277VN SWITCHGEAR AND TEMPORARY 800A SPARE BREAKER,

TEMPORARY CRITICAL SUPPLY CONDUCTORS FROM PARALLELING

SWITCHGEAR EGB-F14-277VG AND TEMPORARY 800A BREAKER,

TEMPORARY LOAD SIDE CABLES TO CAM LOCK BOX.

c. REMOVE SUPPLY CABLES FROM ATS-C4 TO SWITCHBOARD DPB-

H15-277VC. INSTALL CAMLOCK BOX BI-DIRECTIONAL BREAKER AND

NEW DPB-J4-480VC BREAKER IN SWITCHBOARD DPB-H15-177VC.

TERMINATE CAMLOCK BOX CABLES.

d. COMPLETE TEMPORARY POWER TRANSFER TO TEMPORARY ATS

FOR SWITCHBOARD DPB-H15-277VC AND ISOLATE SWITCHBOARD

TO PREPARE FOR THE FEEDER SECTION RECONFIGURATION AND

SWITCHBOARD ADDITIONS.

e. INSTALL NEW DPB-H15-277VC-1 AND FEEDER TO ATS -C4.

f. PROVIDE TESTING OF ATS-C4.

g. AFTER TESTING IS COMPLETE, INSTALL FEEDER CONNECTION

BETWEEN DPB-H15-277VC-1 AND DPB-H15-277VC-2 AND

DISCONNECT TEMPORARY ATS SYSTEM.

h. COMPLETE SWITCHBOARD DPB-J4-480VC FEEDER RELOCATION TO

DPB-H15-277VC.

i. COMPLETE REMAINING INSTALLATION INCLUDING LABELING AND

CLEAN UP.

j. REMOVE TEMPORARY ATS SYSTEM.

2. ATS-C1 SYSTEM:

a. PREPARE ATS C1 AND SWITCHBOARD REPLACEMENT AS MUCH AS

POSSIBLE.

b. PROVIDE A TEMPORARY DP CRITICAL-1 POWER SWITCHBOARD

WITH SAME OVERCURRENT AND BRANCH CIRCUIT PROTECTION AS

EXISTING. PROVIDE TEMPORARY CONNECTION FROM CRITICAL

POWER CAM LOCK BOX TO TEMPORARY SWITCHBOARD.

c. TRANSFER ONE BRANCH FEEDER FROM CRITICAL-1 POWER

SWITCHBOARD TO TEMPORARY SWITCHBOARD AT A TIME. PULL

CABLES OUT FROM NEAREST PULL BOX AND EXTEND AS NEEDED

FOR TEMPORARY POWER. PROVIDE NEW JUNCTION BOXES AND

CONDUIT IF NEEDED.

d. AFTER ALL LOADS HAVE BEEN TEMPORARY LOCATED TO TEMP

POWER SWITCHBOARD, REPLACE DP CRITICAL-1 SWITCHBOARD

AND ATS-C1.

e. PROVIDE TESTING OF ATS-C1.

f. TRANSFER LOADS BACK FROM TEMPORARY SWITCHBOARD TO

NEW SWITCHBOARD. EXTEND CABLES AND CONDUIT AS NEEDED

FOR A COMPLETE INSTALLATION.

g. COMPLETE REMAINING INSTALLATION INCLUDING, REMOVAL OF

TEMPORARY CABLES AND EQUIPMENT, LABELING AND CLEAN UP.

3. ATS-C2 SYSTEM:

a. PREPARE ATS C2 AND SWITCHBOARD REPLACEMENT AS MUCH AS

POSSIBLE.

b. PROVIDE A TEMPORARY DP CRITICAL-2 POWER SWITCHBOARD

WITH SAME OVERCURRENT AND BRANCH CIRCUIT PROTECTION AS

EXISTING. PROVIDE TEMPORARY CONNECTION FROM CRITICAL

POWER CAM LOCK BOX TO TEMPORARY SWITCHBOARD.

c. TRANSFER ONE BRANCH FEEDER FROM CRITICAL-2 POWER

SWITCHBOARD TO TEMPORARY SWITCHBOARD AT A TIME. PULL

CABLES OUT FROM NEAREST PULL BOX AND EXTEND AS NEEDED

FOR TEMPORARY POWER. PROVIDE NEW JUNCTION BOXES AND

CONDUIT IF NEEDED.

d. AFTER ALL LOADS HAVE BEEN TEMPORARY LOCATED TO TEMP

POWER SWITCHBOARD, REPLACE DP CRITICAL-2 SWITCHBOARD

AND ATS-C2.

e. PROVIDE TESTING OF ATS-C2.

f. TRANSFER LOADS BACK FROM TEMPORARY SWITCHBOARD TO

NEW SWITCHBOARD AND COMPLETE INSTALLATION. EXTEND

CABLES AND CONDUIT AS NEEDED FOR A COMPLETE

INSTALLATION.

g. COMPLETE REMAINING INSTALLATION INCLUDING REMOVAL OF

TEMPORARY CABLES AND EQUIPMENT, LABELING AND CLEAN UP.

4. ATS-C3 SYSTEM:

a. PREPARE ATS C3 AND SWITCHBOARD REPLACEMENT AS MUCH AS

POSSIBLE.

b. DISCONNECT AND PROTECT SUPPLY CABLES FROM DISTRIBUTION

SWITCHBOARD DPB-G14-480VC.

c. PROVIDE TEMPORARY CABLES FROM CRITICAL CAM LOCK BOX AND

TERMINATE ON DPB-G14-480VC.

d. REPLACE ATS-C3 AND PROVIDE TESTING.

e. TRANSFER LOADS BACK FROM CRITICAL CAM LOCK BOX TO

PERMANENT SUPPLY CONDUCTORS.

f. COMPLETE REMAINING INSTALLATION INCLUDING REMOVAL OF

TEMPORARY CABLES LABELING AND CLEAN UP.

Revisions: Date:

BUILDING ONE CRITICAL POWER ATS'S

PHASING:

L

NE

ATS-LS

600A-4 POLE

480Y/277V-3~-4W

BYPASS ISOLATION

SOLID GROUND

ATS-EL

600A-4

POLE

480Y/277V-3ɸ-3W

BYPASS

ISOLATION

SOLID

GROUND

FOR CONT.

SEE SHEET

ED11

S P A C E

S P A C E

150AT

3P

100AT

3P

150AT

3P

150AF150AF 150AF

DP-LIFE SAFETY, GE SPECTRA SERIES, 600A,

150AT

3P

150AF

L P B D D .9 V E

L P B H V E

L P B H V E

TO DPB-J14-480VE

175A

FD35K

3P

PPP-K8-480VQ

EATON PRL3A

600A

S P A C E175A

FD35K

3P

125A

FD35K

3P

125A

FD35K

3P

125A

FD35K

3P

E

LE

V A

TO

R

E

LE

V A

TO

R

E

LE

V A

TO

R

E

LE

V A

TO

R

E

LE

V A

TO

R

TO CIRCUIT BREAKER IN PARALLELING SWITCHGEAR EGB-F14-277CG

TO CIRCUIT BREAKER IN PARALLELING SWITCHGEAR EGB-F14-277CG

TO CIRCUIT BREAKER IN DPB-H14-277VN

TO CIRCUIT BREAKER IN DPB-Ha13-277VN, 2000A BUS

(2)SETS OF (4)#350, (1)#1/0G. 3"C.

(2)SETS OF (4)#350, (1)#1/0G. 3"C.

(2)SETS OF (4)#350,

(1)#1/0G. 3"C.

250AT

3P

250AF

L P B G V E

480V-3∅, 4W, 65KAIC

E45

D022

D020

D022

1 1

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

100% CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

10360 Ellison Circle Omaha, NE 68134 Phone: 402.991.5520 www.specializedeng.com

SES Project : 23133

A u to d e s k D o c s /2

.0

V A

C o lu m b ia

M

O

C o rr e c t E le c tr ic a l D e fi c ie n c ie s /5

A

-2

-1

.E

.R

.r v t

/1

/2

:4

:4

P

M

ED12

B1 LIFE SAFETY ATS ONE-LINE

DIAGRAM DEMOLITIONIntroba

6 S Old Orchard Ave Suit 285

Saint Louis, MO 63119

800.404.7677

CORRECT ELECTRICAL

DEFICIENCIES, HARRY S TRUMAN

VAMC

800 Hospital Drive, Columbia, MO 65201

589A4-23-104

05/17/2024

SHEET NOTES:

1. DISCONNECT AND REMOVE EXISTING ATS. PREPARE EXISTING

INCOMING AND OUTGOING FEEDERS FOR RECONNECTION TO NEW

ATS.

12" = 1'-0"

ATS DEMO B1 LIFE SAFETY

GENERAL:

A. ANY POWER OUTAGE FOR LIFE SAFETY POWER SYSTEM SHALL

HAVE METHOD OF PROCEDURE SUBMITTED 8 WEEKS BEFORE

EXPECTED WORK BEGINS FOR THE OUTAGE. INCLUDE METERED

LOAD OF POWER TO CONFIRM TEMPORARY POWER WILL BE

ADEQUATE.

B. PREPARE ALL FEEDERS, SWITCHBOARDS AND JUNCTION BOXES

THAT DO NOT REQUIRE A POWER OUTAGE PRIOR TO STARTING

WORK.

C. SIZING FOR TEMPORARY CABLES AND EQUIPMENT SHALL MATCH

EXISTING CABLES AND EQUIPMENT THAT REQUIRES TEMPORARY

POWER.

D. REPLACE ONE ATS AND ASSOCIATED SWITCHBOARDS AT A TIME.

E. DURING POWER OUTAGE, ONLY THE TIME TO TRANSFER A LIFE

SAFETY POWER SINGLE FEEDER AT A TIME SHOULD TAKE PLACE.

NO ASSUMPTION SHOULD BE MADE THAT COMBINING MULTIPLE

FEEDER REPLACEMENTS IN A SINGLE TIME PERIOD IS ALLOWED.

MULTIPLE FEEDER REPLACEMENTS MAY ONLY BE ALLOWED IF

METHOD OF PROCEDURE (MOP) IS APPROVED.

1. ATS-LS SYSTEM:

a. PREPARE ATS LS REPLACEMENT AS MUCH AS POSSIBLE.

b. DISCONNECT AND PROTECT SUPPLY CABLES FROM DISTRIBUTION

SWITCHBOARD DPB-LIFE SAFETY.

c. PROVIDE TEMPORARY CABLES FROM CRITICAL CAM LOCK BOX AND

TERMINATE ON DPB-LIFE SAFETY SWITCHBOARD.

d. REPLACE ATS-LS AND PROVIDE TESTING.

e. TRANSFER LOADS BACK FROM CRITICAL CAM LOCK BOX TO

PERMANENT SUPPLY CONDUCTORS.

f. COMPLETE REMAINING INSTALLATION INCLUDING REMOVAL OF

TEMPORARY CABLES LABELING AND CLEAN UP.

2. ATS-EL SYSTEM:

a. PREPARE ATS EL REPLACEMENT AS MUCH AS POSSIBLE.

b. DISCONNECT AND PULL BACK LOAD SIDE CABLES FROM ATS-EL.

c. PROVIDE TEMPORARY CABLES FROM CRITICAL CAM LOCK BOX AND

SPLICE WITH LOAD SIDE ATS-EL CABLES.

d. REPLACE ATS-EL AND PROVIDE TESTING.

e. PROVIDE NEW JUNCTION BOX AND EXTEND CABLES AS NEEDED TO

TRANSFER LOADS BACK FROM CRITICAL CAM LOCK BOX TO

PERMANENT SUPPLY CONDUCTORS.

l. COMPLETE REMAINING INSTALLATION INCLUDING REMOVAL OF

TEMPORARY CABLES LABELING AND CLEAN UP.

Revisions: Date:

1. DEDUCT 3: REMOVE SCOPE OF WORK FOR REPLACEMENT AND

ASSOCIATED WORK FOR THE REPLACEMENT OF ATS-1, ATS-3, ATS-EL,

ATS LS, AND ATS-CH INCLUDING ATS METERING, SUPPLY AND LOAD

FEEDERS AND ATS-CH DISCONNECTS FOR DEDUCT ALTERNATE 3.

NOTE, THIS MEANS ALL WORK SHOWN ON THIS SHEET.

SHEET DEDUCT GENERAL NOTES:

BUILDING ONE LIFE SAFETY POWER

ATS'S PHASING:

N E

L

E N

L

E N

L

E N

M

L

E N

M

60 60

40 40

ATS-3

ASCO-7000

250A

CLOSED TRANSITION

MAINT. BYPASS

SOLID NEUTRAL

NO NEUTRAL

CONDUCTORS

ATS-1

ASCO-7000

400A

CLOSED TRANSITION

MAINT. BYPASS

(3)#350,(1)#4G,2 1/2"C

(3)#350,(1)#4G,2 1/2"C

(2) SETS OF (3)#350MCM,(1)#4G, 2-1/2"C

800AT

3P

300AT

3P

400AT

3P

800AT

3P

300AT

3P

400AT

3P

800AF800AF 800AF 800AF800AF 800AF

400AT

3P

800AF

3200AT

3P

3200AF

800A

SPACE

3P

300AP

3P

400AP

3P

800AP

3P

400AT

3P

800AF 800AF800AF 800AF

1200AT

3P

1600AF

150A

3P 3P 3P

100A 100A 200A

P-9 P-10

150A 150A

HJ150 HJ150 HJ150

S-11A S-11B

MCC-D8-480VA

480/277V, 3 PHASE, 3W

800A BUS

400A

MAIN

3P

100AF

100AT

3P

250AF250AF

175AT

3P

150AF

150AT

3P

125AT

3P

250AF

SPACE

3P

250AF

125AT

3P

TO

LP

B V N (3)#6, (1)#6G. 3/4"C.

S P A C E

1200A

3P

800A

3P

1200AF

3P

400AF

3P

1200A

3P

1200A

3P

S P A C E

S P A C E

S P A C E

S P A C E

C H

IL

LE

R

C H

IL

LE

R

C H

IL

LE

R

1000A1200A1200A

1000AT200AT

601A

4000AT

3P, LSIG

4000AF

NO

LSIG

400AF

3P

200AT

400AF

3P

200AT

1600AF

3P

1200AT

LSILSILSIG

C H

IL

LE

R

100AF

3P

60AT

LSI

ATS-4

ASCO-7000

400A

SWITCHED

NEUTRAL

MDP

SIEMENS

RCIII

SOLID NEUTRAL

NO NEUTRAL

CONDUCTORS

LVB-B3-277VN

(2) SETS OF (3)#3/0,(1)#3G,2"C

(2) SETS OF (3)#3/0,(1)#3G,2"C

(2) SETS OF (3)#3/0,(1)#3G,2"C

LVB-C8-277VG

GE AKD-8

SWITCHGEAR

GROUND FAULT MONITORING:

MAIN

ATS-2

ATS-4

DPB-C8-480VA, SQUARE D,

HCM23646 E1, 600A, 2A,

25A, 19A

DPB-D8-277VE, 480/277V, 400A, 22KAIC

T O

M C C D V N

T O

M C C D V N

E-POWER

SIEMENS-NF352

60A

N-POWER

SIEMENS-NF352

60A

(3)#6,(1)#6G,1"C (3)#2,(1)#6G,1 1/4"C

FROM LPB-H12-277VE

2500A

4000A SUPPLY, 4W

2000A VERTICAL, 4W

200,000 AIC 2000A

4000A, 480Y/277V

ALTERNATE

SOURCE SECTION

TO T6B

TO LP1-B1-277VN

ATS-2

ASCO-7000

SWITCHED

NEUTRAL

CLOSED TRANSITION

MAINT. BYPASS

DPB-B3-277VC

TO 200A RECPT FOR

TEMP MRI TRAILER

HOOK-UP

(2) SETS OF (4)#3/0,(1)#3G,2"C (3) SETS OF (4)#300,

(1)#1/0G, 3"C

(3) SETS OF (4)#300, (1)#1/0G. 3"C.

(2) SETS OF (4)#3/0,(1)#3G,2"C

(3)#6, (1)#6G. 3/4"C.

MDP

SIEMENS

RCIII

4000A

3P NC

4000A

100AF

3P

60AT

LSI

TO T6

SWBD MDP-B2-277VN

RCIII, 480Y/277V, 4000A

E46

E46

E009 E009

E009

E009

E003

E009

E003A E009

ATS-CH

480V, 100A, 3P

SOLID GROUND

CLOSED TRANSITION

TRANSFER SWITCH

WALL MOUNTED

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

100% CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

10360 Ellison Circle Omaha, NE 68134 Phone: 402.991.5520 www.specializedeng.com

SES Project : 23133

A u to d e s k D o c s /2

.0

V A

C o lu m b ia

M

O

C o rr e c t E le c tr ic a l D e fi c ie n c ie s /5

A

-2

-1

.E

.R

.r v t

/1

/2

:4

:4

P

M

ED13

ACA & CHILLER HOUSE ATS

ONE-LINE DIAGRAM DEMOLITIONIntroba

6 S Old Orchard Ave Suit 285

Saint Louis, MO 63119

800.404.7677

CORRECT ELECTRICAL

DEFICIENCIES, HARRY S TRUMAN

VAMC

800 Hospital Drive, Columbia, MO 65201

589A4-23-104

05/17/2024

SHEET NOTES:

1. DISCONNECT AND REMOVE EXISTING ATS. PREPARE EXISTING

INCOMING AND OUTGOING FEEDERS FOR RECONNECTION TO NEW

ATS.

2. DISCONNECT AND REMOVE DISCONNECT SWITCH. PREPARE EXISTING

INCOMING AND OUTGOING FEEDERS FOR RECONNECTION TO MANUAL

TRANSFER SWITCH.

3. DISCONNECT AND REMOVE EXISTING FEEDERS.

NO SCALEED13

ATS DEMO ACA1

ATS NEW CHILLER HOUSE

NO SCALE

ED13

GENERAL:

A. ANY POWER OUTAGE FOR ACA EQUIPMENT SAFETY POWER

SYSTEM SHALL HAVE METHOD OF PROCEDURE SUBMITTED 8

WEEKS BEFORE EXPECTED WORK BEGINS FOR THE OUTAGE.

INCLUDE METERED LOAD OF POWER TO CONFIRM TEMPORARY

POWER WILL BE ADEQUATE.

B. PREPARE ALL FEEDERS, SWITCHBOARDS AND JUNCTION BOXES

THAT DO NOT REQUIRE A POWER OUTAGE PRIOR TO STARTING

WORK.

C. REPLACE ONE ATS AND ASSOCIATED SWITCHBOARD WORK AT A

TIME.

D. DURING POWER OUTAGE, ONLY THE TIME TO TRANSFER AN

EQUIPMENT POWER SINGLE FEEDER AT A TIME SHOULD TAKE

PLACE. NO ASSUMPTION SHOULD BE MADE THAT COMBINING

MULTIPLE FEEDER REPLACEMENTS IN A SINGLE TIME PERIOD IS

ALLOWED. MULTIPLE FEEDER REPLACEMENTS MAY ONLY BE

ALLOWED IF METHOD OF PROCEDURE (MOP) IS APPROVED.

A. ACA ATS-3 EQUIPMENT POWER SYSTEM:

a. REVIEW ABOVE CEILING ROUTING OF NORMAL SUPPLY FEEDER.

FEEDER WILL REQUIRED ADDITIONAL PULL BOXES TO AVOID HARD

CEILINGS.

b. INSTALL NORMAL AND EMERGENCY SUPPLY FEEDER TO ATS-3

FROM SWITCHGEAR LVB-B3-277VN AND LVB-C8-277VG EXCEPT FOR

TERMINATIONS.

c. PREPARE ATS-3 SYSTEM REPLACEMENT AS MUCH AS POSSIBLE.

d. REPLACE ATS-3 AND TERMINATE CABLES.

e. COMPLETE REMAINING INSTALLATION INCLUDING REMOVAL OF

TEMPORARY CABLES LABELING AND CLEAN UP.

2. ACA ATS-1 EQUIPMENT POWER SYSTEM:

a. RELOCATE FIRE ALARM AND ATS TERMINATION PANEL BOXES TO

ALLOW ROOM AND WORKING CLEARANCE FOR THE NEW ATS-1

g. PREPARE ATS-1 SYSTEM REPLACEMENT AS MUCH AS POSSIBLE.

h. REPLACE ATS-1.

i. COMPLETE REMAINING INSTALLATION INCLUDING REMOVAL OF

TEMPORARY CABLES LABELING AND CLEAN UP.

Revisions: Date:

ACA BUILDING POWER ATS'S PHASING:

1. DEDUCT 3: REMOVE SCOPE OF WORK FOR REPLACEMENT AND

ASSOCIATED WORK FOR THE REPLACEMENT OF ATS-1, ATS-3, ATS-EL,

ATS LS, AND ATS-CH INCLUDING ATS METERING, SUPPLY AND LOAD

FEEDERS AND ATS-CH DISCONNECTS FOR DEDUCT ALTERNATE 3.

NOTE, THIS MEANS ALL WORK SHOWN ON THIS SHEET.

SHEET DEDUCT GENERAL NOTES:

#6G

#6G

#6G

C1

B1 C1

N.C.

B1

B1A1

A1

PL HC PL HC PL HC

M

M

K

M

K

T1

1500KVA

PAD MTD XFMR.

13.8KV∆-480Y/277V

T2

1500KVA

PAD MTD XFMR.

13.8KV∆-480Y/277V

T3

1500KVA

PAD MTD XFMR.

13.8KV∆-480Y/277V

T5

1500KVA

PAD MTD XFMR.

13.8KV∆-480Y/277V

T4

1500KVA

PAD MTD XFMR.

13.8KV∆-480Y/277V

400A

NON-FUSED

NEMA 4X

FIRE PUMP

DISCONNECT

SWITCH

3P

2-B

MAIN C

2000AF

2000AT

(BUS C)

2000AF

1600AT

3P

1-C

3P

4-C

MAIN B

2000AT

2000AF

(BUS B)

N.C.

1600AT

3P

2000AF

5-D 3-B

N.O.

3P N.C.

MAIN A

2000AT

2000AF

7-B

(BUS A)

2000AT

3P

2000AF

WPH-16

SPACE

1600A-3P 6-C 5-B

1200A BUSDUCT

1600AF

1200AT

3P

6-B

MAIN HOSPITAL NORMAL SWITCHGEAR

2000A BUSDUCT

N.O.

KEY INTERLOCKS (TYP.)

65KAIC

3P

1200AT

1600AF

1-B

SM-5

100E

SM-5

125E

SM-5

100E

#1096 #1098 #1095

T1-S T2-S T3-S

2-C

TIE B-C

2000AF

2000AT

3P

5-C

TIE A-B

2000AF

2000AT

3P

SETTINGS:

GFPU AT 0.2

GFD AT 1 (I T OUT)

LTPU AT 1

LTD AT 3

STPU AT 6.5

STD AT 1 (I T OUT)

TO

DPB-H14-277VN

N .C

E

S M

T O

T

T

N .C

E

S M

T O

T

T

N .O

E

S M

T O

T

N .C

E

S M

T O

T

T

N .C

E

S M

T O

T

T

N .C

E

S M

T O

T

SG-H14-MVN1

13.8KV 1200A BUS

SG-H14-MVN1

13.8KV 1200A BUS

1200AF

400AT

3P N.O.

1200AF

400AT

3P N.O.

KIRK KEY

INTERLOCKED

WITH

LVBE2-277VNCB4

NORMALLY OPEN

KIRK KEY

INTERLOCKED

WITH

LVBE2-277VNCB5

NORMALLY

CLOSED

LVBE2-277VNCB4LVBE2-277VNCB5

2500A BUS DUCT

3ɸ, 4W WITH

GROUND

3000A

POWER

FUSES

3000A

POWER

FUSES

TO 2500A BUS DUCT

3∅. 4W WITH GROUND

TO 2500A BUS DUCT

3∅. 4W WITH GROUND

DPB-Ja14-277VN

1200A BUSDUCT

TO DPB-G13-480VNTO DPB-J4-480VN

TO

DPB-HA13-277VNTO DPB-J13-277VN

TO 1200A BREAKER

#1087 N.O. TIE

TO 1200A BREAKER

#1087 N.O. TIE

TO GEN G4

TO GEN G4

CHILLER HOUSE

INCOMING SERVICE.

ATS-EQ1

REFER TO ED10

ATS-EQ2

REFER TO ED10

OUTSIDE

SOUTH SIDE

OUTSIDE

SOUTH SIDE

OUTSIDE

SOUTH SIDE

OUTSIDE

NORTH SIDE

OUTSIDE

NORTH SIDE

D023

D022D D022D

1 1 1

1 1

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

100% CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

10360 Ellison Circle Omaha, NE 68134 Phone: 402.991.5520 www.specializedeng.com

SES Project : 23133

A u to d e s k D o c s /2

.0

V A

C o lu m b ia

M

O

C o rr e c t E le c tr ic a l D e fi c ie n c ie s /5

A

-2

-1

.E

.R

.r v t

/1

/2

:4

:4

P

M

ED14

TRANSFORMER ONE-LINE

DIAGRAM DEMOLITIONIntroba

6 S Old Orchard Ave Suit 285

Saint Louis, MO 63119

800.404.7677

CORRECT ELECTRICAL

DEFICIENCIES, HARRY S TRUMAN

VAMC

800 Hospital Drive, Columbia, MO 65201

589A4-23-104

05/17/2024

SHEET NOTES:

1. DISCONNECT AND REMOVE EXISTING EXTERIOR 1500KVA, PAD

MOUNTED TRANSFORMER. INSPECT EXISTING PAD FOR DAMAGE.

REPAIR OR REPLACE AS REQUIRED. PREPARE EXISTING INCOMING

AND OUTGOING FEEDERS FOR RECONNECTION TO NEW

TRANSFORMER.

2. REPLACE PRIMARY FEEDERS AND FIRE PUMP DISCONNECT SWITCH.

EXTEND SECONDARY CONDUIT AND CONDUCTORS ONLY AS REQUIRED

FOR TRANSFORMER REPLACEMENT.

NO SCALEED14

XFMR DEMO1

Revisions: Date:

1. DEDUCT 1: REMOVE SCOPE OF WORK FOR REPLACEMENT AND

ASSOCIATED WORK FOR THE REPLACEMENT OF TRANSFORMER 4 AND

TRANSFORMER 5 FOR DEDUCT ALTERNATE 1.

2. DEDUCT 2: REMOVE SCOPE OF WORK FOR REPLACEMENT AND

ASSOCIATED WORK OF TRANSFORMER 1, TRANSFORMER 2, AND

TRANSFORMER 3 INCLUDING FIRE PUMP DISCONNECT SWITCH FOR

DEDUCT ALTERNATE 2.

DN

UP

DN

DN

EaGa

Ha

Ja J

H

G F EFa Eb

J

J

J J

J

A. THE INTENT OF THE DEMOLITION DRAWINGS IS TO DEFINE THE SCOPE OF ELECTRICAL DEMOLITION WORK. EXISTING ELECTRICAL SYSTEMS (DEVICES, FIXTURES, EQUIPMENT, WIRING, AND RACEWAYS INCLUDING DATA/COMMUNICATION SYSTEMS). EXISTING ELECTRICAL SYSTEMS SERVING ADJACENT AREAS SHALL REMAIN UNLESS OTHERWISE INDICATED. RE-SUPPORT EXISTING CONDUITS AND CABLES THAT MUST

REMAIN. REFER TO FLOORPLANS FOR INDICATION OF DEMOLITION TYPE FOR EACH AREA:

a. BLANKET DEMOLITION AREAS:

• EXISTING ELECTRICAL SYSTEMS WITHIN LIMITS OF DEMOLITION SHALL BE REMOVED UNLESS

OTHERWISE INDICATED.

b. SELECTIVE DEMOLITIONS AREAS:

• PROVIDE DEMOLITION FOR ITEMS AS SHOWN. EXISTING ELECTRICAL SYSTEMS WITHIN LIMITS OF

DEMOLITION SHALL REMAIN UNLESS OTHERWISE INDICATED.

B. ITEMS INDICATED WITH A SUBSCRIPT 'E' SHALL BE EXISTING TO REMAIN (E-EXISTING). ITEMS INDICATED WITH A

SUBSCRIPT 'D' OR SHOWN DASHED SHALL BE REMOVED (D-DEMOLITION). ITEMS INDICATED WITH A SUBSCRIPT

'R' SHALL BE REMOVED, STORED, AND REINSTALLED PER NEW WORK (R-RELOCATION).

C. THESE DRAWINGS DO NOT IDENTIFY EACH INDIVIDUAL ITEM TO BE REMOVED. THE CONTRACTOR IS RESPONSIBLE FOR DETERMINING ITEMS WHICH MUST BE REMOVED TO FACILITATE NEW CONSTRUCTION. SEE ARCHITECTURAL PLANS FOR EXACT LIMITS OF DEMOLITION AND CONSTRUCTION. THESE PLANS ARE BASED

ON PAST PROJECT DRAWINGS AND SITE OBSERVATIONS. THE DRAWINGS ARE PROVIDED TO THE

CONTRACTOR AS AN AID IN DETERMINING THE EXTENT OF WORK REQUIRED FOR DEMOLITION AND TO PROVIDE GENERAL INFORMATION ABOUT EXISTING SYSTEMS. THESE DRAWINGS MAY NOT BE ACCURATE IN ALL AREAS. THE CONTRACTOR SHALL VISIT THE SITE AND BECOME FAMILIAR WITH EXISTING CONDITIONS AND

IS ENCOURAGED TO REVIEW FACILITY DRAWINGS PRIOR TO THE BID DATE.

D. THE OWNER SHALL HAVE FIRST SALVAGE RIGHTS TO ALL ITEMS REMOVED. IF OWNER REFUSES SALVAGE, CONTRACTOR IS RESPONSIBLE FOR DISPOSAL.

E. WHERE EXISTING WALLS ARE TO BE REMOVED, ALL ASSOCIATED ELECTRICAL EQUIPMENT SHALL BE REMOVED. DISCONNECT POWER SO THAT DEVICES AND EQUIPMENT MAY BE REMOVED WITH WALLS. SEE ARCHITECTURAL DRAWINGS FOR WALLS TO BE REMOVED. ABANDON CONCEALED CONDUITS WHERE WALLS ARE NOT REMOVED. CONCEALED CONDUITS MAY BE REUSED WHERE AVAILABLE. WHERE EXISTING CIRCUITING/CABLING IS TO BE DEMOLISHED AND NOT REUSED, REMOVE CONDUCTORS AND ASSOCIATED ACCESSIBLE RACEWAYS/CONDUIT BACK TO THE SOURCE. WHERE EXISTING ELECTRICAL CONDUITS SERVING CIRCUITS TO BE DEMOLISHED ARE EMBEDDED IN CONCRETE FLOORS OR WALLS, CONDUITS MAY BE ABANDONED IN PLACE. EXISTING CONDUCTORS SHALL BE REMOVED BACK TO SOURCE AND CONDUITS SHALL BE CUT AT SURFACE OF CONCRETE AND FILLED. EXISTING BACK BOXES AND CONDUITS REMAINING FROM DEVICES BEING REMOVED MAY BE UTILIZED FOR NEW DEVICES WHERE LOCATIONS PERMIT. REMOVE AND PATCH WHERE BOXES ARE NOT REUSED. REMOVE CONCRETE EQUIPMENT PADS THAT REMAIN, TO BE FLUSH

WITH FLOOR/GRADE.

F. SEE ARCHITECTURAL DRAWINGS FOR ADDITIONAL ELECTRICAL DEMOLITION ITEMS. DISCONNECT AND REMOVE ELECTRICAL DEVICES, EQUIPMENT AND ASSOCIATED WIRING AS REQUIRED TO ACCOMMODATE NEW WORK. IF THE CONTRACTOR IS UNCLEAR REGARDING A SPECIFIC ITEM TO REMAIN OR BE REMOVED, THE

CONTRACTOR SHALL SEEK CLARIFICATION FROM THE ARCHITECT.

G. SYSTEMS SERVING ADJACENT AREAS AND ITEMS THAT REMAIN SHALL BE MAINTAINED AT ALL TIMES. MODIFY SYSTEMS AS REQUIRED THROUGHOUT CONSTRUCTION TO MAINTAIN CONTINUITY OF SERVICE. DO NOT INTERRUPT SERVICE WITHOUT OWNER'S PRIOR WRITTEN APPROVAL. LIMIT DURATION OF INTERRUPTION ONLY TO THE TIME NECESSARY FOR DISCONNECTION AND IMMEDIATE RECONNECTION. INTERRUPTION TO SERVICE DEEMED BY OWNER AS ESSENTIAL MAY REQUIRE PREMIUM TIME AND SHALL BE INCLUDED WITH THE BID.

EXTREME CARE SHALL BE TAKEN BY THE CONTRACTOR TO IDENTIFY EXISTING SYSTEM COMPONENTS ASSOCIATED WITH THESE SERVICES. APPROPRIATE METHODS OF MARKING THESE SHALL OCCUR TO ELIMINATE THE POSSIBILITY OF ACCIDENTAL INTERRUPTION. FOR CONDUIT AND CABLING THAT CAN REMAIN, PROVIDE SUPPORT AS REQUIRED. RELOCATE EXISTING JUNCTION BOXES THAT BECOME INACCESSIBLE DUE

TO NEW WORK.

H. COORDINATE DEMOLITION WITH THE WORK OF OTHER TRADES. PROVIDE TEMPORARY POWER AND LIGHTING

AS REQUIRED TO ALLOW THE WORK OF OTHER TRADES TO PROCEED.

I. PROTECT EXISTING ELECTRICAL EQUIPMENT THAT REMAINS. IF DAMAGED OR DISTURBED IN THE COURSE OF THE WORK, REMOVE DAMAGED PORTIONS AND INSTALL NEW PRODUCTS OF EQUAL CAPACITY, QUALITY, AND

FUNCTIONALITY.

J. PATCH AND REPAIR OPENINGS IN EXISTING WALLS AND FLOORS RESULTANT FROM SPECIFIED ELECTRICAL DEMOLITION. PATCH SHALL MATCH EXISTING CONSTRUCTION, FIRE RATING, AND FINISH. SEE ARCHITECTURAL

SPECIFICATIONS FOR MEANS AND METHODS.

K. THIS PROJECT WILL BE PHASED. SEE PROJECT MANUAL AND ARCHITECTURAL PLANS FOR DETAILS. SYSTEM SERVICES TO AREAS NOT IN THE CURRENT PHASE OF CONSTRUCTION SHALL BE MAINTAINED AT ALL TIMES.

L. WHERE DEMOLITION OF EQUIPMENT INVOLVES REMOVAL OF EQUIPMENT LOCATED ON CONCRETE HOUSEKEEPING PADS, PADS SHALL ALSO BE REMOVED AND FLOOR/GRADE SHALL BE FINISHED TO MATCH

ADJACENT SURFACE.

M. ALL UNLABELED ELECTRICAL DEVICES [WITH CIRCUITRY OR DEVICES MODIFIED DURING CONSTRUCTION] [THAT EXIST IN ALL ROOMS WHERE THERE IS WORK WITHIN SCOPE] SHALL BE CIRCUIT TRACED AS NEEDED WITH A

LABEL PROVIDED.

(ELECTRICAL DEMOLITION NOTES APPLY TO ALL ELECTRICAL DEMOLITION PLANS AND

ALL ELECTRICAL DEMOLITION WORK)

ELECTRICAL DEMOLITION GENERAL NOTES:

EX 1250KW GENSET #1

EX 1250KW GENSET #2

EX ATS-GEN

EX LPB-G14-277VG

EX LPB-G14-120VG

EX ATS-EL EX ATS-LS

EX DS-C2

EX DS-DPB-J4-480VC

EX DS-LPB-G14

EX TS-G14-120VG

EX LPB-Hb14-120VG

EX ATS-C3

EX DPB-G14-480VC

EX TB-Ha13.5-120VC

EX TB-Ha13.5-120VN

EX DPB-H13-120VN

EX ATS-C1

E X

D P

B -G

-4

V

N

E X

D P

B -G

-2

V

C

EX TB-H14-120VQ

EX LPB-H14-120VQ

EX DPB-H13-120VC

EX PPB-J13-277VC

EX DPB-J13-277VN EX LPB-H13-120VN

EX TB-H13-120VN

DPB-Ja14-277VN

EX EGB-F14-277VG

EX MSG-H14-MVN

EX SG-H14-MVN1

EX MCCB-G14-480VQF

EX ACA BLDG ATS

E X

L P

B -G

-1

V

N

EX MCCB-H13-480VNF EX MCCB-H13-480VNR

EX T3-S EX T2-S EX T1-S

EX DPB-Ha13-277VN

EX LPB-H12-277VC

EX LPB-H12-120VC

EX LPB-H12-277VE

EX DPB-H15-480VC

EX ATS-C4

EX LPB-G12-120VE

EX LPB-G12-120VN

EX LPB-G12-277VN

EX DPB-G12-208VN

EX TB-G12-120VC

EX TB-G12-120VN

EX TB-G12-120VE

EX PPB-WH-277VE

EX DPB-H14-277VN

E X

D P

-C R

IT

IC

A L-

EX DP-LIFE SAFETY

3 3

T3

1500KVA

PAD MT'D.

XFMR

13.8KVA

480Y/277V

T2

1500KVA

PAD MT'D.

XFMR

13.8KVA

480Y/277V

T1

1500KVA

PAD MT'D.

XFMR

13.8KVA

480Y/277V

4 4 4

EX AHU

EX

D/S

EX F/A PULL BOXEX CONTROL PANEL

E X

V F

D H

E -3

E

X V

F D

H E

-4

E X

V F

D H

E -3

E

X V

F D

H E

-3

E X

V F

D E

F -1

EX CONTROL PANEL

CL'G HUNG

CL'G HUNG

EX DPB-G12-208VC

DOOR

OPENING

E X

V F

D

E X

P U

LL

B

O X

E X

T B

-G

-1

V

NCL'G HUNG

EX AHU

EX DUCT

EXISTING CONCRETE PAD

EX AHU

EX

PVC

EX

3/4"C.

EXISTING

CONCRETE PAD

EXISTING

CONCRETE PAD

EX. DIST. PANEL DPB-H14-480VQ

EX ATS-EQ

EX ATS EQ2

FUSE CAB

EX PIPE

UNIT HTR SWCH EX PULL BOX

EX ATS-C2

EX PULL BOX

EX PULL BOX

EX TLS 350

EX F/A PNL

EX MISC PNL

WALL MT'D

EX MISC PNL

EX MISC XFMR

EX MISC PNL

EX SG-H14-MVN1

FILTER

BOX

EX MCCB-G14-480VQR

E X

A T

S -E

C

P U

LL

B

O X

MAIN HOSPTIAL NORMAL SWITCHGEAR

PARALLELING

SWITCHGEAR

D022CD022D

D022D023

D020

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

100% CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

10360 Ellison Circle Omaha, NE 68134 Phone: 402.991.5520 www.specializedeng.com

SES Project : 23133

A u to d e s k D o c s /2

.0

V A

C o lu m b ia

M

O

C o rr e c t E le c tr ic a l D e fi c ie n c ie s /5

A

-2

-1

.E

.R

.r v t

/1

/2

:4

:4

P

M

ED50

ENLARGED ELECTRICAL

DEMOLITION PLANS - BASEMENTIntroba

6 S Old Orchard Ave Suit 285

Saint Louis, MO 63119

800.404.7677

CORRECT ELECTRICAL

DEFICIENCIES, HARRY S TRUMAN

VAMC

800 Hospital Drive, Columbia, MO 65201

589A4-23-104

05/17/2024

SHEET NOTES:

1. REFER TO B1 EQUIPMENT ATS ONE-LINE DIAGRAM DEMOLITION, SHEET ED10 FOR MORE INFORMATION.

2. REFER TO B1 CRITICAL ATS ONE-LINE DIAGRAM DEMOLITION, SHEET ED11 FOR MORE INFORMATION.

3. REFER TO B1 LIFE SAFETY ATS ONE-LINE DIAGRAM DEMOLITION, SHEET ED12 FOR MORE INFORMATION.

4. REFER TO TRANSFORMER ONE-LINE DIAGRAM DEMOLITION, SHEET ED14 FOR MORE INFORMATION.

5. RELOCATE EXISTING 45 KVA TRANSFORMER TB-G13-120VN AND EXISTING 150A, 208Y/120V, 3PH, 4 W, PANELBOARD LPB-G13-120VN TO ALLOW FOR NEW DISTRIBUTION PANELBOARD AND CAM LOCK BOXES.

EXTEND BRANCH CIRCUIT CONDUITS, CONDUCTORS AS REQUIRED FOR PANELBOARD AND TRANSFORMER RELOCATION. PROVIDE ALL JUNCTION BOXES, GROUNDS CONDUIT AND CONDUCTORS TO EXTEND PRIMARY , SECONDARY AND BRANCH CIRCUITS TO NEW LOCATION. REFER TO NEW WORK PLAN FOR MORE

INFORMATION.

6. DEMOLISH EXISTING VERTICAL BRANCH MECHANICAL DUCT FROM MAIN HORIZONTAL DUCT TO BELOW

FLOOR IN PIPE BASEMENT. SEAL HORIZONTAL DUCT AND MATCH INSULATION.

7. RELOCATED RECEPTACLE AND EXTEND BRANCH CIRCUIT TO ALLOW FOR INSTALLATION OF NEW SWITCHBOARD. NEW LOCATION TO BE IN ACCESSIBLE LOCATION ADJACENT TO NEW SWITCHBOARD AND

RELOCATED PANELBOARD.

1/4" = 1'-0"ED50

ENLARGED MAIN ELECTRICAL ROOM DEMOLITION- D020,D022,D022D,D0231

N

04' 4' 8'

Revisions: Date:

1. DEDUCT 2: REMOVE SCOPE OF WORK FOR REPLACEMENT AND ASSOCIATED WORK OF TRANSFORMER 1, TRANSFORMER 2, AND TRANSFORMER 3 INCLUDING FIRE PUMP DISCONNECT SWITCH FOR DEDUCT ALTERNATE 2.

2. DEDUCT 4: REMOVE SCOPE OF WORK FOR REPLACEMENT AND ASSOCIATED WORK FOR THE REPLACEMENT OF ATS-EQ1, ATS-EQ2, ATS-EQ3, AND ATS-EQ4 INCLUDING ATS METERING, SUPPLY AND LOAD FEEDERS, SWITCHBOARDS DPB- G13-277VQ, DPB-H14-277VQ, DPB-G14-277VQ, DPB-J13-277VQ, AND CAMLOCK BOX FOR DEDUCT ALTERNATE 4.

EE3275

Yes

01-CBA8-32725

Yes Unit is mounted in cabinet on S wall of corridor , approx. 20ft from SE Basement exit to FM Trailer.

JAN19

FLR1_1-134-2943753_PH4

FE

D

E

F

C

B

EX ATS-4

EX DPB-D8-277VE

EX LPB-D8-277VE

E X

M C

C -D

8-

0V A

EX MISC VFD

EX LPB-C8-277VC

TB-C8-120VC

ATS-3EX ATS-1

EX DPB-C8-480VQ

E X

B U

S B

A R

EX TB-5

EX

SURGE

PROT.

EX DPB-

D8-120VE

EX PPB-

D8-120VE-1

EX PPB-

D8-120VE-2

EX LVB-C8-277VG

EX LVB-H14-277VG

TB-D8-120VE-1

EX MISC XFMR

E X

P P

B -C

8-

0V N

E X

P P

B -C

8-

0V C

E X

V F

D

E X

P U

LL

B

O X

T

E009

T

EX PPB-C8-120VE

PPB-C8-120VC

ATS-2

EX PPB-B3-277VE

TB-6

E X

P P

B -B

3-

0V N

-1

E X

P P

B -B

3-

0V N

-2

E X

L P

B -B

3-

7V N

DPB-B3-480VN

E X

M R

I D /S

E X

C

LC

D /S

E X

W

IR

E W

A Y

GND BUS

EX XFMR

EX HOUSE PUMPS D/S

EX PPB-F6-120VN

SECT A,B,C D/S

EX TB-1

N150-TB-1-B3

EX PP1/PP2-D2-120VC D/S EX TB-3

EX PP1/PP2-D6.3-120VC D/S

EX MCC-B3-480VN

EX N150-TB-2-B3

EX DPB-B3-277VC

D P

B -B

3-

7V N

LVB-B3-277VN

EX MISC XFMR

EX MISC D/S

FLR MT'D

2 2

E003

A. THE INTENT OF THE DEMOLITION DRAWINGS IS TO DEFINE THE SCOPE OF ELECTRICAL DEMOLITION WORK. EXISTING ELECTRICAL SYSTEMS (DEVICES, FIXTURES, EQUIPMENT, WIRING, AND RACEWAYS INCLUDING DATA/COMMUNICATION SYSTEMS). EXISTING ELECTRICAL SYSTEMS SERVING ADJACENT AREAS SHALL REMAIN UNLESS OTHERWISE INDICATED. RE-SUPPORT EXISTING CONDUITS AND CABLES THAT MUST

REMAIN. REFER TO FLOORPLANS FOR INDICATION OF DEMOLITION TYPE FOR EACH AREA:

B. THESE DRAWINGS DO NOT IDENTIFY EACH INDIVIDUAL ITEM TO BE REMOVED. THE CONTRACTOR IS RESPONSIBLE FOR DETERMINING ITEMS WHICH MUST BE REMOVED TO FACILITATE NEW CONSTRUCTION. THE DRAWINGS ARE PROVIDED TO THE CONTRACTOR AS AN AID IN DETERMINING THE EXTENT OF WORK REQUIRED FOR DEMOLITION AND TO PROVIDE GENERAL INFORMATION ABOUT EXISTING SYSTEMS. THE CONTRACTOR SHALL VISIT THE SITE AND BECOME FAMILIAR WITH EXISTING CONDITIONS PRIOR TO THE BID DATE.

C. THE OWNER SHALL HAVE FIRST SALVAGE RIGHTS TO ALL ITEMS REMOVED. IF OWNER REFUSES SALVAGE, CONTRACTOR IS RESPONSIBLE FOR DISPOSAL.

D. COORDINATE DEMOLITION WITH THE WORK OF OTHER TRADES. PROVIDE TEMPORARY POWER AND LIGHTING

AS REQUIRED TO ALLOW THE WORK OF OTHER TRADES TO PROCEED.

E. PROTECT EXISTING ELECTRICAL EQUIPMENT THAT REMAINS. IF DAMAGED OR DISTURBED IN THE COURSE OF THE WORK, REMOVE DAMAGED PORTIONS AND INSTALL NEW PRODUCTS OF EQUAL CAPACITY, QUALITY, AND

FUNCTIONALITY.

F. PATCH AND REPAIR OPENINGS IN EXISTING WALLS AND FLOORS RESULTANT FROM SPECIFIED ELECTRICAL DEMOLITION. PATCH SHALL MATCH EXISTING CONSTRUCTION, FIRE RATING, AND FINISH. SEE ARCHITECTURAL

SPECIFICATIONS FOR MEANS AND METHODS.

G. ANY CONDUIT, SUPPORTS OR DEVICES ABANDONED BY THE SCOPE OF THIS WORK SHALL BE REMOVED.

(ELECTRICAL DEMOLITION NOTES APPLY TO ALL ELECTRICAL DEMOLITION PLANS AND

ALL ELECTRICAL DEMOLITION WORK)

ELECTRICAL DEMOLITION GENERAL NOTES:

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

VA FORM 08 - 6231

A

100% CONSTRUCTION

DOCUMENTS

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD

A/E:

STAMPCONSULTANT

321 4 5 6 7 8 9 10

10360 Ellison Circle Omaha, NE 68134 Phone: 402.991.5520 www.specializedeng.com

SES Project : 23133

A u to d e s k D o c s /2

.0

V A

C o lu m b ia

M

O

C o rr e c t E le c tr ic a l D e fi c ie n c ie s /5

A

-2

-1

.E

.R

.r v t

/1

/2

:4

:4

P

M

ED51

ENLARGED ELECTRICAL

DEMOLITION PLANS - BASEMENTIntroba

6 S Old Orchard Ave Suit 285

Saint Louis, MO 63119

800.404.7677

CORRECT ELECTRICAL

DEFICIENCIES, HARRY S TRUMAN

VAMC

800 Hospital Drive, Columbia, MO 65201

589A4-23-104

05/17/2024

SHEET NOTES:

1. REFER TO ACA & CHILLER ATS ONE-LINE DIAGRAM DEMOLITION, SHEET ED13 FOR MORE INFORMATION.

2. REFER TO TRANSFORMER ONE-LINE DIAGRAM DEMOLITION, SHEET ED14 FOR MORE INFORMATION.

3. RELOCATED THERMOSTAT TO ALLOW FOR INSTALLATION OF NEW ATS.

4. REMOVE EXISTING SOUTH 3-WAY LIGHTING SWITCH.

5. REMOVE ONE 3-WAY SWITCH LEG AS NEEDED TO ALLOW LIGHTS TO TURN ON/OFF AFTER REMOVAL OF

SOUTH 3-WAY SWITCH.

N

N

1/4" = 1'-0"ED51

ENLARGED ELECTRICAL ROOM DEMOLITION- E0093

1/4" = 1'-0"ED51

ENLARGED…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .