P02 MR Sources Sought Att1 SOW 556-20-013 CLC B134 2022.02.04.pdf

PDF 149 KB Posted

Attached to
Z1DA--556-20-013 Renovate CLC 3A/C. Federal contract opportunity
Solicitation number
36C25222B0022
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 12

About this file

This document is a sources sought notice from the Department of Veterans Affairs for construction services to renovate Building 134 at the Captain James A. Lovell Federal Health Care Center in North Chicago, Illinois. The project scope involves demolishing one wing and renovating two others to expand community living center facilities by 12 beds, along with associated utility, administrative, and public spaces. Interested small businesses, including service-disabled veteran-owned small businesses, veteran-owned small businesses, women-owned small businesses, HUBZone, and 8(a) firms, are requested to submit capability statements by February 22, 2022 responding to the $5-10 million magnitude renovation work under NAICS 236220 with a response period of 175 calendar days upon notice to proceed. Responses should include company information, examples of similar past projects, bonding capacity, and intentions for subcontracting or teaming. This notice is to determine contractor availability before selecting an acquisition method.

View the file

Other files for this federal contract opportunity

Other files attached to Z1DA--556-20-013 Renovate CLC 3A/C., newest first.
File Type Posted
36C25222B0022.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONSTRUCTION STATEMENT OF WORK

Date: 2 February 2022

Project Name: Renovate Building 134 CLC 3A/C

Project Number: 556-20-013

Place of Performance: Captain James A. Lovell FHCC

3001 Green Bay Road North Chicago IL 60064

Part 1: Project Scope of Work Overview:

The intent of this project is to demo 3A and renovate the 3A and 3C wings of the CLC (Community Living Center) in building 134 at the Captain James A. Lovell Federal Health Care Facility in North Chicago, Il. When completed, this updated CLC will serve elderly veterans who require round-the-clock care and end-of-life care. It will expand current CLC facilities by adding 12 additional beds, as well as accompanying utility, administrative, and public spaces (kitchen, .

This renovation is a critical step in the continuation of FHCC’s ability to provide state-of-the-art care for veterans at all stages of life.

Contractor shall provide all tools, materials, labor, quality assurance, and supervision for renovations resulting in a complete, compliant, and fully-functional project, including erection of temporary enclosures preventing the release of dust outside of the work area, selective demolition, metal studs, gypsum wall board, paint, ceilings, and flooring, electrical power and light, a new HVAC system serving this space, modifications to the fire protection system, telecom cabling, fire alarm, and other work to affect a complete turn-key space supporting described clinical function(s) and equipment.

Part 2: Period of Performance:

1. Complete all work including submittals, reviews, quality assurance, and closeout within the stated term from Notice to Proceed (NTP) as shown below.

Notes:

A. Durations shown are in calendar days.

B. Time consumed for resubmission and review must be made up by the GC.

C. Time consumed by the GC beyond that shown must be made up.

D. Failure to complete all work, including submission of compliant closeout documents, before the end of the Period of Performance can result in adverse contract action.

E. Accommodate the Period of Performance by including accelerated material and or equipment delivery costs as well as adjusting crew sizes.

Activity Calendar

Days for the Work

VA

Review

Total days after NTP

Kick-Off Meeting and NTP 0

Shop Drawings and Product Submittals 21 14 35

Material Procurement and Delivery 30 65

Mobilization on Site, and Infection Control Barriers 14 1 80

Construct Renovations 45 14 139

Remove Infection Control Barriers 7 1 147

Acceptance and Closeout 14 14 175

Part 3: Detailed Project Requirements:

1. Project Objectives:

A. This project is required to renovate the existing CLC 3A and 3C wings as expediently as practical.

B. Meet or exceed all Code, technical, and programmatic requirements adopted, established, revised, and or published by VA.

C. Expedite the delivery of a highly functional, complete, compliant, and safe workspace for the user service.

2. List of AE Documents to be included in this Contract:

A. See: 00 01 10 Table of Contents

B. See: 00 01 15 List of Drawing Sheets

3. Pre-Bid Conference:

A. VA shall schedule one pre-bid conference required to be attended by prospective bidders to observe current conditions within the work area(s) and the stored HVAC equipment.

B. The AE shall not attend the pre-bid event. No questions will be allowed during the event. All questions by all prospective contractors shall follow the RFI process described in the Solicitation.

C. Prospective bidders shall not attempt to contact the AE or VA facilities engineering staff during the solicitation and bidding period. The AE and VA facilities engineering staff are instructed to ignore all such inquiries and report them to the VA Contracting Officer. All inquiries regarding this project shall be presented as complete and coherent Requests for Information (RFI) specifically citing design or specification sections, pages, paragraphs, notes, details, etc. to enable responses to RFI’s. Follow the instructions provided by the Contracting Officer within the Solicitation regarding submission of RFI’s.

VA will post responses developed to enable all prospective bidders to receive the same information at the same time.

4. Mobilization on Site:

A. The contractor shall not mobilize on site until all required Kick-Off Meeting and Documentation deliverables are submitted, reviewed, and accepted by VA.

Kick-Off Meeting Documentation is described in Part 4.

B. Approval to mobilize shall be in writing by the Contracting Officer in consultation with the COR and Facility Safety Manager.

C. Mobilization will not begin unless and until all administrative and material submittals have been verified for compliance by the contractor PM, and then the VA Contracting Officer’s Representative (COR). Significant time for this essential is included in the Period of Performance.

D. Post and maintain at each work area all current emergency contact information, VA Infection Control Risk Assessment (ICRA)/Permit, Interim Life Safety Measures (ILSM), and other information required by VA, on the wall at all entry points to the work area.

E. For facility access and badging, submission of personnel data required for background checks well in advance of need is imperative.

4. Performance of the Work:

A. Erect and maintain a dust-tight containment around the work area which complies with applicable Code associated with UL-Rated wall assemblies and maintenance of egress paths.

B. Containment shall enable access to the work, without obstructing access to adjacent suites or rooms. Establish HEPA air purification. Review and follow specification 01 35 33 Infection Control Requirements as applicable to this location and work. Follow PRA & ICRA plan and permit generated and issued by VA. Remove only upon completion approval of the COR.

C. After establishing and gaining approval of the temporary modular hard plastic dust-tight construction dust control barrier system, including lockable door. Where this is the sole containment, include differential pressure monitoring for the work area, with monitor located adjacent to the temporary entry door.

D. Where fire or smoke-rated wall assemblies are planned for alternation – even if temporarily, provide a dust-tight 1-hour rated temporary construction wall with locking door to isolate the area of work, finished with one coat of paint on the outside were indicated.

E. The 1-hour temporary wall shall include differential pressure monitoring for the work area, with monitor located adjacent to the temporary entry door.

F. The 1-hour temporary wall and differential pressure monitoring must be complete and approved prior to removal of the (outer) temporary modular wall barrier, and commencement of demolition within the space.

5. Perform selective demolition and construction as described in the specifications and drawings.

6. Special Acceptance Criteria for the work shall include:

A. HVAC system shall not be acceptable in whole or in part unless and until Testing, Adjusting, and Balancing (TAB) is completed and accepted in accordance with the Specifications, Drawings, and the current edition ASHRAE 170 Ventilation of Health Care Facilities (and errata) requirements specific to the room/suite type and purpose.

VA reserves the right to conduct, or have conducted, verification testing.

B. The contractor shall provide EIA/TIA testing and certification of all new Cat 6e communications cable.

7. Prior to removal of a temporary 1-hour wall, re-erect the temporary modular hard plastic, dust-tight, barrier system.

8. Restore all finishes damaged during the work – match existing.

9. In no case shall any containment be removed unless and until the work area, including the inside of the ventilation system, has been thoroughly cleaned and approved for progress toward activation.

10. Immediately prior to turnover, remove all air filters from the ventilation system used during construction, and supply and install new specified filters. Supply case quantities of each filter to VA with the system.

11. Thoroughly clean all surfaces using HEPA-filtered vacuum cleaner and anti-bacterial wipes.

Part 4: Meetings, Submittals, and Deliverables:

1. Kick-Off Meeting and Documentation

A. The contractor’s Project Manager and Field Supervisor shall attend a Preconstruction Safety and Coordination Meeting to discuss project details.

B. Kick-Off Meeting Documentation:

1) Prepare and submit for review and acceptance a proposed baseline schedule reflecting each phase of the work beginning with Mobilization, including each critical activity, and each essential task required to optimally meet the objectives of the project. It is expected that this timeline will be shorter than that presented in the Period of Performance from Mobilization to Closeout. Upon acceptance, this will become the Baseline Schedule from which subsequent progress updates are developed and reported, and how progress payment applications are objectively reviewed.

2) To enable objective assessment of costs and progress, submit a fully-loaded time and cost schedule using Critical Path Method (versus Network Analysis) and accompanying Schedule of Values with harmonized category values – each totaling the contract value.

a. Develop the CPM schedule in sufficient detail to enable readers to understand all planned activities, their predecessors and successors, who is performing the work, durations, and costs. Activity durations shall not exceed two calendar weeks.

b. Use the Project Manual index of specifications is a useful guide for starting the CPM schedule and Schedule of Values in sufficient detail. For example: Simply listing “HVAC” is unacceptable for projects including more than basic work in this category. The inclusion of specifications for an AHU, controls, ductwork, demolition of each, testing and balancing, etc. also prompt their inclusion as categories of activities and tasks in the schedule. In fact, for larger work categories, breaking down the cost by system/material and installation and testing enables partial payment for higher cost items upon delivery into the facility work area.

c. Preparation and processing of submittals are not work activities contributing to the compensable work in the field. Should the contractor elect to include submittal planning in the schedule for their own purposes, do not show those line items in the schedule submitted to VA for consideration in the Baseline Schedule.

d. Not less than one item per subcontractor at any tier. Subcontractors, by definition, are contributing work in the field to the project.

e. Include all expected utility system shutdowns, crane lifts, and off-hours work.

f. Do not list dollar values for administrative, planning, submittals, mobilization, or demobilization, closeouts, or other non-work activities (work to be completed in the field which adds value to the final product). Distribute (prorate) the administrative, overhead, and profit values evenly through the work activities to determine their value. Do not front-load the values of the schedule of values.

The costs shown must be the actual value of the work put in place.

3) The contractor shall prepare and submit SF-1413 for each subcontractor to the CO, copying the COR. List of all subcontractors and suppliers, including:

Company names, office address, and main point of contact name with telephone number.

4) As required at 01 35 26 Safety Requirements: Develop and submit a Project-

Specific Construction Safety and Accident Prevention Plan with project-specific procedures, processes, analysis, and details, including but not limited to:

a. Access and use the U.S. Army Corps of Engineers EM 385-1-1 Safety and Health Requirements and its Appendix A – Minimum Basic Outline for Accident Prevention Plans for development of meaningful, effective, and compliant project safety plans.

b. Submission of generic, non-project specific plans will be rejected, resulting in a contractor-caused delay in commencement of the work.

c. Project-specific Activity Hazard Analysis, which forms the basis of the Construction Safety and Accident Prevention Plan highlighting identified risks such as isolation of stored energy (Lock-Out*), fall protection, or confined space access.

d. (*) Note that tag-out is not an acceptable form of isolation, therefore it was intentional not to use the term LOTO.

e. Submit an electronic copy of all workers OSHA 30-hour Construction Safety Training certificates or cards prior to allowing entry to the site.

f. Assist the COR in completing project-specific VA Infection Control Risk Assessment (ICRA) documentation.

C. Quality Control Plan and Quality Assurance Plan:

1) 01 40 00 Quality Requirements is included in its entirety in this contract. This specification is brief but very informative and enabling to those who approach it as an opportunity.

2) Submittal Tracker Log is described in Quality Assurance of the above specification.

3) (Dis)Approval of a submittal never constitutes a change to the quantity, quality, cost, or duration of a contract. The General Contractor is solely responsible for submitting and delivering complete and compliant work. Defective work shall be removed and replaced at the contractor’s expense. The Government has the right and responsibility to withhold funds equivalent to the cost for the Government to complete the work should the contractor fail to promptly act in executing the work or remedying defective work.

2. Construction Progress Meetings:

A. The Contractor’s Project Manager and Field Supervisor shall provide on-site weekly construction progress meetings with the COR for the entire period of performance.

B. Include preparation of meeting agendas, and subsequent minutes of the meeting for each event not later than 1 day (next business day) after each meeting.

C. Construction Progress Meeting Agenda’s and Minutes shall include: List of invitees/attendees, list of past/ongoing and new issues or concerns, indicate days remaining per the contract, detail any safety incidents, and include current updated copies of the RFI Log, the Shop Drawing Log, and a detailed 2-week look-ahead and utility shutdown schedule.

3. Daily Reports:

A. The Contractor shall provide a Daily Report each day, along with accompanying digital photos and other supporting documents. The Daily Report shall include: List of issues or concerns, days remaining per the contract, detail regarding any safety incidents, detail of daily safety inspections (including items checked and corrective actions taken), notations regarding any visitors to the work area.

B. Use of VA Form 10-6131 Daily Log (fillable PDF) and VA Form 10101 Contractor Production Report (fillable PDF) are required each day – even on days with no contractor activity, which is what to report on such days.

C. The report must be accompanied by relevant time and date-stamped photos of construction progress of sufficient quantity and detail to enable viewers to clearly see the progress of all work to-date, all issues discovered (including those which become the subject of RFI’s). Email the Daily Report and photos to the COR not later than 9 AM the next working day.

1) No photography on VA premises is allowed without written permission of the COR.

2) In no case will photographs be taken with patients, visitors, or employees in the picture.

4. Acceptance and Closeout:

A. Acceptance criteria for the work:

1) Schedule demonstration of new equipment and systems at least 21 calendar days in advance with the COR.

2) Provide factory startup and certification of all systems.

3) Demonstrate the operation of the system.

4) Newly installed water or medical gas piping and distribution system components shall be flushed and disinfected prior to being placed in service.

Include documenting completion/certifications.

5) Startup and testing of new systems or equipment, or moving in VA purchased equipment or furnishings, or their use, does not constitute any form of Acceptance (or Beneficial Occupancy). The project is planned around the complete, complaint, and unconditional fulfillment of all requirements of the contract which enable the work to be complete – by definition. Please work with VA to expedite this process.

B. Closeout Records: Provide one full-size, and one half-size printed set of as-built drawings, as well as CD-ROM or DVD-ROM media containing a complete archive of all project documents and files, including but not limited to:

1) As-built record drawings of the installed condition.

2) Approved shop drawings.

3) Operations and Maintenance Manuals.

4) Spare parts lists.

5) All photographs.

6) All daily reports.

7) All communications.

8) All pay applications.

9) All communication, change, and cost data.

10) All safety records.

11) A project Warranty for Construction written by the General Contractor, projected to start upon Final Acceptance by VA (typically within a business week of receiving a complete and compliant closeout package).

• Where manufacturer’s warranties exceed one year, provide all documentation necessary for VA to exercise warranty rights beyond the standard GC warranty.

• Where specified, such as with roofing systems, provide the warranty written by the manufacturer to VA for the term specified or greater.

• Note that moving furnishings or equipment into the space does not constitute occupancy or acceptance, however, damage to completed work during these activities shall be the responsibility of VA to correct.

12) Lien Waivers and other documents required by the Contracting Officer.

Part 5: Applicable Performance Standards

1. All work shall comply with

A. All VA and FHCC policies including and not limited to: VA Construction Safety and VA Infection Control Policies.

B. Codes, Standards and Executive Orders (Topic 1) found at http://www.cfm.va.gov/til/cPro.asp

C. 01 35 26 Safety Requirements

D. 01 35 33 Infection Control Requirements

E. 01 40 00 Quality Requirements

F. 01 41 00 Regulatory Requirements

G. 01 42 16 Definitions and Abbreviations

2. Coordinating with VA-retained Commissioning Agent (CxA) and Architect-Engineer

(AE).

A. VA intends to retain the services of an independent CxA.

B. AE field-verification and documentation of compliant systems remains an essential part of Construction Period Services.

C. The General Contractor is responsible for communication and cooperation with the AE and CxA, and for enabling compliant execution of contracts.

3. The General Contractor shall have a Competent Supervisory Person on site at all times when any worker(s) or subcontractor(s) are present. The General Contractor is also required to maintain on site a competent Site Safety and Health Officer (see 01 35 26 Safety Requirements when any worker(s) or subcontractor(s) are present.

The VA COR may, at his or her discretion, allow the Competent Supervisory Person to also act at the SSHO, based on demonstrated competency and performance in the two roles. Demonstrated lack of competency or effectiveness in either role is observed, the VA COR may revoke the privilege.

4. Safety:

A. Prior to any activity, review the following with all project and craft team leaders: 01 35 26 Safety Requirements.

http://www.cfm.va.gov/til/cPro.asp

B. The Contractor shall provide a proactive and complaint Construction Safety and Accident Prevention plan in accordance with the Occupational Safety and Health Act, 01 35 26 Safety Requirements, and site-specific policies:

C. All persons working on any electrical systems rated 50 volts or more shall have the minimum qualification as a State Licensed Master Electrician or Registered Journeyman Electrician, and all activities shall follow the safe work practices in compliance with NFPA 70E Electrical Safety in the Workplace.

D. 01 35 26 Safety Requirements is included in its entirety in this contract. Each contractor-employer is required to be solely responsible for the health and safety of its employees in accordance with 29 CFR 1910, 1926, & 1960 of the Occupational Safety and Health Act of 1970, as amended.

E. Because each contractor-employer is required to be solely responsible for the health and safety of its employees, part of a compliant and effective safety management program requires each employer to plan and implement their own compliant permit-required work – including written permits. DO NOT rely on, or request that VA generate required permits such as Hot Work or Confined Space documents.

F. Prior to the beginning of any work, fire extinguisher(s) complying with NFPA 10 shall be pedestal-mounted in the work area. Inspection of the work area includes verification that inspection tags are current. Where non-compliant, the contractor may be required to remove and replace the unit(s) before resuming work activity.

G. All work in crawl spaces shall be planned and carried out as OSHA Permit-Required Confined Space.

H. Immediately stop work and notify the COR if asbestos is noticed or suspected in the area of work.

I. Fire-seal all penetrations made or discovered through any wall or floor assembly with UL Listed fire-rated products or systems.

5. Infection Control:

A. 01 35 33 Infection Control Requirements is included in its entirety in this contract. Its construct is enabling for each condition experienced through each phase of the work.

B. Prior to any activity, review the following with all project team leaders: 01 35 33 Infection Control Requirements.

C. Review and comply with containment construction and sequence described in the design and specification documents.

D. Provide a modular dust-tight system designed and manufactured specifically to be used as a temporary construction isolation barrier.

E. Before the start of work provide pressure differential monitoring system at the entry door to the construction area to prove that the construction area is under negative pressure. Maintain daily logs of readings and submit to the COR weekly. Remove at the completion of construction.

F. Walk-off sticky mats are required at all times inside and outside all entry/exit points to all workspaces. Sticky mats must be changed at least once per shift, or more as required by the construction or COR. Size sticky mats to match the width of the door opening and ensure that no less than 24” depth is provided.

G. Block off all HVAC return ductwork and louvers to prevent introduction of dust into the HVAC system.

1) Where existing HVAC ducts are being removed, immediately, permanently, and compliantly seal off the opening.

H. Provide High-Efficiency Particulate Air Filtration (HEPA) recirculating air equipment inside the workspace. Size the air filtration system sufficiently large enough to ensure that negative pressure remains effective when doors are opened.

I. When working above the ceiling outside of the work area, such as in a corridor, open only one ceiling tile at a time, and provide dust containment tent or portable containment cube, with HEPA filtering negative air system to seal the one opening.

J. Broom-sweep the work area at the end of each day (or shift during days with multiple shifts). Provide HEPA vacuum and damp (not wet) mop daily where broom sweeping creates airborne dust.

K. Provide fire-sealing of all existing wall and ceiling openings in area of work needed to allow the HEPA filtration equipment to effectively generate negative air pressure within the work area, with respect to the surrounding area.

L. Provide HEPA-filtered vacuum cleaning of all surfaces, and damp mop the work area every day.

M. Do not allow corrugated carboard to be stored for any period of time within the hospital.

Upon arrival, unpack, and transfer all products from cardboard containers to sealed plastic containers, and immediately dispose of the cardboard – outside of the building.

Part 6: Site-Specific Requirements

1. Include the project number in the subject line of all emails and documents. Example: “556- 20-013 Renovate CLC 3A/C” and then specific subject such as Pay App, RFI, Submittal, Meeting, etc. Transmissions deviating from this focused and simple standard may be rejected, or simply lost because recipients could not readily-acquire their subject or importance over the plethora of ambiguous emails received each day.

2. Comply with all site-specific requirements and SOPs including and not limited to: Key Policy, Badging Policy, Rules of Behavior, and Smoking Policy.

3. Normal construction work hours are 7:00 AM to 3:30 PM Monday through Friday.

a. Normal work hours can be modified only by written approval of the COR, and at no additional cost to VA.

b. No work by the Contractor on Federal Holidays, and no work on the weekend when the Federal Holiday is on the respective Monday or Friday.

c. No work in stairs, corridors, lobbies, or other interior / exterior public areas shall be performed during the above-designated work hours.

d. Any work including and not limited to noise, vibration, dust, odors, core drilling, hammer-drilling, saw cutting, equipment moving in public corridors, soil compaction shall be performed during the above-designated work hours only.

e. Crane lifts, or any work that closes drive isles, closes building entries, or closes public corridors shall be during low patient times and performed between Saturday 6 PM through midnight concluding by 6 PM on the following Sunday.

4. All building systems shall be maintained in full operation at all times:

a. Request utility system shutdowns in writing not less than 21 calendar days in advance and scheduled with the COR at times least impacting patient care.

b. Shutdown work shall be during low patient times and performed between Saturday 6 PM through midnight concluding by 6 PM on the following Sunday.

5. Wherever demolition is planned, ceiling tiles are to be removed, or the sprinkler system is to be disabled, GC shall first provide uniform heat detection throughout the work area, connected to the existing supervised building master fire alarm system, for the duration of the work. Fire and or smoke detection devices shall be provided prior to turnover and acceptance.

6. Deliveries, Parking, Elevators:

a. Deliveries only at the dock, and pre-coordinated with the COR. At time of delivery:

Provide vehicle information to the VA Police and remove the vehicle as soon as delivery is complete. Move materials in public corridors during low patient times between 6 PM through midnight, concluding by 6 AM the following day.

b. No parking in the VA garages. As part of the Mobilization Plan submission, indicate where workers are to park.

c. Contractor shall use freight elevators. Do not move materials and employees in passenger elevators without written approval of the COR, and never within elevators occupied by staff or patients.

7. The Mobilization Plan submission shall indicate if and where a construction dumpster is intended to be placed. The contractor shall provide a construction dumpster with a locked safety fence surrounding it, at a location submitted to and approved by the COR.

Pavement, concrete surfaces, and landscaping shall be protected from damage resulting from delivery, retrieval, loading, unloading, and dumpster weight.

a. Construction Waste Diversion Reports are required for every dumpster removed from every construction site at every VA facility. Provide these reports to VA COR immediately after the waste hauler removes each dumpster to comply with VA GEMS Policy.

b. No trash, used packaging, or construction spoils shall be stored in the work area.

Never use dumpsters other than those rented for this work. Severe penalties, including potential criminal charges may be levied for use of government-rented or owned containers, or those of other contractors.

c. Trash removal from the work area shall be within gondolas which have sealed covers (completely enclosed), and during non-business hours, via the freight elevators.

8. No on-site office or storage container shall be allowed. Provide “just-in-time” delivery and pickup. Coordinate with the COR for staging within the area of work.

9. No music radios within work areas.

10. No noise generated within the work area can be allowed to leave it.

11. The use of powder-actuated fasteners is forbidden.

12. Two-way communications radios are allowed where transmit/receive frequencies will not disrupt any hospital system.

13. Before starting work the contractor shall give 21 days’ notice to the COR so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described elsewhere in this section.

14. VA reserves the right to close or shut down the project site and or require Contractor employees to leave the premises in the event of a civil emergency or operational requirement. The Contractor may return to the site only with the written approval of the

COR

15. Compatible system procurements shall include the following:

A. Locks and Keys: Temporary and permanent door hardware shall be compatible with Best® 7-pin, G-keyway, interchangeable core. Prior to commencement of work, the contractor shall provide VA with blank cores; quantity matching the number of openings planned. VA shall then provide construction coring, and a key for same to the General Contractor, who will sign acknowledgement and receipt and responsibility for the key until returned to the VA COR. Final pinout and keying are provided by VA.

B. Exit Signs: All exit signs shall be City of Chicago approved specification red letters on white edge-lit LED fixtures continuously illuminated 90 mins after loss of power, push-to-test switch and LED pilot light on the housing, available as single or double-sided models, and meeting UL924.

C. Building Automation: Components, programming and start up: Native BACnet communications protocol for Building Automation and Control (BAC) connected to the existing Johnson Controls head end equipment

D. 27 15 00 Communications Cabling (and other specifications which include telecom cabling): All new telecom cabling shall be Cat 6a vs. 5e. Cat 6a telecom cable, termination punch-down T-568-(B.1, B.2, C.2, etc.), tested and certified (submit result to COR), 6-port modular wall jacks with two RJ45 on top and bottom and two blanks in middle. While VA facilities generally do not include plenum return spaces above ceilings, it nonetheless requires plenum-rated teledata cabling complying with codes pertaining to plenum environments.

E. 22 05 23 General Duty Valves for Plumbing Piping (multiple occurrences), and all other occurrences of specification for similar valves:

a. Bronze (brass) valves and fittings of any type shall be incapable of dezincification, not dezincification resistant materials. Alternatively, (simply) provide valves meeting the following minimum requirements: Domestically-manufactured premium brand products made of 316 stainless steel housing, ball, stem, lever nut, and handles, as well as (reinforced; modified) PTFE seats, packing, and seals, and 250 lb. steam trim

– regardless of service less than this rating. Selected valves shall also include 2.25” extended stems to enable insulating the entire valve with 2” preformed insulation and all-weather jacketing, while leaving the handle lever exposed and operational, with no potential for rough edges which could harm maintenance staff (fold metal jacketing in, typ. Of these locations). Lever handles shall include spring-loaded latch lock handles which enable lock-out and prevent inadvertent handle movement.

Exceptions to the content regarding levers or ball-type operation include locations where other types of valves are indicated (ex. gate, butterfly, actuated, etc.). These exceptions do not relieve the requirement for dezincification-proof metallurgy.

b. Valves shall be installed within “strike-zone” reach of maintenance workers, standing on the floor, without being caused to reach around obstructions – especially hot surfaces, and secured to prevent torque-fatigue damage to connected piping and fittings. Where valves must be installed above the specified range, configure for chain operation, and provide valve operation chain within strike-zone reach of maintenance workers. Do not configure with site or shop-fabricated levers which can become a head-injury hazard.

c. Ensure lever handles point in the direction of flow when open.

d. Drain-down valves shall be fitted with a pipe nipple (after/below the valve) of sufficient length to prevent scalding operator’s hand when opening the valve handle and equipped with a tethered threaded cap for use in prevention of inadvertent discharge or especially scalding during periodic maintenance.

e. Alternatively, depending on configuration, provide a threaded brass hose thread connection after the valve, and install a hose rated for steam use which runs to a nearby floor drain without crossing walking paths or otherwise creating a trip hazard.

F. 22 07 11 Plumbing Insulation:

a. All hot or cold content piping shall be completely insulated, except for flanges (distance equal to bolt or stud plus one inch), unions (allowing removal of nut without removal of insulation system), valve and gauge stems, and similar locations requiring inspection or periodic maintenance.

b. The all-service jacketing (ASJ) described as white finish with kraft paper bonded to aluminum foil and fiberglass reinforced with pressure-sensitive adhesive closure is important to the performance of a pipe insulation system, but not complete. In fact, the text appears to describe a proper vapor retarder-enhanced, pre-formed fiberglass insulation product. The system must be completely sealed and protected, yet serviceable. All piping insulation shall be pre-formed type, including longitudinal and circumferential fittings and completely sealed from outside air and moisture. Where proper fitting of preformed insulation is impractical or impossible, ceramic wool offers an effective solution. Use of aerosol expanding foam products is not allowed on mechanical components.

c. Use of glass fiber or metal fabric or netting with or without asphalt or epoxy resin, mastics, or cements, is outmoded for this application as well as costly, and unreliable, as is the use of pins, nails, staples, and or tacks. Experienced insulation mechanics know how to cut and place materials properly, ensuring tight joints and even surfaces ready for installation of vapor retarder system, and then PVC or metal jacketing – including exposed ends at unions and flanges.

d. For indoor locations at low operating temperatures provide PVC jacketing, including pre-formed elbow, tee, and end covers, completely sealing all insulation. Do not use fasteners, adhesives, or assembly methods not expressly approved by, or provided by the PVC jacketing manufacturer. Outdoor locations, and indoor systems with operating temperatures PVC jacketing is not indicated for, provide corrugated aluminum or stainless sheet metal jacketing, including pre-formed elbow, tee, and end covers trimmed tightly to prevent air gaps - completely sealing all insulation.

Where air gaps occur, careful use of silver color GE or another premium brand silicone caulk is acceptable. Use ½” (nom.) aluminum or stainless-steel bands over metal jacketing. Use of 18 gage soft annealed aluminum wire during assembly is acceptable provided it does not affect the jacketing.

e. Where painting pipe is specified, allow to fully cure before applying insulation.

Always label new work ASBESTOS FREE over jacketing. No part of the piping insulation system shall obstruct access and reading specified brass valve and device tags. Apply ANSI/ASME A13.1 standard pipe labels over installed jacketing.

f. Provide a laminated P&ID drawing labeled with tag numbers along with a laminated Isolation Device Listing for compliant lock-out planning and execution.

16. Sole Source Procurement, the contractor shall provide fully functional complete systems, including the following sole source procurements for the following special systems:

A. Fire Alarm: Components, programming and start up within the West Campus is by Johnson Controls/Simplex.

B. Building Automation: Components, programming and start up: Automated Logic Company of Chicago.

C. Proximity card reader and door lock release entry system: Components, programming and start up: eNorman