The document titled "Other Contract Forms" is a compilation of standard contract forms for the Overbrook Seawall Replacement project by Sarasota County Government in Florida. The forms include a Consent of Surety to Final Payment, a Contractor's Final Affidavit & Release of Lien, a Stored Materials Affidavit, and a Performance and Payment Bond. The project involves excavation, grading, and stabilization of canal banks, with specific work located at Lemon Bay: Overbrook at Neptune Drive, aimed at reducing stream bank erosion, removing exotic vegetation, reducing sedimentation, and providing storm water treatment.
The Performance and Payment Bond, in compliance with Florida Statute Chapter 255.05(1)(a), outlines the contractor's obligations to perform the contract as specified, make prompt payments to all claimants supplying labor, materials, or supplies, pay any losses or damages sustained by the owner, and guarantee all work and materials for the specified contract period. The bond serves as a financial protection mechanism for Sarasota County, ensuring the contractor's compliance with contract terms and protecting subcontractors and suppliers from potential non-payment. The bond is a standard risk mitigation tool in construction contracts, providing assurance to the county that the project will be completed according to the agreed-upon specifications and terms.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Plans.pdf | ||
| Project_Map.pdf | ||
| Technical_Specifications.pdf | ||
| Project_Documents_252729AMS.pdf | ||
| General_Conditions.pdf | ||
| NRCS_Hurricane_Ian_Repair_Grant_Provisions.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 6
OTHER
CONTRACT
FORMS
CONSENT OF SURETY FORM PAGE CS-1
SARASOTA COUNTY GOVERNMENT
CONSENT OF SURETY TO FINAL PAYMENT
SURETY:
BOND NO.:
OWNER: SARASOTA COUNTY BOARD OF COUNTY COMMISSIONERS
PROJECT TITLE: OVERBROOK SEAWALL REPLACEMENT
CONTRACT #
CONTRACTOR:
EFFECTIVE DATE OF BOND:
In accordance with the provisions of the Contract referenced above between the above Owner and Contractor, the Surety Company named below:
SURETY COMPANY NAME:
SURETY COMPANY ADDRESS:
under Bond with the Contractor named below:
CONTRACTOR NAME:
CONTRACTOR ADDRESS:
Hereby approves final payment by the Owner to the Contractor and agrees that final payment does not relieve the Surety of its obligations under the Bond to the Owner named below:
SARASOTA COUNTY COMMISSION
1660 RINGLING BOULEVARD
SARASOTA, FL 34234
IN WITNESS WHEREOF, the Surety has hereto set its hands on this date_________, 20__
Surety
Signature of Authorized Representative
Printed Name and Title Attest/Witness:
(Seal):________________________
Attached: Notarized Power of Attorney
RELEASE OF LIEN PAGE RL-1
Standard Form For CONTRACTOR’S FINAL AFFIDAVIT & RELEASE of LIEN
STATE OF FLORIDA, COUNTY OF ______________
Before me, the undersigned authority, personally appeared , who, after being by me first duly sworn, deposes and says that:
1. He is of , (Title of Officer) (Name of Company) doing business in the State of Florida, hereinafter called "Contractor".
2. Contractor pursuant to a Contract dated ____________________________, hereinafter referred to as "Contract", with Sarasota County, Florida, hereinafter referred to as "County", has heretofore furnished or caused to be furnished labor, material and services for the construction of certain improvements as more particularly set forth in said contract.
3. Contractor represents that all work to be performed under the aforesaid Contract has been fully completed and that all persons and firms who furnished material, labor and/or services incident to the completion of said work have been paid in full except to the following:
(Write in "None" if all persons and firms have been paid in full)
NAME ADDRESS AMOUNT DUE
4. The undersigned affiant for and in consideration of final payment to him in the amount of $___________________, and all other previous payments paid by County to contractor, does hereby for and in behalf of the Contractor, waive, release, remise and relinquish the contractor’s right to claim, demand or impose a lien or liens for work done or materials and/or services furnished or any other class of lien whatsoever, on any of the premises owned by County on which improvements have been completed in connection with the aforementioned contract.
5. The affiant herein does hereby represent that he has authority to execute a full and final Release of Lien for and in behalf of the Contractor as set forth above.
6. The affiant herein makes this Affidavit and Release of Lien for the express purpose of inducing County to make final disbursement and payment to the Contractor in the amount of $_______________________.
7. This Affidavit and Release of Lien is made by affiant with full knowledge of the applicable laws of the State of Florida. In addition to such rights as may be afforded to County under said applicable laws, affiant expressly agrees to indemnify and save
County harmless from any and all actual costs and expenses, including reasonable attorney’s fees, arising out of claims by laborers, subcontractors or materialmen who might claim that they have not been paid for services or material furnished by or through the contractor in connection with the work performed under the aforementioned Contract.
RELEASE OF LIEN PAGE RL-2
Name of Corporation
By: _______________________________________
President
(CORPORATE SEAL)
ATTEST:
Name of Corporation
Secretary
Sworn to and subscribed before me this day
(date)
Notary Public
(NOTARY SEAL)
My Commission Expires:_______________________
STORED MATERIALS AFFIDAVIT PAGE SMA-1
STORED MATERIALS AFFIDAVIT
STATE OF FLORIDA, COUNTY OF __________________
Before me, the undersigned authority, personally appeared , who being duly sworn, says that he is a subcontractor for of , General Contractor for
Project, and that all materials billed on the attached invoice are being held in the subcontractor’s warehouse at , Florida, for this project, and are fully insured against loss or damage.
(Subcontractor Firm Name)
By:
(Name of Representative)
(Title of Representative)
SWORN TO AND SUBSCRIBED BEFORE ME THIS DAY OF , 20
Notary Public:
My commission expires:
FOR
General Contractor for this project states that the stored materials constitute a part of the
Performance, payment and guarantee bond, and are for this project only.
SWORN TO AND SUBSCRIBED BEFORE ME THIS DAY OF , 20
Notary Public:
My commission expires:
SARASOTA COUNTY GOVERNMENT
PERFORMANCE AND PAYMENT BOND
In compliance with F.S. Chapter 255.05(1)(a)
15 July 09 Revision
PERFORMANCE AND PAYMENT BOND PAGE PB-1
BOND NO.:
CONTRACTOR NAME:
CONTRACTOR ADDRESS:
CONTRACTOR PHONE NO.:
SURETY COMPANY:
SURETY AGENT:
OWNER NAME: Sarasota County Board of County Commissioners OWNER ADDRESS: 1660 Ringling Boulevard Sarasota FL 34236
OWNER PHONE NO.: 941-861-5000
BOND AMOUNT:
CONTRACT NO.: (if applicable)
DESCRIPTION OF WORK: Excavation, grading and stabilization of canal banks with excavation of sediment traps. Construction of several restoration projects within select locations of Lemon and Roberts Bay to reduce stream bank erosion, Remove exotic vegetation, reduce sedimentation and and provide treatment for storm water.
PROJECT ADDRESS: Lemon Bay: Overbrook at Neptune Drive
LEGAL DESCRIPTION: Section 14/Township 40S/Range 19E Parcel: 0487070001
By this bond, we, _____________________________________, as Principal and
________________________________, a corporation, as Surety, are bound to Sarasota
County Board of County Commissioners, herein called Owner, in the sum of
$_________________________________, for payment of which we bind ourselves, our heirs, personal representatives, successors, and assigns, jointly and severally.
The conditions of this bond is that if Principal:
In compliance with F.S. Chapter 255.05(1)(a)
15 July 09 Revision
PERFORMANCE AND PAYMENT BOND PAGE PB-2
1. Performs the Contract dated , between principal and Owner for construction of Overbrook Seawall Replacement, Bid #25XXXXXX, the contract being made a part of this bond by reference, at the times and in the manner prescribed in the contract; and
2. Promptly makes payments to all claimants, as defined in Section 255.05 (1)
Florida Statutes, supplying principal with labor, materials, or supplies, used directly or indirectly by principal in the prosecution of the work provided for in the contract; and
3. Pays Owner all losses, damages, expenses, costs, and attorney’s fees, including appellate proceedings, that Owner sustains because of a default by principal under the contract work; and
4. Performs the guarantee of all work and materials furnished under the contract for the time specified in the contract, then this bond is void;
otherwise it remains in full force.
Any changes in or under the contract documents and compliance or noncompliance with any formalities connected with the contract or the changes does not affect surety’s obligation under this bond.
Any action instituted by a claimant under this bond for payment must be in accordance with the notice and time limitation provisions in Section 255.05(2), Florida Statutes.
In compliance with F.S. Chapter 255.05(1)(a)
15 July 09 Revision
PERFORMANCE AND PAYMENT BOND PAGE PB-3
In witness whereof, the said Principal and Surety have signed and sealed this instrument this
(date)
Principal
As President
(SEAL)
Surety
Approved as to form and execution:
By: ____________________________________________
Attorney to Board of County Commissioners of Sarasota County, Florida
Any Claims under this bond may be addressed to (name and address of Surety):
Telephone No: ___________________________________________
Name and address of agent or representative in Florida if different from above: