This document is a bid tabulation for the Guardrail Replacement Project 2025 (PW1652-25) for Marion County, Oregon, involving two bidders: Mid Valley Excavation LLC and Dirt & Aggregate Int. Inc. The project encompasses comprehensive guardrail infrastructure replacement, including mobilization, traffic management, erosion control, construction survey work, clearing and grubbing, and native plant seeding. The bid was released on 4/1/2025, with bid opening and report date set for 4/2/2025. The project involves multiple line items for guardrail system components, including end pieces, posts, terminals, and a Midwest Guardrail System, with quantities ranging from 1-725 units across various categories.

The bid shows significant price variations between the two bidders, with Mid Valley Excavation LLC submitting a total bid of $111,770.00 and Dirt & Aggregate Int. Inc. proposing $169,900.00. Key price differences are evident in items like aggregate shoulder (Mid Valley at $10,000.00 vs. Dirt & Aggregate at $31,250.00) and Midwest Guardrail System (Mid Valley at $29,000.00 vs. Dirt & Aggregate at $24,650.00). The project includes specific technical requirements such as sediment barriers, temporary signs, flaggers, and specialized guardrail installations, with unit prices and total quantities clearly delineated for each line item.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Report Date Bid Release Bid Opening 4/2/2025 4/1/2025 4/2/2025

MID VALLEY

EXCAVATION LLC

DIRT &

AGGREGATE INT.

INC

Line Number Description Unit Quantity Price Total Price Total 1 0210-0100 MOBILIZATION LS (Lump Sum) 1 $11,500.00 $11,500.00 $19,500.00 $19,500.00

2 0225-0050

TEMPORARY PROTECTION AND

DIRECTION OF TRAFFIC LS (Lump Sum) 1 $1,500.00 $1,500.00 $21,030.00 $21,030.00

3 0225-0070 TEMPORARY SIGNS SF (Square Foot) 232 $5.00 $1,160.00 $20.00 $4,640.00 4 0225-0490 FLAGGERS HR (Hour) 256 $65.00 $16,640.00 $70.00 $17,920.00 5 0280-0100 EROSION CONTROL LS (Lump Sum) 1 $500.00 $500.00 $500.00 $500.00 6 0280-0322 SEDIMENT BARRIER, TYPE 3 FT (Foot) 920 $3.50 $3,220.00 $12.00 $11,040.00 7 0290-0100 POLLUTION CONTROL PLAN LS (Lump Sum) 1 $500.00 $500.00 $500.00 $500.00 8 0305-0100 CONSTRUCTION SURVEY WORK LS (Lump Sum) 1 $6,300.00 $6,300.00 $2,500.00 $2,500.00

9 0310-0100

REMOVAL OF STRUCTURES AND

OBSTRUCTIONS LS (Lump Sum) 1 $3,250.00 $3,250.00 $5,000.00 $5,000.00

10 0320-0100 CLEARING AND GRUBBING LS (Lump Sum) 1 $3,500.00 $3,500.00 $5,000.00 $5,000.00 11 0640-0200 AGGREGATE SHOULDER TN (Ton) 250 $40.00 $10,000.00 $125.00 $31,250.00 12 0810-0220 GUARDRAIL END PIECES, TYPE C EA (Each) 2 $225.00 $450.00 $300.00 $600.00 13 0810-0300 EXTRA FOR 8' POSTS EA (Each) 12 $180.00 $2,160.00 $60.00 $720.00 14 0810-0302 EXTRA FOR 11' POSTS EA (Each) 6 $250.00 $1,500.00 $175.00 $1,050.00 15 0810-0320 EXTRA FOR POST HOLE IN ROCK EA (Each) 6 $715.00 $4,290.00 $250.00 $1,500.00

16 0810-0350

GUARDRAIL TERMINALS, NON-

FLARED EA (Each) 1 $4,800.00 $4,800.00 $7,500.00 $7,500.00

17 0810-0400 GUARDRAIL TERMINALS, FLARED EA (Each) 1 $5,000.00 $5,000.00 $7,500.00 $7,500.00

18 0810-0450

MIDWEST GUARDRAIL ANCHOR

SYSTEM DOWSTREAM ANCHOR

TERMINAL EA (Each) 2 $3,000.00 $6,000.00 $2,000.00 $4,000.00

19 0810-0500

MIDWEST GUARDRAIL SYSTEM, TYPE

2A FT (Foot) 725 $40.00 $29,000.00 $34.00 $24,650.00

20 1030-0228 NATIVE PLANT SEEDING LS (Lump Sum) 1 $500.00 $500.00 $3,500.00 $3,500.00 $111,770.00 $169,900.00