This Addendum #1 document, issued by the State of Delaware Office of Management and Budget, Division of Facilities Management (OMB/DFM), provides supplemental instructions for the Plummer Community Corrections Center Building(s) Demolition project (Contract #MC1002001330). The project scope encompasses complete demolition and removal of nine existing buildings at the former Plummer Community Corrections Center, including all associated foundations, footings, concrete slabs, and below-grade construction. All demolition debris must be legally disposed of in accordance with applicable regulations. The contractor must disconnect, cut, and permanently cap existing site utilities at or immediately adjacent to each building while maintaining existing site utility distribution systems and protecting all designated site improvements including asphalt paving, parking areas, sidewalks, curbing, perimeter fencing, and utility infrastructure. The pre-bid meeting was held on November 5, 2026, at 9:00 a.m. and attendance was mandatory. Sealed bids are due by 1:00 p.m. local time on Monday, November 23, 2026, via the Bonfire Portal or in-person delivery to the specified address. Bids will be opened and read aloud at 2:00 p.m. on the same date at the Haslet Armory in Dover, Delaware. The State anticipates contract award within approximately 30 days of bid opening, with the successful contractor required to execute the contract and provide bonds and insurance certificates within 20 days of Notice of Award. The RFI deadline is Monday, November 16, 2026, at 1:00 p.m.

Pricing is structured on a lump-sum basis and includes an Owner's Contingency Allowance of $25,000.00, with any unused allowance monies to be returned to the Owner via credit change order at project conclusion. Prevailing wage rates for 2026 apply to all laborers and mechanics, as detailed in the bid documents. The contractor must provide all required forms including a completed Subcontractor List (with full names and addresses of all subcontractors and third-tier contractors), a Non-Collusion Statement, an Affidavit of Employee Drug Testing Program, and an Affidavit of Contractor Qualifications, all notarized. Bid security in the form of a bid bond is required at ten percent of the total bid amount. Hazardous material abatement is currently underway and anticipated to be completed by mid-December, with an abatement completion certificate and supporting documentation to be provided to the awarded contractor. The contractor is responsible for all demolition permits and associated fees, coordination with utility providers for disconnections, and provision of security and site access management. Work hours are limited to 8:00 a.m. to 4:30 p.m., Monday through Friday, with all construction operations limited to the building premises. The project is funded through Delaware state appropriations for facility management and infrastructure improvements.

View the file

Other files

File Type Posted
OMB-MC1002001330-rfp.pdf PDF
OMB-MC1002001330-Exemption.pdf PDF
OMB-MC1002001330-wages.pdf PDF
OMB-MC1002001330-specs.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date: November 5, 2026 @ 9:00 AM

Project: Plummer Community Corrections Center Building(s) Demolition OMB/DFM Contract #MC1002001330

The work herein shall be considered part of the bid documents for the referenced project and carried out in accordance with the following supplemental instructions issued in accordance with the Contract Documents without change in Contract Sum or Contract Time. Acknowledge receipt of addendum on the bid form as indicated.

General

1. Project Identification:

OMB/DFM Contract No. MC1002001330 StudioJAED Project #26128

2. Attendance at this meeting is a prerequisite for bidding on this contract.

Each individual must sign in for themselves and not for anyone that is not present. All attendees shall indicate time when signed in and signed out on the sign-in sheet.

Sealed bids for OMB/DFM Contract No. MC1002001330 – Plummer Community Corrections Center Building(s) Demolition will be received by the State of Delaware, Office of Management and Budget, Division of Facilities Management, by way of the Bonfire Portal at https://DFM.bonfirehub.com until 1:00 pm local time on Monday, November 23, 2026. Bids may also be delivered in person to 122 Martin Luther King Jr BLVD S Dover DE 19901 no later than the date and time indicated above. Bidder bears the risk of late submission.

Bids will be opened and read aloud at 2:00 PM local time on Monday, November 23, 2026 at the Haslet Armory, 122 Martin Luther King Blvd. S., Dover, DE 19901.

3. The deadline for RFIs to StudioJAED is Monday, November 16, 2026 at 1:00 pm.

4. RFI and questions are to be submitted via email to Philip Conte, Ben Shaffer, and Nimesh Patel at StudioJAED.

contep@studiojaed.com shafferb@studiojaed.com pateln@studiojaed.com

All questions will be responded to in an Addendum.

5. Digital bid documents can be purchased at RCI Printing and Graphics. All addendums will be distributed by RCI or found on the State of Delaware Bid Solicitation Directory website.

Addendum #1 mailto:contep@studiojaed.com mailto:shafferb@studiojaed.com mailto:pateln@studiojaed.com

Pre-Bid Meeting Notes

1. Attendance at the Pre-Bid Meeting is mandatory. A copy of the sign in sheet will be included in Addendum #1.

2. General Project Scope Review

a. Complete demolition and removal of nine (9) existing buildings at the former Plummer Community Corrections Center.

b. Remove all associated foundations, footings, concrete slabs, and below-grade building construction.

c. Remove and legally dispose of all demolition debris in accordance with applicable regulations.

d. Disconnect, cut, and permanently cap existing site utilities at or immediately adjacent to each building.

e. Maintain existing site utility distribution systems in place.

f. Protect and preserve all existing site improvements, including:

i. Asphalt paving and roadways

ii. Parking areas

iii. Sidewalks and curbing

iv. Perimeter fencing

g. Backfill all building excavations following demolition.

h. Where building demolition leaves gap in perimeter fencing, contractor shall provide chain-link fencing of equal height to maintain secure fence line.

i. Rough grade disturbed areas to establish safe, stable, and properly draining conditions.

j. Comprehensive site grading, paving replacement, landscaping, and site redevelopment are excluded from the project scope.

3. Bid Form Review

a. Complete forms as presented, do not edit or alter.

b. Provide all information requested in full or bid will not be accepted.

c. Acknowledge all addendums as individual items.

d. Contract time shall indicate full contract time from Notice to

Proceed through Closeout.

e. Contractor to provide Affidavit of Employee Drug Testing Program with submission of bids. Subcontractor’s Employee Drug Testing Forms will be required, post bid, from the successful bidder.

f. List all Sub-contractors and any third-tier sub-contractors performing work.

g. If Contractor is self-performing work, please list as part of sub-contractor list.

4. Sub-Contractor List Review

a. Proposed trades will be included as listed contractors:

i. Demolition

5. Unit Prices Review

a. None

6. Allowances Review

a. Allowance No. 1: Owner’s Contingency – For general contingencies and repairs, the remaining balance of which is to be returned to the Owner by credit change order at project conclusion. Twenty-five thousand dollars ($25,000.00)

7. Alternates Review

a. None

8. Prevailing Wage Project

a. 2026 wage rates apply. These are included on the Bid Solicitation Directory and are included in the bid documents.

9. Schedule

a. The Owner anticipates Contract award within approximately (30) days of the bid opening. The successful Contractor will be required to execute the Contract and provide associated bonds and insurance certificates within 20 days of Notice of Award.

10. Contractor Use of Premises

a. Construction Operations: Limited to the building premises.

i. Work hours are between 8:00 am to 4:30 pm, Monday through Friday. Alternate hours will only be considered on a special-need basis.

ii. Laydown space limited to area of work and coordinated with the Owner.

iii. Contractor responsible to provide porta-potty.

iv. Contractor shall be responsible for securing all materials.

b. Provide and maintain access to and from the project site as required by applicable laws, regulations, and the Owner:

i. Coordinate all construction access, demolition operations, equipment staging, material storage, and debris removal routes with the Owner prior to commencing work.

ii. Do not obstruct existing roadways, sidewalks, parking areas, emergency access routes, or other public ways without prior authorization from the Owner and applicable authorities.

iii. Maintain safe access for emergency vehicles and authorized personnel throughout demolition operations.

iv. Provide temporary barriers, fencing, signage, and other protective measures as necessary to secure demolition areas and prevent unauthorized access.

v. Contractor parking, equipment staging, and material storage shall be limited to areas approved by the Owner.

vi. Protect existing site improvements designated to remain, including roadways, asphalt paving, parking areas, sidewalks, curbing, fencing, and utility infrastructure.

Repair damage resulting from demolition operations at no additional cost to the Owner.

c. Utility Outage and Shutdown:

i. Coordinate all utility disconnections, interruptions, and shutdowns with the Owner and applicable utility providers at least fourteen (14) calendar days prior to the anticipated work.

ii. Verify the location, type, and operational status of all existing utilities serving the buildings scheduled for demolition prior to commencing demolition activities.

iii. Disconnect, cut, and permanently cap existing utilities at or immediately adjacent to each building scheduled for demolition, as indicated in the Contract Documents.

Existing site utility distribution systems shall remain in place unless otherwise indicated.

iv. Protect and maintain uninterrupted utility services to adjacent buildings, facilities, and site infrastructure designated to remain operational.

v. Limit utility interruptions and shutdowns to the minimum duration necessary to safely complete the work. Obtain Owner approval prior to proceeding with any planned shutdown.

vi. Coordinate any required access to areas outside the designated demolition limits with the Owner at least seven

(7) calendar days in advance.

vii. The Owner reserves the right to postpone or reschedule planned utility shutdowns or associated demolition activities with minimal advance notice when necessary to address emergencies, operational requirements, or unforeseen conditions.

viii. Do not commence demolition of any building until all utilities serving that building have been properly disconnected, isolated, and made safe. Verify completion of utility disconnections and capping prior to demolition.

ix. Contractor shall be responsible for coordination with applicable utility providers and obtaining any permits, approvals, inspections, and certifications required for utility disconnections and permanent capping.

11. Owner Occupancy

a. The owner will NOT occupy the Plummer Community Corrections Center Building(s) and site throughout demolition.

12. Permitting

a. All demolition permit submissions and fees shall be by the contractor.

13. Abatement

a. Hazardous material abatement is currently underway and is anticipated to be completed by mid-December. Upon completion, an abatement completion certificate and supporting documentation will be provided to the awarded contractor.

14. If there is interest in a subcontractor walkthrough, send e-mail to StudioJAED (Philip Conte, Ben Shaffer, Nimesh Patel) and we will coordinate a date and time with Owner.

Attachments:

1. Sign In Sheets – (This document has been scanned and transcribed. SJ assumes no responsibility for typographical errors or inaccuracies in contact information resulting from the original sign-in sheet. A copy of the scanned sign-in sheets are provided)

2. Revised Front Ends

a. 00 41 13 – Bid Forms

i. Added bid due date

ii. Revised incorrect contract number.

b. 00 43 13 – Bid Bond

i. Revised incorrect contract number.

c. 00 61 13.13 – Performance Bond

i. Revised incorrect contract number.

d. 00 61 13.16 – Payment Bond

i. Revised incorrect contract number.

END

Pre-Bid Sign-In Sheet

Please Note:

Vendors must sign-in on this sheet to verify attendance at the Pre-Bid meeting.

Representative Name Firm Phone Email Time

Don Yanick Castle Construction of DE Inc 302-420-7443 Donald.yanick@castlede.com 9am

James Kelly FRB Wrecking 610-256-5491 Jkelly@frbwrecking.com 9am

Theresa Beinke FRB Wrecking 856-269-7626 Tbeinke@frbwrecking.com 9am

George Rodriguez Dependable Construction of DE 615-705-4410 George.dcod@gmail.com 9am

Project: Plummer Community Corrections Center Building(s) Demolition Solicitation No.: OMB/DFM Contract #MC1002001330 / SJ Project #26128 Location: Plummer Community Corrections Center, Maintenance Shed, located on 32nd St.

Date & Time: Thursday, November 5, 2026 at 9:00 am local time / Ended 9:20am mailto:Donald.yanick@castlede.com mailto:Tbeinke@frbwrecking.com mailto:George.dcod@gmail.com

Representative Name Firm Phone Email Time

Dan Driscoll Scheibel Construction Bids@scheibelconstruction.com 9am

Anthony Pascuzzi Manafort Brothers Inc. 860-836-9964 Apascuzzi@manfort.com 9am

Zachary Johnson Tamco Construction 267-337-4702 ZjohnsonDemo2@gmail.com 9am

Audrey Sarro Berg Demo Group 717-916-3247 asarro@bergdemo.com 9am

Pasquale Marconi Geppert Bros 215-822-7900 Estimating@geppertbros.com 9am

Representative Name Firm Phone Email Time

Joe Lafferty Brightfields 302-723-1846 JLafferty@brightfields.com 9am

Rick Pearcy Amakor Inc. 302-834-8664 Amakor@aol.com 9am

Gabe Cheung StudioJAED 302-832-1652 cheungg@studiojaed.com 9am

Robbie Mullin OMB/DFM 302-739-5644 Robbie.mullin@delaware.gov 9am mailto:cheungg@studiojaed.com mailto:Robbie.mullin@delaware.gov

Plummer Community Corrections Center Building(s) Demolition November 5, 2026 OMB/DFM Contract #MC1002001330

Revised per Addendum #1

StudioJAED Architects & Engineers BID FORMS Project No. 26128 00 41 13 - 1

Plummer Community Corrections Center – Building(s) Demolition 38 Todds Lane

Wilmington, DE 19802 OMB / DFM Contract # MC1002001330

BID FORM

For Bids Due: November 23, 2026 To: State of Delaware OMB / DFM Haslet Armory 122 Martin Luther King Jr Blvd S, 2nd Floor Dover, DE 19901

Name of Bidder:

Delaware Business License No.: Taxpayer ID No.:

(Other License Nos.):

Phone No.: ( ) - Fax No.: ( ) -

The undersigned, representing that he has read and understands the Bidding Documents and that this bid is made in accordance therewith, that he has visited the site and has familiarized himself with the local conditions under which the Work is to be performed, and that his bid is based upon the materials, systems and equipment described in the Bidding Documents without exception, hereby proposes and agrees to provide all labor, materials, plant, equipment, supplies, transport and other facilities required to execute the work described by the aforesaid documents for the lump sum itemized below:

ALLOWANCES

Allowances conform to applicable project specification section. Refer to the specifications for a complete description of the following Allowances:

ALLOWANCE No. 1: Include an allowance entitled “General Owner’s Allowance” in the amount of $25,000.00. This allowance will be utilized by the Owner for Owner-elected changes to the work. Any or all unused allowance monies shall be returned to the Owner via a credit change order at the end of the project. This allowance shall be carried as an individual line item on the Application for Payment. Acknowledge / Initial: ________

Building(s) Demolition Plummer Community Corrections Center OMB/DFM Contract #MC1002001330 November 5, 2026 Revised per Addendum #1

BID FORMS StudioJAED Architects & Engineers 00 41 13 - 2 Project No. 26128

Plummer Community Corrections Center – Building(s) Demolition 38 Todds Lane

Wilmington, DE 19802 OMB / DFM Contract # MC1002001330

BID FORM

I/We acknowledge Addendums numbered and the price(s) submitted include any cost/schedule impact they may have.

This bid shall remain valid and cannot be withdrawn for thirty (30) days from the date of opening of bids (60 days for School Districts and Department of Education), and the undersigned shall abide by the Bid Security forfeiture provisions. Bid Security is attached to this Bid.

The Owner shall have the right to reject any or all bids, and to waive any informality or irregularity in any bid received.

This bid is based upon work being accomplished by the Sub-Contractors named on the list attached to this bid.

Should I/We be awarded this contract, I/We pledge to achieve substantial completion of all the work within calendar days of the Notice to Proceed.

The undersigned represents and warrants that he has complied and shall comply with all requirements of local, state, and national laws; that no legal requirement has been or shall be violated in making or accepting this bid, in awarding the contract to him or in the prosecution of the work required; that the bid is legal and firm; that he has not, directly or indirectly, entered into any agreement, participated in any collusion, or otherwise taken action in restraint of free competitive bidding.

Upon receipt of written notice of the acceptance of this Bid, the Bidder shall, within twenty (20) calendar days, execute the agreement in the required form and deliver the Contract Bonds, and Insurance Certificates, required by the Contract Documents.

I am / We are an Individual / a Partnership / a Corporation

By Trading as (Individual’s / General Partner’s / Corporate Name)

(State of Corporation)

Business Address:

Witness: By:

( Authorized Signature )

(SEAL)

( Title )

Date:

ATTACHMENTS

Sub-Contractor List Non-Collusion Statement Affidavit of Employee Drug Testing Program Affidavit of Contractor Qualifications Bid Security (Others as Required by Project Manuals)

Revised per Addendum #1

StudioJAED Architects & Engineers BID FORMS Project No. 26128 00 41 13 - 3

Plummer Community Corrections Center – Building(s) Demolition 38 Todds Lane

Wilmington, DE 19802 OMB / DFM Contract # MC1002001330

BID FORM

SUBCONTRACTOR LIST

In accordance with Title 29, Chapter 69, Section 6962(d)(10)b of the Delaware Code, the following subcontractor listing must accompany any bid submittal. The bidder must list in each category the full name and address (City & State) of the sub-contractor that the bidder will be using to perform the work and provide material for that subcontractor category. Should the bidder’s listed subcontractor intend to provide any of their subcontractor category of work through a third-tier contractor, the bidder shall list that third-tier contractor’s full name and address (City & State). If the bidder intends to perform any category of work itself, it must list its full name and address. For clarification, if the bidder intends to perform the work themselves, the bidder may not insert “not applicable”, “N/A”, “self” or anything other than its own full name and address (City & State). To do so shall cause the bid to be rejected. In addition, the failure to produce a completed subcontractor list with the bid submittal shall cause the bid to be rejected. If you have more than three (3) third-tier contractors to report in any subcontractor category, print out additional page(s) containing the appropriate category, complete the rest of your list of third-tier contractors for that category, notate the addition in parentheses as (CONTINUATION) next to the subcontractor category and an asterisk (*) next to any additional third-tier contractors, and submit it with your bid.

Subcontractor Category Subcontractor Address (City & State) Subcontractors tax-payer ID # or Delaware Business license #

1. Demolition

A.

B.

C.

Revised per Addendum #1

BID FORMS StudioJAED Architects & Engineers 00 41 13 - 4 Project No. 26128

Plummer Community Corrections Center – Building(s) Demolition 38 Todds Lane

Wilmington, DE 19802 OMB / DFM Contract # MC1002001330

BID FORM

NON-COLLUSION STATEMENT

This is to certify that the undersigned bidder has neither directly nor indirectly, entered into any agreement, participated in any collusion or otherwise taken any action in restraint of free competitive bidding in connection with this proposal submitted this date (to the Office of Management and Budget, Division of Facilities Management).

All the terms and conditions of OMB/DFM Contract #MC1002001330 have been thoroughly examined and are understood.

NAME OF BIDDER:

AUTHORIZED REPRESENTATIVE

(TYPED):

AUTHORIZED REPRESENTATIVE

(SIGNATURE):

TITLE:

ADDRESS OF BIDDER:

E-MAIL: ______________________________________________________________

PHONE NUMBER:

Sworn to and Subscribed before me this day of 20 .

My Commission expires . NOTARY PUBLIC .

THIS PAGE MUST BE SIGNED AND NOTARIZED FOR YOUR BID TO BE CONSIDERED.

Revised per Addendum #1

StudioJAED Architects & Engineers BID FORMS Project No. 26128 00 41 13 - 5

AFFIDAVIT

OF

EMPLOYEE DRUG TESTING PROGRAM

4104 Regulations for the Drug Testing of Contractor and Subcontractor Employees Working on Large Public Works Projects requires that Contractors and Subcontractors implement a program of mandatory drug testing for Employees who work on Large Public Works Contracts funded all or in part with public funds.

We hereby certify that we have in place or will implement during the entire term of the contract a Mandatory Drug Testing Program for our employees on the jobsite, including subcontractors, that complies with this regulation:

Contractor/Subcontractor Name:

Contractor/Subcontractor Address:

Authorized Representative (typed or printed):

Authorized Representative (signature):

Title:

Sworn to and Subscribed before me this day of 20 .

Revised per Addendum #1

BID FORMS StudioJAED Architects & Engineers 00 41 13 - 6 Project No. 26128

Plummer Community Corrections Center – Building(s) Demolition 38 Todds Lane

Wilmington, DE 19802 OMB / DFM Contract # MC1002001330

AFFIDAVIT

OF

CONTRACTOR QUALIFICATIONS

We hereby certify that we will abide by the contractor’s qualifications outlined in the construction bid specifications for the duration of the contract term.

In accordance with Title 29, Chapter 69, Section 6962(d)(10)b.3 of the Delaware Code, after a contract has been awarded the successful bidder shall not substitute another subcontractor whose name was submitted on the Subcontractor Form except for the reasons in the statute and not without written consent from the awarding agency. Failure to utilize the subcontractors on the list will subject the successful bidder to penalties as outlined in the General Requirements Section 5.2 of the contract.

Contractor Name:

Contractor Address:

Authorized Representative (typed or printed):

Authorized Representative (signature):

Title:

Sworn to and Subscribed before me this day of 20 .

Revised per Addendum #1

StudioJAED Architects & Engineers BID BOND Project No. 26128 00 43 13 - 1

STATE OF DELAWARE

OFFICE OF MANAGEMENT AND BUDGET

BID BOND

TO ACCOMPANY PROPOSAL

(Not necessary if security is used)

KNOW ALL MEN BY THESE PRESENTS That:

of in the County of and State of as Principal, and of in the County of and State of as Surety, legally authorized to do business in the State of Delaware (“State”), are held and firmly unto the State in the sum of ten percent (10%) of the total amount of the base bid plus ten percent (10%) of the total amount of all additive alternates not to exceed

Dollars ($ ) of amount of bid on Contract No. MC1002001330, to be paid to the State for the use and benefit of OMB/Division of Facilities Management for which payment well and truly to be made, we do bind ourselves, our and each of our heirs, executors, administrators, and successors, jointly and severally for and in the whole firmly by these presents.

NOW THE CONDITION OF THIS OBLIGATION IS SUCH That if the above bonded Principal who has submitted to the OMB/Division of Facilities Management a certain proposal to enter into this contract for the furnishing of certain material and/or services within the State, shall be awarded this Contract, and if said Principal shall well and truly enter into and execute this Contract as may be required by the terms of this Contract and approved by the OMB/Division of Facilities Management this Contract to be entered into within twenty days after the date of official notice of the award thereof in accordance with the terms of said proposal, then this obligation shall be void or else to be and remain in full force and virtue.

Sealed with seal and dated this day of in the year of our Lord two thousand and (20 ).

SEALED, AND DELIVERED IN THE

Presence of

Name of Bidder (Organization)

Corporate By:

Seal Authorized Signature

Attest Title

Name of Surety

Witness: By:

Title

Revised per Addendum #1

StudioJAED Architects & Engineers PERFORMANCE BOND Project No. 26128 00 61 13.13 - 1

STATE OF DELAWARE

OFFICE OF MANAGEMENT AND BUDGET

PERFORMANCE BOND

Bond Number: ___________________

KNOW ALL PERSONS BY THESE PRESENTS, that we, ______________________, as principal (“Principal”), and ______________________, a ______________________ corporation, legally authorized to do business in the State of Delaware, as surety (“Surety”), are held and firmly bound unto the State of Delaware Office of Management & Budget (“Owner”), in the amount of _________________ ($___________), to be paid to Owner, for which payment well and truly to be made, we do bind ourselves, our and each and every of our heirs, executors, administrations, successors and assigns, jointly and severally, for and in the whole, firmly by these presents.

Sealed with our seals and dated this __________ day of ____________, 20__.

NOW THE CONDITION OF THIS OBLIGATION IS SUCH, that if Principal, who has been awarded by Owner that certain contract known as Contract No. MC1002001330 dated the __________ day of ____________, 20__ (the “Contract”), which Contract is incorporated herein by reference, shall well and truly provide and furnish all materials, appliances and tools and perform all the work required under and pursuant to the terms and conditions of the Contract and the Contract Documents (as defined in the Contract) or any changes or modifications thereto made as therein provided, shall make good and reimburse Owner sufficient funds to pay the costs of completing the Contract that Owner may sustain by reason of any failure or default on the part of Principal, and shall also indemnify and save harmless Owner from all costs, damages and expenses arising out of or by reason of the performance of the Contract and for as long as provided by the Contract; then this obligation shall be void, otherwise to be and remain in full force and effect.

Surety, for value received, hereby stipulates and agrees, if requested to do so by Owner, to fully perform and complete the work to be performed under the Contract pursuant to the terms, conditions and covenants thereof, if for any cause Principal fails or neglects to so fully perform and complete such work.

Surety, for value received, for itself and its successors and assigns, hereby stipulates and agrees that the obligation of Surety and its bond shall be in no way impaired or affected by any extension of time, modification, omission, addition or change in or to the Contract or the work to be performed thereunder, or by any payment thereunder before the time required therein, or by any waiver of any provisions thereof, or by any assignment, subletting or other transfer thereof or of any work to be performed or any monies due or to become due thereunder; and Surety hereby waives notice of any and all such extensions, modifications, omissions, additions, changes, payments, waivers, assignments, subcontracts and transfers and hereby expressly stipulates and agrees that any and all things done and omitted to be done by and in relation to assignees, subcontractors, and other transferees shall have the same effect as to Surety as though done or omitted to be done by or in relation to Principal.

Revised per Addendum #1

PERFORMANCE BOND StudioJAED Architects & Engineers 00 61 13.13 - 2 Project No. 26128

Surety hereby stipulates and agrees that no modifications, omissions or additions in or to the terms of the Contract shall in any way whatsoever affect the obligation of Surety and its bond.

Any proceeding, legal or equitable, under this Bond may be brought in any court of competent jurisdiction in the State of Delaware. Notices to Surety or Contractor may be mailed or delivered to them at their respective addresses shown below.

IN WITNESS WHEREOF, Principal and Surety have hereunto set their hand and seals, and such of them as are corporations have caused their corporate seal to be hereto affixed and these presents to be signed by their duly authorized officers, the day and year first above written.

PRINCIPAL

Name:

Witness or Attest: Address:

By: (SEAL) Name: Name:

Title:

(Corporate Seal)

SURETY

Name:

Witness or Attest: Address:

By: (SEAL) Name: Name:

Title:

(Corporate Seal)

Revised per Addendum #1

StudioJAED Architects & Engineers PAYMENT BOND Project No. 26128 00 61 13.16 - 1

STATE OF DELAWARE

OFFICE OF MANAGEMENT AND BUDGET

PAYMENT BOND

Bond Number: ___________________

KNOW ALL PERSONS BY THESE PRESENTS, that we, ____________________, as principal (“Principal”), and __________________, a ____________________ corporation, legally authorized to do business in the State of Delaware, as surety (“Surety”), are held and firmly bound unto the State of Delaware Office of Management & Budget (“Owner”), in the amount of _________________ ($___________), to be paid to Owner, for which payment well and truly to be made, we do bind ourselves, our and each and every of our heirs, executors, administrations, successors and assigns, jointly and severally, for and in the whole firmly by these presents.

Sealed with our seals and dated this _____________ day of____________, 20__.

NOW THE CONDITION OF THIS OBLIGATION IS SUCH, that if Principal, who has been awarded by Owner that certain contract known as Contract No. MC1002001330 dated the _______ day of _____________, 20__ (the “Contract”), which Contract is incorporated herein by reference, shall well and truly pay all and every person furnishing materials or performing labor or service in and about the performance of the work under the Contract, all and every sums of money due him, her, them or any of them, for all such materials, labor and service for which Principal is liable, shall make good and reimburse Owner sufficient funds to pay such costs in the completion of the Contract as Owner may sustain by reason of any failure or default on the part of Principal, and shall also indemnify and save harmless Owner from all costs, damages and expenses arising out of or by reason of the performance of the Contract and for as long as provided by the Contract;

then this obligation shall be void, otherwise to be and remain in full force and effect.

Surety, for value received, for itself and its successors and assigns, hereby stipulates and agrees that the obligation of Surety and its bond shall be in no way impaired or affected by any extension of time, modification, omission, addition or change in or to the Contract or the work to be performed thereunder, or by any payment thereunder before the time required therein, or by any waiver of any provisions thereof, or by any assignment, subletting or other transfer thereof or of any work to be performed or any monies due or to become due thereunder; and Surety hereby waives notice of any and all such extensions, modifications, omissions, additions, changes, payments, waivers, assignments, subcontracts and transfers and hereby expressly stipulates and agrees that any and all things done and omitted to be done by and in relation to assignees, subcontractors, and other transferees shall have the same effect as to Surety as though done or omitted to be done by or in relation to Principal.

Surety hereby stipulates and agrees that no modifications, omission or additions in or to the terms of the Contract shall in any way whatsoever affect the obligation of Surety and its bond.

Revised per Addendum #1

PAYMENT BOND StudioJAED Architects & Engineers 00 61 13.16 - 2 Project No. 26128

Any proceeding, legal or equitable, under this Bond may be brought in any court of competent jurisdiction in the State of Delaware. Notices to Surety or Contractor may be mailed or delivered to them at their respective addresses shown below.

IN WITNESS WHEREOF, Principal and Surety have hereunto set their hand and seals, and such of them as are corporations have caused their corporate seal to be hereto affixed and these presents to be signed by their duly authorized officers, the day and year first above written.

PRINCIPAL

Name:

Witness or Attest: Address:

By: (SEAL) Name: Name:

Title:

(Corporate Seal)

SURETY

Name:

Witness or Attest: Address:

By: (SEAL) Name: Name:

Title:

(Corporate Seal)

General
1. Project Identification:
OMB/DFM Contract No. MC1002001330 StudioJAED Project #26128
2. Attendance at this meeting is a prerequisite for bidding on this contract.
Each individual must sign in for themselves and not for anyone that is not present. All attendees shall indicate time when signed in and signed out on the sign-in sheet.
Sealed bids for OMB/DFM Contract No. MC1002001330 – Plummer Community Corrections Center Building(s) Demolition will be received by the State of Delaware, Office of Management and Budget, Division of Facilities Management, by way of the Bonfire Portal at https://DFM.bonfirehub.com until 1:00 pm local time on Monday, November 23, 2026. Bids may also be delivered in person to 122 Martin Luther King Jr BLVD S Dover DE 19901 no later than the date and time indicated above. Bidder bears the risk of late submission.
Bids will be opened and read aloud at 2:00 PM local time on Monday, November 23, 2026 at the Haslet Armory, 122 Martin Luther King Blvd. S., Dover, DE 19901.
3. The deadline for RFIs to StudioJAED is Monday, November 16, 2026 at 1:00 pm.
4. RFI and questions are to be submitted via email to Philip Conte, Ben Shaffer, and Nimesh Patel at StudioJAED.
contep@studiojaed.com
shafferb@studiojaed.com
pateln@studiojaed.com
All questions will be responded to in an Addendum.
5. Digital bid documents can be purchased at RCI Printing and Graphics. All addendums will be distributed by RCI or found on the State of Delaware Bid Solicitation Directory website.
Pre-Bid Meeting Notes
END