This is a Work Plan Cover Sheet and detailed scope of work submitted by the Village of Medina to the New York Department of State for the NY Forward Canal Basin Work Plan (Contract Number C1003036, RFA 24-DRINYF-37). The project, titled "Transform Canal Basin Park into a Waterfront Gateway," involves transforming a parking lot along the Erie Canal into a waterfront gateway featuring green space, seating areas, boater and cyclist amenities, designated pedestrian walkways, flexible greenspace with park and streetscape amenities, and an improved parking lot configuration. The work plan is divided into two main sections: Project Tasks (Tasks 1.1 through 1.9) and Reporting Requirements (Tasks 2.1 through 2.3). Project tasks include consultant selection and procurement compliance, draft design development, environmental quality review under SEQRA, final design and construction document preparation, permit acquisition, bid process and construction subcontractor selection, installation of project signage (to remain for at least 60 days after construction completion), construction management with monthly progress notifications and site inspections, and final project completion with certified as-built plans and photo documentation. All deliverables must be submitted in specified formats including PDF, CAD, JPG, and ArcGIS data with required metadata.

The Village of Medina, led by Mayor Deborah L. Padoleski with primary contact Jada Burgess (Village Clerk), received a New York Forward Grant of $1,345,000.00 to fund this project under the oversight of the New York Department of State with OPD Project Manager Samantha Aldrich. The Contractor must obtain Department approval for all professional services through locally compliant procurement procedures, ensure that a licensed professional engineer, architect, or landscape architect certified to practice in New York State prepares and certifies final designs and supervises construction, and maintain MWBE utilization reporting with goals of 15 percent for both Minority Business Enterprises and Women Business Enterprises. The Village must certify compliance with General Municipal Law procurement provisions, submit semi-annual project status reports, and complete a Final Project Summary Report before final payment authorization. The Department of State will review and approve all subcontracts, design documents, site plans, and preconstruction materials before construction may commence, and will participate in project kick-off and subsequent important meetings throughout the contract term.

View the file

Other files

File Type Posted
Procurement Policy.pdf PDF
Workplace Violence Prevention Policy Statement 2026.pdf PDF
Sexual Harassment.pdf PDF
Medina_SIP_CanalBasin.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WORK PLAN COVER SHEET

Name of Recipient:
Medina (V)
Title of Project:
Transform Canal Basin Park into a Waterfront Gateway
RFA number
24-DRINYF-37
Contract number:
C1003036
OPD Project Manager:
Samantha Aldrich
OPD Supervisor:
Amanda Smith
OPD Admin:
Amanda Jochum

Recipient CEO:

Name:
Deborah L. Padoleski
Title:
Mayor
Phone number:
585-798-0710
Email address:
dlpadoleski@villagemedina.gov

Recipient Primary Contact:

Name:
Jada Burgess
Title:
Village Clerk
Affiliation:
Village of Medina
Phone number:
585-798-0710
Email address:
jburgess@villagemedina.gov

Recipient Secondary Contact:

Name:

Title:

Affiliation:

Phone number:

Email address:

Contract Number: C1003036 Page 1 of 6, Attachment C - Work Plan D&C Single CTV

ATTACHMENT C - WORK PLAN

Transform Canal Basin Park into a Waterfront Gateway

1. Project Description

The Village of Medina will advance the Medina NY Forward through the following project:

Transform Canal Basin Park into a Waterfront Gateway Transform the parking lot along the Erie Canal into a “waterfront gateway” complete with green space, seating areas and boater/cyclist amenities. Improvements may include but are not limited to: designated pedestrian walkways, flexible greenspace with park and streetscape amenities for expanded programming, and an improved parking lot configuration.

2. Required Products

The Contractor must submit to the Department all required products, clearly labeled with the NYS Comptroller's contract number as indicated on the Face Page of this Contract and where applicable, the related task number from this Work Plan.

Unless otherwise specified in the Work Plan tasks, the Contractor shall submit products in the following formats:

· Draft products: one electronic copy of each product must be submitted in Adobe® Acrobat® Portable Document Format (PDF), created using 300 dpi scanning resolution and Microsoft Word, if applicable.

· Final products: one electronic copy of each product must be submitted in PDF, created using 300 dpi scanning resolution and Microsoft Word, if applicable. In addition, one paper copy of each final product (including reports, designs, maps, drawings, and plans) must be submitted.

· Electronic data for all Geographic Information System-based mapping products must be submitted in either ArcGIS format, or similar product acceptable to the Department, and comply with the requirements for Contract GIS Products. Formal metadata must be provided with all digital GIS data which includes, at minimum, a file summary/abstract, intended use, data, source data, and author information.

· Electronic data for all designs, drawings, and plans must be submitted in the original software that they were created (such as CAD format or other similar product acceptable to the Department), as well as in JPG format.

· Photographs and images must be submitted in JPG format with a minimum resolution of 300 dpi and must be dated and captioned with the location and a brief description of the activity being documented and include any associated metadata (including the photo’s GPS location where available).

3. Compliance with Procurement Requirements

The municipal attorney, chief legal officer or financial administrator of the municipality shall certify in writing to the Department that applicable provisions of General Municipal Law were fully complied with.

4. Project Tasks

Task 1.1 Consultant Selection and Compliance with Procurement Requirements

In consultation with the Department, the Contractor shall retain professional services through the locally approved procurement process per General Municipal Law. The municipal attorney, chief legal officer or financial administrator of the municipality shall certify in writing to the Department that applicable provisions of General Municipal Law were fully complied with.

For preparation/certification of final designs and construction documents, and for supervision of construction, a licensed professional engineer, architect or landscape architect licensed to practice in New York State is required.

The Contractor shall prepare the draft subcontract(s) to conduct project work with the selected consultant(s). The subcontract(s) shall contain a detailed work plan with adequate opportunity for review at appropriate stages of product completion, a payment schedule with payments tied to receipt of products, and project costs.

The Contractor shall submit the draft subcontract(s) to the Department for review of the subcontract work plan for alignment with the appropriate tasks of the work plan as set forth in this contract. The Contractor shall incorporate the Department’s comments on the subcontract work plan, or scope of services, prior to execution of the final subcontract(s). The Contractor remains responsible for the legal sufficiency of the subcontract in accordance with the requirements in the Master Grant Contract and Attachment A-1.

Products: Consultant(s) selected and approved by the Department. Written certification of compliance with procurement procedures. Draft and final, executed consultant subcontracts.

Task 1.2 Draft Design

The Contractor shall prepare, or cause to be prepared, a draft design based upon the conceptual designs from the Strategic Investment Plan. The draft design shall include all required maps, tables, data, written discussions, and other information as identified in the contract and subcontract work plans. The draft design shall be provided to the Department for review. Department comments must be addressed to the satisfaction of the Department in subsequent revisions of the final design.

Products: Draft design and supporting materials.

Task 1.3 Environmental Quality Review

The Contractor shall prepare, or cause to be prepared, all documents necessary to comply with the State Environmental Quality Review Act (SEQRA) through determination of significance. If a positive declaration is made, a Draft Environmental Impact Statement shall be prepared.

Products: SEQRA documents and, if necessary, a Draft Environmental Impact Statement.

Task 1.4 Final Design and Construction Documents

The Contractor shall prepare, or cause to be prepared, the final design and construction drawings, plans, specifications, and cost estimates. The final design and construction documents shall be provided to the Department for review. Final design and construction documents are subject to approval by the Department. These documents must be certified by a licensed professional engineer, architect, or landscape architect and the appropriate seal must be affixed to these documents.

Products: Final design and construction documents, certified by a licensed professional engineer, architect or landscape architect.

Task 1.5 Permits

The Contractor shall prepare, or cause to be prepared, the necessary permits or other approval applications and obtain the required permits or approvals. Prior to construction the Contractor or its consultant(s) shall also demonstrate that the project is in compliance with 6 NYCRR Part 502, "Floodplain Management Criteria for State Projects" by obtaining a floodplain development permit, if local regulations establish such requirements, or by submitting a signed certification, by an official authorized to enforce local floodplain management regulations, that the project complies with the requirements of the statute.

Products: Copies of all required permits and approvals shall be submitted to the Department upon receipt.

Task 1.6 Bid Process and Selection of Construction Subcontractor

After the final design and construction documents have been approved by the Department, the Contractor shall prepare and distribute, or cause to be prepared and distributed, a bid invitation to select a construction subcontractor or subcontractors. Prior to distributing the bid invitation, the Contractor or its consultant(s) shall submit the bid invitation to the Department for review and comment.

The Contractor shall select the construction subcontractor(s) from the bid respondents and shall prepare a draft contract or contract(s) to conduct the work with the selected construction subcontractor(s). The contract(s) shall contain a detailed work plan with adequate opportunity for review at appropriate stages of project completion, a payment schedule with payments tied to receipt of products/project milestones, and project costs. The Contractor must certify to the Department that applicable public bidding procedures of General Municipal Law were followed for the selection of all construction or other subcontractors.

The Contractor shall submit the draft subcontract(s) to the Department for review and approval and shall incorporate the Department's comments in the final subcontract(s). A copy of the final, executed subcontract(s) shall be submitted to the Department.

Products: Executed construction subcontract(s). Written certification of procurement procedures.

Task 1.7 Project Signage The Contractor shall install, or cause to be installed, a sign satisfactory to the Department identifying the State’s funding of the project. The project sign shall remain in place for at least 60 days after completion of construction or initial occupancy, which ever duration is longer.

Products:Department-approved sign design, and photo-documentation that sign is installed in project area.
Task 1.8Construction, Construction Management and Site Inspection

After receipt of all necessary permits, the Contractor or its construction subcontractor(s) may begin construction work according to the final design and construction documents – including any site remediation as necessary to remove contaminated soil. The Contractor shall provide, or cause to be provided, notification to the Department monthly (or more frequently) in writing of work progress, including any delays which have occurred. After 70% of the work is completed, the progress notification will include a punch list of any incomplete items and an estimated schedule for project completion.

The Contractor and/or the Department shall verify progress and completion of the work through periodic site inspections. The Contractor or its consultant(s) shall submit to the Department written summaries of progress including photo documentation and identification of problems to be addressed based on periodic site inspections.

Products: Written summary of periodic site visits including photo-documentation and identification of any problems that need to be addressed. Punch list and construction completion estimates.

Task 1.9 Completion of Project

Following satisfaction of punch list items, the Contractor shall submit, or cause to be submitted, a statement that the work has been completed in accordance with the contract and subcontract(s), the final design and construction specifications, and all permit requirements. The completion statement must be prepared and/or certified by a licensed professional engineer, architect or landscape architect. Unless otherwise specified during project kick-off meeting, the Contractor shall submit, or cause to be submitted, two sets of as-built plans, certified by a licensed professional engineer, architect or landscape architect. When the Contractor is satisfied work is complete, it shall submit a final project report to the Department, including a copy of the completion statement and a copy of the certified as-built plans and photo-documentation in the form of digital images of the site prior to, during and upon completion of work. The Contractor shall not submit a final payment request to the Department, until the Department concurs that the work is complete.

Products: Statement of completion, certified as-built plans, and final project report including photo-documentation.

Task 2.1 MWBE Reporting

Comply with MWBE Reporting Requirements by completing the following actions:

· Submit Form D - MWBE Utilization Plan to indicate any state-certified MWBE firms selected to work on this contract. Form D must be updated and submitted to the Department whenever changes to the selected MWBE firms occur (addition or removal).

· Record payments to MWBE subcontractors using DOS funds through the New York State Contract System (NYSCS).

Technical assistance for use of the NYSCS system can be obtained through the NYSCS website at https://ny.newnycontracts.com by clicking on the “Contact Us & Support” link.

Products: Ongoing reporting through NYSCS during the life of the contract.

Task 2.2 Project Status Reports

The Contractor shall submit project status reports semi-annually (every June 30 and December 31) on the form provided, including a description of the work accomplished, the status of all tasks in this work plan, schedule of completion of remaining tasks, and an explanation of any problems encountered.

Products: Completed project status reports submitted to DOS during the life of the contract.

Task 2.3 Final Project Summary Report

The Contractor or its consultant(s) shall work with the Department project manager to complete the Final Project Summary Report. Final payment shall not be authorized until this report has been completed and filed with project deliverables.

Products: Completed Final Project Summary Report submitted to DOS.

5. Project Responsibilities

The Contractor shall administer the grant, execute a contract with the Department, and ensure the completion of work in accordance with the approved Work Plan and budget.

The Contractor:

· will be responsible for conducting all project work in conformance with the Work Plan included in the executed contract with the Department.

· will be responsible for all project activities including drafting request for proposals and managing subcontracts with consultants and subconsultants.

· will certify to the Department that the procurement record for project consultants and subcontractors complies with the applicable provisions of General Municipal Law.

· will receive approval from the Department for any and all consultant subcontracts before beginning project work.

· will be responsible for submission of all products and payment requests.

· will be responsible for coordinating participation and soliciting comments from local government personnel, project volunteers, and the public.

· will keep the Department informed of all important meetings for the duration of this contract.

· will receive approval from the Department before purchase of any equipment.

· will secure all necessary permits and perform all required environmental reviews.

· will ensure that all materials printed, constructed, and/or produced acknowledge the contributions of the Department to the project.

· will ensure that all products prepared as a part of this contract shall include the NYS Comptroller's contract number as indicated on the Face Page of this contract.

· will ensure the project objectives are being achieved.

· will ensure that comments received from the Department, or other advisory group, are satisfactorily responded to and reflected in subsequent work.

· will recognize that payments made to consultants or subcontractors covering work carried out or products produced prior to receiving approval from the Department will not be reimbursed unless and until the Department finds the work or products to be acceptable.

· will participate, if requested by the Department, in a training session or sessions focused on developing and implementing revitalization strategies. The purpose of the training session(s) is to build knowledge and provide support to community leaders to advance revitalization efforts and complete priority projects.

The Department:

· will review and approve or disapprove of subcontracts between the Contractor and consultant(s) and any other subcontractor(s).

· will participate in initial project kick-off meeting and subsequent meetings that are important to the project.

· will review all draft and final products and provide comments as necessary to meet the objectives.

· must approve or disapprove any and all design, site plan, and preconstruction documents before construction may begin.

Contract Number: C1003036 Page 1 of 6, Attachment C - Work Plan