NWHC_modernization_AE_Cx_SOW.docx

DOCX document 37 KB Posted

Attached to
ARCHITECTURAL AND ENGINEERING SERVICES, PHASED MOD Federal contract opportunity
Solicitation number
140G0322R0001
Issued by
Department of the Interior US Geological Survey Office of Acquisitions and Grants

About this file

This statement of work outlines commissioning services required for the modernization of the U.S. Geological Survey's National Wildlife Health Center in Madison, Wisconsin. The commissioning authority will provide fundamental, enhanced, and monitoring-based commissioning of mechanical, electrical, plumbing, and renewable systems, as well as envelope commissioning. Specific services include construction document review, submittal review, equipment startup oversight, functional performance testing, short-term diagnostic testing, training coordination, and post-occupancy evaluation. Deliverables comprise a commissioning plan, pre-functional and functional testing checklists, an issues log, field reports, and a final commissioning report. All services must be completed within 30 days of substantial completion. This statement of work is related to solicitation 140G0322R0001 issued by the Department of the Interior US Geological Survey Office of Acquisitions and Grants for architectural and engineering services for the phased modernization of the National Wildlife Health Center.

View the file

Other files for this federal contract opportunity

Other files attached to ARCHITECTURAL AND ENGINEERING SERVICES, PHASED MOD, newest first.
File Type Posted
NWHC_modernization_AE_QA_0001.docx DOCX document
Sol_140G0322R0001_Amd_0001.pdf PDF
NWHC_modernization_AE_special_inspections_SOW.docx DOCX document
NWHC_modernization_AE_SOW_final_03_01_22.docx DOCX document
Sol_140G0322R0001.pdf PDF
NWHC_modernization_AE_TCs_v1.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Professional Enhanced Commissioning Services – STATEMENT of WORK USGS NWHC modernization, Madison, WI - DRAFT

The U. S. Geological Survey (USGS) has a requirement for Professional Commissioning Services. The services provided shall include fundamental and enhanced commissioning services to further support the design, construction, and eventual operation of a project that meets the owner’s project requirements for energy, water, indoor environmental quality, and durability.

Services provided are for the modernization of the USGS’ National Wildlife Health Center (NWHC) in Madison, WI – further scope TBD.

BACKGROUND

National Wildlife Health Center (NWHC) The NWHC was established in 1975 to serve the nation and its natural resources by providing sound science and technical support regarding wildlife disease, and to disseminate information to promote science-based decisions affecting wildlife and ecosystem health. NWHC personnel study emerging and resurging diseases, wildlife and ecosystem health, zoonotic diseases, and environmental health and degradation. The NWHC is located on 24 acres and maintains offices and high security disease laboratories in the Main Building (MB) and the Tight Isolation Building (TIB).

This Statement of Work for Professional Commissioning Services is integral to the design and construction for the new facilities – further scope TBD.

I. SCOPE OF WORK

A. Scope of new facilities to be constructed will be described here.

Commissioning Authority

The CxA must have documented commissioning process experience on at least three building projects with a similar scope of work. The experience must extend from early design phase through at least 10 months of occupancy.

Enhanced commissioning Complete the following commissioning process (CxP) activities for mechanical, electrical, plumbing, and renewable energy systems and assemblies in accordance with ASHRAE Guideline 0–2005 and ASHRAE Guideline 1.1–2007 for HVAC&R systems, as they relate to energy, water, indoor environmental quality, and durability.

The commissioning authority must do the following:

· Review design submittals. 65% and 95% CD’s.

· Verify inclusion of systems manual requirements in construction documents.

· Verify inclusion of operator and occupant training requirements in construction documents.

· Verify systems manual updates and delivery.

· Verify operator and occupant training delivery and effectiveness.

· Verify seasonal testing.

· Review building operations 10 months after substantial completion.

· Develop an on-going commissioning plan.

Include all enhanced commissioning tasks in the BOD.

Enhanced and monitoring-based commissioning

Develop monitoring-based procedures and identify points to be measured and evaluated to assess performance of energy- and water-consuming systems.

Include the procedures and measurement points in the commissioning plan. Address the following:

· roles and responsibilities;

· measurement requirements (meters, points, metering systems, data access);

· the points to be tracked, with frequency and duration for trend monitoring;

· the limits of acceptable values for tracked points and metered values (where appropriate, predictive algorithms may be used to compare ideal values with actual values);

· the elements used to evaluate performance, including conflict between systems, out-of-sequence operation of systems components, and energy and water usage profiles;

· an action plan for identifying and correcting operational errors and deficiencies;

· training to prevent errors;

· planning for repairs needed to maintain performance; and

· the frequency of analyses in the first year of occupancy (at least quarterly).

Update the systems manual with any modifications or new settings and give the reason for any modifications from the original design.

Envelope commissioning

Fulfill the requirements in EA Prerequisite Fundamental Commissioning and Verification as they apply to the building’s thermal envelope in addition to mechanical and electrical systems and assemblies.

Complete the following commissioning process (CxP) activities for the building’s thermal envelope in accordance with ASHRAE Guideline 0–2005 and the National Institute of Building Sciences (NIBS) Guideline 3–2012, Exterior Enclosure Technical Requirements for the Commissioning Process, as they relate to energy, water, indoor environmental quality, and durability.

Commissioning authority must complete the following:

· Review contractor submittals.

· Verify inclusion of systems manual requirements in construction documents.

· Verify inclusion of operator and occupant training requirements in construction documents.

· Verify systems manual updates and delivery.

· Verify operator and occupant training delivery and effectiveness.

· Verify seasonal testing.

· Review building operations 10 months after substantial completion.

· Develop an on-going commissioning plan.

B. Building commissioning of the following systems:

a. HVAC components and equipment.

b. HVAC system: interaction of cooling, heating, and comfort delivery systems.

c. Building Automation System (BAS): control hardware and software, sequence of operations, and integration of factory controls with BAS.

d. Lighting Control System and interface with daylighting.

e. Domestic hot water systems.

C. Commissioning Agent shall provide overall coordination and management of the commissioning program.

D. Assign representatives with expertise and authority to act on its behalf and shall schedule them to participate in and perform commissioning process activities including, but not limited to, the following:

a. Create and maintain a commissioning issues log.

b. Identify observed performance deficiencies identified in test reports and monitor corrective action, in collaboration with entity responsible for system and equipment installation.

c. Cooperate with the contractor for resolution of issues recorded in the issues log.

d. Attend commissioning team meetings.

e. Assist contractor in coordinating commissioning process activities with construction schedule.

f. Prepare and maintain a construction checklist log. Provide construction checklist to the contractor.

g. Complete electronic construction checklists as work is complete and monitor on a weekly basis.

h. Develop commissioning process test procedures provided to the contractor.

i. Observe contractor completion of commissioning process test procedures.

E. Verify the execution of commissioning process activities using random sampling. The sampling rate may vary from 1 to 100 percent. Verification will include, but not limited to, equipment submittals, construction checklists, training, operating and maintenance data, tests, and test reports to verify compliance with the contract specifications. When a random sample does not meet the requirement, the Commissioning Agent will report the failure in the issues log.

F. Witness systems, assemblies, equipment, and component startup.

G. Compile test data, inspection reports, and certificates; include them in the systems manual and commissioning process report.

H. Coordinate HVAC commissioning activities through the Contractor, including the following:

a. Provide project specific construction checklists and commissioning process test procedures for actual HVAC systems, and equipment to be commissioned as part of the construction contract.

b. Direct commissioning testing and witness contractor demonstration of equipment to be commissioned.

c. Verify testing, adjusting, and balancing of work provided by contractor.

d. Provide test data, inspection reports, and certificates in Systems Manuals.

I. Provide documentation required by the applicable project specifications.

II. ADMINISTRATIVE PROCEDURES AND EXECUTION

A. After Award and issuance of the NTP, the Commissioning Agent will coordinate all site visits through the COR. A copy of the COR’s authorized duties and responsibilities will be provided with the NTP. All site visits will be in compliance with USGS COVID protocols.

B. All commissioning personnel and representatives visiting USGS sites will be required to sign in upon arrival. Each visiting individual will be required to enter his/her name, company’s name, USGS project title, date, reason for the visit, and the times of arrival and departure. Additionally, all persons must always wear a visitor’s badge. Arrangements for after-normal-working-hour site visits must be made in advance during normal working hours.

C. Commissioning Team: The commissioning process will require cooperation of the Contractor, subcontractors, vendors, Architect/Engineer, Commissioning Agent, and the USGS. The commissioning team shall be comprised of the following:

a. Contractor

i. Project Manager

ii. Test Engineer

b. Subcontractors: As appropriate to product or system being commissioned.

c. Commissioning Agent

i. Project Manager

ii. Project Engineers

d. USGS Representative(s)

e. Architect/Engineer

i. Architect

ii. MEP engineers

iii. Specialty Consultant(s)

D. Progress Meetings: Attend construction job-site meetings, as necessary, to monitor construction and commissioning progress.

E. Coordinate with contractor to address coordination, deficiency resolution and planning issues.

i. Plan and coordinate additional meetings as required to progress the work.

F. Functional Testing Coordination: Equipment shall not be “temporarily” started for commissioning.

a. Functional performance testing shall not begin until pre-functional, start-up and TAB is completed for a given system.

b. The controls system and equipment it controls shall not be functionally tested until all points have been calibrated and pre-functional checklists are completed.

G. Indoor Air Quality (IAQ) baseline evaluation: Coordinate with IAQ baseline evaluation as specified under - Indoor Air Quality (IAQ) Management.

H. QUALITY CONTROL

a. Qualifications for Commissioning Agents: Engage commissioning service personnel, that specialize in the types of inspections and tests to be performed.

i. We expect the work to be overseen by a commissioning professional certified in accordance with ANSI/ISO/IEC 17024. At the time of this writing, that means one of the following: ACG Certified Commissioning Authority (CxA); ASHRAE Building Commissioning Professional (BCxP); and Building Commissioning Certification Board Certified Commissioning Professional.

ii. Certification as a Certified Commissioning Firm (CCF) from the Building Commissioning Association (BCA) is preferred.

I. TEST EQUIPMENT

a. Instrumentation shall meet the following standards:

i. Be of sufficient quality and accuracy to test and measure system performance within the tolerances required to determine adequate performance.

ii. Be calibrated on the manufacturer’s recommended intervals with calibration tags permanently affixed to the instrument being used.

iii. Be maintained in good repair and operation condition throughout the duration of use on this project.

b. All standard testing equipment required to perform startup and initial checkout and required functional performance testing shall be provided by the contractor for the equipment being tested.

c. Datalogging equipment or software required to test equipment will be provided by the Commissioning Agent but shall not become the property of the Owner.

J. COMMISSIONING PROCESS

a. The following activities outline the commissioning tasks and the general order in which they occur. The Commissioning Agent shall coordinate all activities.

i. Design Review

1. Construction Document Review

ii. Commissioning Scoping Meeting

iii. Commissioning Plan

iv. Submittals Review

v. Start-Up/Prefunctional Checklists

vi. Functional Performance Testing

vii. Short-Term Diagnostic Testing

viii. Deficiency Report and Resolution Record

ix. Final Commissioning Report

x. Deferred Testing

1. Unforeseen Deferred Tests

2. Seasonal Testing

3. End-of-Warranty Review

K. DESIGN REVIEW

a. Construction Document Review: Review construction documents as required to validate the commissioning plan.

L. COMMISSIONING SCOPING MEETING

a. Commissioning Scoping Meeting:

i. Schedule, coordinate, and facilitate a scoping meeting.

ii. Review each building system to be commissioned, including its intended operation, commissioning requirements, and completion and start-up schedules.

iii. Establish the scope of work, tasks, schedules, deliverables, and responsibilities for implementation of the Commissioning Plan.

b. Attendance: Commissioning Team members.

M. SUBMITTALS REVIEW

a. Submittal Review: Review the contractor submittals as required to validate the commissioning plan.

N. START-UP/PREFUNCTIONAL CHECKLISTS

a. Start-Up/Prefunctional Checklists: Coordinate start-up plans and documentation formats, including providing contractor with pre-functional checklists to be completed during the startup process.

i. Manufacturer’s start-up checklists and other technical documentation guidelines may be used as the basis for pre-functional checklists.

b. Start-Up/Pre-Functional Checklist shall help verify that the systems are complete and operational, so that the functional performance testing can be scheduled.

O. FUNCTIONAL PERFORMANCE TESTING

a. Functional Performance Testing: Test procedures shall fully describe system configuration and steps required for each test; appropriately documented so that another party can repeat the tests with virtually identical results.

i. Test Methods; Functional performance testing and verification may be achieved by direct manipulation of system inputs (i.e. heating or cooling sensors), manipulation of system inputs with the building automation system (i.e. software override of sensor inputs), trend logs of system inputs and outputs using the building automation system, or short-term monitoring of system inputs and outputs using stand alone data loggers. A combination of methods may be required to completely test the complete sequence of operations. The Commissioning Agent shall determine which method, or combination, is most appropriate.

ii. Setup: Each test procedure shall be performed under conditions that simulate normal operating conditions as closely as possible. Where equipment requires integral safety devices to stop/prevent equipment operation unless minimum safety standards or conditions are met, functional performance test procedures shall demonstrate the actual performance of safety shut offs in a real or closely- simulated conditions of failure.

iii. Sampling: Multiple identical pieces of non-life-safety or non-critical equipment may be functionally tested using a sampling strategy. The sampling strategy shall be developed by the Commissioning Agent. If, after three attempts at testing the specified sample percentage, failures are still present, then all remaining units shall be tested at the contractors’ expense.

iv. Develop functional performance test procedures for equipment and systems. Identify specific test procedures and forms to verify and document proper operation of each piece of equipment and system. Coordinate test procedures with the contractor for feasibility, safety, equipment and warranty protection.

v. Functional performance test forms shall include the following information:

1. System and equipment or component name(s).

2. Equipment location and ID number.

3. Date.

4. Project name.

5. Participating parties.

6. Instructions for setting up the test, including special cautions, alarm limits, etc.

7. Specific step-by-step procedures to execute the test.

8. Acceptance criteria of proper performance with a Yes / No checkbox.

9. A section for comments.

b. Coordinate, observe and record the results of contractor’s functional performance testing.

i. Coordinate retesting as necessary until satisfactory performance is verified.

ii. Verify the intended operation of individual components and system interactions under various conditions and modes of operation.

P. SHORT-TERM DIAGNOSTIC TESTING

a. Short-Term Diagnostic Testing: After initial occupancy, perform short-term diagnostic testing, using data acquisition equipment or the building automation system to record system operation over a two to three-week period.

i. Investigate the dynamic interactions between components in the building system.

ii. Evaluate the scheduling, the interaction between heating and cooling, and the effectiveness of the HVAC system in meeting the comfort requirements.

Q. DEFICIENCY REPORT AND RESOLUTION RECORD

a. Deficiency Report and Resolution Record: Document items of non-compliance in materials, installation or operation.

b. Non-Conformance. Non-conformance and deficiencies observed shall be addressed immediately, in terms of notification to responsible parties, and providing recommended actions to correct deficiencies.

1. Corrections of minor deficiencies identified may be made during the tests at the discretion of the Commissioning Agent. In such cases the deficiency and resolution shall be documented on the procedure form.

2. For identified deficiencies:

a. If there is no dispute on the deficiency and the responsibility to correct it:

i. The Commissioning Agent documents the deficiency and the adjustments or alterations required to correct it. The contractor corrects the deficiency and notifies the Commissioning Agent that the equipment is ready to be retested.

ii. The Commissioning Agent rescheduled the test and the test is repeated.

3. If there is a dispute about a deficiency or who is responsible:

i. The deficiency is documented on the non-compliance form and a copy given to the Contractor.

ii. Resolutions are made at the lowest management level possible. Additional parties are brought into the discussions as needed. Contractor shall have responsibility for resolving construction deficiencies. If a design revision is deemed necessary and approved by Owner, Architect/Engineer shall have responsibility for providing design revision.

iii. The Commissioning Agent documents the resolution process.

iv. Once the interpretation and resolution have been decided, the appropriate party corrects the deficiency and notifies the Commissioning Agent that the equipment is ready to be retested.

v. The Commissioning Agent rescheduled the test and the test is repeated until satisfactory performance is achieved.

4. Cost of Retesting: Costs for retesting shall be charged to the Contractor.

R. OPERATIONS AND MAINTENANCE TRAINING

a. O&M Manual: Review the operation and maintenance manuals compiled by the contractor for completeness and for adherence to the requirements of the specifications.

i. Obtain additional materials from the contractor as necessary to stress and enhance the importance of system interactions, troubleshooting, and long-term preventative maintenance and operation.

b. Training: Develop a Training Plan. Coordinate and review the training programs for Owner’s personnel.

i. Obtain additional materials from the contractor as necessary to stress and enhance the importance of system interactions, troubleshooting, and long-term preventative maintenance and operation.

S. RECORD DOCUMENTS REVIEW

a. Record Documents: Review record documents to verify accuracy.

T. DEFERRED TESTING

a. Unforeseen Deferred Tests: If a test cannot be completed due to the building structure, required occupancy condition, or other deficiency, the functional testing may be delayed upon recommendation of the Commissioning Agent and the approval of the Owner. These tests are conducted in the same manner as the seasonal tests as soon as possible.

b. Seasonal Testing:

i. Schedule, coordinate, observe, and document additional testing for seasonal variation in operations and control strategies during the opposite season to verify performance of the HVAC system and controls. Complete testing during the warranty period to fully test all sequences of operation.

ii. Update O&M manuals and Record Documents as necessary due to the testing.

c. End-of-Warranty Review: Conduct end of warranty review prior to the end of the warranty period. Review the current building operation with the facility maintenance staff. The review shall include outstanding issues from original or seasonal testing. Interview facility staff to identify concerns with building operation. Provide suggestions for improvements and assist owner in developing reports or documentation to remedy problems.

i. Update O&M manuals and Record Documents as necessary due to the testing.

U. COMMISSIONING SERVICES DELIVERABLES

a. The Commissioning Agent shall develop and provide to the USGS the following:

i. Provide a commissioning plan

1. Commissioning Plan: Develop a commissioning plan to identify how commissioning activities will be integrated into general construction and trade activities. The commissioning plan shall identify how commissioning responsibilities are distributed. The intent of this plan is to evoke questions, expose issues, and resolve them with input from the entire commissioning team early in construction. Submit commissioning plan and schedule within 30 calendar days of authorization to proceed. Update as necessary during the work to reflect the progress on the components and systems. Forward updates in a timely manner.

a. Identify who will be responsible for producing the various procedures, reports, Owner notifications and forms.

b. Include the commissioning schedule.

c. Describe the test/acceptance procedure.

ii. Pre - Functional and functional testing checklists. Submit minimum 30 calendar days prior to testing.

iii. Issues log

1. Document items of non-compliance in materials, installation or operation. Document the results from start-up/pre- functional checklists, functional performance testing, and short-term diagnostic monitoring. Include details of the components or systems found to be non- compliant with the drawings and specifications. Identify adjustments and alterations required to correct the system operation and identify who is responsible for making the corrective changes.

iv. Field Reports (within 5 days of field observation)

v. Final Commissioning Report

1. Compile a final Commissioning Report. Summarize all the tasks, findings, conclusions, and recommendations of the commissioning process. Indicate the actual performance of the building systems in reference to the Owner’s Project Requirements and contract documents. Include completed pre-functional inspection checklists, functional performance testing records, diagnostic monitoring results, identified deficiencies, recommendations, and a summary of commissioning activities.

V. PERIOD OF PERFORMANCE

a. All services must be completed not later than 30 days after Substantial Completion.

END OF STATEMENT OF WORK

NWHC modernization A&E Cx SOW - Page 2 of 2 (Attachment 2, Exhibit A)

File details come from the government source that posted it. Updated .