NVPS Athletics (Balance) - Bid Clarification 06.pdf

PDF 284 KB Posted

Attached to
Northview High School Athletic Stadium Addition & Renovation
Solicitation number
RFP NVP 260000002718 8
Issued by
Michigan

About this file

This is Bid Clarification No. 6 for the Northview High School Athletic Stadium Addition & Renovation project in Michigan, issued by Rockford Construction on behalf of the project management team. The clarification addresses questions raised at bid time and provides critical updates for all subcontractors and suppliers participating in the bidding process. The updated bid due date is November 10, 2026, at 1:00 p.m. EST, with bids to be submitted via Procore; a Zoom meeting link is provided for bidders requiring access. Key scope items include the addition of a Band Tower as detailed in Addendum #02, which General Trades Bidders (BP 06) must price in their bid submissions. An Entry/Arch structure clarification confirms that this component is not part of the signage package and shall be constructed per applicable trade scopes. Bid Forms have been updated on Procore to reflect scope changes, and bidders are instructed to work from the most current versions. The project team requests that all bidders update their bidding status on Procore by marking "Will Bid" or "Will Not Bid."

Sitework Bidders (BP 31) are required to price the pavement base bid per drawings and the Geotechnical Report as an alternate, noting a discrepancy between the geotechnical report recommendation of MDOT 22A Gravel and the drawing specification of 21AA Limestone with different thickness requirements. Bid RFI 27 regarding civil clarifications remains awaiting response. All bidders must ensure Procore access is established by contacting Morgan Gross at mgross@rockfordconstruction.com and must upload their bids before the 1:00 p.m. EST deadline, as the system will not accept submissions at or after that time.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 | P a g e

601 First Street NW Grand Rapids, Michigan 49504

(616) 285-6933 www.rockford.com

BID CLARIFICATION NO. 6

TO: All Subcontractors / Suppliers

FROM: Dan Korcek, Senior Project Manager; Morgan Gross, Assistant Project Manager

DATE: November 06, 2026

RE: NVPS Athletics Addition and Renovation

This Bid Clarification No. 6 is being sent to all bidders to address questions raised at bid time.

1. BID DUE DATE REMINDER

a. Bid Due Date is updated to November 10, 2026 @ 1:00pm EST.

b. ZOOM link:

i. https://rockfordconstruction.zoom.us/j/92749052347?from=addon

ii. Meeting ID - 927 4905 2347

c. Reminder that all bids must be uploaded on Procore. If you do not have access to Procore, please contact Morgan Gross at mgross@rockfordconstruction.com to add you to Procore to ensure that your bid can be uploaded.

d. Please be reminded that Procore will not accept bids at 1:00 pm EST or after on bid day. Please ensure that bids are uploaded before 1:00 pm.

2. Addendum #02

a. Addendum #02 has been released. This Specification/details the addition of a

Band Tower.

b. BP 06 General Trades Bidders shall include this in their scope of work and provide a price for this work as detailed in Addendum 02.

3. Bid RFIs have been generated; Responses are attached in files, with RFI Subjects shown below.

a. Bid RFI 27 – Civil Clarifications – AWAITING RESPONSE

b. Bid RFI 09 – Clarification: RFI 9 item 3 asked for who was responsible for clarification on scope for the wildcat stadium sign vs entry arch. Please Note that the “Entry/Arch structure is not part of the signage package. Entry is to be constructed as specified by all applicable trade scopes.

4. Scope Clarifications

a. Please note, Bid Forms have been updated on Procore to reflect scope changes. Ensure that you are working from the most up to date bid forms as you work to submit your bids.

b. BP 31 Sitework Bidders shall price, per the drawings, as base bid and Geotechnical report as alternate. The geotechnical report recommends MDOT 22A Gravel in 6 and 8 inch thicknesses for pavement areas yet the drawings call out 21AA Limestone (8 and 10 inch thickness).

https://protect.checkpoint.com/v2/r01/___http:/www.rockford.com___.YzJ1OnJvY2tmb3JkMTpjOm9mZmljZTM2NV9lbWFpbHNfYXR0YWNobWVudDo5M2QwMjI2MWQxMmRhNzdlYmEzMzkzODgzYTMyNTAwMDo3OmE1OGI6NWEyYTg3YTcwZmI4OWM3M2VlNmEzNjAzOGZhZGM4YzE5NDE3ODNlY2Q3Y2YwOWZiNGUzYWY2Y2NiZmQ2YjRmOTpwOlQ6Rg https://protect.checkpoint.com/v2/r01/___https:/rockfordconstruction.zoom.us/j/92749052347?from=addon___.YzJ1OnJvY2tmb3JkMTpjOm9mZmljZTM2NV9lbWFpbHNfYXR0YWNobWVudDplMjVhZjA3YzlhYzY1ZTI3NzNhODliZjk5MzFmYjY0Mjo3OjI2NjU6YTI4MjNkMGM4ZTllZjRmOWI4YmQ0YTEyZTE0ZGM1MDMzYzkyZDIyMTQzNTg4ZmZlNzAwNTA3ZGEyYzY4N2FhMTpwOlQ6Rg mailto:mgross@rockfordconstruction.com

2 | P a g e

5. Bidding Status

a. Please mark your bidding status on Procore this helps us understand who is bidding. It is extremely helpful to mark “Will Bid” or “Will Not Bid”.

End of Clarification

(616) 285-6933
BID CLARIFICATION NO. 6
FROM: Dan Korcek, Senior Project Manager; Morgan Gross, Assistant Project Manager

File details come from the government source that posted it. Updated .