NVPS Athletics (Balance) - Bid Clarification 01.pdf
PDF 269 KB Posted
- Solicitation number
- RFP NVP 260000002718 8
- Issued by
- Michigan
About this file
This document is Bid Clarification No. 1 issued by Rockford Construction, on behalf of Northview Public Schools in Grand Rapids, Michigan, for the NVPS Athletics Addition and Renovation project. The clarification addresses questions raised during the bidding process and modifies certain scope elements across multiple bid packages (BP). Key clarifications include the exclusion of soccer and lacrosse goals from BP 6 (to be furnished by owner), confirmation that the bleacher contractor (BP 13) is responsible for providing concrete slabs, assignment of turf drain tile responsibility to BP 32D, and several revised and new alternates for various packages including concrete curb anchors, netting replacement, turf specifications, and existing turf and shock pad removal. Additional clarifications address demolition requirements for South D Zone and North D Zone work, including sawcutting of track edges and removal of various surfaces and drainage systems. All bid Requests for Information (RFIs) were due by October 15, 2026, with responses to be incorporated into subsequent addenda.
The document does not contain explicit pricing information, contract award dates, funding sources, or set-aside designations. The clarification primarily serves to refine scope boundaries between trade contractors and establish responsibility for specific work items, materials, and disposal requirements across the project's multiple bid packages. No incumbency information, specific contract term details, or renewal options are referenced in this clarification document.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
601 First Street NW Grand Rapids, Michigan 49504
(616) 285-6933 www.rockford.com
BID CLARIFICATION NO. 1
TO: All Subcontractors / Suppliers
FROM: Dan Korcek, Senior Project Manager; Morgan Gross, Assistant Project Manager
DATE: October 14, 2026
RE: NVPS Athletics Addition and Renovation
This Bid Clarification No.1 is being sent to all bidders to address questions raised at bid time.
1. Bid RFIs have been generated; no responses have been received from design team as of this clarification. Responses will be provided in future bid clarifications. AS A REMINDER ALL BID
RFIS ARE DUE BY 10/15/2026 TO ALLOW TIME FOR RESPONSE AND INCORPORATION INTO
ADDENDUM.
2. Scope Clarifications
a. BP 6; Soccer and Lacrosse goals previously listed to be included shall not be included in this bid package. Soccer and Lacrosse Goals will be furnished and installed by owner.
b. BP 13 Bleacher Contractor is responsible for providing concrete slabs under proposed bleachers. Reference sheets LD1.09, L5.01, L5.02, LD5.01, LD5.02, LD5.03, LD5.04, LD 5.05.
c. BP 32D shall be responsible for Specification section 33 4615 Turf Drain Tile under their turf system.
d. Revised Alternate 3 for BP 3 Concrete to provide alternate to furnish and install curb turf anchors at 2 Bullpens. Reference LD1.07
e. BP 32C Alternate 1 provide Alternate for Netting replacement at Quad which is not currently specified to be replaced. $__________
f. BP 32D Alternate 4 Provide Alternate to provide 52 oz turf in lieu of 46 oz turf. This will also be issued in the addendum.
g. BP 31 Provide revised Alternate 5 Demo, Removal and Off Site Disposal of Existing Turf and Shock pad. $___________
h. BP 31 ALTERNATE 6 Include Complete removal of Existing Turf base, drain tiles, flat drains at band field. Dispose of offsite A $_____________ B. This material can be used as access roads $________
i. South D Zone Demo. BP 31 shall sawcut edge of track as required to prevent damage to track and allow for Demo all weather surface in D zone, asphalt surface, aggregate, trench train etc. to allow for new Aggregate Base and drainage system to be installed by
BP 32D.
j. North D Zone Demo. BP 31 shall sawcut edge of track as required to demo items as specified in D zone to allow for new storm drainage aggregate base by BP 31.
k. BP 3 Alternate 3 Disregard Alternate 3 as this is provided by BP 13.