This is Addendum No. 1 to the Invitation for Bids (IFB) issued by the Virginia Department of Behavioral Health and Developmental Services (DBHDS) for the replacement of six air handling units (AHUs) at the Northern Virginia Mental Health Institute in Falls Church, Virginia. The project scope consists of removing and replacing existing AHUs while providing temporary air handling units and power to maintain heating and cooling loads during the transition, with work phased to minimize facility downtime. The mandatory pre-bid conference was held on October 13, 2026, at 11:00 a.m. at the project site. Sealed bids are due by 2:00 p.m. on Wednesday, November 4, 2026, submitted electronically through eVA or delivered to DBHDS at 1220 Bank Street, 7th Floor, Richmond, VA 23218. Bids will be opened and read aloud at 2:00 p.m. on Thursday, November 5, 2026. The contract will be awarded on a lump sum basis, with substantial completion required within 365 calendar days following the Notice to Proceed and final completion within 30 calendar days thereafter. All bidders must possess a valid Virginia Contractor License and be registered in eVA prior to bid submission.
Addendum No. 1 corrected the project code from 720-10800-28-12 to 720-10880-28-12 and provided an updated Wage Determination issued by the Virginia Department of Labor and Industry, which bidders must use in preparing their bids. A bid guarantee (bond) of 5 percent is required, and the successful bidder must submit performance and labor/material payment bonds regardless of contract amount. Prevailing wage requirements apply to all trades identified in the wage determination schedule, with rates effective as of the October 7, 2026 publication date. The contractor is responsible for arranging TOVA training for the superintendent and at least one alternate, with sessions offered twice monthly. Permitted working hours are 7:00 a.m. to 6:00 p.m. Pre-bid questions were accepted through 5:00 p.m. on October 23, 2026, and directed to rbalog@wileywilson.com with copies to Shawn.gore@dbhds.virginia.gov. The architect of record is Wiley|Wilson, and the owner's representative is Shawn Gore, Sr., Capital Program Manager for VA-DBHDS.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DBHDS NVMHI AHU Replacement, Phase 1
DBHDS Project Code: 720-10880-28-12
Addendum #1 October 14, 2026
Bidding Addendum
Addendum No. 1 for Department of Behavioral Health and Developmental Services NVMHI AHU Replacement, Phase 1 DBHDS Project Code: 720-10880-28-12
To: All Bidding Document Holders of Record
From: Wiley|Wilson Richmond, Virginia
This Addendum consists of one (1) page, plus attachments, and forms a part of the bidding documents and modifies the Project Manual and Drawings dated September 30, 2026, as noted below.
Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject bidder to disqualification.
REVISIONS:
1. The Wage Determination included in the Project Manual is hereby deleted in its entirety and replaced with the updated Wage Determination included as an attachment to this Addendum.
Bidders shall use the updated Wage Determination in preparing their bids.
2. Revise the DBHDS Project Code throughout the Bid Documents from 720-10800-28-12 to 720-10880-28-12. All references to the previous project code shall be replaced with the corrected project code..
PRE-BID CONFERENCE NOTES:
1. A mandatory pre-bid meeting was held on October 13, 2026. The meeting minutes and Pre-bid meeting sign-in sheet from this meeting are included by attachment to this addendum.
ATTACHMENTS:
• Updated Wage Determination
• Pre-Bid Conference Meeting Minutes
• Pre-Bid Attendee’s Sign-In sheet
End of Addendum No. 1
WILEY|WILSON
Melanie Delano, P.E.
10/14/2026
COMMONWEALTH of VIRGINIA
DEPARTMENT OF LABOR AND INDUSTRY
Virginia Department of Labor and Industry Wage Determination Decision
Project Name NVMHI: Replace AHUs Phase 1
State Project Code 720-10880-28-12
DOLI Project Number DBHDS-26-0003 UPDATE
County or Independent City Falls Church (City)
Publication Date 10/07/2026
Construction Type Building
Wage Determinations Wage Fringe Asbestos Worker/Heat & Frost Insulator: Mechanical (Duct, Pipe & Mechanical System Insulation)* $40.77 $20.17 Boilermaker $38.97 $27.39 Brick Pointer/Caulker/Cleaner $19.68 Bricklayer $23.67 Carpenter (Includes Acoustical Ceiling Installation, Drywall Hanging and Form Work) $23.34 $5.04 Cement Mason/Concrete Finisher $24.69 $5.55 Drywall Finisher/Taper $25.53 $7.86 Electrician (Includes Low Voltage Wiring and Installation of Alarms and Sound and Communication Systems) $59.50 $23.06
6606 W. Broad Street, Suite 500
Richmond, Virginia 23230
PHONE (804) 371-2327
FAX (804) 371-6524
James S. Frederick
COMMISSIONER
Wage Determinations Wage Fringe Firestopper (Includes the application of materials or devices within or around penetrations and openings in all rated wall or floor assemblies, in order to prevent the passage of fire, smoke of other gases.
The application includes all components involved in creating the rated barrier at perimeter slab edges and exterior cavities, the head of gypsum board or concrete walls, joints between rated wall or floor components, sealing of penetrating items and blank openings.)** $30.21 $10.43 Floor Layer: Soft Floors $18.75 Glazier $32.41 $14.46 Ironworker: Ornamental $37.86 $25.86 Ironworker: Reinforcing $31.88 $23.78 Ironworker: Structural $37.86 $25.86 Laborer: Common or General (Includes Brick Mason Tending and Cement Mason Tending) $15.74 $3.43 Laborer: Pipelayer $16.81 $4.26 Marble Finisher $28.85 $12.55 Mason - Stone $45.65 $21.21 Operator: Backhoe/Excavator/Trackhoe $21.81 Operator: Bobcat/Skid Steer/Skid Loader $18.95 $4.03 Operator: Bulldozer $21.99 $4.98 Operator: Crane $32.52 $2.64 Operator: Forklift $21.56 $7.57 Operator: Loader $22.26 $3.57 Operator: Roller $16.25 $4.88 Painter: Brush, Roller and Spray $29.16 $11.86 Pipefitter (Includes HVAC Pipe, Unit and Temperature Controls Installations)*** $55.00 $24.46 Plumber**** $53.30 $23.71 Roofer $21.55 $7.01 Sheet Metal Worker (Includes HVAC Duct Installation)***** $53.42 $23.20 Sprinkler Fitter (Fire Sprinklers) $45.22 $27.69 Tile Finisher $23.40 Tile Setter $34.34 $14.20 Truck Driver: Dump Truck $19.22 $2.58 Waterproofer $21.75 $1.57
Additional Notes
* Asbestos Worker/Heat & Frost Insulator (Duct, Pipe & Mechanical System Insulation)* PAID HOLIDAYS: New Year's Day, Martin Luther King Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, the day after Thanksgiving and Christmas Day provided the employee works the regular workday before and after the paid holiday. *
** Firestopper ** PAID HOLIDAYS: New Year's Day, Martin Luther King Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, the day after Thanksgiving and Christmas Day provided the employee works the regular workday before and after the paid holiday. **
*** Pipefitter (Includes HVAC Pipe, Unit and Temperature Controls Installations) *** PAID HOLIDAYS: New Year's Day, Martin Luther King Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, the day after Thanksgiving and Christmas Day. ***
**** Plumber **** PAID HOLIDAYS: New Year's Day, Martin Luther King Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, the day after Thanksgiving and Christmas Day. ****
***** Sheet Metal Worker (Includes HVAC Duct Installer) ***** PAID HOLIDAYS: New Year's Day, Martin Luther King Day, Memorial Day, Independence Day, Labor Day, Veterans' Day, Thanksgiving Day, the day after Thanksgiving and Christmas Day. *****
All wage rates to be used on a contract will be set at the time the contract is awarded.
While DOLI maintains a list of wage determinations online for reference purposes, only the wage determinations made in an official Wage Determination Decision, sent by DOLI to the contracting agency, can be used to ascertain the exact rates to be paid for a specific contract.
All rates are determined by DOLI and any additional classifications may be requested through the Additional Wage Classification form available at https://doli.virginia.gov/wp-content/uploads/2025/07/Request-for-Additional-Wage-Classification-10-2022.pdf
Understand your duties as a contractor under Virginia law by referencing our Contractor Responsibilities information sheet available at https://doli.virginia.gov/prevailing-wage-law/#CR
Your employees have specific rights, which can be found on our List of Employee Rights information sheet available at https://doli.virginia.gov/prevailing-wage-law/#ERB
Any further questions should be directed to PrevailingWage@doli.virginia.gov
Virginia Department of Behavioral Health and Developmental Services Northern Virginia Mental Health Institute
Falls Church, Virginia Pre-Bid Conference Meeting Minutes
October 13, 2026
PROJECT: NVMHI AHU Replacement, Phase 1 Project Code: 720-10880-28-12 OWNER: Virginia Department of Behavioral Health and Developmental Services LOCATION: Falls Church, Virginia DATE/TIME: October 13, 2026 at 11:00 a.m.
PURPOSE: Mandatory Pre-Bid Conference for Referenced Project OWNER’S REP: Shawn Gore, Sr. Capital Program Mgr. VA-DBHDS A/E Firm: Melanie Delano, P.E., Wiley|Wilson Scott Little, P.E., Wiley|Wilson
RECORD OF ATTENDEES (refer to the attached List of Pre-Bid Conference Attendees for contractor attendance):
The electronic Invitation for Bids for the above project, including the specifications containing the information necessary for bidding, may be obtained from the office of Wiley|Wilson.
AGENDA
NOTICE OF INVITATION FOR BIDDERS
• Sealed Bids received by 2:00 p.m. on Wednesday, November 4, 2026. Bids will be received electronically through eVA or at DBHDS, 1220 Bank St, 7th Floor, Richmond, VA, 23218.
• Bids will be opened and read aloud at 2:00 p.m. on Thursday, November 5, 2026 at the same location
INSTRUCTIONS TO BIDDERS
• INSTRUCTIONS TO BIDDERS DGS-30-055 CO-7A are reviewed with an emphasis on the following items below, however, the Contractors are encouraged to read and fully understand the Instructions before submitting a bid.
• eVA Business Vendor Registration: All bidders must be registered prior to bid submission. Failure to register will result in the contractors bid being rejected for noncompliance.
• No oral explanation regarding the meaning of the drawings and specifications will be made and no oral instructions will be given prior to the award of contract. Contractors seeking clarification of the bidding documents shall use the Prebid Question Form provided in the Project Manual. Refer to paragraph 2. “Explanation to Bidders” for details. All Prebid Questions shall be e-mailed to rbalog@wileywilson.com with copies to Shawn.gore@dbhds.virginia.gov.
• Bid Guarantee (Bid Bond) of 5% is REQUIRED as stated in the IFB. Refer to the Instructions for Bidders paragraph 5. “Bid Guarantee” for provisions allowing alternative forms of bid security. Successful bidder will be required to submit Performance Bond & Standard Labor and Material Payment Bond regardless of contract amount.
• Contractors claiming an error in their bids after the bid opening may withdraw their bid from consideration only if the error can be identified as an honest mistake and provided the contractor claiming the error has submitted the required work papers in accordance with paragraph 9. “Errors in Bids” mailto:rbalog@wileywilson.com mailto:Shawn.gore@dbhds.virginia.gov
• Preparation and Submission of Bids: Bidders must have a valid Virginia Contractor License Number to qualify as a bidder.
• Bidders must utilize the Prevailing Wage Determination from Department of Labor and Industry.
PRE-BID QUESTION FORM.
• Wiley|Wilson will respond to all properly submitted pre-bid questions in the form of an Addendum and the Addendum will be electronically distributed to all documented plan holders and posted on eVA.
• If responses are in the Contract Document, the questions and responses will not be included in the Addendum.
BID FORM
• The contract shall be awarded on a lump sum basis as follows: the Total Base Bid Amount including any properly submitted and received bid modifications.
• The Time for Completion listed on the Bid Form is in calendar days for Substantial Completion from Notice to Proceed (NTP). Substantial Completion for the entire project is on or before 365 days following the NTP. Final Completion shall occur within 30 calendar days after the date of Substantial completion.
• The Bid Form shall be filled out completely, signed by the responsible parties and dated.
SUPPLEMENTAL GENERAL CONDITIONS
• Addendum will be issued
SPECIAL CONDITIONS
• View Division 01, Section 010000 of Project Manual
GENERAL REQUIREMENTS
• View Division 01 of Project Manual
GENERAL REVIEW OF SCOPE OF WORK
• The scope of work primarily consists of the removal and replacement of six existing air handling units (AHUs). Temporary air handling units and power will be provided by the contractor to maintain all heating and cooling loads during replacement, minimizing downtime to the brief periods required to transition each unit to the temporary AHU. The work will be phased so that one temporary air handling unit can serve each space while its existing air handling unit is being replaced.
QUESTION AND ANSWER PERIOD
• Formal pre-bid questions will be accepted until 5:00pm on Friday, October 23, 2026.
• Responses to questions that may impact the scope of work and /or a bid price proposal must be made in an addendum to the Bidding Documents. Responses that only involve finding information that is already in the Bidding Documents may be made verbally during this Q&A period.
• An addendum will be issued that will include these meeting minutes, any questions from the Pre-Bid Question form, and a copy of the attendee sign-in sheet.
PRE-BID QUESTIONS
• What are the working hours?
o Answer: Permitted working hours are 7:00 a.m. to 6:00 p.m., as specified in the Project Manual.
• What is the duration of the project?
o Answer: Substantial Completion shall be achieved within 365 calendar days following the Notice to Proceed (NTP), as specified in the Project Manual.
• Where should contractors park?
o Answer: Limited parking is available on-site. Additional parking is available in a nearby parking garage.
• Will there be a laydown area?
o Answer: A construction material laydown area can be provided and must be coordinated with the Facilities Manager.
• Where should bids be submitted?
o Answer: This was clarified and is specified in the project manual. Bids will be received electronically through eVA or at DBHDS, 1220 Bank St, 7th Floor, Richmond, VA, 23218.
OWNER’S REP NOTES
• Other construction projects may be ongoing concurrently with this project.
• The contractor is required to participate in a two-day TOVA training session to supervise construction personnel on-site. The superintendent and at least one alternate must complete the training. If work is performed in multiple areas simultaneously, additional personnel must complete the training to provide the required supervision. TOVA training sessions are offered twice per month, with limited availability. The Contractor shall coordinate training accordingly.
• The general contractor is responsible for escorting and supervising subcontractors as specified in the project manual or have them participate in the TOVA training themselves.
• Office space within the building will not be available for contractor use.
• Bidding contractors may schedule a follow-up site visit to inspect the remaining mechanical rooms by contacting Shawn Gore at DBHDS.
End of Pre-Bid Conference Meeting Minutes