ntb2511pinld00050ad1.pdf

PDF 227 KB Posted

Attached to
TxDOT Aviation Division- Notice to Bidders
Solicitation number
NTB2511PINLD00050
Issued by
San Augustine County, Texas

About this file

This document is Addendum No. 1 to the contract documents for a pavement rehabilitation project at Pineland Municipal Airport, issued jointly by KSA Engineers, Inc. and TxDOT Aviation Division on April 22, 2026. The project involves full-depth reclamation, stabilization, and hot-mix asphalt concrete (HMAC) overlay of Runway 17-35 and connector taxiway, with construction phased to include pavement rehabilitation and pavement marking within the runway safety area (RSA). The pre-bid meeting was held on Tuesday, April 14, 2026, at Pineland Municipal Airport, with technical questions required to be submitted in writing to James McKenzie by Friday, April 17, 2026, at 5:00 p.m. Sealed bids must be delivered to Kelle Chancey at TxDOT Aviation Division, 6230 E. Stassney Ln, 2nd Floor, Austin, TX 78744, by 2:00 p.m. on April 30, 2026, at which time bids will be publicly opened and read. The contract will be awarded within 60 calendar days from bid opening, with a contract time of 60 calendar days and liquidated damages assessed per calendar day.

The engineer's estimate of probable construction cost is $2,298,740. The project is state-funded with a HUB Goal of 0.0%; however, a Hub Subcontracting Plan (HSP) must be submitted with the bid or the bid will be deemed non-responsive. Wage rate requirements apply as shown in the contract documents. The contractor is responsible for quality control including all personnel, procedures, inspections, sampling, testing, and field process controls for construction and placement operations such as asphalt placement, compaction, and density control, separate from owner/engineer verification activities. Water is available on site via a 2-inch water line behind the southernmost hangar and a fire hydrant at the north airport entrance; contractors should contact the City of Pineland for a temporary meter. No retainage will be held on the project, with payment made up to 95 percent of the contract amount for installed work items. Contractor responsibilities include protection of existing utilities, stormwater pollution prevention (SW3P) compliance, and adherence to FAA Advisory Circular 150/5370-2G for operational safety during construction.

View the file

Other files

File Type Posted
ntb2511pinld00050.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum No. 1

To: All Plan Holders

Airport: Pineland Municipal Airport

Date: April 22, 2026

Project: Pavement Rehabilitation Project

KSA Project No.: 102793

TxDot CSJ No.: 2511PNLD

The plans, specifications, and contract documents are modified as described below. All bidders shall acknowledge receipt of this and all other addenda on the Request for Bids Form. This addendum becomes a part of the contract documents. All provisions of the original plans, specifications, and contract documents shall remain in full force and effect, except as modified by this addendum.

I. Questions/Comments:

1. Question: Does this project require DBE or HUB participation?

Answer: A HUB Subcontracting Plan must be submitted with each bid. The Hub Goal is 0%

2. Question: Is water available on site?

Answer: A 2” water line is available behind the southernmost hangar. There is a fire hydrant at the north airport entrance (723 S. Temple Ave). Contact the City of Pineland for a temporary meter.

3. Question: During the pre-bid meeting, it was discussed that QC would be the responsibility of the General Contractor. We understand this to include material testing; however, we would like clarification on whether QC is also required for construction/placement activities (e.g., asphalt placement, density, and field quality control operations), or if those items fall solely under testing requirements. Please advise on the intended scope of QC responsibilities for this project.

Answer: Quality Control (QC) is the responsibility of the Contractor and includes more than material testing alone. Contractor QC shall include all personnel, procedures, inspections, sampling/testing, and field/process controls required to ensure the work conforms to the Contract

Documents.

This includes, as applicable, QC for construction and placement operations, including asphalt placement, compaction/density control, and related field quality control operations, in addition to material testing.

Owner/Engineer verification and acceptance activities are separate from Contractor QC and will be performed in accordance with the Contract Documents.

II. Bid Form Changes:

1. None.

III. Plan Sheet Changes:

None.

IV. Specification Revisions

1. None.

Addendum No. 1

April 22, 2026

V. Attachments

1. Pre-bid meeting agenda and sign-in sheet.

Addendum No. 1 Issued By:

4/22/2026

TBPE Firm Registration No. F-1356

KSA

James A. McKenzie, P.E.

Senior Project Manager

Pre-Bid Meeting

Airport: Pineland Municipal Airport

Date: Tuesday, April 14, 2026

Project: Pavement Rehabilitation Project

Organizer: KSA Engineers, Inc.

KSA Project No.: 102793

Client Project No.: 2511PNLD

I. Sign In Sheet

II. Introductions and Roles

A.

B. Earl Spurlock, TxDOT Aviation

C. Bob Thurber, KSA

D. James McKenzie, KSA

E.

F.

III. Bidding Procedures

A. See Notice to Bidders and Instructions to Bidders section in Contract Documents for bidding information.

B. All bidders are encouraged to review all contract documents including TxDOT General Provisions, Special

Provisions, and Project Specifications.

C. Technical questions/comments should be submitted to James McKenzie, (jmckenzie@ksaeng.com or 214-

668-1048 by Friday, April 17, 2026 at 5:00 p.m. Questions must be in writing and received prior to date mentioned.

D. For bid document questions or other information visit the TxDOT Aviation website or call TxDOT, Kelle

Chancey at 512-633-0253.

E. Sealed bids for the construction of airport improvements at Pineland Municipal Airport are to be delivered to Kelle Chancey, TxDOT Aviation Division, 6230 E. Stassney Ln, 2nd Floor, Austin, TX 78744. Bids will be received until 2:00 p.m., April 30, 2026, then publicly opened and read. Any bid received after closing time will be returned unopened.

F. Bid Proposal

1. Bidders must utilize the bid proposal form provided on TxDOT’s website.

2. Bidders must provide pricing for all items in the Base Bid. The contract award will be based on the lowest qualified bid.

G. Each bid should be furnished with a Bidder Qualifications as stated in the Contract Documents.

H. Bidder shall reference the Aviation Division General Construction Contract Provisions.

1. http://txdot.gov/inside-txdot/division/aviation/general-provisions.html

I. Contract will be awarded within __60__ calendar days from bid opening.

Pre-Bid Meeting

April 14th, 2026

J. State funded project

1. The HUB Goal 0.0%. Questions regarding HUB Goal and Good Faith Efforts should be directed to

TxDOT, Kelle Chancey at 512-633-0253.

2. Hub subcontracting plan (HSP) must be submitted with the bid or it will be deemed non-responsive.

3. Wage rate requirements will be required as shown in the Contract Documents.

IV. Scope of Work

A. Pavement Rehabilitation – Full-depth reclamation, stabilization, and HMAC overlay of Runway 17-35 and connector taxiway.

B. Engineer’s estimate of probably construction cost: $2,298,740

V. Site Access / Staging Areas

A. Site access will be from Airport Drive, as shown on plans.

B. Staging Area is north of the terminal apron.

VI. Construction Safety and Phasing Plan

A. Contractor will be required to comply with FAA Advisory Circular 150/5370-2G, Operational Safety on Airports

During Construction.

1. Phase 1: Pavement Rehabilitation inside RSA

2. Phase 2: Pavement Marking inside RSA

B. Contractor will be required to comply with the construction safety phasing plan included in the bid documents.

C. Safety Plan Compliance Document will be required by the Contractor.

VII. Other Information

A. Contract Time

1. 60 calendar days.

2. Liquidated Damages assessed per calendar day.

B. Materials Acceptance by Owner / Materials Quality Control by Contractor

C. Protection of any existing utilities in the project area is the responsibility of the Contractor. Engineer has endeavored to show all known utilities within the Contract documents, but this shall not relieve the

Contractor from full responsibility in anticipating all underground obstruction, whether or not shown on the plans; Contractor should call for utility locates and verify locations of all utilities prior to starting construction.

D. SW3P – Contractor Responsibility

E. No retainage on project. Payment will be made up to 95% of the contract amount of installed work items if over or under the current contract before final acceptance.

F. Any addenda issued will be available on TxDOT’s website.

G. Site visit.