ntb2508haskl00031ad1.pdf
PDF 5 MB Posted
- Attached to
- TxDOT Aviation Division - Addenda
- Solicitation number
- NTB2508HASKL00031
- Issued by
- Hidalgo County, Texas
About this file
This addendum document issued by Centurion Planning and Design on June 4, 2026, provides critical modifications to the sealed bid construction contract for Haskell Municipal Airport's pavement rehabilitation project administered by the Texas Department of Transportation (TxDOT) Aviation Division. The project scope includes demolition of existing pavements, runway rehabilitation with new asphalt placement, crack sealing and surface treatment for taxiway and apron areas, and pavement markings for all rehabilitated areas. Key work items include removal of asphalt pavement, proof rolling, flexible pavement structure repair at 6 inches depth, prime coat application, asphalt surface course placement, joint sealant application, thermoplastic coal tar emulsion surface treatment, and reflective and non-reflective pavement markings in various colors. The addendum consolidates responses to contractor questions submitted during the advertisement period, incorporates modifications based on the pre-bid meeting held on May 27, 2026, and includes revised plan sheets addressing clarifications regarding pavement depth specifications, base work requirements, and joint sealant quantities. Sealed bids are due by 2:00 PM on June 11, 2026, and will be publicly opened and read immediately thereafter at the TxDOT Aviation Division office in Austin, Texas. The contract duration is 75 calendar days under the base bid with liquidated damages of $1,000 per calendar day.
The project is state-funded with an engineers' estimate of probable cost of $1,058,811.00 for the base bid. Bidders must submit sealed bids on the TxDOT-formatted bid form with all certifications, including a bid bond equivalent to two percent of the total bid price, bidder qualifications, and an addendum acknowledgement. All bid documents must be signed with ink or digital signature. A mandatory Historically Underutilized Business (HUB) Subcontracting Plan is required despite a 0% HUB goal, and successful bidders must provide performance and payment bonds in the full contract amount. The prime contractor is required to perform 30% of the work, and Buy American compliance is mandatory. The contractor bears responsibility for establishing a quality control plan with required testing laboratory support, while the engineer manages quality assurance. Safety requirements include continuous monitoring of CTAF frequency 122.9 MHz during airfield operations, mandatory flagging and identification of all construction vehicles, and runway closures limited to areas where construction occurs within 60 feet of the runway centerline. Contract documents must be electronically submitted through the eGrants system, including pay requests, change orders, certified payroll, and DBE/HUB reports.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ntb2508haskl00031.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
19 W. Beauregard Avenue
San Angelo, TX 76903
(325) 757-1001 centurionplan.design
ADDENDUM NO. 1
To: All Plan Holders
From: James W. Davidson, P.E., Centurion Planning and Design, LLC.
CC: Steve Harp, Eli Lopez
Date: June 4, 2026
Subject: Haskell Municipal Airport – Airport Pavement Rehab Bidding; CSJ 2508HASKL, Addendum No. 1
Attention of all Prospective Proposers/Plan Holders is directed to the following modifications to referenced Plans and Technical Specifications. This Addendum becomes a part of Contract
Documents and modifies original Contract Documents dated June 2026. Please find attached the required addendum for the above-mentioned project. Below are the listed changes made.
1. Attachment A contains the pre-bid meeting agenda and minutes
2. Attachment B contains the sign-in sheet from the pre-bid meeting.
3. Attachment C contains the Questions and Answers Memo addressing questions submitted during project advertisement.
4. Attachment D contains revised plan set sheets based on Questions submitted during project advertisement and the pre-bid meeting
5. The revised bid form is included as a separate fillable PDF to be downloaded in addition to this addendum packet.
Attachments:
Attachment A – Pre-Bid Meeting Agenda and Minutes
Attachment B – Pre-Bid Meeting Sign-In Sheet
Attachment C – Question and Answer Sheet
Attachment D – Revised Plan Set Sheets
James W. Davidson, P.E.
6/4/2026
Attachment A
Meeting Agenda and Notes
Meeting Minutes
Meeting Topic: Haskell Municipal Airport – Airport Pavement Rehab Pre Bid; CSJ 2508HASKL
Date/Time: 5/27/2026, 1:30 PM
Location: Haskell City Hall
Attendees/ Invitees
Name Organization Attended Name Organization Attended
Monty Brown Centurion X Eli Lopez TxDOT X
Dan Neelley Centurion X Clayton Zuber Allen Keller X
Richard Smith Centurion X
Steve Harp TxDOT X
Meeting Agenda
1. INTRODUCTION
A. City of Haskell/Haskell Municipal Airport – Matt Ussrey, Director of Public Works
B. Centurion Planning & Design (Engineer) – Dan Neelley, P.E., Richard Smith, E.I.T.
2. GENERAL PROJECT DESCRIPTION AND OVERVIEW
A. Project Description
i. Base bid includes: demolition of existing pavements with incidental base work, and new pavement placement along Runway. Application of crack seal and surface treatment for taxiway and apron area.
Pavement markings for all areas being rehabilitated.
3. BIDDING PROCESS:
A. Bid Requirements
i. Sealed bids for the construction of airport improvements at Haskell Municipal Airport need to be addressed and delivered to Kelle Chancey, TxDOT Aviation Division, 6230 E. Stassney Lane, 2nd Floor, Austin, Texas
78744. Bids will be received until 2:00 P.M., June 11, 2026, then publicly opened and read. Any bid received after closing time will be returned unopened.
ii. Bidders must submit the completed bid on the formatted bid form furnished by TxDOT, with all blank spaces in the TxDOT bid form correctly typed in for each item for which a quantity is given to be considered complete.
iii. Project is State funded, so for a bid to be considered complete, it must include all necessary bid certifications. This includes: bid form, bid bond, bidder qualifications, addendum acknowledgement.
iv. All bid documents (including Bid Form) should be signed with ink or an official digital signature.
v. Contractor Questions can be submitted until 2:00 P.M., June 4, 2026. Any questions received after this time will not be answered.
B. Addenda:
i. Bid addendum will be issued after the question deadline
ii. Addendum No. 1 will include the following
1. Prebid Sign-in sheet.
2. Prebid Agenda with minutes.
3. Issues or clarification from Prebid Meeting.
4. Question and answer sheet of all questions received during bidding.
5. Plan sheets, specifications, or bid documents that require revision.
4. PROJECT DISCUSSION
A. Specific Work Items Discussion
i. Item 1 Base Bid – Mobilization and Erosion/Sedimentation Control Measures
1. Mobilization
ii. Item 2 Base Bid – Runway Pavement Rehabilitation
1. TxDOT Item 105 Remove Asphalt Pavement
2. TxDOT Item 216 Proof Rolling
3. TxDOT Item 351 Flexible Pavement Structure Repair
4. TxDOT Item 310 Prime Coat
5. TxDOT Item 341 Asphalt Mix Pavement Surface Course
6. FAA Item T-901 Seeding
7. FAA Item P-152 Excavation and Embankment
8. Current width of Runway(50’), FAA is 60’ Minimum (Outside of Scope)
iii. Item 3 Base Bid – Apron and Taxiway Pavement Rehabilitation
1. FAA item P-101 Prepare Surface
2. FAA item P-101 Clean, Prepare Joints for Ceiling
3. FAA item P-605 Joint Sealants for Pavements
4. FAA item P-629 Thermoplastic Coal Tar Surface Treatment
iv. Item 4 Base Bid – Airfield Electrical Items
1. FAA item P-620 Reflective Pavement Markings – white, yellow
2. FAA item P-620 Non-Reflective Pavement Markings – black, green
3. FAA item P-620 Temporary Pavement Markings - white
B. Project General Provisions
i. Contract Time – 75 calendar days under base bid.
ii. Liquidated Damages – $1,000 per calendar day.
Additional Items of Discussion
• SP-004 requires prime to perform 30% of the work.
• Buy American required compliance (Section 1 of General Provisions).
• Contractor is responsible for quality control plan; testing lab required.
• Centurion is responsible for quality assurance plan.
• 0% HUB goal but the HSP (HUB Subcontracting Plan) is required if utilizing any HUBs on the contract.
• Subcontract plan is due at time of bids and contractor needs to give subcontractors plenty of time to respond.
• Confusion on different details in plans with full depth repair showing 6” but Item 351 is for 2”.
Resolution - Items and plan sheets to be updated with addendum 1.
Critical Dates
Addendum to TxDOT June 3, 2026
TxDOT to Post Publications/Addendum June 4, 2026
Attachment B
Attachment C
19 W. Beauregard Avenue
San Angelo, TX 76903
(325) 757-1001 centurionplan.design
QUESTIONS AND ANSWERS
To: All Plan Holders
From: James W. Davidson, P.E., Centurion Planning and Design, LLC.
CC: Steve Harp, Eli Lopez
Date: June 4, 2026
Subject: Haskell Municipal Airport – Airport Pavement Rehab Bidding; CSJ 2508HASKL, Addendum No. 1
Attention of all Prospective Proposers/Plan Holders is directed to the following questions that were brought to the Engineers attention during project advertisement. Below each question is the provided answer in an attempt to provide clarity to the project. Please find the list of questions and answers below.
Questions
Q1: Per Sheet C-001, the Summary of Quantities has TxDOT item 351 “Flexible Pavement Structure
Repair” listed with a depth of 2”, but sheet C-009 detail 04 shows full depth repair to be 6”.
Is the repair to be 2” or 6”?
A1: Bid form and Plan Sheet C-001 have been revised for a depth of 6”. Please see revised bid form and sheet.
Q2: Per Sheet C-010 detail 01, the cross section shows “Reworked Existing Base (3”-4”)”. Is this to be the entire length of runway, and if so there is currently no pay item for 3”-4” of base work
A2: Reworking of base is only to occur in areas where repair is needed after proof rolling, Plan
Sheet C-010 detail 01 has been revised accordingly. Please see revised sheet.
Q3: Per Sheet C-006, Demolition Note 6 states that “Removal of structures found in an excavation area shall be considered unclassified excavation and shall be paid for with the corresponding unit price as noted in FAA Item P-152.” Can you confirm whether there are any known existing structures within the excavation limits that bidders should account for, or is this note intended as a general provision?
A3: The note is intended as a general provision, and no known existing structures are to be impacted.
Q4: Per Sheet C-001, the Summary of Quantities shows 1,114 LF for item P-605. Will you please verify that the quantity is correct?
A4: The quantity shown on C-001 is the correct estimated amount of joint sealant.
Attachment D
GENERAL NOTES
ADDITIONAL NOTES ON PLAN SHEETS
C -0
HA
SK
L
CI
TY
O
F
HA
SK
EL
L
HA
SK
EL
L M
U N
IC
IP
AL
A
IR
PO
RT
HA
SK
EL
L, T
EX
AS
FI
N
AL
D
ES
IG
N S
U
BM
IT
TA
L
MARK REVISION DATE
LATEST REVISION:
DRAWN BY:
DESIGNED BY:
JOB NO.
06/03/2026
BS
JWD
15F2501D
Sheet No.
Seal:
Centurion Planning and Design 19 W. Beauregard Ave San Angelo, TX 76903
Phone No. (325) 757-1001 Firm No. 19840
Z:
\S
H
AR
ED
\0
3-
PR
O
JE
C
TS
\H
AS
KE
LL
M U
N
IC
IP
AL
A
IR
PO
R
T (1
5F )\1
5F
D
PA
VE
M
EN
T
R
EH
AB
IL
IT
AT
IO
N
\0
- D
ES
IG
N
\0
- C
AD
\0
SH
EE
TS
\0
F-
N O
TE
S.
D W
G
GE
N
ER
AL
N O
TE
S
AN
D
SU
M
M
AR
Y O
F Q
U
AN
TI
TI
ES
SAFETY NOTES:
1. WHILE THE AIRPORT IS OPEN, NO VEHICLE OR EQUIPMENT SHALL
MOVE UPON APRONS, TAXIWAYS AND/OR RUNWAYS WITHOUT
FIRST NOTIFYING THE AIRPORT. NOTIFICATION SHALL BE
COORDINATED THROUGH THE AIRPORT DIRECTOR, MATT
USSERY (940-224-4361).
2. ALL VEHICLES OPERATING ON THE AIRFIELD MUST BE
MONITORING CTAF FREQUENCY 122.9 MHz AND BE IDENTIFIED BY
FLAG AND/OR FLASHING AMBER LIGHT.
3. FLAGMEN WILL BE REQUIRED TO DIRECT THE CONTRACTOR'S
VEHICLES AND EQUIPMENT WHICH ARE OPERATING IN THE AREA
OF MOVING AIRCRAFT. FLAGMEN TO MONITOR CTAF, FREQUENCY
122.9 MHz. AIRCRAFT ALWAYS HAVE THE RIGHT-OF-WAY.
4. CONSTRUCTION PERSONNEL AND EQUIPMENT WILL NOT BE
ALLOWED WITHIN THE OPERATIONS AREA OF THE AIRPORT UNTIL
THE AREA HAS BEEN CLOSED TO AIRCRAFT AND NOTAMS ISSUED.
5. REFERENCE AC 150/5370-2G, "OPERATIONAL SAFETY ON
AIRPORTS DURING CONSTRUCTION".
6. GENERAL SAFETY REQUIREMENTS: DURING PERFORMANCE OF
THIS CONTRACT, THE AIRPORT RUNWAYS, TAXIWAYS, AND
AIRCRAFT PARKING APRONS SHALL REMAIN IN USE BY AIRCRAFT
TO THE MAXIMUM EXTENT POSSIBLE. AIRCRAFT USE OF AREAS
NEAR THE CONTRACTOR'S WORK WILL BE CONTROLLED TO
MINIMIZE DISTURBANCE TO THE CONTRACTOR'S OPERATION.
THE CONTRACTOR SHALL NOT ALLOW HIS/HER EMPLOYEES,
SUBCONTRACTOR'S SUPPLIERS, OR ANY PERSON OVER WHOM
HE/SHE HAS CONTROL TO ENTER OR REMAIN IN ANY PART OF
THE AIRPORT WHICH WOULD BE HAZARDOUS TO PERSONS OR
TO AIRCRAFT OPERATIONS. WHENEVER AIRCRAFT OPERATIONS
REQUIRE, THE ENGINEER MAY ORDER THE CONTRACTOR TO
SUSPEND OPERATIONS, MOVE PLANT, PERSONNEL, EQUIPMENT,
AND MATERIALS TO A SAFE LOCATION AND STAND BY UNTIL
AIRCRAFT USE IS COMPLETED.
7. VEHICLE IDENTIFICATION AND PARKING: (A) CONTRACTOR
VEHICLES AND EQUIPMENT SHALL BE IDENTIFIED BY FLAGS AND
AMBER FLASHING LIGHTS. (B) EMPLOYEE PARKING SHALL BE IN
THE CONTRACTOR'S STAGING AND STORAGE AREA.
8. THE CONTRACTOR SHALL NOT, FOR ANY REASON ENTER ACTIVE
AIRFIELD AREAS WITHOUT EXPLICIT APPROVAL BY AIRPORT
MANAGEMENT. THE CONTRACTOR SHALL LIMIT OPERATIONS TO
LIMITS OF CONSTRUCTION ACTIVITIES.
9. RUNWAY 18/36 MUST BE CLOSED ANYTIME CONSTRUCTION
ACTIVITY IS OCCURRING WITHIN 60' ON EITHER SIDE OF THE
RUNWAY CENTERLINE. THE NUMBER AND THE DURATION OF
RUNWAY CLOSINGS SHALL BE MINIMIZED. IN ORDER TO MINIMIZE
RUNWAY CLOSURES, MULTIPLE CONSTRUCTION ACTIVITIES NEAR
THE RUNWAY SHOULD OCCUR SIMULTANEOUSLY WHEN IT IS
CLOSED.
10. THE CONTRACTOR SHALL EQUIP ALL CONSTRUCTION VEHICLES
AND EQUIPMENT WITH A FLAG ON A STAFF ATTACHED TO THE
VEHICLE AND READILY VISIBLE OR AMBER FLASHING LIGHT
DURING DAY HOURS AND AMBER FLASHING LIGHT DURING NIGHT
HOURS. THE FLAG SHALL BE NOT LESS THAN 3 FEET SQUARE
CONSISTING OF A CHECKERED PATTERN OF INTERNATIONAL
ORANGE AND WHITE SQUARES NOT LESS THAN ONE FOOT ON
EACH SIDE AND DISPLAYED IN FULL VIEW ABOVE THE VEHICLE.
11. ALL EQUIPMENT AND MATERIALS SHALL BE STORED IN THE
CONTRACTORS STAGING AREA WHEN NOT IN USE. EQUIPMENT
AND MATERIALS SHALL NOT ENCROACH UPON ACTIVE
OPERATIONAL AREAS. MINIMUM CLEARANCES SHALL BE
MAINTAINED ON RUNWAYS IN ACCORDANCE WITH PART 77 OF
THE FEDERAL AVIATION REGULATIONS.
12. ALL EXCAVATIONS, OPEN TRENCHES AND STOCKPILED MATERIAL
AT THE CONSTRUCTION SITE SHALL BE PROMINENTLY MARKED
WITH FLAGS AND LIGHT UNITS ACCEPTABLE TO THE ENGINEER
DURING HOURS OF RESTRICTED VISIBILITY OR DARKNESS.
13. WASTE AND LOOSE MATERIAL CAPABLE OF CAUSING DAMAGE TO
AIRPLANES MUST NOT BE PLACED ON ACTIVE AIRPLANE
MOVEMENT AREAS. MATERIAL TRACKED ON THESE AREAS MUST
BE REMOVED CONTINUOUSLY BY A SWEEPER OR VACUUM
TRUCK SUPPLIED BY THE CONTRACTOR DURING THE PROJECT.
NO DIRECT PAY IN BID PROPOSAL.
CONSTRUCTION NOTES:
1. THE CONTRACTOR SHALL SUPPLY HIS OWN FENCING, GATES AND
LOCK FOR STAGING AREA, AS NECESSARY FOR SECURITY OF
EQUIPMENT AND DELINEATION OF STAGING AREA. THE AIRPORT
IS NOT RESPONSIBLE FOR THE EQUIPMENT OR ANY OTHER OF
THE CONTRACTOR AND/OR EMPLOYEE'S ITEMS.
2. EACH CONSTRUCTION AREA SHALL BE SHAPED TO ALLOW
DRAINAGE OF SURFACE WATER DURING EACH WORK
OPERATION. THE CONTRACTOR SHALL PUMP SURFACE WATER
IMMEDIATELY FROM EACH CONSTRUCTION AREA AFTER EACH
RAIN.
3. THE MAJORITY OF THE WORK WILL BE ACCOMPLISHED DURING
NORMAL DAYTIME WORKING HOURS, OR AS APPROVED BY THE
ENGINEER.
4. STOCKPILE LOCATION SHALL BE COORDINATED WITH THE
ENGINEER. STOCKPILE SHALL NOT CREATE ANY PONDING OF
WATER OR ALTER DRAINAGE PATTERNS OF THE AIRPORT
PROPERTY EXCEPT AS SHOWN IN THESE PLANS.
5. ALL WASTE OR SPOIL MATERIAL SHALL BE DISPOSED OF OFF THE
AIRPORT PROPERTY BY THE CONTRACTOR, UNLESS OTHERWISE
NOTED OR DIRECTED BY THE ENGINEER.
6. CONTRACTOR SHALL PROVIDE AND INSTALL ALL MATERIALS AND
DRAINAGE STRUCTURES TO CONSTRUCT A STABILIZED
CONSTRUCTION EXIT AT EACH POINT WHERE CONSTRUCTION
CREWS OR EQUIPMENT WILL EXIT AIRPORT PROPERTY.
7. THE CONTRACTOR SHALL BE RESPONSIBLE FOR REPAIR OF ANY
DAMAGE TO EXISTING PAVEMENTS, UNDERGROUND CABLES,
PIPELINES, ETC. ENCOUNTERED DURING CONSTRUCTION. ALL
REPAIRS MUST BE MADE IN COMPLIANCE WITH LOCAL
REGULATIONS, THE ENGINEER, AND THE FAA REQUIREMENTS.
8. CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING AND
ACQUIRING AN ACCEPTABLE WATER SOURCE AS REQUIRED FOR
CONSTRUCTION. NO DIRECT PAY PROVIDED IN BID PROPOSAL.
9. THE CONTRACTOR MUST PROVIDE A MINIMUM OF 72 HOURS
NOTICE TO THE RESIDENT PROJECT REPRESENTATIVE (RPR),
PRIOR TO BEGINNING CONSTRUCTION ACTIVITIES. A NOTICE TO
AIRMEN (NOTAM) SHALL BE ISSUED. THE CONTRACTOR SHALL
NOTIFY THE RPR WHO WILL THEN NOTIFY THE ENGINEER AND
THE AIRPORT.
10. CONTRACTOR SHALL CLEAN UP ALL MUD, DIRT AND DEBRIS
DROPPED ON EXISTING PAVEMENT AS A RESULT OF
CONSTRUCTION ACTIVITIES ON A DAILY BASIS. ALL CLEANUP
MUST BE COMPLETED PRIOR TO FINAL ACCEPTANCE OF THE
PROJECT.
11. CONTRACTOR SHALL PROVIDE RESTROOM FACILITIES FOR HIS
EMPLOYEES.
ACCESS ROUTE NOTES:
1. DAMAGE TO EXISTING PAVEMENTS WHICH IS CAUSED BY THE
CONTRACTOR'S OPERATIONS SHALL BE REPAIRED TO ORIGINAL
OR BETTER CONDITION AT NO EXPENSE TO THE OWNER.
2. ACCESS ROUTES FOR EACH CONSTRUCTION PHASE SHALL BE
COORDINATED WITH THE ENGINEER. ROUTES SHOWN ARE
PRELIMINARY ONLY, AND SUBJECT TO APPROVAL AND
ADJUSTMENT BY THE ENGINEER. THE CONTRACTOR SHALL BE
RESPONSIBLE FOR MAINTAINING ALL ACCESS ROUTES (PAVED &
UNPAVED). SEE PHASING PLANS FOR ADDITIONAL ACCESS
ROUTE INFORMATION.
3. THE PAVEMENT ON THE ACCESS ROUTES MAY NOT SUPPORT
CONSTRUCTION TRAFFIC. THE CONTRACTOR SHALL LIMIT LOADS
AS NECESSARY TO PREVENT DAMAGE. IF PAVEMENTS TO REMAIN
ARE DAMAGED OR REMOVED DURING CONSTRUCTION, THE
CONTRACTOR SHALL REPLACE AND/OR REPAIR THE PAVEMENT
TO ORIGINAL CONDITION OR BETTER, AT THE CONTRACTOR'S
EXPENSE, AND IN ACCORDANCE WITH THE CITY OF HASKELL'S
SPECIFICATIONS.
4. CONTRACTOR SHALL SWEEP PAVEMENTS FREQUENTLY TO KEEP
FREE OF DEBRIS.
5. CONTRACTOR SHALL SPRINKLE ALL EXCAVATION, EMBANKMENT,
BORROW AREAS AND ACCESS ROUTES WITH WATER AS
REQUIRED TO MINIMIZE DUST ON THE RUNWAY, TAXIWAYS AND
OTHER AIRCRAFT OPERATIONS AREAS AS DIRECTED BY THE
ENGINEER OR HIS REPRESENTATIVE. CONTRACTOR SHALL BE
RESPONSIBLE FOR DUST CONTROL OVER THE DURATION OF THE
PROJECT.
6. CONTRACTOR SHALL LOCATE, MARK, AND PROTECT EXISTING
ELECTRICAL CABLES, TELEPHONE CABLES, WATER UTILITIES,
AND WASTE WATER UTILITIES. ANY DAMAGE TO THESE
FACILITIES SHALL BE REPAIRED AT NO COST TO THE OWNER.
EXISTING UTILITY & PIPELINE NOTES:
1. TYPE AND LOCATION OF UNDERGROUND UTILITIES IS NOT
GUARANTEED TO BE ACCURATE OR ALL INCLUSIVE. THE
CONTRACTOR IS RESPONSIBLE FOR MAKING HIS OWN
DETERMINATIONS AS TO TYPE AND LOCATION OF UTILITIES
PRIOR TO CONSTRUCTION. CONTRACTOR SHALL PROTECT
EXISTING UTILITIES DURING CONSTRUCTION AND SHALL REPAIR
ALL DAMAGES TO SAID UTILITIES AT NO EXPENSE TO THE
OWNER.
2. CONTRACTOR SHALL VERIFY LOCATION OF UNDERGROUND
UTILITY LINES AND SHALL NOTIFY THE FOLLOWING AGENCY 48
HOURS PRIOR TO EXCAVATING NEAR EXISTING FACILITIES:
NATIONAL ONE-CALL 8-1-1
ENVIRONMENTAL NOTES:
1. IN THE EVENT THAT UNANTICIPATED ARCHEOLOGICAL DEPOSITS
ARE ENCOUNTERED DURING CONSTRUCTION, WORK IN THE
IMMEDIATE AREA WILL CEASE AND THE ENGINEER WILL CONTACT
PROFESSIONAL ARCHEOLOGISTS TO INITIATE POST-REVIEW
DISCOVERY PROCEDURES UNDER THE PROVISIONS OF 36 CRF
800.13.
2. IN THE EVENT THAT UNANTICIPATED HAZARDOUS MATERIALS
ARE ENCOUNTERED DURING CONSTRUCTION, WORK IN THE
IMMEDIATE AREA WILL CEASE AND THE ENGINEER WILL BE
NOTIFIED.
3. STOCKPILES AND STAGING AREAS WILL NOT BE PLACED WITHIN
ANY WATER OF THE UNITED STATES, INCLUDING WETLANDS.
4. HAZARDOUS WASTE: ALL SPILLS MUST BE REPORTED
IMMEDIATELY TO THE PROJECT MANAGER.
SUMMARY OF QUANTITIES
Item 1: Mobilization, Temporary Access and Erosion/Sedimentation Control Measures
Item Spec. Estimated Actual No. No. Description Units Quantity Quantity
1.01 C-105 Mobilization and SW3P Permitting LS 1
1.02 C-100 Contractor Quality Control Program LS 1
1.03 … Barricades and Markings for Pavement Closures LS 1
1.04 C-102 Temporary Sediment Control Fence LF 858
1.05 … Construction Entrance LS 1
Item 2: Runway Pavement Rehabilitation Item Spec. Estimated Actual No. No. Description Units Quantity Quantity
2.01 TxDOT 105-7001 Remove Asphalt Pavement (0" - 0.5") SY 19,735
2.02 TxDOT 105-7001 Remove Asphalt Pavement (2") SY 313
2.03 TxDOT 216 Proof Rolling HR 8
2.04 TxDOT 351 Flexible Pavement Structure Repair (6") SY 1,974
2.05 TxDOT 310 Prime Coat (AE-P) (0.2 GAL/1 SY) GAL 4,010
2.06 TxDOT 341-D
"Asphalt Mix Pavement Surface Course - TxDOT Item 341, Type DG-D (2"" TYP.)" TON 2,219
2.07 T-901 Seeding AC 2
2.08 P-152 Excavation and Embankment CY 20
Item 3: Apron and Taxiway Pavement Rehabilitation Item Spec. Estimated Actual No. No. Description Units Quantity Quantity
3.01 P-101 Prepare Surface; Remove Sealant, Markings SY 4,020
3.02 P-101 Clean, Prepare Joints for Sealing LF 1,114
3.03 P-605 Joint Sealants for Pavements LF 1,114
3.04 P-629 Thermoplastic Coal Tar Emulsion Surface Treatment (Sand Slurry Seal) SY 4,020
Item 4: Runway, Taxiway, and Apron Pavement Markings Item Spec. Estimated Actual No. No. Description Units Quantity Quantity
4.01 P-620 Reflective Pavement Markings - White SF 16,940
4.02 P-620 Reflective Pavement Markings - Yellow SF 2,670
4.03 P-620 Non-Reflective Pavement Markings - Black SF 6,990
4.04 P-621 Non-Reflective Pavement Markings - Green SF 757
4.05 P-620 Temporary Pavement Markings - White SF 16,940
1 ADDENDUM 1 6/4/26
6/3/2026
SCALE:01
PROPOSED RUNWAY CROSS
SECTION
N/A
NOTES:
1. SURFACE TREATMENT SHALL BE THERMOPLASTIC COAL TAR EMULSION (SAND SLURRY SEAL)
SURFACE TREATMENT MEETING FAA ITEM P-629 SPECIFICATIONS.
2. PREPARATION FOR P-629 SURFACE TREATMENT MUST MEET THE MANUFACTURER’S SPECIFICATIONS AND PROJECT TECHNICAL SPECIFICATIONS. CONTRACTOR SHALL PROVIDE WRITTEN CONFIRMATION
OF SURFACE READINESS BEFORE RESEALING BEGINS.
3. CONTRACTOR SHALL VERIFY ALL SURFACE SEALANT REMOVAL AND CLEANING METHODS WITH THE ENGINEER BEFORE STARTING WORK. SAMPLE TEST SECTIONS MAY BE REQUIRED FOR APPROVAL.
SCALE:02
PROPOSED SURFACE TREATMENT
DETAIL
N/A
EXISTING
HOT MIX ASPHALTIC CONCRETE (HMAC)
PROPOSED P-629 THERMOPLASTIC COAL TAR
EMULSION (SAND SLURRY SEAL) COAT1% TO 2% CROSS SLOPE
3% TO 5%
10'
60'
1.5% TO 5%
NOTES:
1. HMAC SHALL BE TXDOT ITEM 341, TYPE DG-D, COMPACTED TO BETWEEN 92% AND 97% OF THE PAVEMENT'S RICE SPECIFIC GRAVITY. HMAC SHALL HAVE A PERFORMANCE GRADE OF PG 64-22.
2. ANY REPAIRS NECESSARY TO THE BASE COURSE, AFTER REMOVAL OF THE EXISTING SURFACE
COURSE, SHALL BE PERFORMED THROUGH ITEM TXDOT 351 - FLEXIBLE PAVEMENT STRUCTURE
REPAIR AND SHALL UTILIZE COMPACTED BASE / CRUSHED LIMESTONE PER TxDOT ITEM 247, TYPE A, GRADE 1-2 COMPACTED TO AT LEAST 95% STANDARD PROCTOR DENSITY AT A MOISTURE CONTENT
WITHIN ±2% POINTS OF THE OPTIMUM MOISTURE CONTENT.
3. ENSURE LONGITUDINAL RUNWAY GRADE DOES NOT EXCEED ±2%. ENSURE THE GROUND AT THE END
OF THE RUNWAY HAS A SLOPE OF 0% TO 3% DOWNWARDS.
4. CONSTRUCT A 1.5" ± 0.5" DROP BETWEEN PAVED AND UNPAVED SURFACES.
TxDOT 310: PRIME COAT (AE-P) (0.2 GAL/SY)
PROOF ROLL EXISTING BASE
EXISTING SUBGRADE
25'
1.5"
TxDOT 341-D: ASPHALT SURFACE COURSE (2")
C -0
HA
SK
L
CI
TY
O
F
HA
SK
EL
L
HA
SK
EL
L M
U N
IC
IP
AL
A
IR
PO
RT
HA
SK
EL
L, T
EX
AS
FI
N
AL
D
ES
IG
N S
U
BM
IT
TA
L
MARK REVISION DATE
LATEST REVISION:
DRAWN BY:
DESIGNED BY:
JOB NO.
06/03/2026
BS
JWD
15F2501D
Sheet No.
Seal:
Centurion Planning and Design 19 W. Beauregard Ave San Angelo, TX 76903
Phone No. (325) 757-1001 Firm No. 19840
Z:
\S
H
AR
ED
\0
3-
PR
O
JE
C
TS
\H
AS
KE
LL
M U
N
IC
IP
AL
A
IR
PO
R
T (1
5F )\1
5F
D
PA
VE
M
EN
T
R
EH
AB
IL
IT
AT
IO
N
\0
- D
ES
IG
N
\0
- C
AD
\0
SH
EE
TS
\0
F-
R U
N W
AY
A
N D
T
AX
IW
AY
.D W
G
PA
VI
N G
DE
TA
IL
S
120' RSA
2"
8"
3-4"
0.5"
3-4"
2"
8"
2"
1% TO 2% CROSS SLOPE
LESS THAN 1.5% SLOPE
1% TO 2% CROSS SLOPE
LESS THAN 1.5% SLOPE
EXISTING PAVEMENT ELEVATION
SCALE:03
EXISTING RUNWAY-TAXIWAY
CONNECTION
N/A SCALE:04
PROPOSED RUNWAY-TAXIWAY
CONNECTION
N/A
NOTES:
1. HMAC SHALL BE TXDOT ITEM 341, TYPE DG-D, COMPACTED TO BETWEEN 92% AND 97% OF THE PAVEMENT'S RICE SPECIFIC GRAVITY. HMAC SHALL HAVE
A PERFORMANCE GRADE OF PG 64-22.
2. ANY REPAIRS NECESSARY TO THE BASE COURSE, AFTER REMOVAL OF THE EXISTING SURFACE COURSE, SHALL BE PERFORMED THROUGH ITEM TXDOT 351 - FLEXIBLE PAVEMENT STRUCTURE REPAIR AND SHALL UTILIZE COMPACTED BASE / CRUSHED LIMESTONE PER TxDOT ITEM 247, TYPE A, GRADE 1-2 COMPACTED TO AT LEAST 95% STANDARD PROCTOR DENSITY AT A MOISTURE CONTENT WITHIN ±2% POINTS OF THE OPTIMUM MOISTURE CONTENT.
3. ENSURE TRANSVERSE RUNWAY GRADE IS BETWEEN 1 AND 2%. ENSURE LONGITUDINAL TAXIWAY GRADE IS LESS THAN 1.5%. ENSURE TRANSVERSE
TAXIWAY GRADE IS BETWEEN 1 AND 1.5%
4. ELEVATIONS AND RELATIVE SLOPES SHOWN ON THIS DETAIL ARE FOR REFERENCE ONLY. ACTUAL CONDITIONS TO BE FIELD DETERMINED BY
CONNECTING PROPOSED RUNWAY TO EXISTING TAXIWAY GRADE.
NOTES:
1. ELEVATIONS AND RELATIVE SLOPES SHOWN ON THIS DETAIL ARE FOR REFERENCE ONLY. ACTUAL
CONDITIONS TO BE FIELD DETERMINED.
SAWCUT ACCORDING TO
SHEET C-009 AT PAVEMENT
RECONNECTION POINT
15'
1 ADDENDUM 1 6/4/26
6/3/2026