Notice of Change Order- CO5 - FR441- Vermillion River Danville Dam Removal .docx

DOCX document 16 KB Posted

Attached to
DNR-OWR-CO#5 (Notice of Change Order)-FR441 Danville Dam Removal and Streambank Stabilization
Solicitation number
19-422DNR-WTRRE-B-7971
Issued by
St. Clair County, Illinois

About this file

This document is a Change Order Notice from the Illinois Department of Natural Resources (IDNR) for the DNR-OWR-CO#5 -FR441 Vermillion River Danville Dam Removal project. The change order extends the contract with Halverson Construction Co., Inc. by 123 days until 11/01/2019 due to weather delays that prevented the contractor from completing the work of removing a concrete dam and placing riprap for streambank stabilization in the Vermilion River. The original contract amount remains the same, and this change order represents a 0% increase. The circumstances that led to the change order were unforeseeable at the time and germane to the original contract, in accordance with state procurement law.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Change Order Notice

Agency: Illinois Department of Natural Resources

Title of Procurement: DNR-OWR-CO#5 -FR441 Vermillion River Danville Dam Removal

BidBuy Reference Number: 19-422DNR-WTRRE-B-7971

The Illinois Department of Natural Resources requires one (1) change order to a contract with Halverson Construction Co., Inc. to extend contract by 123 days for the following reasons:

CHANGE ORDER NOTICE:CO#5:

The weather has delayed the Contractor from working in the Vermilion River to complete the project. It requires a concrete dam to be removed in the Vermilion River and riprap to be placed on the streambanks for stabilization. The River flows have been higher than normal, thereby preventing the work from being completed.

Contract change order is required to extend the contract until 11/01/2019. No other changes: contract amount remains the same. This change order is a 0% increase to the current contract amount.

These circumstances were unforeseeable at the time and germane to the original contract. Change order is in accordance with 720 ILCS 5/33E-9. (ref. original contract - P-2919)