Design and Installation of Nadir Research Portals in a NASA Gulfstream C-20B Aircraft
Statement of Work
August 17, 2017
Background
A former U.S. Air Force Gulfstream C-20B (Gulfstream Model G-1159A) aircraft (serial number (S/N) 478) is a NASA Langley Research Center (LaRC) public-use aircraft, which will be utilized for research missions. Scientists at NASA LaRC have developed a suite of active (lidar) and passive (optical radiometric) sensors to be flown on a flight platform in a research configuration in support of NASA and other Federally-sponsored initiatives.
Project Scope
The vendor shall provide a design for two nadir research portals in NASA LaRC’s C-20B aircraft. The vendor shall provide copies of the appropriate documentation as listed in Item 6 of the Meeting/Deliverables/Documentation Requirements section of this SOW.
The vendor shall secure approval for the specific aircraft modifications via a Federal Aviation Administration (FAA) Designated Engineering Representative (DER) using FAA Form 8110-3. However, formal FAA approvals for the work performed under this SOW are not required. In preparation for the installation of the research packages, a design for two nadir research portals is required with options to install one or both structural nadir research portals along with several other modifications as described in this Statement of Work (SOW).
Task 1: Design of Two Nadir Portals
1. The vendor shall provide a design for the two nadir portals with aluminum blanks and structural floor plugs as described below:
a. The nadir portals shall have a minimum acceptable circular dimension of 18-
in. diameter. Rectangular openings are acceptable only if they can accommodate an 18-in. diameter portal within their boundary.
b. The perimeter of each nadir portal shall incorporate a fastener pattern to allow for the installation of an aluminum sealing blank or a subsequent glass adapter plate.
c. The second nadir portal shall be located a minimum of six ft aft of the forward nadir portal.
d. Both nadir portals shall be located within the pressurized portion of the passenger cabin.
e. The second nadir portal shall be identical to the first nadir portal.
2. The vendor shall design an aluminum blank for each nadir portal which shall be installed in lieu of optical glass.
3. The vendor shall provide a design which incorporates a geometrically corresponding opening in the cabin floor around each nadir portal. The floor opening shall be rectangular with a minimum footprint of 25 x 25 in., centered over each nadir opening.
4. The vendor shall provide a design which provides a structural floor plug for each portal that can be installed to close the cabin floor openings. The floor plugs shall restore the floor to its original strength and also provide seat tracks matching the original layout. Upon installation, the structural plug shall enable the aircraft cabin to be used when scientific instruments are not utilizing the nadir portals.
5. The vendor shall design an externally-mounted Foreign Object Damage (FOD) shutter to cover each nadir research portal during takeoffs and landings. The FOD shutters shall be electrically driven with positive indication of position (e.g.
open/closed limit switches) and cockpit control switches with corresponding indicator lights.
6. The vendor shall incorporate in the design the relocation of those antennas or beacons that must be relocated in order to install the two nadir research portals.
7. The vendor shall incorporate in the design the rerouting/relocation of those hydraulic lines, electrical cables, and control cables that interfere with the installation of the nadir research portals.
8. The vendor shall incorporate in the design aircraft attachment provisions for a rectangular pressure dome (“dog house”) for the aft portal with the following specific features:
a. The design shall incorporate a pressure-sealing aircraft interface around the second nadir portal.
b. The sealing interface at the aircraft outer mold line (OML)/skin shall be rectangular with a minimum footprint of 25 x 25 in., centered over the nadir opening.
c. The perimeter of the pressure-sealing interface shall be fit with a fastener pattern to allow the installation of a rectangular pressure dome.
Note: The Contractor is not responsible for the design and fabrication of the pressure dome (“dog house”). This effort will be performed by NASA at a later date.
9. The vendor shall present design information and status at the Preliminary Design
Review (PDR) and Critical Design Review (CDR) design points via teleconferencing or at face-to-face meetings, as stated in the Schedule of
Requirements as stated below. The Terms of Reference for the PDR and CDR are given in NASA LaRC document number RSD-FLT-008 (Attachment 1).
10. The vendor shall provide copies of all documentation generated as a consequence of Task 1, including all installation and removal documentation, drawings, and approvals of task modifications, all substantiation analyses, and all quality-assurance approvals at the conclusion of this Task (see Schedule of Requirements and Item 6 of the Meeting/Deliverables/Documentation Requirements section of this SOW).
Task 2: Fabricate and install the forward nadir portal (optional task)
1. The vendor shall install the forward nadir portal in accordance with the design approved in Task 1. This task shall include:
a. Installation of a forward nadir portal with the characteristics given in Task 1.1.a-d.
b. Installation of an aluminum blank, in lieu of optical glass, as described in Task 1.2.
c. Installation of a geometrically corresponding opening in the cabin floor around the forward nadir portal as described in Task 1.3.
d. Fabrication and installation of a structural floor plug for the forward portal that can be installed to close the cabin floor opening as described in Task 1.4.
e. Fabrication and installation of an externally-mounted Foreign Object Damage (FOD) shutter to cover the forward nadir research portal during takeoffs and landing as described in Task 1.5.
f. Relocation of those antennas or beacons that must be relocated in order to install the forward nadir research portal as described in Task 1.6.
g. Rerouting/relocation of those hydraulic lines, electrical cables, and control cables that interfere with the installation of the nadir research portals as described in Task 1.7.
2. As a result of the installation, the vendor shall provide the revised and updated engineering designs and analyses required to document the as-delivered modifications to the aircraft in accordance with the Schedule of Requirements section of this SOW. The contractor shall participate in the iterative exchange between the engineers and the fabricators once actual fabrication and installation commences. Therefore, the final design of Task 1 may have to be modified during accomplishment of Task 2. The fabrication/engineering interactions are typically documented with design updates, corresponding analyses updates (if any), redlined drawings, and revised drawings with redlines incorporated, which shall be delivered to the Government.
3. The vendor shall provide all materials associated with the completion of Task 2 to include, but not limited to, structural materials, fasteners and other components required for fabrication and installation.
4. The vendor shall install the structural floor plug and perform a ground pressurization check.
5. The vendor shall restore the aircraft to the as-delivered condition with the exception of the modifications performed per this SOW.
6. In accordance with NASA Procedural Requirements NPR 7900.3D Section 2.8.4
(Attachment 2), the vendor shall provide on-site aircraft access to NASA-designated personnel to include, but not limited to, engineering, maintenance, and quality assurance.
7. The vendor shall assist NASA LaRC personnel during system activation and aircraft preparation for the Functional Check Flight (FCF) and departure from the vendor’s facility.
8. After completion of aircraft modification, the vendor shall perform and provide to
NASA an updated Weight and Balance for the aircraft.
9. In accordance with Langley Management System Test Directive TD-0940 paragraph 5.4 (Attachment 3), the vendor shall participate in a short-duration NASA Flight Readiness Review (FRR) via teleconference (approximately 1 hour in duration) prior to release of the aircraft for flight. The date is to be determined after award.
10. The vendor shall assist NASA in conducting a FCF following successful completion of the ground pressurization checks to demonstrate the functional operability of the modifications associated with this task. NASA will provide the pilots for this mission.
11. The vendor shall resolve any discrepancies or issues that may be revealed during the FCF due to the installation of the forward nadir portal and the associated structural floor plug.
12. The vendor shall secure written approval from the NASA Contracting Officer prior to commencing any work activities other than those set forth in the SOW.
Task 3: Fabricate and install the aft nadir portal (optional task)
1. The vendor shall install the aft nadir portal, with no optical glass, in accordance with the design approved in Task 1. This task shall include:
a. Installation of an aft nadir portal with the characteristics given in Task 1.1.a-e.
b. Installation of an aluminum blank, in lieu of optical glass, as described in
Task 1.2.
c. Installation of a geometrically corresponding opening in the cabin floor around the aft nadir portal as described in Task 1.3.
d. Fabrication and installation of a structural floor plug for the aft portal that can be installed to close the cabin floor opening as described in Task 1.4.
e. Fabrication and installation of an externally-mounted Foreign Object Damage (FOD) shutter to cover the aft nadir research portal during takeoffs and landings as described in Task 1.5.
f. Relocation of those antennas or beacons that must be relocated in order to install the aft nadir research portal, as described in Task 1.6.
g. Rerouting/relocation of those hydraulic lines, electrical cables, and control cables that interfere with the installation of the nadir research portals, as described in Task 1.7.
h. Fabrication and installation of aircraft attachment provisions for a rectangular pressure dome (“dog house”) for the aft portal, as described in Task 1.8.a-c.
If Tasks 2 and 3 are performed simultaneously, Subtasks 2.2-12 will be combined with Subtasks 3.2-12.
2. As a result of the installation, the vendor shall provide the revised and updated engineering designs and analyses required to document the as-delivered modifications to the aircraft in accordance with the Schedule of Requirements section of this SOW. The contractor shall participate in the iterative exchange between the engineers and the fabricators once actual fabrication and installation commences. Therefore, the final design of Task 1 may have to be modified during accomplishment of Task 3. The fabrication/engineering interactions are typically documented with design updates, corresponding analyses updates (if any), redlined drawings, and revised drawings with redlines incorporated, which shall be delivered to the Government.
3. The vendor shall provide all materials associated with the completion of Task 3 to include, but not limited to, structural materials, fasteners and other components required for fabrication and installation.
4. The vendor shall install the structural floor plug and perform a ground pressurization check.
5. The vendor shall restore the aircraft to the as-delivered condition with the exception of the modifications performed per this SOW.
6. In accordance with NASA Procedural Requirements NPR 7900.3D Section 2.8.4
(Attachment 2), the vendor shall provide on-site aircraft access to NASA-designated personnel to include, but not limited to, engineering, maintenance, and quality assurance.
7. The vendor shall assist NASA LaRC personnel during system activation and aircraft preparation for the Functional Check Flight (FCF) and departure from the vendor’s facility.
8. After completion of aircraft modification, the vendor shall perform and provide to
NASA an updated Weight and Balance for the aircraft.
9. In accordance with Langley Management System Test Directive TD-0940 paragraph 5.4(Attachment 3), the vendor shall participate in a short-duration NASA Flight Readiness Review (FRR) via teleconference (approximately 1 hour in duration) prior to release of the aircraft for flight. The date is to be determined after award.
10. The vendor shall assist NASA in conducting a FCF following successful completion of the ground pressurization checks to demonstrate the functional operability of the modifications associated with this task. NASA will provide the pilots for this mission.
11. The vendor shall resolve any discrepancies or issues that may be revealed during the FCF due to the installation of the forward nadir portal and the associated structural floor plug.
12. The vendor shall secure written approval from the NASA Contracting Officer prior to commencing any work activities other than those set forth in the SOW.
Meeting/Deliverables/Documentation Requirements
1. In accordance with NPR 7900.3D Section 2.8.4 (Attachment 2), the vendor shall ensure that access to project management and coordination is provided while working with NASA-designated personnel and shall be available for technical and program interface via teleconferencing or face-to-face meetings at the vendor’s facility to update schedule and activity status at a mutually agreed upon date and time.
2. The vendor shall have the structural design of the nadir portals reviewed and approved by a DER using FAA Form 8110-3. The vendor shall provide the signed documents and analysis document to NASA LaRC.
Note: Formal approvals by the FAA are not required.
3. In accordance with LaRC Management System Test Directive LMS-TD-0940 paragraph 5.4 (Attachment 3) and FAR 52.246-11, the NASA Quality Assurance (QA) personnel shall conduct the final inspection and approval of all modifications done to the Gulfstream C-20B aircraft. This activity will occur at the vendor’s facility.
Note: NASA’s quality assurance authority is limited to normal quality control issues and does not allow NASA to change FAA-approved design data and/or installation drawings or procedures.
4. Upon completion of Tasks 2 and 3 in this SOW, the vendor shall participate in a short-duration NASA Flight Readiness Review (FRR) via teleconference.
Note: The typical duration of a FRR is one hour.
5. The vendor shall ensure that their project management staff shall be available to work with NASA LaRC personnel for technical and program interface, via teleconferencing and/or face-to-face meetings at the vendor’s facility, at a mutually agreed upon dates and times. The meetings will include updated schedule milestones, issues, risks, technical design and analysis progress and installation activity status.
6. The vendor shall provide copies of all documentation generated as a consequence of this contractual effort, including all installation and removal documentation, drawings, and approvals of task modifications, all substantiation analyses, and all quality-assurance approvals.
a. Copies of all signed documents and two copies of all engineering drawings
(half size) shall be provided in accordance with accepted aerospace industry standards.
b. All document copies shall be in the electronic PDF format.
c. All electronic copies of electronic drawings shall be in AutoCAD-compatible format, such as DWG or DXF.
d. All electronic copies of solid models shall be in a Pro-E compatible format, such as IGES, or STP. The associated PRT, DRW, and ASM files also will be provided.
NASA LaRC Responsibilities:
1. Clarify and review the PDR and CDR requirements with the vendor within two weeks after award of the contract.
2. Clarify and review the FRR requirements with the vendor within two weeks after award of the contract.
3. Provide the specific C-20B aircraft for installation during a three-month period during Fiscal Year 2018, based on aircraft availability.
NOTE: The exact dates for delivery of the aircraft during this window will be agreed upon between the vendor and NASA LaRC.
4. Conduct the FRR using NASA LaRC procedures upon completion and documentation of all modification activity.
5. Observe all ground pressurization checks of the nadir port installations and the associated structural plugs.
6. Perform a Functional Check Flight (FCF) at the vendor’s installation facility upon the completion of the installation of the nadir port(s), associated structural plug(s) and ground pressurization check(s).
7. Provide the design and fabrication of a pressure dome for either of the nadir portals (“dog house”) at a later date independent of this SOW.
8. The NASA Quality Assurance (QA) personnel, in conjunction with NASA
Technical personnel, shall conduct the final inspection and approval of all modifications done to the Gulfstream C-20B aircraft. This activity will occur at the vendor’s facility.
Schedule of Requirements:
TASK REFERENCE DELIVERABLE
FREQUENCY/
DUE DATE
SOW Task 1.9 Conduct Preliminary Design Review At 20% design stage
SOW Task 1.9 Conduct Critical Design Review At 90% design stage
SOW Task 1.10 Provide copies of all signed design documents At conclusion of Task 1
SOW Tasks 2.1 & 2.3
Install the forward nadir portal, blanking plate and structural plug and perform ground pressurization check
Before the Functional Check Flight
SOW Task 2.2
Provide the revised and updated engineering designs and analyses required to document the as-delivered modifications to the aircraft associated with Task 2
At conclusion of Task 2
SOW Tasks 3.1 & 3.3
Install the aft nadir portal, blanking plate and structural plug and perform ground pressurization check
Before the Functional Check Flight
SOW Task 3.2
Provide the revised and updated engineering designs and analyses required to document the as-delivered modifications to the aircraft associated with Task 3
At conclusion of Task 3
SOW Tasks 2.8 and 3.8 Provide updated Weight and Balance for the aircraft.
Before the Functional Check Flight
SOW section “Meetings/Deliverables/Documentation”
Para. 2
Provide approved documentation from an FAA DER for the nadir portals
Upon completion of Task 1
SOW section “Meetings/Deliverables/Documentation”
Para. 6
Provide copies of all signed documents
Upon completion of contract
SOW section “Meetings/Deliverables/Documentation”
Para. 4
Participate in FRR via teleconference
Upon completion and documentation of all modification activity
SOW Tasks 2.9 and 3.9 Assist in conducting FCF
Following successful completion of the ground pressurization checks
Return C-20B aircraft in airworthy condition with the modifications performed per this SOW