RFP NNG16598592R

Amendment No. 1

The Milestone Payment Schedule is hereby amended as shown below.

B.3 GSFC 52.232-99 Milestone Payment Schedule (FIXED PRICE) (NOV 2013)

Item

No.

Event Qty

Contract

Value %

Total

Amount Completion Determination

Kick-Off Meeting /

Systems Requirements

Review (SRR)

1 5% TBP

Final presentation package received in accordance with

Section 3.1 of Restore-L-SOW-

001980

Preliminary Design

Review (PDR)

1 10% TBP

Final presentation package received in accordance with

Section 3.1 of Restore-L-SOW-

001980

Critical Design Review

(CDR)

1 10% TBP

Final presentation package received in accordance with

Section 3.1 of Restore-L-SOW-

001980

Engineering

Development Unit

(EDU) Delivery

1 20% TBP

Final presentation package received in accordance with

Section 3.1 of Restore-L-SOW-

001980

Pre-Environmental

Review (PER)

1 10% TBP

Final presentation package received in accordance with

Section 3.1 of Restore-L-SOW-

001980

6 Pre-Ship Review (PSR) 1 10% TBP

Final presentation package received in accordance with

Section 3.1 of Restore-L-SOW-

001980

7 Flight Unit Delivery 4 35% TBP

Hardware received. EIDP received in accordance with

Section 6.7 of Restore-L-SOW-

001980