Attachment A
RESTORE-L-SOW-001980
Revision -
CHECK WITH SSCO NGIN DATABASE AT:
https://sscongin.ndc.nasa.gov/
TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE.
CM FOREWORD
This document is a Satellite Servicing Capabilities Office (SSCO) Configuration Management
(CM)-controlled document. Changes to this document require prior approval of the applicable
Configuration Control Board (CCB) Chairperson or designee. Proposed changes shall be submitted to the SSCO Code 408 CM Office (CMO), along with supportive material justifying the proposed change. Changes to this document will be made by complete revision.
Questions or comments concerning this document should be addressed to:
NASA/Goddard Space Flight Center
SSCO, Code 408
Attention: Configuration Management Office
Greenbelt, Maryland 20771 ii
SATELLITE SERVICING CAPABILITIES OFFICE
DOCUMENT CHANGE RECORD
Date: September 20, 2016 Sheet 1 of 1
TITLE: Rendezvous & Proximity Operations Subsystem IRCam Statement of Work
REV
LEVEL
DESCRIPTION OF CHANGE AUTHORIZATION
- Baseline Release Per SSCO-CCR-000133R1
SSCO CM RELEASE
iii
TABLE OF CONTENTS
Page
1.0 Introduction ....................................................................................................................... 1-1
1.1 General Information ............................................................................................. 1-1
1.2 Basic Hardware Description ................................................................................ 1-1
1.3 Required Quantities ............................................................................................. 1-3
1.4 Optional Quantites ............................................................................................... 1-4
1.5 Verb Application .................................................................................................. 1-4
1.6 Document Change Procedure .............................................................................. 1-4
1.7 Applicable Documents ......................................................................................... 1-5
1.7.1 Precedence ............................................................................................... 1-5
2.0 Schedule ............................................................................................................................. 2-1
2.1 Required Hardware Deliverables ......................................................................... 2-1
2.2 Optional Hardware Deliverables .......................................................................... 2-1
2.3 Project Schedule................................................................................................... 2-1
3.0 Management, Reporting, Documentation, and Reviews ............................................... 3-1
3.1 Reviews and Meetings ......................................................................................... 3-1
3.1.1 Weekly Status Teleconference ................................................................. 3-1
3.1.2 Written Monthly Reports ......................................................................... 3-1
3.1.3 Kickoff Meeting (KOM)/ Systems Requirements Review (SRR) ........... 3-2
3.1.4 Preliminary Design Review (PDR) .......................................................... 3-3
3.1.5 Critical Design Review (CDR) ................................................................ 3-4
3.1.6 Pre-Environmental Review (PER) ........................................................... 3-5
3.1.7 Test Readiness Review ............................................................................ 3-6
3.1.8 Pre-Ship Reviews (PSR) .......................................................................... 3-7
4.0 Manufacturing Requirements.......................................................................................... 4-1
4.1 Use of Travelers ................................................................................................... 4-2
4.2 Prohibited Plating and Alloys .............................................................................. 4-2
4.3 Fastener Integrity ................................................................................................. 4-2
4.3.1 Thread Locking ........................................................................................ 4-2
4.3.2 Fastener Torqueing .................................................................................. 4-3
4.4 Soldering .............................................................................................................. 4-3
4.5 Silicones ............................................................................................................... 4-3
4.6 Contamination Control......................................................................................... 4-3
5.0 Quality Assurance Requirements .................................................................................... 5-1
5.1 Mandatory Inspection Points ............................................................................... 5-1
6.0 Contract Data Requirements List (CDRL) .................................................................... 6-1
6.1 Technical Requirements Compliance Matrix ...................................................... 6-1
6.2 Materials Identification and Usage List ............................................................... 6-2
6.3 Optical Deliverables............................................................................................. 6-2 iv
6.3.1 Optical Model .......................................................................................... 6-2
6.3.2 Stray Light Analysis ................................................................................ 6-2
6.4 Mechanical Deliverables ...................................................................................... 6-2
6.4.1 Interface Control Drawing (ICD)............................................................. 6-2
6.4.2 Computer Aided Design (CAD) Electronic Model ................................. 6-2
6.4.3 Stress Analysis Report ............................................................................. 6-3
6.5 Electrical Deliverables ......................................................................................... 6-4
6.5.1 Electrical ICD .......................................................................................... 6-4
6.5.2 EEE Parts List .......................................................................................... 6-4
6.5.3 Radiation Test Report .............................................................................. 6-4
6.6 Thermal Deliverables ........................................................................................... 6-4
6.7 End Item Data Package ........................................................................................ 6-5
6.7.1 Certificate of Conformance...................................................................... 6-5
6.7.2 As-Built Parts List.................................................................................... 6-5
6.7.3 As-Built Assembly Procedures ................................................................ 6-5
6.7.4 Material Certifications ............................................................................. 6-6
6.7.5 Test Reports ............................................................................................. 6-6
6.7.6 Summary of Non-conformances .............................................................. 6-7
6.8 Data Deliverables Summary and Expected Delivery ........................................... 6-8
7.0 Testing ................................................................................................................................ 7-1
7.1 Performance Test ................................................................................................. 7-1
7.2 EMI / EMC Test................................................................................................... 7-2
7.3 Random Vibration Test ........................................................................................ 7-2
7.4 Thermal Vacuum Test.......................................................................................... 7-2
7.5 Optical Performance Testing ............................................................................... 7-2
8.0 Hardware Handling, Cleaning, Packing & Shipping ................................................... 8-1
8.1 Handling & Storage ............................................................................................. 8-1
8.2 Cleaning ............................................................................................................... 8-1
8.3 Packing ................................................................................................................. 8-1
8.4 Shipping ............................................................................................................... 8-1
9.0 Abbreviations and Acronyms .......................................................................................... 9-1 v
LIST OF TABLES
Table Page
Table 1-1: Applicable Documents ............................................................................................... 1-5
Table 2-1: Required Hardware Deliverable Schedule ................................................................. 2-1
Table 2-2: Optional Hardware Deliverable Schedule .................................................................. 2-1
Table 6-1: Data Deliverable Schedule ......................................................................................... 6-8
Table 9-1: Acronym List .............................................................................................................. 9-1
1-1
1.0 INTRODUCTION
1.1 GENERAL INFORMATION
The Satellite Servicing Capabilities Office (SSCO) at Goddard Space Flight Center (GSFC) was established in 2009 to continue NASA’s 40-year legacy of satellite servicing and repair. Among its various pursuits, SSCO is responsible for the development of the Restore-L satellite servicing mission. Restore-L is a free-flying mission to be launched in 2020 to perform on-orbit satellite servicing on an operational Government asset (the Client) in Low Earth Orbit (LEO).
This Statement of Work (SOW) defines the scope of work to be performed for the design, development, fabrication, testing, and delivery of the Restore-L Rendezvous and Proximity
Operations (RPO) subsystem infrared wavelength camera (IRCam) system.
The technical requirements for performance, interfaces, design, performance testing, and certification are provided in the accompanying technical specification, RESTORE-L-SPEC-
001981.
1.2 BASIC HARDWARE DESCRIPTION
The RPO IRCam will be utilized on the Restore-L servicing vehicle to provide bearing and relative translation and attitude information of the Client vehicle. The RPO IRCam will be utilized during the “Autonomous Rendezvous & Docking” portion of the mission as shown below.
Figure 1: Restore-L Mission Concept of Operations
1-2
Each RPO IRCam will consist of the following major components: an optical assembly (lens) and camera body (including the detector, processor, electrical interface, etc.). The implementation of a stray light rejection baffle system is left to the discretion of the Contractor.
The Contractor will be responsible for the design, fabrication, integration, and test of all RPO
IRCam components, including the baffle if applicable.
As stated in the accompanying technical specification, the Government desires to utilize the RPO
IRCam for future NASA missions such as the Asteroid Robotic Redirect Mission (ARRM).
Therefore, the Contractor will design the RPO IRCam to the overlapping Restore-L and ARRM requirements specified within the technical specification (RESTORE-L-SPEC-001981). This direction will require the Contractor to ensure that the RPO IRCam will meet all of its requirements for a four year mission duration in interplanetary orbit.
1-3
1.3 REQUIRED QUANTITIES
The Contractor will design, fabricate, test and deliver the following units:
Order quantity of one (1) protoflight RPO IRCam unit, as defined in the accompanying technical specification document, “RESTORE-L-SPEC-001981.”
Order quantity of one (1) protoflight RPO IRCam unit, as defined in the accompanying o This sole RPO IRCam will be fabricated per flight standards as dictated by this
Statement of Work (SOW) document as well as the accompanying technical specification document, “RESTORE-L-SPEC-001981.” However, the
Government waives all environmental testing on this particular unit. As such, sections 4.5.3 through section 4.5.6 of RESTORE-L-SPEC-001981 do not apply.
Note: This unit is intended as a flight spare IRCam. Environmental testing will be completed by the Government if the need for the spare arises.
Order quantity of one (1) Engineering Development Unit (EDU) RPO IRCam, as defined in the accompanying technical specification document, “RESTORE-L-SPEC-001981.”
Order quantity of one (1) set of Electrical Ground Support Equipment (EGSE), as defined in the accompanying technical specification document, “RESTORE-L-SPEC-001981.
Set of documentation deliverables as defined in Section 6.0, the Contract Data
Requirements List (CDRL).
1-4
1.4 OPTIONAL QUANTITES
As an option, the Contractor will design, fabricate, test and deliver the following units:
Order quantity of one (1) Engineering Development Unit (EDU) RPO IRCam, without baffle assembly (if applicable), as defined in the accompanying technical specification document, “RESTORE-L-SPEC-001981.”
Order quantity of one (1) RPO IRCam digital emulator, as defined in the accompanying
Order quantity of one (1) RPO IRCam Camera Data Generator (CDG), as defined in the accompanying technical specification document, “RESTORE-L-SPEC-001981.”
Note: The Government wishes to evaluate each of these options independently from one another.
1.5 VERB APPLICATION
Statements containing the verb “shall” are binding requirements regardless of location within this statement of work. The verbs “should” and “may” are used for stating non-mandatory goals or denoting a statement of best practice. The verb “will” is used in a statement of fact, expected occurrence, or declaration of purpose.
1.6 DOCUMENT CHANGE PROCEDURE
The Satellite Servicing Capabilities Office (SSCO, Code 408) maintains configuration control of this document. All changes will require a document revision to be processed through the SSCO
Next-Generation Integrated Network (NGIN) Configuration Management System.
3-1
3.0 MANAGEMENT, REPORTING, DOCUMENTATION, AND REVIEWS
3.1 REVIEWS AND MEETINGS
The Contractor will provide labor, facilities, equipment, materials, and data (electronic and hard copy) to support the meetings and reviews defined in this SOW. Reviews may be conducted at
NASA GSFC, at the Contractor’s facility, or remotely via teleconference or videoconference.
The Contractor will provide a review agenda no less than 2 weeks prior to the start of the review.
Advanced (draft acceptable) review packages will be provided no less than 2 days prior to the start of the review.
A final version of the presentation package will be delivered within five (5) working days following the review and will include review meeting minutes, final agenda, all required deliverable data described in each review subsection, and responses to all recommendations and action items discussed during the review.
3.1.1 Weekly Status Teleconference
The Contractor will provide an informal weekly status teleconference via phone. This approximately thirty-minute long meeting will provide updates on technical and schedule progress.
3.1.2 Written Monthly Reports
The Contractor will provide a monthly status report via email. The first report will be delivered approximately thirty (30) days after authority to proceed is received. These reports will provide data for the assessment of technical and programmatic (i.e., cost, schedule, etc.) progress. The monthly status reports will include:
Current project schedule and changes from previous version.
Work accomplished for current reporting period.
Action item status.
Work planned for next reporting period.
Current problems which impede performance or impact program schedule, and proposed corrective action.
Other information that assists NASA GSFC in evaluating technical and schedule performance.
Any Class 1 MRB issues which are required to be reported and tracked
3-2
3.1.3 Kickoff Meeting (KOM)/ Systems Requirements Review (SRR)
Within thirty (30) days after contract award, the Contractor will convene a Kickoff Meeting /
SRR. The Kickoff Meeting will provide a forum for the Contractor to present the preliminary technical specification compliance matrix and solicit additional clarifications from NASA GSFC.
The KOM / SRR package will cover the following:
Review of preliminary technical specification Compliance Matrix per Section 6.1
Additional clarification of requirements from RPO IRCam technical specification
Discussion of design concepts, manufacturing plans, integration and test plans, cleanliness plans (as available)
Identification of trade studies (if available)
Review and additional identification of Mandatory Inspection Points (MIPs) not specifically outlined in Section 5.1
Scheduling of additional milestone reviews (PDR, CDR, PER, PSR, etc.)
3-3
3.1.4 Preliminary Design Review (PDR)
A PDR will be held at a Government approved location to review the preliminary design of the
RPO IRCam and evaluate the design for compliance with the requirements of RESTORE-L-
SPEC-001981.
The PDR package will contain the following:
Preliminary RPO IRCam design and architecture
Estimated technical parameters and comparison to requirements
Discussion of critical trade studies, as applicable
Results of any electrical breadboard testing
Review of updates to Technical Compliance Matrix per Section 6.1
Review of preliminary Materials Identification and Usage List (MIUL) per Section 6.2
Review of preliminary optical models per Section 6.3.1
Review of preliminary mechanical Interface Control Drawing per Section 6.4.1
Review of preliminary mechanical CAD model per Section 6.4.2
Review of preliminary electrical Interface Control Document per Section 6.5.1
Review of preliminary EEE Parts List per Section 6.5.2
Review of preliminary thermal analysis per Section 6.6Manufacturing plans, including:
o Provisions for meeting cleanliness requirements o Provisions for meeting ESD requirements o Provisions for meeting RPO IRCam delivery dates per Section 2.1
Identification of long-lead and / or high-risk items
Review of any required radiation test plans (if applicable)
Risk mitigation plans, if any
3-4
3.1.5 Critical Design Review (CDR)
A CDR will be held at a Government approved location to review the final design of the RPO
IRCam and evaluate the design’s readiness to proceed to manufacturing.
The CDR package will contain the following:
Final RPO IRCam design / architecture
Final technical parameters and comparison to requirements
Any delta’s from PDR
Responses to any PDR Requests For Action (RFA)
Results of engineering unit testing, as applicable
Review of updates to Technical Compliance Matrix per Section 6.1
Delivery of final Materials Identification and Usage List (MIUL) per Section 6.2
Delivery of final optical models per Section 6.3.1
Delivery of final stray light analysis per Section 6.3.2
Delivery of final Mechanical Interface Control Drawing per Section 6.4.1
Delivery of final mechanical CAD model per Section 6.4.2
Delivery of final stress analysis report per Section 6.4.3
Delivery of final Electrical Interface Control Document per Section 6.5.1
Delivery of final EEE Parts List per Section 6.5.2
Delivery of final radiation test report (if applicable) per Section 6.5.3
Delivery of final thermal analysis per Section 6.6
Review of Assembly Procedures
A drawing tree with Configuration Management status of all detailed drawings o Goal is at least 80% of drawings released into Contractor’s CM system prior to start of manufacturing
Review of hardware performance test procedures
Review of any outstanding impediments to expedient delivery
3-5
3.1.6 Pre-Environmental Review (PER)
A PER will be held at a Government approved location to review the status of the RPO IRCam program prior to start of environmental testing.
The PER package will contain the following:
Review of updates to Technical Compliance Matrix per Section 6.1
Any delta’s from CDR
Responses to any CDR Request For Action
Review of executed Assembly Procedures for completed hardware
Review of as-built inspection photos for completed hardware
Review of executed Procedures
Review of environmental / performance test plans:
o Optical Performance o EMI/EMC o Vibration o Thermal Vacuum
3-6
3.1.7 Test Readiness Review
The Contractor will hold a Test Readiness Reviews (TRR) prior to the commencement of each environmental test. Government concurrence of a successful TRR is required in order for the
Contractor to proceed to test. Government participation in TRRs is expected remotely via teleconference.
The TRR will verify:
Acceptability of test procedures for the specific test under consideration
Test facilities are functionally able to receive the hardware
Test equipment, MGSE and EGSE is certified and calibrated, available for test duration, configured, and properly checked prior to connection to the flight hardware
All pre-test operations are complete
Calibration of all environmental equipment is current
Test specification/verification documents are under configuration control and available
Necessary test personnel are appropriately trained and certified and they are available to support the test
All associated risks and / or non-conformances have been mitigated or resolved
Any unresolved risks and / or non-conformances will have NASA GSFC written concurrence to proceed at-risk
At the conclusion of the TRR, all parties must provide positive concurrence the subject hardware is ready for test. The Contractor will provide for managing all resources, controlling schedules, managing all engineering, manufacturing and procurement activities, configuration management, Quality Assurance, documentation control, and distribution.
3-7
3.1.8 Pre-Ship Reviews (PSR)
The Contractor will hold a Pre-Ship Reviews (PSR) prior to delivering the final flight hardware to NASA GSFC. Hardware deliverables are detailed in Table 2-1. The populated compliance matrix will be presented at this review. Evidence for verification of each item in the compliance matrix for which the Contractor is responsible will be provided.
The PSR will take place at the completion of requirement verification tests and prior to shipment of the hardware to NASA GSFC.
The Pre-Ship Review (PSR) package will contain the following:
Final review and approval of Technical Compliance Matrix per Section 6.1
Detailed review of executed environmental test procedures
Witness of final pre-ship functional test execution to verify hardware functionality prior to shipment.
o No further assembly, test or modification of hardware will occur after the
Government witnessed Acceptance Test Procedure (ATP) without a failure report and a Government approved waiver.
A visual inspection for cosmetic defects and workmanship, and for proper marking and serialization
Documentation of any liens, nonconformance reports, NASA GSFC MRB’s, requests for deviation, open/unresolved issues and GSFC approved plans to close/resolve the issues
Detailed Review of the Correlated Thermal Model per Section 6.6
Detailed Review of the End Item Data Package per Section 6.7
4-1
4.0 MANUFACTURING REQUIREMENTS
The RPO IRCam shall be manufactured in accordance with the, “Restore-L Mission Assurance
Requirements (MAR)” document (RESTORE-L-RQMT-000518).
The Contractor shall review the MAR and provide a compliance matrix indicating its ability to conform to the various requirements. Within this compliance matrix, the Contractor shall indicate one the following responses for each of the various sections or Data Item Deliverables
(DID):
Full Compliance: The Contractor fully meets the requirement as defined by the MAR.
Full Compliance, with exception: The Contractor fully meets the intent of the requirement, but with an exception. (i.e., a different industry standard is used or an internal work instruction). Additional details on the specific exception shall be provided.
This scenario may required the contractor to submit an SSCO Request For Waiver
(RFW) form.
Partial-Compliance: The Contractor meets some subset, but not all of the requirement as defined by the MAR. Additional details on the specific shortcomings of compliance shall be provided. Under this scenario, the Contractor shall submit an SSCO Request For
Waiver (RFW) form.
Non-Compliance: The Contractor does not meet any aspect of the requirement as defined by the MAR. Under this scenario, the Contractor shall submit an SSCO Request For
Waiver (RFW) form.
As the MAR is a program-level document whose contents may not be applicable to all component-level hardware builds, the Government will address exceptions, partial, and non-compliances on a case-by-case basis as part of the negotiations during the contract award process. Waivers may be granted where permissible.
4-2
4.1 USE OF TRAVELERS
Each RPO IRCam shall have an associated fabrication / assembly traveler that documents, the following information:
Detailed fabrication / assembly steps
Material lots and date codes
As-built material and parts lists
Polymeric mix records, cure data, and shelf life (including hardness verification)
Calibration information for measurement equipment
Actual inspected dimensions, where applicable
Actual recorded running and final torque for torqueing operations
Approval of Government mandated Mandatory Inspection Points (see Section 5.1)
Travelers shall describe each step in the assembly process in detail; including the name and signature of the operator, the name and signature of the inspector, and the date the operation was completed.
4.2 PROHIBITED PLATING AND ALLOYS
Cadmium and zinc plating is prohibited. Zinc containing alloys shall be considered for vacuum suitability. Only tin alloys containing less than 97% tin are acceptable. The use of electrolytic nickel plating requires a Materials Usage Agreement (MUA) to assess that it does not result in electromagnetic interference.
4.3 FASTENER INTEGRITY
The requirements of section 4.2.6.5 of NASA-STD-6016 are applicable as written (including those in sections 4.2.6.5.1 and 4.2.6.5.2), except as discussed below.
NASA GSFC directive 541-PG-8072.1.2B shall be used instead of NASA-STD-6008 to define the fastener management and control policy, responsibilities, and practices for structural fasteners, fracture-critical fasteners, and safety-critical fasteners that are procured, received, tested, inventoried, installed in space flight hardware, or used in critical ground support equipment applications (such as vibration test fixtures).
Where procurement and screening of fasteners in accordance with this specification is prohibitive in terms of cost, schedule, or special processing requirements, the Contractor may solicit pre-screened fasteners from NASA GSFC as Government Furnished Equipment (GFE).
4.3.1 Thread Locking
All fasteners shall be thread locked, staked, or otherwise positively secured in accordance with
540-PG-8072.1.2, Sections 1.4 and 1.5.
4-3
4.3.2 Fastener Torqueing
All fasteners shall be torqued in accordance with 540-PG-8072.1.2, Section 2.
4.4 SOLDERING
Any solder joints and soldering practices used in the RPO IRCam shall be compliant with the requirements of IPC J-STD-001ES. Operators performing soldering shall be certified to or IPC
J-STD-001ES.
4.5 SILICONES
The use of silicone containing materials shall require a Government approved MUA.
4.6 CONTAMINATION CONTROL
The Contractor shall provide its contamination control plan to the Government for approval.
Individual parts and assembly of the RPO IRCam shall conform to the Contractor’s contamination control plan for assembly of spaceflight hardware.
Cleaning of component parts shall be performed with acetone, hexane, and/or isopropyl alcohol
(IPA). If either solvent is too aggressive for a particular part, the Contractor shall apply a cleaning procedure using an alternative solvent that results in a surface contamination level of molecular contaminate of less than 1.0 mg/m2 (< Level A per IEST-STD-1246E). Cleaning of optics shall be performed using Optima grade acetone.
Prior to Government delivery, each RPO IRCam shall be cleaned to a VC-0.5-1000-1500UV
(365 nm) per IEST-STD-1246E. Each RPO IRCam shall be double-bagged in heat-sealed, waterproof, vapor-proof, ESD-shielded, cleanroom compatible bagging along with redundant maximum humidity indicators.
5-1
5.0 QUALITY ASSURANCE REQUIREMENTS
The Contractor shall meet the quality assurance requirements for the RPO IRCam program found in the Restore-L Mission Assurance Requirements, “RESTORE-L-RQMT-000518.”
5.1 MANDATORY INSPECTION POINTS
Government Source Inspection is required. All work on this order is subject to inspection and test by the Government. The Government Quality Assurance (QA) representative shall be notified no less than five (5) working days in advance of the time articles or materials are ready for inspection or test. Shipment of RPO IRCam hardware shall not be made until inspected by or documented authorization to ship is received from the Government QA representative.
Mandatory government source inspection points shall include the following:
Manufacturing Facility Source Inspection: Prior to the start of hardware fabrication, the Contractor shall allow Government inspection the Contractor’s manufacturing facility in order to verify compliance with the ANDI/ISO/ASQ Q9001 standard.
Camera Assembly: Solder joints and soldering applications on the RPO IRCam flight
Printed Circuit Boards (PCB) shall be inspected post assembly, prior to burn in and conformal coating. Inspections will be conducted by the Government to determine compliance with IPC J-STD-001ES.
Camera Assembly: Staking and conformal coating applications to the RPO IRCam
PCBs shall be inspected prior to installation into the camera flight housings. Inspections will be conducted to determine compliance with NASA-STD-8739.1, as referenced in
Section 7.1 of the Restore-L Mission Assurance Requirements, “RESTORE-L-RQMT-
000518.”
Camera Testing: Performance testing of each serial numbered RPO IRCam unit shall be witnessed by the Government to verify conformance with the camera technical specification, “RESTORE-L-SPEC-001394, Rev B,” unless waived by the Government.
6-1
6.0 CONTRACT DATA REQUIREMENTS LIST (CDRL)
Unless otherwise specified, all data deliverables shall be delivered electronically in Government approved formats such as Word, Excel, Acrobat, etc. Engineering records such as drawings, reports, calculations, etc. shall be provided to the Government in root file format. As-run travelers, procedures and / or Work Instructions shall be delivered as a scanned image file with
‘paper capture’ or Optical Character Recognition (OCR) to convert the file to a searchable format, such as Adobe PDF (Portable Document Format).
All documents provided to the Government that contain an Export Control Determination, or similar information sensitivity marking, shall have that marking maintained with that document and information at all times.
Data deliverables shall include all items outlined in the following subsections.
6.1 TECHNICAL REQUIREMENTS COMPLIANCE MATRIX
The Contractor shall develop a compliance matrix that contains the technical requirements listed in RESTORE-L-SPEC-001981.
This matrix shall indicate the particular requirement and the document, procedure, or test that the
Contractor will utilize to confirm that said requirement has been met (i.e., analysis document or test document). In addition, the Contractor shall identify any exceptions within the compliance matrix that are planned and shall propose a method for meeting the intent of each requirement, or explain why the requirement is not feasible.
A preliminary completed compliance matrix addressing all requirements of the technical specification, indicating a plan for how each requirement will be met will be presented at the
Kickoff Meeting / SRR as requested in Section 3.1.3.
The compliance matrix shall be updated throughout the contract with the final completed version due to the Government as part of the End Item Data Package (EIDP).
6-2
6.2 MATERIALS IDENTIFICATION AND USAGE LIST
The Contractor shall provide an electronic searchable parts list or separate electronic searchable
Materials Identification and Usage List (MIUL), as described in Section 9.3 of the Restore-L
Mission Assurance Requirements (MAR).
A single MIUL will be acceptable (i.e., each serial number camera will not require an individual materials list). The MIUL shall be submitted to the Government’s Material and Processes
Engineer (MPE) for review and approval, in a format agreed upon by both parties.
Material Usage Agreement (MUA) forms shall be prepared and submitted to the Government
MPE for all materials that do not meet the requirements specified in the MAR, as described in
Section 9.2 of that document.
6.3 OPTICAL DELIVERABLES
6.3.1 Optical Model
The Contractor shall provide the optical design model of the RPO IRCam optical assembly in its native file format (Code V, Zemax, etc.) prior to the start of lens manufacturing.
6.3.2 Stray Light Analysis
The Contractor shall submit a report detailing the stray light analysis performed on the RPO
IRCam optical design in accordance with Requirements 3.2.11 and 3.2.12.
6.4 MECHANICAL DELIVERABLES
6.4.1 Interface Control Drawing (ICD)
The Contractor shall submit a top-level interface control drawing of the RPO IRCam as defined by requirements 3.5.1 of RESTORE-L-SPEC-001981. The ICD shall include details of the RPO
IRCam both with and without the stray light baffle (if applicable). A final version of the ICD shall be included in the EIDP reviewed at the PSR.
6.4.2 Computer Aided Design (CAD) Electronic Model
The Contractor shall provide a mechanical CAD model for the RPO IRCam as defined by requirement 3.5.2 of RESTORE-L-SPEC-001981.
6-3
6.4.3 Stress Analysis Report
A full stress analysis, based on the loading cases given in RESTORE-L-SPEC-001981, shall be performed and an analysis report shall be supplied as part of the CDR data package for a) verification of fracture classification and b) demonstration of compliance with structural factors of safety. The stress analysis report shall be made available as early in the contract as possible so that the Government may identify any fracture-critical parts that require Non-Destructive
Evaluation (NDE) and additional crack growth analysis before integration into the final assembly. A one-time submittal for the report will be acceptable (i.e., each serial number camera will not require a separate analysis). The final stress report shall also be included in the EIDP.
6-4
6.5 ELECTRICAL DELIVERABLES
6.5.1 Electrical ICD
The Contractor shall provide an electrical ICD for the RPO IRCam as defined by requirement
3.6.5.1 of RESTORE-L-SPEC-001981. A final version of the ICD shall be included in the EIDP reviewed at the PSR.
6.5.2 EEE Parts List
The Contractor shall provide a EEE parts list for the RPO IRCam as defined by requirement 8.4 of RESTORE-L-RQMT-000518. A final version of the parts list shall be included in the EIDP reviewed at the PSR.
6.5.3 Radiation Test Report
If applicable, the Contractor shall provide a test report detailing the radiation testing performed on any RPO IRCam EEE part (including the camera detector) required to meet the radiation environment defined in Section 3.8.8 of RESTORE-L-SPEC-001981.
6.6 THERMAL DELIVERABLES
The Contractor shall provide correlated thermal model of the RPO IRCam as defined by requirements 3.7.1 and 3.7.2 of RESTORE-L-SPEC-001981.
6-5
6.7 END ITEM DATA PACKAGE
The End Item Data Package (EIDP) shall be delivered with the RPO IRCam and be made available for review at the Pre-Ship Review (PSR).
To expedite acceptance of the completed cameras, the Contractor shall provide any partial or completed EIDP data as early as possible prior start of the PSR, preferably at least five (5) working days prior to the start of the review.
The EIDP shall include all deliverables described in the following subsections. Minor deviations in the EIDP may be approved on a case-by-case basis by the Government.
6.7.1 Certificate of Conformance
The Contractor shall submit a Certificate of Conformance (C of C), to certify that the materials and processes used in the parts supplied on this order, as well as the finished RPO IRCam assembly, meet all drawing, specification, and contract requirements. The C of C shall include the following information:
Supplier’s name and address
Purchase order number
Part number as specified on the purchase order
As-built revision level
Serial or lot number(s)
Date code
Date of manufacture for each enclosed item (if applicable)
Quantity
Certifying signature, title, and date
Any Class 1 MRB or deviation/waiver
6.7.2 As-Built Parts List
The Contractor shall provide the completed As-Built Parts List for each delivered RPO IRCam assembly serial numbers. This list shall include serialization, revisions, lot number, and expiration dates associated with all components used in the RPO IRCam assembly.
6.7.3 As-Built Assembly Procedures
The Contractor shall provide the completed as-built procedures that were used to fabricate and assemble each RPO IRCam.
6-6
6.7.4 Material Certifications
The Contractor shall provide complete Materials Certifications and Test Reports for every component used in the RPO IRCam assembly.
This documentation shall include:
Material chemical and physical reports
Material hardness test(s) results
Non-Destructive Examination reports
Sub-tier supplier certification paperwork
In-process work orders / logs
Polymeric mix records / cure data, including hardness verification
Dimensional inspection reports
6.7.5 Test Reports
The Contractor shall provide test reports for all mandatory testing performed on the RPO IRCam as outlined in Section 4.5 of RESTORE-L-SPEC-001981.
Test reports shall include the following:
Actual test data and confirmation of acceptance / rejection by Contractor QAE
Conclusions and recommendations regarding success of the test activity
Description of deviations from nominal results, failures, approved corrective actions and procedures, and retest
Traceability back to the requirement being verified by the specific test
Copy of as-run procedure (as appropriate), including name and signature of the Test
Operator and Quality Assurance witness
Identification of test configuration
Specific results of each procedure including automated test segments and associated analyses
Photograph(s) of test configuration
Photograph of test article prior to and upon completion of test
In addition to a copy of the as-run procedure, data collected during testing shall be compiled into a single file for all serial numbers and delivered electronically in mutually agreed upon format
(such as Excel), unless otherwise specified.
6-7
6.7.6 Summary of Non-conformances
The Contractor shall provide a summary list of all non-conformances affecting the RPO IRCam.
This completed list shall include the following information:
Problem/anomaly reporting (complete copies of reports & correspondences)
Deviations/waivers/open items/non-conformances and their dispositions
Material Review Board (MRB) Reports
Failure Review Board (FRB) Reports
Root Cause and Corrective Action Notices / Forms
7-1
7.0 TESTING
The Contractor will perform the testing outlined in this section as it pertains to the specific RPO
IRCam types:
The sole RPO IRCam protoflight unit shall be tested per the following sections to
Protoflight Qualification levels as defined by GSFC-STD-7000A, “General
Environmental Verification Standard (GEVS).”
The RPO IRCam protoflight spare unit will not undergo environmental testing. As such, only Section 7.1 and 7.5 herein applies.
The RPO IRCam engineering development unit (EDU) will not undergo environmental testing. As such, only Section 7.1 and 7.5 herein applies.
Additional information and applicable caveats for each subset of tests are provided to the
Contractor below for consideration.
7.1 PERFORMANCE TEST
The summary of the required performance testing is covered in Section 4.5.2 of RESTORE-L-
SPEC-001981. The Government will review the RPO IRCam performance test procedure at the program CDR. All RPO IRCam units shall undergo performance testing at the following milestones:
Upon completion of RPO IRCam manufacturing
Pre & post each environmental test o Not applicable to RPO IRCam Spare & EDU
Prior to delivery of the hardware to the Government
7-2
7.2 EMI / EMC TEST
The summary of the required EMI / EMC testing is covered in Section 4.5.3 of RESTORE-L-
SPEC-001981. The Government will review the RPO IRCam EMI / EMC test plan at the program PER.
7.3 RANDOM VIBRATION TEST
The summary of the required vibration testing is covered in Sections 4.5.4 and 4.5.5 of
RESTORE-L-SPEC-001981. The Government will review the RPO IRCam vibration test plan at the program PER.
7.4 THERMAL VACUUM TEST
The summary of the required thermal vacuum testing is covered in Section 4.5.6 of RESTORE-
L-SPEC-001981. The Government will review the RPO IRCam thermal vacuum test plan at the program PER.
7.5 OPTICAL PERFORMANCE TESTING
The summary of the required optical performance testing is covered in Section 4.5.7 of
RESTORE-L-SPEC-001981. The Government will review the RPO IRCam optical performance test plan at the program PER.
The optical performance testing shall occur pre & post the full environmental test campaign.
8-1
8.0 HARDWARE HANDLING, CLEANING, PACKING & SHIPPING
8.1 HANDLING & STORAGE
All RPO IRCam units shall be stored, preserved, and packaged when not in use to prevent loss of marking, deterioration, contamination, excessive condensation and moisture, or damage during all phases of the program.
8.2 CLEANING
Each RPO IRCam unit shall undergo a final cleaning prior to delivery to the Government per the accepted methods defined in Section 4.6. The camera units shall receive a cleaning to a VC-0.5-
1000-1500UV (365 nm) per IEST-STD-1246E.
8.3 PACKING
The Contractor shall provide an acceptable hardware case that protects the hardware appropriately, such as a Pelican case or similar. Each RPO IRCam shall have its own individual hardware case. While in the hardware case, each RPO IRCam shall be double-bagged in heat-sealed, waterproof, vapor-proof, ESD-shielded, cleanroom compatible bagging (inner bag – nitrogen purged with humidity indicator; outer bag – humidity indicator). Pink poly ESD bagging is prohibited by NASA and is not acceptable. Each RPO IRCam lens and baffle assembly (if applicable) shall be covered when not in use.
8.4 SHIPPING
Multiple RPO IRCams, in their own hardware case, may be packed into a single shipping container. The shipping container shall include 5G, 10G and 20G shock indicators as well as humidity indicators. The Contractor shall document what action the Government is to take if the shock sensors have been tripped when hardware arrives at the Government receiving area. A copy of this document shall be included with shipping documentation.
The Contractor shall ship Freight On Board (F.O.B.) to Greenbelt, Maryland. The Contractor shall be responsible for any damage incurred during shipment.
9-1
9.0 ABBREVIATIONS AND ACRONYMS
Table 9-1: Acronym List
Abbreviation/ Acronym Definition
CAD Computer Aided Design
CDR Critical Design Review
CDRL Contract Data Requirements List
DID Data Item Deliverable
EDU Engineering Development Unit
EEE Electrical, Electronic and Electromechanical
EGSE Electrical Ground Support Equipment
EIDP End of Item Data Package
EMC Electromagnetic Compatibility
EMI Electromagnetic Interference
ESD Electrostatic Discharge
GEVS General Environmental Verification Standard
GFE Government Furnished Equipment
FRB Failure Review Board
GSFC Goddard Space Flight Center
ICD Interface Control Document
LEO Low Earth Orbit
MAR Mission Assurance Requirements
MGSE Mechanical Ground Support Equipment
MIPS Mandatory Inspection Points
MIUL Materials Identification and Usage List
MPE Materials & Process Engineer
MRB Material Review Board
MUA Material Usage Agreement
NGIN Next-Generation Integrated Network
OCR Optical Character Recognition
PCB Printed Circuit Board
PDF Portable Document Format
PDR Preliminary Design Review
PER Pre-Environmental Review
QA Quality Assurance
RFA Request For Action
RFP Request For Procurement
RPO Rendezvous Proximity Operations
PSR Pre-Ship Review
SOW Statement of Work
SRR System Requirements Review
SSCO Satellite Servicing Capabilities Office
TRR Test Readiness Review