Attachment B Specifications Section 26 13 00 SF6/High-Firepoint Fluids Insulated Pad-Mounted Switchgear
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| South_Island_Electric_Industry_Questions_96_ _97.pdf | ||
| South_Island_Electrical_Q A_94_ _95.pdf | ||
| NNG16591912E_Amendment_2.pdf | ||
| 33_77_19.00_40.pdf | ||
| Amendment 2 South Island Electrical.pdf | ||
| 26_12_19.10.pdf | ||
| NNG16591912E_Site_Visit_Sign_In_Sheet.pdf | ||
| NNG16591912E_NASA_Response_to_Industry_Questions_1_to_93.pdf | ||
| NNG16591912E_Amendment_1_.pdf | ||
| NNG16591912E_Attachment_C_Amendment_1.pdf | ||
| NNG16591912E_Attachment_B.pdf | ||
| NNG16591912E_Attachment_E.pdf | ||
| NNG16591912E_Attachment_D.pdf | ||
| NNG16591912E_Attachment_H.pdf | ||
| NNG16591912E_Notice_to_All_Bidders.pdf | ||
| NNG16591912E_Solicitation.pdf | ||
| NNG16591912E_Attachment_F.pdf | ||
| NNG16591912E_Attachment_A.pdf | ||
| NNG16591912E_Attachment_G.pdf | ||
| NNG16591912E_Attachment_C.pdf | ||
| NNG16591912E_Site_Visit_Instructions.pdf |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 26 13 00
SF6/HIGH-FIREPOINT FLUIDS INSULATED PAD-MOUNTED SWITCHGEAR
11/14
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM A167 (2011) Standard Specification for Stainless and Heat-Resisting Chromium-Nickel Steel Plate, Sheet, and Strip
ASTM D1535 (2014) Specifying Color by the Munsell System
ASTM D2472 (2000; R 2014) Standard Specification for Sulphur Hexafluoride
ASTM D6871 (2003; R 2008) Standard Specification for Natural (Vegetable Oil) Ester Fluids Used in Electrical Apparatus
INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)
IEEE 386 (2006; INT 1 2011) Standard for Separable Insulated Connector Systems for Power Distribution Systems Above 600V
IEEE C2 (2012; Errata 1 2012; INT 1-4 2012; Errata
2 2013; INT 5-7 2013; INT 8-10 2014; INT
11 2015; INT 12 2016) National Electrical Safety Code
IEEE C37.60 (2012) Standard Requirements for Overhead, Pad Mounted, Dry Vault and Submersible Automatic Circuit Reclosers and Fault Interrupters for Alternating Current Systems Up to 38 kV
IEEE C37.74 (2014) Standard Requirements for Subsurface, Vault, and Pad-Mounted Load-Interrupter Switchgear and Fused Load-Interrupter Switchgear for Alternating Current Systems Up to 38 kV
IEEE C57.12.28 (2014) Standard for Pad-Mounted Equipment
- Enclosure Integrity
IEEE C57.12.29 (2014) Standard for Pad-Mounted Equipment
- Enclosure Integrity for Coastal Environments
IEEE C62.11 (2012) Standard for Metal-Oxide Surge Arresters for Alternating Current Power Circuits (>1kV)
INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)
NETA ATS (2013) Standard for Acceptance Testing Specifications for Electrical Power Equipment and Systems
INTERNATIONAL ELECTROTECHNICAL COMMISSION (IEC)
IEC 61099 (2010; ED 2.0) Insulating Liquids - Specifications for Unused Synthetic Organic Esters for Electrical Purposes
IEC 62271-103 (2013; Corr 1 2013) High-Voltage Switchgear and Controlgear – Part 103:
Switches for Rated Voltages Above 1 Kv up to and Including 52 Kv
IEC 62271-111 (2012; ED 2.0) High Voltage Switchgear And Controlgear - Part 111: Automatic Circuit Reclosers and Fault Interrupters for Alternating Current Systems up to 38 kV
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2014; AMD 1 2013; Errata 1 2013; AMD 2 2013; Errata 2 2013; AMD 3 2014; Errata 3-4 2014; AMD 4-6 2014) National Electrical Code
NFPA 70B (2016) Recommended Practice for Electrical Equipment Maintenance
U.S. DEPARTMENT OF DEFENSE (DOD)
DOD 8500.01 (2014) Cybersecurity
DOD 8510.01 (2014) Risk Management Framework (RMF) for DoD Information Technology (IT)
UNDERWRITERS LABORATORIES (UL)
UL 467 (2013) Grounding and Bonding Equipment
1.2 RELATED REQUIREMENTS
Section 26 08 00 APPARATUS INSPECTION AND TESTING, applies to this section, with the additions and modifications specified herein.
1.3 DEFINITIONS
1.3.1 Switched Way
A switched way is considered a three-phase circuit entrance to the bus through a switch. For single-phase switches, it is a single-phase entrance to the bus through a switch.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Use the "S" classification only in SD-11 Closeout Submittals. The "S" following a submittal item indicates that the submittal is required for the Sustainability Notebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
Switchgear Drawings; G
SD-03 Product Data
SF6/High-Firepoint Fluid Insulated Pad-mounted Switchgear; G
Include data on switches and associated accessories with each submittal. Include manufacturer's information for each component, device and accessory provided with the equipment with each submittal.
Insulated High-Voltage Connectors; G
Surge Arresters; G
SD-06 Test Reports
Acceptance Checks and Tests; G
SD-07 Certificates
Paint Coating System; G
Cybersecurity; G
SD-09 Manufacturer's Field Reports
Switchgear design and production tests; G
SD-10 Operation and Maintenance Data
SF6/High-Firepoint Fluid Insulated Pad-mounted Switchgear, Data Package 5; G
Submit in accordance with Section 01 78 23 OPERATION AND
MAINTENANCE DATA.
1.5 QUALITY ASSURANCE
1.5.1 Switchgear Drawings
Furnish drawings that include, but are not limited to, the following:
a. Overall dimensions, weights, plan view, and front view
b. Ratings
c. Single-line diagram.
1.5.2 Paint Coating System
Submit IEEE C57.12.28 paint coating system performance requirement tests.
1.6 MAINTENANCE
1.6.1 SF6/High-Firepoint Fluid Insulated Pad-mounted Switchgear Operation and Maintenance
Submit Operation and Maintenance Manuals in accordance with Section 01 78 23
OPERATION AND MAINTENANCE DATA.
PART 2 PRODUCTS
2.1 SF6/HIGH-FIREPOINT FLUID INSULATED PAD-MOUNTED SWITCHGEAR
IEEE C37.74
2.1.1 Ratings and Test Requirements
The voltage rating of the switchgear must be [15.5 kV][27 kV][38 kV][as indicated]. Provide the corresponding ratings associated with the required switchgear voltage rating as follows:
Rated Maximum Voltage, kV 15.5
Rated Withstand Impulse Voltage, kV BIL 95
Continuous and Load Interrupting Current, A 600
Short-Time Current, kA rms Sym 12.5
[Short-Circuit interrupting Current,kA rms Sym
12.5
2.1.2 Switchgear Construction
Provide switchgear with switch contacts and cable entrance terminations contained in a sealed, dielectric-filled stainless steel tank. Switchgear must be shipped factory filled with appropriate levels of SF6 gas conforming to ASTM D2472 or less-flammable, high-firepoint biodegradable fluid conforming to ASTM D6871 and IEC 61099. Provide switchgear with front accessible terminations suitable for cables entering from below with manual operating provisions either mounted on the rear or capable of hookstick operation per IEEE C37.74. Switch contact positions for switched ways must be visible through viewing windows in the switchgear tank located adjacent to the manual operating provisions. Provide internal gas pressure gage or fluid level gage in viewable location from switch operating handle.
2.1.2.1 Pad-mounting Provisions
Provide enclosed switchgear suitable for installation on a concrete pad.
Fabricate switchgear support frame enclosure base enclosure] with ASTM A167 type 304 or 304L stainless steel. Enclosure base must include any part of the switchgear enclosure that is within 3 inches of concrete pad. Paint enclosure including base ASTM D1535 Munsell 7GY3.29/1.5 green. Comply with IEEE C57.12.28 for the paint coating system regardless of equipment material.
2.1.3 Load Interrupting Switched Ways
2.1.3.1 Three-Pole Group Operated Switched Ways
Provide three-pole group operated load interrupting switched ways as indicated.
2.1.4 2.1.5 Dead-Front High-Voltage Bushings
IEEE 386. 15 kV, 95 kV BIL. Provide 600 ampere one-piece deadbreak apparatus bushings for each switched way.
Provide insulated standoff bushings for parking of energized load-break connectors on each parking stands.
2.2 Insulated High-Voltage Connectors
IEEE 386. Provide corresponding connector for each switched way. Provide a grounding eye and test point on each connector.
a. 600 Ampere deadbreak connector ratings: Voltage: 15 kV, 95 kV BIL.
Short time rating: 25,000 rms symmetrical amperes. Provide connectors with 200 ampere bushing interface.
2.3 Surge Arresters
IEEE C62.11, rated 9 kV as indicated, fully shielded, dead-front, metal-oxide-varistor, elbow type with resistance-graded gap, suitable for plugging into inserts. Provide arresters on switched ways as indicated.
2.4 SOURCE QUALITY CONTROL
2.4.1 Switchgear Design and Production Tests
Furnish reports which include results of design and production tests performed according to IEEE C37.74. Perform manufacturer production tests on each switchgear assembly to ensure that design performance is maintained in production.
PART 3 EXECUTION
3.1 INSTALLATION
Conform to IEEE C2, NFPA 70, and to the requirements specified herein.
3.2 GROUNDING
NFPA 70 and IEEE C2, except provide grounds and grounding systems with a resistance to solid earth ground not exceeding 25 ohms. When work, in addition to that indicated or specified, is directed to obtain the specified ground resistance, the provision of the contract covering "Changes" applies.
3.2.1 Grounding Electrodes
Provide driven ground rods as specified in at each corner of switchgear pad as indicated.
3.2.2 Switchgear Grounding
Connect #4/0 bare copper conductor ground ring, not less than 24 inches below grade, to the upper end of the ground rods by exothermic welds or compression connectors. Provide #4/0 bare copper conductors connecting the switchgear grounding provisions to two different ground rods.
3.2.3 Connections
Make joints in grounding conductors and ground ring by exothermic weld or compression connector. Install exothermic welds and compression connectors as specified in Section 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION.
3.2.4 Grounding and Bonding Equipment
UL 467, except as indicated or specified otherwise.
3.3 FIELD QUALITY CONTROL
3.3.1 Performance of Acceptance Checks and Tests
Perform in accordance with the manufacturer's recommendations, NFPA 70B, NETA ATS and referenced ANSI standards.
Include the following visual and mechanical inspections and electrical tests, performed in accordance with NETA ATS.
3.3.1.1 Switchgear
a. Visual and Mechanical Inspection
1. Compare equipment nameplate information with specifications and approved shop drawings.
2. Inspect physical and mechanical condition.
3. Check for proper anchorage, alignment, required area clearances, and grounding.
4. Perform mechanical operator tests in accordance with manufacturer's instructions.
5. Verify that insulating SF6 gas pressure or dielectric fluid level is correct.
6. Inspect all indicating devices for proper operation.
b. Electrical Tests
1. Perform contact-resistance tests.
3. Perform insulation-resistance tests.
4. Perform an over-potential test on each switched way pole with the switched way in the open position in accordance with the manufacturer's instructions.
3.3.1.2 Grounding System
a. Visual and Mechanical Inspection
Inspect ground system for compliance with contract plans and specifications.
b. Electrical Tests
1. Perform ground-impedance measurements utilizing the fall-of-potential method. On systems consisting of interconnected ground rods, perform tests after interconnections are complete.
On systems consisting of a single ground rod perform tests before any wire is connected. Take measurements in normally dry weather, not less than 48 hours after rainfall. Use a portable ground resistance tester in accordance with manufacturer's instructions to test each ground or group of grounds. Use an instrument equipped with a meter reading directly in ohms or fractions thereof to indicate the ground value of the ground rod or grounding systems under test.
2. Submit the measured ground resistance of each ground rod and grounding system, indicating the location of the rod and grounding system. Include the test method and test setup (i.e., pin location) used to determine ground resistance and soil conditions at the time the measurements were made.
3.3.2 Follow-Up Verification
Upon completion of acceptance checks and tests, show by demonstration in service that devices are in good operating condition and properly performing the intended function. Perform each test function not less than three times. As an exception to requirements stated elsewhere in the contract, notify the Contracting Officer five working days in advance of the dates and times for checks and tests.
-- End of Section --