Attachment E - Financial Management Reporting Requirement

View the file

Other files for this federal contract opportunity

Other files attached to High Performance Spaceflight Computing (HPSC) Processor Chiplet, newest first.
File Type Posted
Attachment_B_-_Contractor_Proposed_Enhancements.pdf PDF
Attachment_D_-_Small_Business_Subcontracting_Plan.pdf PDF
Attachment_A-1_-_Requirements_Document.pdf PDF
Attachment_C_-_Organizational_Conflicts_of_Interest_(OCI)_Avoidance_Plan.pdf PDF
Exhibit_12_-_Past_Performance_Questionnaire_Instructions.pdf PDF
Amendment__1.pdf PDF
HPSC_Cover_Letter.pdf PDF
HPSC_RFP_Cover_Page_-_SF33.pdf PDF
HPSC_-_Cost_Exhibits_.pdf PDF
Attachment_A-1_HPSC_Requirements.pdf PDF
Attachment_A_-_HPSC_SOW.pdf PDF
HPSC_PastPerfQues.pdf PDF
HPSC_RFP_Sections_B_-_M.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT E

FINANCIAL MANAGEMENT REPORTING REQUIREMENTS

Financial Management Reports shall be submitted by the Contractor on the NASA 533 series reports, in accordance with the instructions on the reverse of the forms, NASA

Procedural Requirements NPR 9501.2E entitled "NASA Contractor Financial

Management Reporting,” dated May 27, 2011, and additional instructions issued by the

Contracting Officer.

a. Level of Detail

An individual 533 Report shall be provided for each Task Order in addition to a cumulative 533 Report summarizing all Task Orders issued. The reports shall contain a breakdown of hours and costs by the elements of cost categories listed in Section d below.

b. Variance Narrative Reporting

In accordance with Section 3.6 of NPR 9501.2, the Contractor shall include a narrative explanation for variances exceeding plus or minus 10% percent between the Total Direct

Labor Hours (prime and subcontractors) and/or Total Estimated Cost amount shown in the prior month and the Actual Total Direct Labor Hours and/or Actual Total Cost amount shown in the current month for each individual task order. (For example, the

Total Estimated Cost amount shown for June in column 8a in the May NF 533M and the

Actual June Total Cost amount shown in column 7a in the June NF 533M.)

Each task order variance narrative shall explain the: (1) reason for the variance, (2) impact(s) on the individual task order, and (3) specific corrective action(s) being taken or to be taken.

c. Distribution

The Contractor shall distribute 533 reports to each addressee indicated in the contract clause entitled, "Financial Management Reporting." The Contractor shall submit an initial report in the NF 533Q format within 30 working days after contract award.

After the initial report, the NF 533M reports shall be distributed not later than the fifteenth (15th) working day following the close of the contractors' monthly accounting period. The 533Q reports shall be distributed not later than the fifteenth 15th) day of the month preceding the quarter being reported. The NF 533M need not be submitted in months in which an NF 533Q is submitted.

d. Reporting Requirements

Each individual report shall, at a minimum, provide cost data by the following elements of cost categories:

1. Prime Direct Labor Hours:

(List applicable labor categories)

Total Prime Direct Labor Hours

2. Subcontractor Direct Labor Hours:

Subcontractor A Direct Labor Hours

Subcontractor B Direct Labor Hours

Subcontractor C Direct Labor Hours

Total Subcontractors Direct Labor Hours

3. Total Prime and Subcontractors Direct Labor Hours

4. Prime Direct Labor Costs:

Total Prime Direct Labor Costs

5. Prime Overhead Expense

6. Other Direct Costs (ODCs):

a. Subcontracts (list separately, Subcontractor A, B, C, etc.)

b. Material

c. Travel

d. Other (specify)

Total ODCs

7. Subtotal (Direct Labor, Overhead & ODCs)

8. G&A Expense

9. Total Estimated Cost