This is a technical specification document for the City of North Miami Beach Public Library Restroom Remodel project (Project No. NMB-FY24-040), prepared by EXP U.S. Services Inc. as of September 4, 2025. The specifications detail the complete plumbing, HVAC, and electrical systems required for the renovation of existing public restroom facilities, including the addition of two unisex restrooms and renovation of existing men's and women's restrooms. The document establishes 100% construction-level requirements across multiple divisions, with sealed responses due by 3:00 pm on Monday, November 16, 2026, through the City's eProcurement Portal. The specifications require comprehensive coordination among all trades, adherence to local codes and standards (including NSF 61 and NSF 372 for potable water components), and detailed shop drawing submittals organized by specification section prior to material procurement and installation.
The technical specifications mandate that all plumbing components meet premium efficiency and lead-free requirements, with specific provisions for dielectric fittings to prevent corrosion in the corrosive coastal environment, stainless steel hardware for certain applications, and comprehensive testing and commissioning procedures. All contractors must provide detailed maintenance manuals, operating instructions, and factory-trained personnel for equipment startup within 30 days of completion. The specifications require that contractors conduct pre-bid site visits to identify existing conditions, verify access for equipment installation, and address any conflicts with existing infrastructure. Pricing must account for temporary services where extended system shutdowns are necessary, emergency drain pans for equipment located above electrical or IT rooms, and all associated firestopping, insulation, and waterproofing requirements. The contractor is responsible for all demolition costs, removal and disposal of existing materials, cleaning and restoration of retained equipment, and coordination with the Owner regarding phasing requirements and shutdown scheduling with a minimum 14-day advance notice.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Technical Specifications
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY - RESTROOM REMODEL
PROJECT NO. NMB-FY24-040
100% CONSTRUCTION DOCUMENTS
SEPTEMBER 4, 2025
VOLUME - 2
EXP U.S. SERVICES INC.
September 4, 2025
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
PROJECT NO.
NMB-FY24-040
TABLE OF CONTENTS
DIVISION 220000 – PLUMBING
220500 COMMON WORK RESULTS FOR PLUMBING
220510 PLUMBING DEMOLITION AND ALTERATIONS
220513 COMMON MOTOR REQUIREMENTS FOR PLUMBING EQUIPMENT
220519 METERS AND GAGES FOR PLUMBING PIPING
220523 GENERAL-DUTY VALVES FOR PLUMBING PIPING
220529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
220553 IDENTIFICATIONS FOR PLUMBING PIPING AND EQUIPMENT
220700 PLUMBING INSULATION
221116 DOMESTIC WATER PIPING
221119 DOMESTIC WATER PIPING SPECIALTIES
221123 DOMESTIC WATER PUMPS
221316 SANITARY WASTE AND VENT PIPING
221319 SANITARY WASTE AND VENT PIPING SPECIALTIES
223300 ELECTRIC DOMESTIC WATER HEATERS
224000 PLUMBING FIXTURES
DIVISION 230000 – HEATING, VENTILATING AND AIR CONDITIONING (HVAC)
230500 COMMON WORK RESULTS FOR HVAC
230510 HVAC DEMOLITION AND ALTERATIONS
230511 HVAC AIR DUCT CLEANING
230513 COMMON MOTOR REQUIREMENTS FOR HAVAC EQUIPMENT
230529 HANGERS AND SUPPORTS FOR HVAC
230553 IDENTIFICATIONS FOR HVAC PIPING AND EQUIPMENT
230593 TESTING, ADJUSTING, AND BALANCING FOR HVAC
230700 HVAC INSULATION
233005 BIM COORDINATION DRAWINGS
233113 METAL DUCTS
233300 AIR DUCT ACCESSORIES
233400 FANS
233713 DIFFUSERS REGISTERS AND GRILLES
DIVISION 260000 – ELECTRICAL
260500 COMMON WORK RESULTS FOR ELECTRICAL
260510 SELECTIVE ELECTRICAL DEMOLITION
260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
260533 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS
260544 SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING
260553 IDENTIFICATIONS FOR ELECTRICAL SYSTEMS
260800 COMMISSIONING OF ELECTRICAL SYSTEMS
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
DIVISION 260000 – ELECTRICAL (CONT’N)
260923 LIGHTING CONTROL DEVICES
262726 WIRING DEVICES
262816 ENCLOSED SWITCHES AND CIRCUIT BREAKERS
265100 INTERIOR LIGHTING
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 1
SECTION 220500 - COMMON WORK RESULTS FOR PLUMBING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
B. Division 07 Section “Penetration Firestopping” for piping, conduit and wiring penetration firestopping installed in fire-resistance-rated walls, horizontal assemblies and smoke barriers.
C. Division 07 "Roof Accessories" and "Sheet Metal Flashing and Trim" for piping, conduit and equipment supports penetrating roofs, exterior walls and floors including flashings, curbs, sealants, clamps and vents.
1.2 SUMMARY
A. This Section includes the following:
1. Piping materials and installation instructions common to most piping systems.
2. Transition fittings.
3. Dielectric fittings.
4. Grout.
5. Flashing Materials.
6. Equipment installation requirements common to equipment sections.
7. Painting and finishing.
8. Concrete bases.
9. Supports and anchorages.
1.3 DEFINITIONS
A. Accessible Fixture: Plumbing fixture that can be approached, entered, and used by people with disabilities.
B. Actual Air: Air delivered at air-compressor outlet. Flow rate is compressed air delivered and measured in ACFM.
C. Concealed, Exterior Installations: Concealed from view and protected from weather conditions and physical contact by building occupants but subject to outdoor ambient temperatures. Examples include installations within unheated shelters.
D. Concealed, Interior Installations: Concealed from view and protected from physical contact by building occupants. Examples include above ceilings and in chases.
E. D.I.S.S.: Diameter-index safety system.
F. Exposed, Interior Installations: Exposed to view indoors. Examples include finished occupied spaces and mechanical equipment rooms.
G. Exposed, Exterior Installations: Exposed to view outdoors or subject to outdoor ambient temperatures and weather conditions. Examples include rooftop locations.
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 2
H. Finished Spaces: Spaces other than mechanical and electrical equipment rooms, furred spaces, pipe chases, unheated spaces immediately below roof, spaces above ceilings, unexcavated spaces, crawlspaces, and tunnels.
I. Fitting: Device that controls the flow of water into or out of the plumbing fixture. Fittings specified in this Section include supplies and stops, faucets and spouts, shower heads and tub spouts, drains and tailpieces, and traps and waste pipes. Piping and general-duty valves are included where indicated.
J. High-Pressure Compressed-Air Piping: System of compressed-air piping and specialties operating at pressures between 150 and 200 psig (1035 and 1380 kPa).
K. Lead Free: Refers to the wetted surface of pipe, fittings and fixtures in potable water systems that have a weighted average lead content ≤0.25% per Safe Drinking Water Act
NSF 372.
L. Low-Pressure Compressed-Air Piping: System of compressed-air piping and specialties operating at pressures of 150 psig (1035 kPa) or less.
M. Low Voltage: As defined in NFPA 70 for circuits and equipment operating at less than 50 V or for remote-control, signaling power-limited circuits.
N. LP Gas: Liquefied-petroleum fuel gas.
O. Plumbed Emergency Plumbing Fixture: Fixture with fixed, potable-water supply.
P. Standard Air: Free air at 68 deg F and 1 atmosphere before compression or expansion and measured in SCFM.
Q. Tepid: Moderately warm.
R. The following are industry abbreviations:
1. ABS: Acrylonitrile-butadiene-styrene plastic.
2. BR: Butyl rubber.
3. Buna-N: Nitrile rubber.
4. CPVC: Chlorinated polyvinyl chloride plastic.
5. CWP: Cold working pressure;
6. EPDM: Ethylene-propylene-diene terpolymer rubber.
7. FOG: Fats, oils, and grease.
8. FPM: Vinylidene fluoride-hexafluoro propylene copolymer rubber.
9. FRP: Fiberglass reinforced plastic.
10. HDPE: High-density polyethylene plastic.
11. LPG: Liquefied-petroleum gas
12. MSS: Manufacturers Standardization Society for The Valve and Fittings Industry Inc.
13. NBR: Acrylonitrile-butadiene rubber.
14. NRS: Non-rising stem.
15. OS&Y: Outside screw and yoke.
16. PE: Polyethylene plastic.
17. PP: Polypropylene plastic.
18. PTFE: Polytetrafluoroethylene plastic.
19. PUR: Polyurethane plastic.
20. PVC: Polyvinyl chloride plastic.
21. PVDF: Polyvinylidene fluoride plastic.
22. SWP: Steam working pressure.
23. TFE: Tetrafluoroethylene plastic.
24. TPE: Thermoplastic elastomer.
25. uPVC: Unplasticized Polyvinyl chloride plastic.
26. WAGD: Waste anesthetic gas disposal.
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 3
1.4 SCOPE
A. Drawings and Specifications form complementary requirements; provide work specified and not shown, and work shown and not specified as though explicitly required by both.
Although work may not be specifically shown or specified, provide supplementary or miscellaneous items, appurtenances, devices and materials obviously necessary for a sound, secure and complete installation.
B. It is the intent that these Specifications and associated Drawings establish minimum requirements for products and equipment with the intent to provide plumbing systems finished, tested and ready for operation. Incidental detail that is not shown or specified, but necessary for proper installation and operation shall be included in the work and in these Contractor's estimates, the same as if specified. Locations of all equipment and material shall be adjusted at no extra cost to the Owner, to accommodate the work interferences anticipated and/or encountered. Prior to installation, determine the exact route and location of each pipe and piece of equipment to minimize conflicts with other trades.
C. This project will be phased, as defined by the Owner. This may necessitate the provision of temporary valving and capping of Plumbing utilities. All associated appurtenances with the utilities shall be provided as part of this project in the appropriate phase coordinated with Owner’s phasing requirements.
D. Information and components shown on riser diagrams but not shown on plans, and vice versa, shall be provided as if expressly required on both.
E. It is the requirement of these Contract Documents to have the contractors provide systems and components that are fully complete, operational and suitable for the intended use.
There may be situations in the documents where insufficient information exists to precisely describe a certain component or subsystem, or the routing of a component or its coordination with other building elements. In cases such as this, where the Contractor has failed to notify the Architect of the situation the Contractor shall include the specific components or subsystems with all parts necessary for the intended use, fully complete and operational, and installed in workmanlike manner either concealed or exposed per the design intent.
1.5 MODIFICATIONS IN LAYOUT
A. Drawings are intended to outline the scope of work required and are not intended to be installation drawings. Drawings are not intended to be absolutely precise; they are not intended to specify or to show every offset, fitting, and component nor do they show the exact routing and locations needed to coordinate with structure and other trades and to meet Architectural requirements. The purpose of the drawings is to indicate a systems concept, the main components of the systems, and the approximate geometrical relationships. Drawings do not necessarily show the exact routings and locations needed to fully coordinate with structure and other trades to meet Architectural requirements. Based on the systems concept, the main components, and the approximate geometrical relationships, the contractor shall provide all other components and materials necessary to make the systems fully complete and operational.
B. Unless specifically stated to the contrary, no measurement of a drawing derived by scaling shall be used as a dimension to work by. Dimensions noted on the drawings are subject to measurements of adjacent and previously completed work. Measurements shall be performed prior to the actual installation of equipment.
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 4
C. Prior to installation of visible material and equipment (including access panels) in finished spaces, review Architectural Drawings for desired locations and where not definitely indicated, request information from Architect.
D. Check Contract Documents, as well as, Submittals and Shop Drawings of all subcontractors to verify and coordinate spaces in which work of Divisions 21 through 28 will be installed.
E. Make reasonable modifications in layout and components needed to prevent conflict with work of other trades. Systems shall be run parallel with or perpendicular to major architectural and structural building elements.
F. Where conflicts or potential conflicts exist and engineering guidance is desired, submit sketch of proposed resolution to Architect for review and approval.
1.6 COORDINATION
A. Coordinate arrangement, mounting, and support of piping and equipment:
1. To maintain maximum headroom; all piping, duct, conduit and associated components to be as tight as possible to underside of structure to provide for ease of disconnecting the equipment with minimum interference to other installations.
2. To allow right of way for piping installed at required slope.
3. To be clear of obstructions and of the working and access space of other equipment.
B. Coordinate installation of required supporting devices and set sleeves in cast-in-place concrete, masonry walls, and other structural components as they are constructed.
C. Coordinate location of access panels and doors for electrical items that are behind finished surfaces or otherwise concealed. Access doors and panels are specified by the architect.
Locations of access doors are to be shown on coordination drawings and approved by the Architect prior to installation.
1.7 COORDINATION DRAWINGS
A. When included as part of the Contract Documents, there shall be full cooperation and coordination of all specialty trades.
B. This Division’s contractors shall comply fully with the requirements set forth in the Division 23 “BIM Coordination Drawings” specification section.
1.8 RECORD DOCUMENTS
A. Record Drawings are specified in Division 01 Section "Project Record Documents."
B. The Contractor shall keep a detailed up-to-date record, of the manner and location in which installations are actually made, indexing pipe, valve, and piece of equipment. Record documents are to reflect all changes in work including change orders, field directives, addenda from bid set of Contract Documents, request for information responses, etc. Upon completion of the project, the contractor shall modify the project electronic drawing and specification files to incorporate this information. Modified
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 5
documents shall be turned over to the Owner in both electronic and hard paper copy formats. Record drawings shall also include:
1. Locations of buried piping or similar items. Include buried depth.
2. Field changes of dimension or detail.
3. Changes made by field order or change order.
4. Details not on original contract drawings.
1.9 MAINTENANCE MANUALS AND OPERATING INSTRUCTIONS
A. Obtain at time of purchase of equipment, three copies of operation, lubrication and maintenance manuals for all items. Assemble literature in a coordinated manual. Manual shall contain names and addresses of manufacturers and local representatives who stock or furnish repair parts for items or equipment.
B. The manuals shall include the following and shall have an index of contents and tabs for each Specification Section and each piece of equipment specified in that Section and be provided in the order listed below, per Specification Section.
1. Copies of all approved submittals/shop drawings.
2. Manufacturer's operating and maintenance instructions and parts lists of all items or equipment. Where manufacturer's data includes several types or models, the applicable type or model shall be clearly designated.
3. Startup and shutdown procedures.
4. Flow diagrams.
5. Test records.
6. Wiring diagrams.
7. Lubrication instructions detailing type of lubricant, amount, and intervals recommended by manufacturer for each item of equipment.
8. Owner's written acknowledgement of satisfactory completion of instruction period.
C. Furnish three copies of manuals to Architect for approval and distribution to Owner. Deliver manuals no less than 30 days prior to acceptance of equipment to permit Owner's personnel to become familiar with equipment and operation prior to acceptance.
D. Operating instructions: Upon completion of installation or when Owner accepts portions of building and equipment for operational use, instruct Owner's operating personnel in any or all parts of all systems. Factory-trained personnel shall perform instructions.
1.10 SUBMITTAL PROCEDURE AND FORMAT
A. This Article supplements Division 1.
B. Submittal Cover Sheet
1. Submittal data for each product shall include a copy of the following cover sheet completely filled out. Incomplete or incorrect cover sheet submittal shall constitute reason for rejection.
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 6
2. Material submittals shall be organized by specification section. All items requiring a submittal per each specification section shall be combined into a single submittal.
Provide each section/item within that submittal with its own cover sheet labeled and tagged to match the drawings.
C. Contractor shall submit a schedule specifically indicating which piping material will be utilized in each application.
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 7
SHOP DRAWING COVER SHEET
PROJECT: CONTRACTOR:
DIVISION NO.: SECTION NO.:
DESCRIPTION:
CONTRACT DRAWING REFERENCE NO:
EQUIPMENT TAG:
SUBMISSION (CIRCLE ONE): FIRST, SECOND, THIRD, FOURTH
DATE:
INFORMATION AND CHECKLIST
1. Contractor's Log #ID
2. Name, address, and phone number of supplier.
3. Are all specified or scheduled items included and exactly match scheduled/specified items?
Yes No
4. Is this item a substitution? Yes No
5. Are deviations clearly identified? Yes No
6. Does equipment fit space shown on construction documents, coordination drawings, and actual field conditions?
Yes No
7. Has support, erection, weights, and installation been coordinated with all trades?
Yes No
8. Does the proposed installation void warranties and/or violate UL or code requirements?
Yes No
9. Does this material/equipment add expense to any other trade or project costs?
Yes No
10. Does equipment require interface with other trades?
List divisions and specifics requiring coordination?
Yes No
11. Is control interface coordinated? Yes No
12. List electrical characteristics (V/Ph/A)
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 8
D. ]Shop Drawings showing layouts of systems shall contain sufficient plans, elevations, sections, details and schematics to describe work clearly. They shall be 1/4 inches = 1 foot 0 inch scale unless specified otherwise.
E. Shop drawings and submittals showing manufacturer's product data shall contain detailed dimensional drawings, accurate and complete description of materials of construction, manufacturer's published performance characteristics and capacity ratings (performance data, alone, is not acceptable), electrical requirements and wiring diagrams. Drawings shall clearly indicate location (terminal block or wire number), voltage and function for all field terminations, and other information necessary to demonstrate compliance with all requirements of Contract Documents.
F. Provide shop drawing submittals showing details of piping connections to ALL equipment.
If connection details are not submitted and connections are found to be installed incorrectly in the field, this contractor shall reinstall them within the original contract price.
G. Shop drawings for different systems and equipment shall be bound separately by specification section as indicated above and not bound by manufacturer. Each separate submittal shall have its own transmittal and cover letter. Submittals which contain different specification section systems bound together may be returned un-reviewed for re-submittal.
1.11 QUALITY ASSURANCE
A. Steel Support Welding: Qualify processes and operators according to AWS D1.1, "Structural Welding Code--Steel."
B. Steel Pipe Welding: Qualify processes and operators according to ASME Boiler and Pressure Vessel Code: Section IX, "Welding and Brazing Qualifications."
1. Comply with provisions in ASME B31 Series, "Code for Pressure Piping."
2. Certify that each welder has passed AWS qualification tests for welding processes involved and that certification is current.
C. All piping materials shall bear label, stamp, or other markings of specified testing agency, including but not limited to Underwriters Laboratory (UL) and the Cast Iron Soil Pipe Institute (CISPI).
D. Electrical Characteristics for Plumbing Equipment: Equipment of different electrical characteristics may be furnished provided such proposed equipment is approved in writing and connecting electrical services, circuit breakers, and conduit sizes are appropriately modified at the contractor’s expense. If minimum energy ratings or efficiencies are specified, equipment shall comply with requirements.
E. All electrical components, devices and accessories shall be listed and labeled as defined in NFPA 70, Article 100, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use. Skid-mounted or packaged assemblies shall be listed and labeled as an assembly, not just the individual components.
F. Fire-Resistance Ratings: Where indicated, provide penetration firestopping devices tested for fire resistance per ASTM E 814 by a testing agency acceptable to authorities having jurisdiction. Indicate design designations from UL's "Fire Resistance Directory."
G. Installer Qualifications:
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 9
1. Pressure-Seal Joining Procedure for Copper Tubing: Qualify operators according to training provided by Viega; Plumbing and Heating Systems.
2. Pressure-Seal Joining Procedure for Steel Piping. Qualify operators according to training provided by Victaulic Company.
3. Brazing: Qualify processes and operators according to ASME Boiler and Pressure Vessel Code: Section IX, "Welding and Brazing Qualifications," or to AWS B2.2, "Standard for Brazing Procedure and Performance Qualification."
4. Welding: Qualify processes and operators according to ASME Boiler and Pressure Vessel Code: Section IX.
5. A factory-trained representative shall provide on-site training for the contractor’s field personnel in the proper installation of all mechanical type joint products within any piping system. The representative shall periodically visit the job site to ensure best practices in grooved joint installations are being followed. A distributor’s representative is not considered qualified to conduct the training
H. NSF Standard: Comply with NSF 61, “Drinking Water System Components – Health Effects,” for all components, including piping, equipment, and fixture material that will be in contact with potable water. Comply with NSF 14, "Plastics Piping Components and Related Materials," for plastic domestic water piping components.
1. All plumbing components, including but not limited to piping, valves, backflow preventers, fixtures, etc that are connected to the domestic water system which convey water to be used for human consumption shall meet the NSF-372, ‘Lead- Free’ requirements. Items not intended to dispense water for human consumption such as flush valves, tub fills, shower valves, or piping accessories connected to non-potable water systems, are not required to meet the ‘Lead Free’ requirements.
I. Acceptable Manufacturers
1. The Engineer’s design for each product is based on the manufacturer listed in the schedule or shown on the drawings. In Part 2 of some technical specifications, other manufacturers are listed as being acceptable. The listing of a manufacturer as acceptable does not imply automatic approval. It is the sole responsibility of the Contractor to ensure that any submittals made are for products that meet or exceed the specifications included herein. These are acceptable only if, as a minimum, they:
a. Meet all performance criteria listed in the schedules and outlined in the specification.
b. Have identical operating characteristics to those called for in the specification.
For example, a two-stroke diesel generator will not be acceptable if a four-stroke model is specified.
c. Fit within the available space it was designed for, including space for maintenance and component removal, with no modification to either the space or the product. Clearances to walls, ceilings and other equipment will be at least equal to those shown on the design drawings. The fact that a manufacturer’s name appears as acceptable shall not be taken to mean that the Engineer has determined that the manufacturer’s products will fit within the available space - this determination is solely the responsibility of the contractor.
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 10
d. Products must adhere to all architectural considerations including but not limited to: being of the same color as the product scheduled or specified, fitting within architectural enclosures and details, and for diffusers, lighting and plumbing fixtures - being the same size and of the same physical appearance as scheduled or specified products.
e. All equipment shall be labeled or listed by the National Board of Underwriters Laboratories (U.L.) where such labeling or listing exists for such material.
J. All components within a single plumbing system shall be compatible with one another per the manufacturer(s).
K. All individual components in each plumbing system shall be from a single manufacturer.
1.12 TEMPORARY SERVICES/CONTINUITY OF UTILITY SERVICES
A. In the absence of specific requirements in Division 1, comply with the following procedures for shut-downs.
B. Provide temporary services where project construction schedule requires extended shut downs of existing equipment and/or systems. Temporary services include the necessary equipment and/or systems to maintain continuity of services. Extended shut downs are interruptions of existing services for a period of time longer than that acceptable to the Owner.
C. Contractor shall coordinate any shutdowns of existing systems as follows:
1. Give proper notice to Owner when making shutdowns; a minimum of fourteen full days is required.
2. Minimize timeline of shutdowns of any system.
3. Provide temporary services where required and perform shutdowns and tie-ins at a time convenient to Owner.
4. Contractor shall be responsible for completing and filing the Owner's shutdown notice questionnaire.
5. Perform required survey and inspection work required by the notice for shutdown.
6. All life safety systems shall be returned to service at the end of each work day, when work is being performed on the systems. It is the responsibility of the Contractor to provide all associated appurtenances necessary to ensure that the systems are in proper working condition at all times.
1.13 DELIVERY, STORAGE, AND HANDLING
A. Store ALL plastic piping and valves protected from direct sunlight. Support to prevent sagging and bending.
B. Protect equipment/materials from damage during shipping, storage, handling and installation. Deliver equipment/materials to the site in manufacturer’s original, unopened containers and packaging, with labels clearly indicating manufacturer and material.
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 11
C. The Contractor shall provide for enclosed storage, when equipment/materials are stored on-site and prior to building “dry-in”, to prevent any damage resulting from inclement weather or construction traffic. Specialties shall not be stored outdoors.
D. Equipment/materials, stored or installed, found to be damaged shall be replaced with new by the Contractor, to the satisfaction of the Owner and at no additional expense. Do not store equipment with PVC material with exposure to direct sunlight.
E. Deliver fuel gas and medical gas pipes and tubes with factory-applied end caps. Maintain end caps through shipping, storage, and handling to prevent pipe end damage and to prevent entrance of dirt, debris, and moisture.
1.14 PERFORMANCE REQUIREMENTS
A. Contractor must adhere to the LEED specification section for VOC requirements for all materials including solvent cements and insulation adhesives. Additionally, contractor must abide to the fixture flow rates/volumes, third party certifications (i.e. Water Sense labeling) and any process fixture requirements.
1.15 CORROSIVE ENVIRONMENTS AND SERVICES
A. Corrosive Environments and Corrosive Services shall utilize piping and supports that will not corrode or oxidize due to the environment in which they are located nor due to the fluid contained within the piping. Unless otherwise noted in this spec, corrosive environments and corrosive services shall be defined as the following:
1. Animal Life Support Systems services and piping
2. In areas designated as “water treatment” or “wet”, including but not limited to: areas over and within 15'-0" of open water tanks, pools or basins; splash zones; submerged conditions; ozone rooms; chemical rooms; salt water environments; and other water treatment zones
3. Pool and fountain piping and equipment rooms.
4. Outdoors and within any open air structures within 1 mile of the coast.
5. Within water softener rooms and/or within 15’ of water softeners when sharing space/room with other equipment.
B. All piping services in corrosive environments utilizing flanged connections shall be provided with 316 stainless steel hardware including bolts, nuts and washers.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. In other Part 2 articles where subparagraph titles below introduce lists, the following requirements apply for product selection. This is applicable for all Division 22 sections.
1. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the manufacturers specified.
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 12
2. Manufacturers: Subject to compliance with requirements, provide products by the manufacturers specified.
2.2 PIPE, TUBE, AND FITTINGS
A. Refer to individual Division 22 piping Sections for pipe, tube, and fitting materials and joining methods.
2.3 JOINING MATERIALS
A. Refer to individual Division 22 piping Sections for special joining materials not listed below.
B. Pipe-Flange Gasket Materials: Suitable for chemical and thermal conditions of piping system contents.
1. ASME B16.21, nonmetallic, flat, asbestos-free, 1/8-inch (3.2-mm) maximum thickness unless thickness or specific material is indicated.
a. Full-Face Type: For flat-face, Class 125, cast-iron and cast-bronze flanges.
b. Narrow-Face Type: For raised-face, Class 250, cast-iron and steel flanges.
2. AWWA C110, rubber, flat face, 1/8 inch (3.2 mm) thick, unless otherwise indicated;
and full-face or ring type, unless otherwise indicated.
C. Flange Bolts and Nuts: ASME B18.2.1, carbon steel, unless otherwise indicated.
D. Solder Filler Metals: ASTM B 32, lead-free alloys. Include water-flushable flux according to
ASTM B 813.
E. Brazing Filler Metals: AWS A5.8, BCuP Series, copper-phosphorus alloys for general-duty brazing, unless otherwise indicated; and AWS A5.8, BAg1, silver alloy for refrigerant piping, unless otherwise indicated.
F. Welding Filler Metals: Comply with AWS D10.12 for welding materials appropriate for wall thickness and chemical analysis of steel pipe being welded.
G. Solvent Cements for Joining Plastic Piping:
1. ABS Piping: ASTM D 2235.
2. CPVC Piping: ASTM F 493.
3. PVC Piping: ASTM D 2564. Include primer according to ASTM F 656.
4. PVC to ABS Piping Transition: ASTM D 3138.
2.4 TRANSITION FITTINGS
A. AWWA Transition Couplings: Same size as, and with pressure rating at least equal to and with ends compatible with, piping to be joined.
1. Underground Piping NPS 1-1/2 (DN 40) and Smaller: Manufactured fitting or coupling.
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 13
2. Underground Piping NPS 2 (DN 50) and Larger: AWWA C219, metal sleeve-type coupling.
B. Plastic-to-Metal Transition Fittings: CPVC and PVC one-piece fitting with manufacturer's Schedule 80 equivalent dimensions; one end with threaded brass insert, and one solvent-cement-joint end.
C. Plastic-to-Metal Transition Adaptors: One-piece fitting with manufacturer's SDR 11 equivalent dimensions; one end with threaded brass insert, and one solvent-cement-joint end.
D. Plastic-to-Metal Transition Unions: MSS SP-107, CPVC and PVC four-part union. Include brass end, solvent-cement-joint end, rubber O-ring, and union nut.
E. Flexible Transition Couplings for Underground Nonpressure Drainage Piping:
ASTM C 1173 with elastomeric sleeve, ends same size as piping to be joined, and corrosion-resistant metal band on each end.
F. Plain End Pressure Piping to join plastic and stainless steel piping: Utilize double lip seal with bolt tightening pattern. Product shall be equal to Norma FGR Series.
2.5 DIELECTRIC FITTINGS
A. Description: Combination fitting of copper alloy and ferrous materials with threaded, solder-joint, plain, or weld-neck end connections that match piping system materials.
B. Insulating Material: Suitable for system fluid, pressure, and temperature.
C. Dielectric Unions: Pipe sizes 2 and smaller, factory-fabricated, union assembly, for 300-psig (1725-kPa) minimum working pressure at 180 deg F (82 deg C).
D. Dielectric Flanges: Pipe sizes 2-1/2” and larger, factory-fabricated, companion-flange assembly, for 300-psig (2070-kPa) minimum working pressure as required to suit system pressures.
E. Dielectric-Flange Kits: Companion-flange assembly for field assembly. Include flanges, full-face- or ring-type neoprene or phenolic gasket, phenolic or polyethylene bolt sleeves, phenolic washers, and steel backing washers.
1. Separate companion flanges and steel bolts and nuts shall have 150- or 300-psig (1035- or 2070-kPa) minimum working pressure where required to suit system pressures.
F. Dielectric Couplings: Galvanized-steel coupling with inert and noncorrosive, thermoplastic lining; threaded ends; and 300-psig (2070-kPa) minimum working pressure at 225 deg F (107 deg C).
G. Dielectric Nipples: Electroplated steel nipple with inert and noncorrosive, thermoplastic lining; plain, threaded, or grooved ends; and 300-psig (2070-kPa) minimum working pressure at 225 deg F (107 deg C).
2.6 GROUT
A. Description: ASTM C 1107, Grade B, nonshrink and nonmetallic, dry hydraulic-cement grout.
1. Characteristics: Post-hardening, volume-adjusting, nonstaining, noncorrosive, nongaseous, and recommended for interior and exterior applications.
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 14
2. Design Mix: 5000-psi (34.5-MPa), 28-day compressive strength.
3. Packaging: Premixed and factory packaged.
2.7 FLASHING MATERIALS
A. All piping, conduits and equipment supports through roofs shall be flashed. Flashing materials and methods shall be in accordance to the roof manufacturer’s and Division 07 requirements.
2.8 CEILING ACCESS AND ACCESS PANELS
A. Access panels are generally not shown on the drawings, but they are required to be provided by Contractor.
B. Furnish access panels for installation under other Sections valves or other items installed under this Division require access and are concealed in floor, wall, furred space or above ceiling. Access panels shall be by Milcor, Knapp, Nystorm or Inland Steel; coordinate selection with other Sections supplying similar access panels. Color of panel shall be selected by the Architect.
C. Access panels shall have same fire rating classification as surface penetrated. Rated access panels must have U.L. Label.
D. Final locations of access panels shall be approved by the architect and/or owner prior to installation.
E. All equipment or valves shall be located within two feet above the access panel.
2.9 SLEEVES
A. Below Ground applications:
1. For piping passing from dirt outside of the building footprint through a foundation/basement wall and into the building, a sleeve with an integral water stop shall be utilized. The sleeve can be either HDPE manufactured by GPT or APS, Gal- Vo-Plast by APS, or approved equal. The sleeve shall be cast into the pour of the structure.
2. When piping is passing from dirt outside of the building footprint to dirt under the building through a structural element, the water-stop on the sleeve is not required. In this application, the sleeve can be either cast iron or PVC piping.
3. Between the carrier piping and the sleeve, a mechanical seal, equal to that manufactured by GPT Link Seal, shall be utilized. Select the number of interlocking rubber links required to make installation watertight.
B. Above ground piping passing through concrete floors:
1. Cast in place sleeves: Piping passing through a floor shall be provided with a sleeve with an integral fire and water-stopping in one device equal to Holdrite Hydroflame.
The sleeve shall be cast into the pour of the structure.
a. If utilizing Holdrite Hydroflame type sleeves, the sleeve size must be selected based on the nominal pipe size without insulation to ensure that
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 15
the water stopping seal is tight up against the pipe. Insulation can then be extended into either end of the sleeve, butting up to the water stop.
b. At the contractor’s option, the sleeve with integral water stop can be HDPE manufactured by GPT or APS, Gal-Vo-Plast by APS, or approved equal. The sleeve shall be cast into the pour of the structure. This method requires separate firestopping by the contractor, and the extension of the sleeve a minimum of 1.5” above the deck to act as the waterstop.
2. Sleeves for core-drilled locations: The annular space between the piping and the core shall be provided with mechanical seals equal to that manufactured by GPT Link Seal. Select the number of interlocking rubber links required to make installation watertight.
3. Note: Sleeves are only required for elevated floors. Slab on grade do not require sleeves when a water proofing membrane is not utilized.
C. Above ground piping passing through concrete walls:
1. All piping passing through a concrete wall shall be sleeved with either steel or cast iron piping.
PART 3 - EXECUTION
3.1 PRE-BID SITE VISIT
A. Before submitting bid, visit and carefully examine site to identify existing conditions and difficulties that will affect work of this division. No extra payment will be allowed for additional work caused by unfamiliarity with site conditions that are visible or readily construed by an experienced observer.
B. Contractor shall visit job site to familiarize himself with the specific location of the new equipment installations in existing areas, to ensure there is adequate access for the installation of equipment. All entries, pathways, corridors, stairwells, etc., that may be used to install equipment shall be investigated. All existing conditions and potential obstructions that may impede access and installation shall be addressed prior to equipment purchasing/ordering.
C. The documentation of existing conditions was derived from As-Built documents and are in part unverified. Actual existing conditions shall be verified prior to commencement of work.
3.2 PIPING SYSTEMS - COMMON REQUIREMENTS
A. Install piping according to the following requirements and Division 22 Sections specifying piping systems.
B. Install all piping, systems, equipment, etc. per local code and per the local authority having jurisdiction’s (AHJ) requirements. Should any part or component of the drawings or specifications conflict with the local code requirements, the local code requirements shall prevail. The contractor shall inform the design team immediately of any code conflicts.
Where the specification are more stringent than any code or standard, the specifications shall be followed.
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 16
C. Drawing plans, schematics, and diagrams indicate general location and arrangement of piping systems. Indicated locations and arrangements were used to size pipe and calculate friction loss, expansion, pump sizing, and other design considerations. Install piping as indicated unless deviations to layout are approved on Coordination Drawings.
D. Install piping in concealed locations, unless otherwise indicated and except in equipment rooms and service areas.
E. Install piping indicated to be exposed and piping in equipment rooms and service areas at right angles or parallel to building walls. Diagonal runs are prohibited unless specifically indicated otherwise. Exposed surface mounted piping subject to potential damage shall be metallic.
F. To maintain maximum headroom, all piping, duct, conduit, and associated components shall be installed as tight as possible to underside of deck/structure to provide for ease of disconnecting the equipment with minimum interference to other installations.
G. Install piping above accessible ceilings to allow sufficient space for ceiling panel removal.
H. Install piping to permit valve servicing. No valving shall be located more than 24” above the access panel or removable ceiling panels. Provide necessary fittings and pipe drops, bends, etc to ensure all valving is accessible.
I. Install piping at indicated slopes.
J. Install piping free of sags and bends.
K. Install fittings for changes in direction and branch connections.
L. Install piping to allow application of insulation.
M. Select system components with pressure rating equal to or greater than system operating pressure.
N. Fire-Resistance-Rated Penetrations, Horizontal Assembly Penetrations, and Smoke-Barrier
Penetrations: Maintain indicated fire or smoke rating of walls, partitions, ceilings, and floors at pipe, conduit and wiring penetrations. Seal penetrations with fire- and smoke-stop materials. Refer to Division 07 for firestopping and fill materials.
O. Waterproof Penetrations: Maintain integrity of waterproof roof, wall and floor penetrations for pipe, conduit and equipment support penetrations. Seal penetrations with waterproof materials with clamps, sleeves, flashings, pipe boots and/or pipe curb assemblies as detailed or specified. Refer to Division 07 for waterproofing methods and materials when not specified in this section.
P. Verify final equipment locations for roughing-in.
Q. Perform work and provide material and equipment as shown on Drawings and/or as specified and/or indicated in this Section of the Specifications. Completely coordinate work with work of other trades and provide a complete and fully functional installation.
R. All exposed piping, fittings, valving, and devices in all food service locations shall be provided with a chrome finish. As an alternate all copper pipe and tube is allowed to be provided with chrome paint in lieu of chrome plating. Exposed copper indirect drain piping does not require painting or plating.
S. All exposed traps, tailpieces, supply and waste piping/tubing and fittings, stops, and the like serving all plumbing fixtures food service locations shall be provided with a chrome finish.
As an alternate all copper pipe and tube is allowed to be provided with chrome paint in lieu of chrome plating.
T. Provide plugs or caps for all opening during the construction phase. The temporary plug shall be plastic cap or equivalent. Duct tape is unacceptable for use as a plug, support or to separate ferrous from non-ferrous materials for the construction phase.
U. All materials (e.g. firestopping, insulation mastic, cutting oils, etc.) that are used not only as part of the plumbing system with the CPVC piping, but all products from any other trade that may come in contact with the CPVC piping, shall be listed as approved
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 17
on the Lubrizol CPVC compatibility charts and by the piping manufacturer. Contractor shall ensure no low voltage cabling is in contact with any CPVC piping.
V. All metal framing members with either factory stamp openings or field punch shall have a plastic sleeve or grommet in place prior to installing any plastic tubing.
W. In concealed locations where piping, other than cast-iron or galvanized steel, is installed through holes or notches in studs, joists, rafters, or similar members less than 1.5” (38mm) from the nearest edge, the piping shall be protected by strike plates (caddy nail plates model #304B2). This is to help protect piping from drywall screws. Piping is to run in the center of stud cavity wherever possible.
X. Install sleeves for piping passing structural elements as indicated above.
Y. Per NFPA 90A, no combustible piping serving water, waste, vent or storm shall be located within any HVAC shaft. Additionally, no gas piping of any type shall share a shaft with ductwork.
Z. Provide a field constructed/fabricated emergency drain pan under all piping located above an electrical room, tele/data room, IT room, transformer room, or any similar room having electrical or low-voltage equipment, gear, panels, and controls to minimize the chance of dripping onto the device. Emergency drain pan shall be designed to have a pipe connection routed to discharge 3" (75mm) above the floor adjacent to the door entering into the space.
AA. All metallic piping/components in direct contact with either dirt or concrete shall be provided with a 35 mil thick flexible wrap or sleeve equal to Tapecoat CT. Primer to be Tapecoat CT Coldprime or approved equal.
1. The exceptions include all stainless steel piping as well as cast iron when installed in non-corrosive soils.
BB. Coordinate with the electrical contractor to ensure all metallic piping is grounded per the NEC requirements.
CC. Horizontal piping is not to be installed/embedded within a concrete slab unless specifically noted as such.
3.3 PIPING CONNECTIONS
A. Make connections according to the following, unless otherwise indicated:
1. Install unions, in piping NPS 2 (DN 50) and smaller, adjacent to each valve and at final connection to each piece of equipment.
2. Install flanges, in piping NPS 2-1/2 (DN 65) and larger, adjacent to flanged valves and at final connection to each piece of equipment.
3. Dry Piping Systems: Install dielectric unions and flanges to connect piping materials of dissimilar metals.
4. Wet Piping Systems: Install dielectric coupling and nipple fittings to connect piping materials of dissimilar metals.
3.4 EQUIPMENT INSTALLATION - COMMON REQUIREMENTS
A. Install all equipment per the manufacturer’s recommendations.
B. Install equipment to allow maximum possible headroom unless specific mounting heights are not indicated.
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 18
C. Install equipment level and plumb, parallel and perpendicular to other building systems and components, unless otherwise indicated.
D. Install plumbing equipment to facilitate service, maintenance, and repair or replacement of components. Connect equipment for ease of disconnecting, with minimum interference to other installations. Extend grease fittings to accessible locations.
E. Install equipment to allow right of way for piping installed at required slope.
F. Any equipment that may require passwords for access of the controls, shall be provided at no cost to the owner for the life of the system.
3.5 PAINTING
A. Painting of Plumbing systems, equipment, and components is specified in Division 09 Sections "Interior Painting" and "Exterior Painting."
B. Damage and Touchup: Repair marred and damaged factory-painted finishes with materials and procedures to match original factory finish.
C. All plastic piping exposed to direct sunlight shall be painted with 2 coats of water based latex paint.
3.6 CONCRETE BASES
A. Provide raised concrete pads for all floor mounted equipment.
B. Concrete Bases: Anchor equipment to concrete base according to equipment manufacturer's written instructions and according to seismic codes (if applicable) at Project.
Where specific requirements are not specified in Division 3 or detailed on the Drawings, comply with the following at a minimum:
1. Construct concrete bases 4 inches (100 mm) high unless otherwise indicated; and extend base not less than 6 inches (150 mm) in each direction beyond the maximum dimensions of supported equipment unless otherwise indicated.
2. Edges of concrete bases shall have a minimum 1-1/2 inch (37 mm) chamfer.
3. Install dowel rods to connect concrete base to concrete floor. Unless otherwise indicated, install dowel rods on 18-inch (450-mm) centers around the full perimeter of the base.
4. Install epoxy-coated anchor bolts for supported equipment that extend through concrete base, and anchor into structural concrete floor.
5. Place and secure anchorage devices. Use supported equipment manufacturer's setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.
6. Cast anchor-bolt insert into bases. Install anchor bolts to elevations required for proper attachment to supported equipment.
7. Install anchor bolts according to anchor-bolt manufacturer's written instructions.
8. Use 3000-psi (20.7-MPa), 28-day compressive-strength concrete with wire-mesh reinforcement.
3.7 ERECTION OF METAL SUPPORTS AND ANCHORAGES
A. Refer to Division 05 Section "Metal Fabrications" for structural steel.
CITY OF NORTH MIAMI BEACH
PUBLIC LIBRARY-
RESTROOM REMODEL
COMMON WORK RESULTS FOR PLUMBING 220500 - 19
B. Cut, fit, and place miscellaneous metal supports accurately in location, alignment, and elevation to support and anchor plumbing materials and equipment.
C. Field Welding: Comply with AWS D1.1.
D. Fireproofing:
1. Clips, hangers, clamps, supports and other attachments to surfaces to be fireproofed shall be installed, insofar as possible, prior to start of spray fiber work.
2. Piping and other items which would interfere with proper application of fireproofing shall be installed after completion of spray fiber work.
3. Patching and repairing of fireproofing due to cutting or damaging to fireproofing during course of work specified under this Section shall be performed by installer of fireproofing and paid for by trade responsible for damage and shall not constitute grounds for extra cost to Owner.
3.8 ERECTION OF WOOD SUPPORTS AND ANCHORAGES
A. Cut, fit, and place wood grounds, nailers, blocking, and anchorages to support, and anchor plumbing materials and equipment.
B. Select fastener sizes that will not penetrate members if opposite side will be exposed to view or will receive finish materials. Tighten connections between members. Install fasteners without splitting wood members.
C. Attach to substrates as required to support applied loads.
3.9 GROUTING
A. Mix and install grout for plumbing equipment base bearing surfaces, pump and other equipment base plates, and anchors.
B. Clean surfaces that will…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .