Pavement Contract Q A.pdf

PDF 47 KB Posted

Attached to
Paving Maintenance Services Contract at National Institutes of Health
Solicitation number
NIHOF2011358
Issued by

View the file

Other files

File Type Posted
PACKAGING_AND_DELIVERY_OF_PROPOSALS.pdf PDF
Paving_Solicitation.pdf PDF
Paving_Solicitation.pdf PDF
Pavement_Contract__SOW.pdf PDF
PavingPricingStructure.pdf PDF
Paving_Solicitation.pdf PDF
Paving_Solicitation.pdf PDF
Pavement_Contract_SOW.pdf PDF
PavingPricingStructure.pdf PDF
Pavement Brief Notes TLH 20 Apr.ppt PPT presentation
paving sign in.PDF PDF
PreProposalQA.docx DOCX document
NIHOF2011358 amend2.pdf PDF
Paving_Solicitation.pdf PDF
SummaryofRelatedActivity.pdf PDF
Sec01700TaskOrderCloseoutProcedures.pdf PDF
InvoicingInstructionsFixedPriceContracts 1 .pdf PDF
PavingPricingStructure.pdf PDF
pastperformancesurvey.pdf PDF
Sec01400QualityControl.pdf PDF
PavementContractSOW.pdf PDF
paving solicitation.pdf PDF
DisclosureofLobbyingActivities.pdf PDF
WageDeterminations.pdf PDF
SF 1442.pdf PDF
packaging_and_delivery_of_proposal-nonrd.pdf PDF
OfferorsPointsofContact.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pavement Contract: Contractor Questions & Government Answers/Responses

Question 1: 11A & 11C – 1 ½ to 2” are already incorporated in the 1” to 3” surface, please clarify.

Answer: Both CLINs 11A and 11C are separate. As an example, CLIN 11C would be used for laying asphalt over a milled surface. Government Task Orders will describe the work requirement that would differentiate work to be performed, including a requirement for“bituminous course” or “asphalt overlay” as part of the work.

Question 2: For all asphalt items, is the liquid asphalt “completely” removed from the unit price or is it included with the stipulation of an “adjustment” paid under 17A & 17B?

Answer: The liquid asphalt price is completely removed from pricing. The pricing of liquid asphalt materials will be included in the proposals for individual Task Orders, and not in the response to this solicitation.

Question 3: 11F & 11G – typically milling is measured in square yards (as in the description) not in cubic yards. Please clarify.

Answer: The use of cubic yards in the CLIN pricing (Estimated Yearly Quantity and Unit of Work) was an error. The CLIN pricing should have been in square yards to reflect the amount of surface to be milled.

The correction has been applied to the CLINs in the Statement of Work within the solicitation.

Response: There is also a correction applied to the Statement of Work within the solicitation to increase the Estimated Yearly Quantity of work to Cold plane/mill asphalt (1/2” to 2” thick) more than 11 sq yd (for CLIN 11G, CLIN 21G, CLIN 31G, CLIN 31G, and CLIN 51G) to 500 square yards for each of the 1G CLINs for the respective five years of the contract.