Questions_and_Answers_NIHAO2016056.pdf
PDF 364 KB Posted
- Attached to
- Administration and Management of the National Biosafety and Biocontainment Training Program (NBBTP)
- Solicitation number
- NIHAO2016056
View the file
Other files
| File | Type | Posted |
|---|---|---|
| NBBTP_Pricing_Template_revised.xls | XLS spreadsheet | |
| Additional_Questions_to_NIHAO2016056.pdf | ||
| Section_K.pdf | ||
| Wage_Determination.pdf | ||
| NBBTP_Pricing_Template.xls | XLS spreadsheet | |
| RFP_NBBTP_Revised.pdf | ||
| NBBTP_Pricing_Template.pdf | ||
| RFP_NBBTP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NIHAO2016056
# Question RFP Reference Response
Under item a., please clarify the dates for the base year. It currently includes September 30, 2016 - September 29, 2016.
Page 8, Section F: Deliveries of
Performance, Article F.1. Period of
Performance, a.
The correct POP has been provided in the Amendment
On Page 8 under item b., the Option periods go through October
14 of each year, however in Attachments 02 and 03, the option years go through September 29 of each year. Should this be updated?
Page 8, Section F: Deliveries of
Performance, Article F.1. Period of
Performance, b., Page 83, Attachment 02: Proposal
Instructions, Section 5: Options, and Page 85, Attachment 03:
Additional Business Volume
Instructions, Section 4: Options
The correct POP has been provided in the Amendment
The RFP states, …"Offerors must submit an HHS Section 508
Product Assessment Template, in accordance with its completion instructions." Please clarify if this is only required from the successful offeror upon contract award. Alternatively, if it is required with the proposal response, please detail where this should be included in the Technical Proposal.
Page 14, Section H: Special
Contract Requirements, Article H.9
Electronic and Information
Technology Accessibility
The 508 Assessment shall be included in the business proposal. This form IS Not included in the page count.
Page 23, Clause 52.216-1 Type of Contract indicates the
Government is anticipating this contract will be issued as a Labor
Hour contract. The pricing template however indicates that this is a FFP LOE + ODC contract. Please confirm which is correct.
Page 23 & NBBTP Pricing
Template
Corrected
This section states that "The data submitted shall be at the level of detail described below," however, there is no additional information provided. Please provide any missing information.
Page 48, Section L: Instructions to
Offerors, C. Business Proposal
Instructions, item 3.b
This section has been removed
The numbering under technical criteria 2 skips from item 7 to item
9. Please clarify if this is missing item 8?
Page 54, Section M: Evaluation
Factors for Award, Technical
Criteria 2
This has been corrected
Responses to Questions and Answers
Under the past performance evaluation criteria, the RFP states that "past performance questionnaire included from at least three entities that they have provided similar facilities support service relative to the PWS." Then later, Section 4 states that "the evaluation will be based on information obtained from references provided by the offeror." Since there was no past performance questionnaire included with the solicitation, please confirm that only past performance references/contact information are required with the proposal.
Page 57, Section M: Evaluation
Factors for Award, Past
Performance and Page 82, Attachment 02: Proposal
Instructions, Section 4: Past
Performance.
Past Performance questionnaires will not be required.
Please note that all offerors shall address their past performance related to this requirement within their technical proposal
At the bottom of the red box, the instructions say to include the
Attachment "Packaging and Delivery of the Proposal," with the
SP. Should we assume that this is not required due to the proposal submission being completed via email?
Page 80, Attachment 02: Proposal
Instructions, red box
This is not requird and has been removed
The outline provided includes two Section 2 headings. Should these be combined, or are they considered separate sections with separate page limits?
Page 81/82, Attachment 02:
Proposal Instructions
Corrected
Item 1 under the first Section 2, and the first bullet under the second Section 2 both require a staffing plan and information regarding the proposed subcontractors, administrative and technical framework indicating clear lines of authority and responsibility, as well as the proposed organizational/ management structure for the project. Since this requirement is duplicated, please clarify which section this information should be included in.
Page 81/82, Attachment 02:
Proposal Instructions, Section 2:
Project Management, #1 and
Section 2: Key Personnel
Section headings have been corrected. Section "2" refers to all personnel, Section "3" refers to key personnel. Please provide the requested information for both sections as requested in RFP
Since the Government reserves the right to exercise the options to carry out the same work specified in the RFP, please clarify what information is requested in Section 5 for "Options should be presented as a separate part of the Technical Proposal and clearly identified as such." Should the offeror confirm that that the services specified in the RFP will be provided for each option year requested?
Page 83, Attachment 02: Proposal
Instructions, Section 5: Options
Services provided in the RFP will be the same for the Option
Years unless otherwise noted.
The requirement for this section ends with " including:" but does not list any information below. Please provide any missing information.
Page 83, Attachment 02: Proposal
Instructions, Section 6: Other
Considerations This has been deleted
The pricing template was previously provided in pdf format.
Please provide the Excel version in order for offerors to input pricing into the template and use the formulas provided to calculate our proposed price appropriately.
NBBTP Pricing Template
See attached
The pricing template provides units for the labor categories. Are these the number of hours each offeror shall use in their pricing?
NBBTP Pricing Template
These are estimated hours based on historical data. Offerors may use these hours as guidance when determining their costs or estimate their own hours to best determine how the requirements needs will be met
Would the government provide the rationale for the hours provided in the pricing template for the positions that are not shown full time equivalents, 2088 hours?
NBBTP Pricing Template
Hours were originally based on historicals which were 2088.
The government has decided to revise to 2080. Please note these hours are to be used as guidance. It is up to each offeror to decided how many hours and which labor categories they find applicable for completing the requirement
The pricing template includes "Other ODCs (Fellows Stipends, Medical, dental/health insurance, etc." two times, once under
ODC's Fellows and once under ODCs. Should both lines contain the same dollar amount or should they be different? If different, please provide guidance on what should be included in each amount.
NBBTP Pricing Template
Corrected
On page 81, there is mention of a Project Manager (PM), is this the same position as the Project Director?
Yes
Since FAR clause 52.222-41 is included, please provide the correct Wage Determination from the Department of Labor.
Attached
Please provide labor category descriptions and job requirements for all of the listed categories in the pricing template.
NBBTP Pricing Template
We would expect the offeror to provide that information in their business plan and technical proposals in the context of value, experience and cost to the government.
Can we propose other labor categories or make changes to the provided number of hours included in the pricing template?
NBBTP Pricing Template
Yes. The offeror may propose any labor category and hours they feel will help fulfill the requirement
Are all labor categories to be staffed at NIH in Bethesda, or can some of the labor categories be staffed at contractor facilities?
Some labor categories can be staffed off-site at the contractor's facility
Please provide an estimate or Not-To-Exceed figure to be used for travel so all offerors are proposing using the same amount.
NBBTP Pricing Template
The NTE shall be determined by each offeror based on the information given
Is there a content management system currently in place for the
NBBTP website maintenance?
page 64, PWS 3.1.7
The NBBTP website is maintained by a sub-contractor. The government does not directly oversee how the data/content is managed within that system.
Is the budget anticipated to be within the range for previous years?
Budget will be determined at time of award
What does NIH see as NBBTP priority areas for improvement going forward?
We would expect the offeror to provide those ideas in their technical proposal.
We received email notification of this RFP, was this notification sent to all responders to the RFI or just small businesses or organizations beyond those responding to the RFI?
This notification was only sent to Small Businesses who responded to the Small Business Sources Sought Notice
The incumbent holds International Association for Continuing
Education and Training accreditation. Is NIH looking for an organization that currently holds this accreditation or is applying for it?
IACET accreditation is not required.
Is NBBTP looking to maintain the 3 fellows per year or is there a desire to increase the number?
The maximum number of fellows per year is currently 3
Will past performance relevancy from work with other USG agencies be rated the same and equally as past performance with
NIH?
Yes
Will the government consider alternative titles and/or LOE’s for the Key
Personnel as “responsive” if these alternatives can be justified as increasing efficiency and/or creating cost savings for the government?
Yes
There are four (4) Key Personnel positions/titles on Pg. 54 of the RFP, but six (6) Key Personnel positions/titles listed on the “NBBTP_Pricing
Template.pdf.” Will the Government please reconcile this difference so the position titles and number of Key Personnel is the same in the PWS and on the “NBBTP Pricing Template.pdf”?
The pricing template references (4) key personnel positions has *asterisk next to the key personnel positions.
Will the government please clarify if the 2-3 page count indicated for resumes and CV’s of key personnel is intended to be the number of pages PER RESUME/CV or the total number of allowable pages for that required section? Does the 30 page maximum for Section 2 of the
Technical proposal include resumes/CVs?
Pg. 82
2-3pgs per resume
Attachment 02: Will the government please clarify where the statement "The Government is conducting this source selection in accordance with the competitive negotiation source selection procedures contained in FAR Part 15.” is required to appear in the
Technical proposal?
Pg. 81, Attachment 02
This Section is a disclaimer to industry stating that the source selection procedures will be in accordance with FAR
Part 15. Offerors will not need to include this in their proposal. Revised
Will the government please explain the task requiring annual updates of the NBBTP Certificate Program considering the PWS does not request, or define, the NBBTP Certificate Program.
Pg. 72, Item 5
The NIH does not anticipate conducting a Certificate program under this requirement. I suspect this language was form a previous PWS.
Offerors must provide a Small Business Subcontracting Plan AND that
Offerors do not have to provide this document due to the solicitation being a Total Small Business Set Aside. Will the government please confirm if a Small Business Subcontracting Plan is required?
Pg 49, Part 4 and Part 4a
A subcontracting plan is not required since this is a small business set-aside, However, if offerors due intend on partnering with other small businesses or large businesses, a small business utilization plan shall be included with the
Technical Proposal stating which work will be portioned out and should address the percentage of work that will be completed by the awardee of the contract and percentage of work that may be performed by other businesses.
How should Offerors include this information if it cannot be included on form NIH 2043?
NIH 2043
Revsied to:
" By signing the Cover Sheet the offeror agrees to the following statement: By submitting this proposal, the offeror, if selected for discussions, grants the contracting officer or an authorized representative the right to examine, at any time before award, any of those books, records, documents, or other records directly pertinent to the information requested or submitted."
1. Pg 84, Attachment 03 indicates Offerors are to use form NIH 2043 for the Business Proposal cover sheet. Section C, pg. 48 requires
Offerors to include nine data points on the Business Proposal cover sheet. However, form NIH 2043 does not allow Offerors to indicate two of the required nine data points listed in Section C, pg 48, specifically:
a. Proposed cost and/or price; and total;
b. “By submitting this proposal, the offeror, if selected for discussions, grants the contracting officer or an authorized representative the right to examine, at any time before award, any of those books, records, documents, or other records directly pertinent to the information requested or submitted.”
NIH 2043
a. Proposed cost and/or price; and total;
Proposed cost/price/total are to be included on a separate
Cost Proposal Sheet.
b. “By submitting this proposal, the offeror, if selected for discussions, grants the contracting officer or an authorized representative the right to examine, at any time before award, any of those books, records, documents, or other records directly pertinent to the information requested or submitted.”
Please note that this is a disclaimer. If an offeror is not in agreeance the company shall disclose in writing that they will not authorize the government to review their records.
Did the government intend for the Base Year performance period to be
September 30, 2016 through September 29, 2017 as indicated on page
8, or for the base year to run from September 30, 2016 - October 14, 2017 to align with the Option Year performance periods below?
Pg. 8, Article F.1 This Period of Performance was a typo. The correct POP has been provided in the Amendment
1. Also, did the government intend for any two option years to run simultaneously for the period of time from September 30-October 14 of a given option year? For example, Option Year 1 and Option Year 2 overlap from September 30-October 14, 2018 (shown below).
Option Option Period
Option Year I, Contract Year 2 September 30, 2017 through
October 14, 2018
Option Year II, Contract Year 3 September 30, 2018 through
October 14, 2019
Option Year III, Contract Year 4 September 30, 2019 through
October 14, 2020
Option Year IV, Contract Year 5 September 30, 2020 through
October 14, 2021
This Period of Performance was a typo. The correct POP has been provided in the Amendment
Offerors “...have to complete and INCLUDE as part of your BUSINESS
PROPOSAL, SECTION K: Which can be accessed electronically from the
Internet at the following address:
http://rcb.cancer.gov/rcb-internet/wkf/sectionk.pdf
H:\My Documents\Contract
Templates\Samples\RFP\Section K.pdf
../../../../Contract Templates/Samples/RFP/Section K.pdf ../../../../Contract Templates/Samples/RFP/Section K.pdf
The following changes have been made to the PWS:
Pg. 60 - Manage has been changed to Administer
Pg. 61, Administrative and Human Resources Support - "and the NIAID Contracting Officer before being offered to a candidate" has been added
Pg. 61, Training of NBBTP Fellows - "The IDP will be..." has been changed from modified to amended.
Pg. 62, 3.1.2 - "Contractor shall..." has been changed from manage to administer
Pg. 63, 3.1.4 - "and/or the Government Program Director" has been added
Pg. 64, 3.1.6 - "to attend professional meetings and" has been added
"All travel costs and per diem shall be in accordance with" has been added
Pg. 64, 3.1.7 - "The Contractor shall review and update the website as needed or when directed by the Government" has been revised.
Pg. 64, 3.1.8 - "Semiannual meetings with the COR, NIAID Contracting Officer and the Program Director shall be held within 2 weeks following the end of each six (6) month period. The purpose of these meetings is to review Contractor performance, review budget, and answer questions regarding operation of the NBBTP. The Contractor shall submit a quality control report at each semiannual meeting. The contractor shall record minutes of each meeting and provide them to the COR as an addendum to the
Semiannual Report (see below) within fifteen (15) days of the meeting. " has been revised.
Pg. 66, 3.3 #5 - "training" has been added
Pg. 66, 3.3 #9 - "COR" has been added
Pg. 68, Reports and Deliverables - 4.1 Monthly Reports has been deleted.
Pg. 68, Reports and Deliverables - 4.1 Semiannual, Section d) "Monthly Progress Reports will not be...." has been deleted
Pg. 68, Reports and Deliverables - 4.3 Annual Report - has been deleted
Pg. 68, Reports and Deliverables - Final Report, last sentence is deleted. "A monthly report will not be required...."
Pg. 70, Technical Progress Reports Table - Item 6 - 5.1.1 "Monthly Progress Report" has been deleted
Pg. 70, Technical Progress Reports Table - Item 6 - 5.1.3 "Annual" has been deleted.
Pg. 71, Evaluation of Developmental Assignments - PD has been spelled out
Pg. 73, Requirement Summary - Monthly Status Report has been deleted