NCR MATOC SOW V6 DRAFT 7.1.25.pdf

PDF 937 KB Posted

Attached to
NATIONAL CAPITAL REGION MULTIPLE AWARD TASK ORDER CONTRACT DRAFT SOW Federal contract opportunity
Solicitation number
W51EW7-26-R-NCR2
Issued by
Department of the Army

About this file

This is a draft Statement of Work (SOW) for a Multiple Award Task Order Contract (MATOC) for Sustainment, Restoration, and Modernization (SRM) and minor construction services for seven U.S. Army Garrison locations in the National Capital Region. The contract is an Indefinite Delivery/Indefinite Quantity (IDIQ) type with a five-year base period and two one-year option periods, totaling seven years. The contract will cover work at Aberdeen Proving Ground, Fort Belvoir, Fort Detrick, Fort George G. Meade, Fort Walker, Joint Base Myer-Henderson Hall, and Arlington National Cemetery.

The contract will support minor construction and repair projects up to $7.5 million, including new construction, renovation, repair, modernization, and demolition across various facility types such as barracks, administrative facilities, maintenance shops, child development centers, fitness centers, food service facilities, training facilities, museums, roads, utilities, gates, warehouses, and research facilities. Key contractor requirements include maintaining qualified personnel (including a Contract Manager, Quality Control Manager, and Contract Superintendent), complying with environmental and safety regulations, providing comprehensive documentation, and executing projects in accordance with federal, state, and local standards. The draft SOW is dated 1 July 2025 and is version 6, indicating ongoing refinement through industry feedback.

View the file

Other files for this federal contract opportunity

Other files attached to NATIONAL CAPITAL REGION MULTIPLE AWARD TASK ORDER CONTRACT DRAFT SOW, newest first.
File Type Posted
NCR MATOC Rate Sheet.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work (SOW) for

U.S. Army Garrison (USAG)

Aberdeen Proving Ground (USAG-ABER)

Fort Belvoir (USAG-FBVA)

Fort Detrick (USAG-DET1)

Fort George G Meade (USAG-MEAD)

Fort Walker (USAG-WALK)

Joint Base Myer-Henderson Hall (USAG-MYER) and

Arlington National Cemetery (ANC)

1 July 2025 Version 6

Statement of Work – National Capital Region Indefinite Delivery-Indefinite quantity Multiple Award Task Order Contract (MATOC)

PART 1 STATEMENT OF WORK

This Multiple Award Task Order Contract (MATOC) is to provide a rapid response vehicle for a broad range of Sustainment, Restoration and Modernization (SRM) work and minor construction on seven (7) installations located in the National Capital Region (NCR). This MATOC covers six (6) U.S. Army Garrison Directorate of Public Works (DPW) and, the Arlington National cemetery (ANC). The six sites are 1. U.S Army Garrisons Aberdeen Proving Ground (USAG-ABER), 2. Fort Belvoir (USAG-FBVA), 3. Fort Detrick (USAG-DET1), 4. Fort George G Meade (USAG-MEAD), 5. Fort Walker (USAG-WALK), and 6. Joint Base Myer-Henderson Hall (USAG-MYER).

All work shall be performed in strict accordance with all the terms, conditions, special contract requirements, specifications, drawings, attachments, and exhibits contained in the contract or incorporated by reference. The Contracting Officer will conduct negotiations with the Contractor(s) and issue individual TOs for restoration and minor construction projects identified by the installations’ Deputy of Public Works (DPW).

1.1 The Statement of Work (SOW) for each task order will include tasks in a variety of engineering areas to include but not limited to electrical, environmental, mechanical, and structural. During the contract period, as specific requirements arise, the Government will develop and issue individual task orders (TOs) to this contract. Individual scopes of work will vary in size depending on the complexity and nature of the work to be completed. The government will conduct bi-weekly meetings with each contractor (Contract manager and Quality Control manager, at a minimum) sequentially at the seven (7) installations to discuss existing and upcoming projects, pending project complexity and workload. The sequence, date and time will be determined after award has been made. The Contractor shall furnish all management, supervision, labor, materials, equipment, and incidentals required for a broad range of restoration and minor construction work at installations covered under this contract. The following types of projects are included in the SOW and may be executed under this contract: new construction work, and repair/renovation work up to $7,500,000: base SRM requirements, minor construction, small renovations, modernization, demolition, and restoration. The Contracting Officer will conduct negotiations with the Contractor and issue individual TOs for restoration and minor construction projects identified by the DPW.

1.2 The Contractor's work and responsibility shall include all Contractor planning, programming, administration, and management necessary to provide all repair or construction and related services as specified. The Contractor shall conduct the work in strict accordance with the contract and all applicable federal, state and local laws, regulations, Unified Facilities Criteria (UFC), Unified Facilities Guide Specifications (UFGS), International Building Codes (IBC), directives, and Installation policies. The Contractor shall ensure that all work provided meets/exceeds the drawings and specifications identified in the Contract and task orders. The Contractor shall provide related services such as preparing and submitting required reports, performing administrative work, and submitting necessary information as specified under this Contract and within individual task orders. The intent of these specifications is to furnish concise IBC and/or commercial standards for maintenance, repair and minor construction of Government facilities. In the absence of specific guidance in the technical specifications, UFC, UFGS, IBC and/or commercial standards, or installation standards as a minimum shall be utilized. In case of a conflict among these laws, regulations, and codes the most stringent law, regulation, or code shall apply.

1.3 Potential projects include, but are not limited to, barracks, administrative facilities, maintenance shops, child development centers (CDC), physical fitness centers, maintenance shops, food service facilities, ranges and training facilities, museums, airfield structures (including rigid and flexible paving), roads, public safety facilities (police, fire and crash rescue), athletic fields, underground utilities, overhead utilities, gates, cemeteries, warehouses, auditoriums, and research, development and testing facilities and other general construction work deemed necessary to support mission requirements. Facility renovations, and construction shall conform to the requirements of the technical criteria described in the SOW for each TO.

1.4 In the absence of specific guidance in the technical specifications, United Facilities Criteria (UFC), United Facilities Guide Specifications (UFGS), International Building Code (IBC) and/or commercial standards, or the respective Army installation standards as a minimum shall be utilized. In case of a conflict amongst these laws, regulations, and codes the most stringent law, regulation, or code shall apply.

Statement of Work – National Capital Region Indefinite Delivery-Indefinite quantity Multiple Award Task

2. Contract Description

This contract will be a Firm Fixed-Priced, indefinite delivery, indefinite quantity (IDIQ) type contract with a five-year base period and two (2) one-year option periods for a total of seven (7) years. This Indefinite Delivery Indefinite Quantity (IDIQ) contract is for SRM, minor construction, and will employ a wide variety of individual construction tasks.

2.1 The contract will be used for the acquisition of base SRM requirements, minor construction, small renovations, modernization, demolition, and restoration. This contract will employ a wide variety of individual construction tasks. The Scope of Work (SOW) for each task order will include tasks in a variety of engineering areas to include but not limited to electrical, environmental, mechanical, and structural. All work associated with this contract is unclassified.

2.2 This contract will provide a rapid response vehicle to execute a broad range of SRM work on real property located on the seven (7) Army sites included in the National Capital Region (listed above). Task Order (TO) requirements will be executed based on the Installation’s Annual Work Plan.

2.3 The Requiring Activity’s reoccurring facilities engineering support services, such as utility plant operation, custodial, grounds maintenance, refuse collection and disposal, and similar work shall not be acquired using this contract. A-E services and Design-Build requirements shall not be acquired under this contract.

2.4 Examples of items that are NOT AUTHORIZED for acquisition under this contract are fuels; utilities past the point of connection of primary utilities; construction equipment that is not being utilized for a specific TO placed under this contract; administrative equipment, furnishings, construction materials (e.g., lumber, concrete, etc.) that are not being utilized for a specific TO placed under this contract; A-E Services (Brooks Act); administrative services such as typing, transportation, reproduction, graphics, and interior design services are not part of this contract; maintenance, overhaul, or repair of equipment; housekeeping services; purchase of supplies that are not being utilized for a specific TO placed under this contract; design (Contractor is to produce shop drawings incidental to the job, reflecting the plan of action and the completed project); orders for the sole purpose of abatement of lead-based paint and/or asbestos.

3. Subject Matter Experts required for this Contract

The below work as identified in each discipline is meant to provide the contractor with an overview of the anticipated work but is not all-inclusive. The Contractor shall ensure all employees and associated subcontractor(s) are certified or licensed within specific disciplines or areas of expertise as required by the states in which the work is occurring. All construction and maintenance affecting real property shall conform to the architectural theme of the respective installation as defined in the Installation Design Guide and is subject to the approval of the Director of Public Works. Types of work that may be included by the Government based on the specific TO are as follows:

3.1 Buildings - Analysis of building systems and ancillary structures (to include timber, concrete, masonry, steel), foundations, underwater structures, reinforced concrete, equipment mounting, shock isolation, reinforced masonry, wood, steel joists, steel decks, structural steel frame systems, steel bracing, steel connections, non-building structures, welding procedures, detailing of structural components and hardened (protective) structures, and snow loads. Additionally, enclosures, shelters, building systems, mobile buildings, chimneys, grout, mortar, concrete, brick, concrete masonry units (CMUs), waterproofing, insulation, caulking and sealants, roofing, gutters, drains, metal decking, joists, siding and exterior surfacing, levelers, docks, ramps, stairs, shelving, windows, doors, painting, finishes, louvers, awnings, shutters, panels, grills, ceilings, acoustical areas, walls, paneling, flooring (conductive and nonconductive), carpeting, tiles, builder's hardware, signage, metals, woods and plastics, millwork, thermal and moisture protection, playground equipment, fireproofing, equipment systemization layouts, building fixtures and furnishings, and handicap systemization. Also to include earthquake consideration of utility systems, non-building structures such as elevated tanks, vertical tanks on ground, horizontal tanks, retaining walls and buried structures, anchorage and support of mechanical and electrical equipment and applications of industry building codes and standards. All work must conform to the architectural theme of the respective Installation as defined in the Installation Design Guide and is subject to the approval of the Director of Public Works.

Statement of Work – National Capital Region Indefinite Delivery-Indefinite quantity Multiple Award Task

3.2 Horizontal Maintenance: Topographic surveying, grading and earthwork, surface and subsurface storm drainage and drainage control structures, storm water management, erosion and sediment control, clearing and grubbing, paving and surfacing for roads, parking areas, and sidewalks, parking layout, pavement markings, traffic control and signage, gates and fencing, curbs and gutters, railroads, dewatering, landscaping, seeding and sodding, riprap, geotechnical investigations, slope stabilization, foundations, borings, trenching, piles and caissons, piers, bridges, spill containment, berms, demolition, and airfield runway and taxiway and aprons.

3.3 Reserved.

3.4 Electrical: Electrical distribution systems (Low, Medium, & High Voltage) and network balancing (aerial and underground), transmission lines, substations, poles (telephone and power), towers, ducts, raceways, conduits, tubing, connectors, wires, cable, cable trays, outlet boxes, cabinets and enclosures, supports, fiber optics cable and equipment, manholes, concrete pads, insulators, lightning arrestors, transformers, capacitors, switches, relays, fuses, grounding, lightning protection, cathodic protection, service entrances, panel boards, circuit breakers, motor control centers, special equipment/systems, targeting systems, resistance heating, starters, uninterrupted power supplies (UPS), beacons, batteries, generators, solar systems, receptacles, lighting fixtures, lamps, ballasts, equipment connections, special outlets, disconnect switches, splices, terminations, control systems, security systems, IDS, utilities monitoring and control systems (UMCS), and similar microprocessor environmental control systems, audio and visual communication systems, telephone systems, instrumentation systems, and fire detection and alarm systems.

3.5 Environmental: Industrial and sanitary sewers, waste treatment facilities, septic tanks with drains, portable toilets, wells, water treatment facilities, water distribution systems, potable and fire water supplies including wells, piping, pumps, valves, sprinklers, water use analyses, sludge removal, leakage analysis, wetland delineation, wetland mitigation and hazardous waste analyses, and disposal of waste products.

3.6 Mechanical Systems: Heating, Ventilation, and Air-Conditioning (HVAC) systems to including HVAC Controls (Air and water side components), chillers, cooling towers, refrigerants, condensers, air-handling units (Central, Constant and/or Variable-Air Volume, Fan-Coils), heat transfer surfaces (heating/cooling coils, infra-red heating), furnaces (electric, Hot water, natural gas), boilers (electric, gas, oil, water tube, fire tube, condensing), air distribution (ductwork, fans, dampers), cooling/heating water distribution piping, pumps, and valves. Air compressors, air dryers and associated distribution systems. Conveying systems to include elevators, moving walkways, dumbwaiters, escalators, hoists, cranes, lifts, and material handling systems. Fuel distribution systems, Petroleum Oil Lubricants (POL) and supporting equipment to include POL storage tanks and associated distribution piping, valves, pumps, and controls. Plumbing systems to include domestic hot/cold water distribution (piping, valves, fixtures, backflow preventors), natural gas distribution, medical and industrial gas distribution, sanitary sewer piping systems, gray water systems, vent piping systems, domestic hot water heaters, irrigation systems, leak detection, and hazardous waste. Fire Protection Systems to include wet-pipe, dry-pipe, deluge, chemical, pre-action, CO2 and associated components such as sprinklers, Fire alarm Control Panels (FACP), heat/smoke detectors, annunciators, and horn/strobes.

3.7 Safety: Life safety, force protection, fire protection systems, industrial hygiene, flammable gases, medical safety and hygiene, asbestos and/or lead based paint evaluation and (removal/encapsulation), blast distances, and Failure Mode and Effects Analysis (FMEA), Occupational Safety and Hazards Act (OSHA), Uniform Federal Accessibility Standards (UFAS) Fed Std.795, Americans with Disabilities Act (ADA), Accessibility Guidelines for Buildings and Facilities, Architectural Barriers Act (ABA), and Accessibility Guidelines published in the Federal Register published in the Federal Register July 23, 2004 amended August 5, 2005 (Volume 69, Number 141).

3.8 Asbestos/Lead: Asbestos and/or lead based paint abatement may be required during equipment/systems remediation. On-site inspection of Repair, Rehabilitation and Construction (RRC) efforts will be required.

Demolition and/or temporary removal and reinstallation of supporting elements in the project related areas will be required. Surveys and assessments of systems/equipment may be required prior to RRC action. Onsite inspection and acceptance may be required. Ancillary work necessary to support the RRC action or to restore the work area to the condition prior to the RRC action shall be included in this contract. This objective shall be achieved through the implementation of task orders issued under the terms of this contract.

Statement of Work – National Capital Region Indefinite Delivery-Indefinite quantity Multiple Award Task

4. Key Personnel Position Requirements/Contractor Staff

Key personnel are identified as the Contract Manager, Quality Control Manager, and Contract Superintendent. The Contractor shall maintain sufficient management and technical staff available to respond to all the requirements set forth in this contract. The Contractor’s staff shall meet the position requirements as stated in the SOW and shall be designated in writing 10 business days prior to contract performance (listing name, address, and cell phone numbers, home telephone number and email address) to the Contracting Officer. The Government reserves the right to approve/disapprove personnel based on the position requirements as stated in the SOW. The Contractor shall provide personnel experienced and knowledgeable in civil, structural, architectural, mechanical, environmental, and electrical engineering disciplines. The Government has the right to reject the Contractor’s choice of key personnel for failure to meet the qualification standards incorporated into the contract.

4.1 The Contractor shall provide a Contract Manager within 10 days of award. This individual and any individual designated to act on his/her behalf, shall have the full authority to contractually commit the Contractor for prompt action on matters pertaining to contract administration of the contract. The Contract Manager shall have a total of 30 hours in OSHA General Construction training courses. The Contract Manager shall meet criteria for the roles/responsibilities and education and qualifications requirements of either (a) or (b) listed in the table below:

Key Personnel Roles/Responsibilities Education Qualification Contract Manager The Contract Manager shall be an employee of the Contractor.

The Contract Manager (or the designated individual) shall have the authority to contractually commit the Contractor during negotiations, and shall have authority to sign task orders and modifications and return documents to the Contracting Officer within four (4) hours of receiving these documents (via email, hand-carry or any other approved electronic means).

The Contract Manager shall designate an individual that will be available to meet on-site at one of the seven (7) installations for contract clarifications/negotiations, site visits, status or any other meetings within 24 hours after the Contract Manager is notified by the Government. At the discretion of the Contracting Officer and to allow for maximum participation by the Contract Manager,

(a) An accredited Bachelor’s Degree in Engineering, Architecture, Construction Management or a related civil, structural, mechanical or electrical field

OR

(b) An accredited Associate’s degree in Engineering, Architecture, Construction Management or a related civil, structural, mechanical or electrical field.

A minimum of 10 years of experience managing multiple construction projects that include engineering design prior to construction (i.e.

design-build projects), facility repair or maintenance projects with an individual project value of at least $1 million and an annual total value of no less than $7.5 million; or experience as a deputy/assistant contract manager or higher.

OR

A minimum of 15 years of experience in managing multiple construction projects that include engineering design prior to construction (i.e.

design-build projects) and facility projects with an individual project minimum value of $1 million and a minimum annual total value of $7.5 million; or experience as a deputy/assistant contract manager or higher.

Statement of Work – National Capital Region Indefinite Delivery-Indefinite quantity Multiple Award Task contract clarifications/negotiations and meetings may be conducted via video teleconference.

The Contract Manager shall be responsible for the overall management, coordination of this contract and all projects, and shall be the central point of contact with the Government for performance of all work under this contract.

Another individual may be designated to act for the Contract Manager;

however, 10 business days advanced written notice of such change shall be provided to the Contracting Officer.

The Contract Manager shall be reachable by phone and email during the hours from 7:30 a.m.

to 4:00 p.m., Monday through Friday, except on Federal holidays.

Regardless of weekday/weekend status, either the Contract Manager or a designated individual with signature authority shall be physically present at the installations if requested by the Contracting Officer, during the end of September for no more than two days from 7:30 a.m. to 1200 midnight as necessary to sign task orders for the fiscal year end close out.

The Contract Manager, Quality Control Manager and Contract Superintendent or their designee(s) must be able to understand, speak, Statement of Work – National Capital Region Indefinite Delivery-Indefinite quantity Multiple Award Task read, and write the English language fluently.

The Contract Manager shall oversee task order accomplishment, administer general instructions to Task Order Project superintendents, and answer all questions from the Contracting Officer pertaining to the task orders during the life of the contract.

The Contract Manager is responsible for providing adequate resources to ensure all submittals, drawings, Contractor/subcontractor payrolls and deliverables are timely and accurate with less than 5% rejection by the Government.

The Contract Manager shall be responsible for coordination and completion of all work under this contract and is ultimately responsible for the proper execution of the contract.

When the Contractor has active on-site work occurring on any task orders, the Contract Manager shall email a list to the Contracting Officer and Contracting Officer Representative (COR) denoting the task order and active dates NLT 24 hours before work occurs.

Individuals designated by the Contract Manager to act for the Contract Manager shall meet the qualifications of the Contract Manager and shall be employees of the Contractor.

4.1.1 The rates for Key Personnel, except the Site Safety and Health Officer, will be incorporated into the base contract and all rates in attachment XX shall be Not To Exceed (NTE) rates the offerors will use when preparing Task Order price proposals. Contractors may quote less than the stated rates but are not to exceed what is in this

Statement of Work – National Capital Region Indefinite Delivery-Indefinite quantity Multiple Award Task attachment for each Task Order. Based on individual task Order Requirements, task Orders may include all, some or none of these rate categories.

4.2 The Contractor shall provide a Quality Control (QC) manager. The QC Manager shall have a total of 30 hours in OSHA General Construction training courses. The QC Manager shall meet criteria for the roles/responsibilities and education and qualifications requirements of either (a) or (b) listed in the table below:

Quality Control (QC) Manager

The QC Manager shall complete the course entitled “Construction Quality Management for Contractors” within 6 months of contract award.

The QC Manager shall be responsible for overall management of Contractor Quality Control (CQC) of the overall contract and have the authority to act in all CQC matters for the Contractor.

The QC Manager shall be present on-site and perform daily inspections while the Contractor has active construction TOs.

Inspectors shall report to the QC Manager. An alternate for the QC Manager shall be identified to serve in the event of the QC Manager’s absence.

The QC Manager cannot at any time act as the on-site Task Order Project Superintendent for any task order.

The Contract Manager shall ensure that duties of the Contract Manager (or the designated individual) shall not interfere with the independence or present a conflict of interest with the appointment of the QC Manager.

The Contractor shall avoid conflicts of having

(a) An accredited AS degree in Construction Management or a related civil, structural, mechanical or electrical field

OR

(b) N/A

A minimum of 5 years specialized experience as A project/job inspector or quality control specialist in a construction environment on multiple projects totaling over $1 million annually

A minimum of 10 years of experience in civil, structural, mechanical or construction.

Statement of Work – National Capital Region Indefinite Delivery-Indefinite quantity Multiple Award Task one individual fulfill QC Manager and On-site Task Order Project Superintendent roles on a

TO.

The QC Manager shall have no other role than that of QC Manager. The QC Manager must be a Contractor employee.

At the request of the COR, the QC Manager must be present on site to meet with Government officials.

4.3 The Contractor shall provide a Contract Superintendent to oversee all task orders issued. The Contract Superintendent shall have a total of 30 hours in OSHA General Construction training courses. The Superintendent shall maintain a file at the job site and made available to the Contracting Officer upon request. The file shall include, but not be limited to, current project documents, executed TO, RTOP, contract drawings, contract specifications, Quality Control Plan (QCP), as-built drawings, and modifications. The Contract Superintendent shall meet criteria for the roles/responsibilities and education and qualifications requirements of either (a) or (b) listed in the table below:

Contract Superintendent The Contract

Superintendent may not be an employee of a subcontractor; the Contractor must list in its technical proposal that the Contract Superintendent will be part of each task order.

The Contract Superintendent qualifications must meet the requirements of the SOW and shall be designated in writing by the Prime Contractor 10 business days after the award of the contract (listing name, address, and cell phone numbers, home telephone number and email address. The Contractor is responsible to provide a Contract Superintendent that complies with the qualifications in the SOW. The Contract

(a) An accredited AS degree in Construction Management or a related civil, structural, mechanical or

(b) N/A

A minimum of 5 years of construction experience on multiple projects totaling over $1 million OR A minimum of 10 years of construction experience on multiple projects totaling over $1 million annually may be substituted for the Associate’s degree and 5 years of experience

Statement of Work – National Capital Region Indefinite Delivery-Indefinite quantity Multiple Award Task

Superintendent shall be present at the installation and performing daily superintendent duties while the Contractor has active construction TOs.

4.4 Site Safety and Health Officer (SSHO): The SSHO shall have a minimum of five (5) years of experience in managing and inspecting construction projects. The SSHO shall have the following current certifications and trainings: OSHA30, and First Aid and Cardiopulmonary resuscitation (CPR) certified.

Site Safety and Health Officer

The Contract Superintendent may not be an employee of a subcontractor; the Contractor must list in its technical proposal that the Contract Superintendent will be part of each task order.

(a) OSHA30, and First Aid and

(b) Cardiopulmonary resuscitation (CPR) certified.

A minimum of 5 years of experience in managing and inspecting construction projects.

4.5 Contractor Personnel: Contractor personnel performing work under this contract shall be U.S. citizens unless the provisions of Army Regulation 25-2, Information Assurance have been fully completed, and approval has been granted by the Contracting Officer for the non-U.S. citizen to perform the required support. Contractor personnel performing work under this contract shall be able to read, write, speak, and understand the English language to effectively carry out all contract requirements. They shall be able to effectively communicate in person or via electronic devices (telephone or Email) with co-workers, customers, and the general public.

4.5.1 The Contractor shall not allow any employee having possession of, or under the influence of alcohol or controlled substances to perform work.

4.5.2 The Contractor shall provide the necessary personnel to accomplish all work within the time frames specified for each TO. The Contractor’s staff shall meet or exceed the position requirements as stated in the TO. The Contractor shall provide experienced and knowledgeable personnel in civil, structural, architectural, mechanical, and electrical engineering disciplines. The replacement and alternate staff shall meet or exceed the same minimum qualifications as stated in the TO. Contractor will not be permitted to conduct work activities if Key Personnel are not approved by the Contracting Officer.

4.6 Contractor and subcontractor Personal: This includes all tiers of subcontracted, employees shall be subject to all installation Regulations and Policies. Violation of such rules, regulations, laws, directives, or requirements shall be grounds for removal (permanently or temporarily as the Government determines) from the work site. Individuals who violate such rules, regulations, laws, directives, or requirements may be denied access to the Installation, either temporarily or permanently.

4.6.1 Contractor and subcontractor, to include all tiers of subcontracted employees shall be appropriately dressed, including individual protective clothing and equipment, for the work to be done.

4.7 Relationship between Government, Contractor, and Contractor Personnel: The services to be delivered by the Contractor to the Government are non-personal services, and no employer-employee or master-servant relationship exists or will exist under the contract between the Government/Government personnel and Contractor.

Contractor personnel shall be responsible not to the Government, but solely to the Contractor, who shall be accountable to the Government. The services to be performed under this contract shall not require the Contractor or

Statement of Work – National Capital Region Indefinite Delivery-Indefinite quantity Multiple Award Task his employees to exercise personal judgment and discretion on behalf of the Government, but rather, Contractor personnel shall act and exercise personal judgment and discretion on behalf of the Contractor.

4.8 The Contractor shall not hire for this Contract any person whose employment would result in a conflict of interest or employment which is prohibited by the Department of Defense Regulation 5500.7-R entitled "Joint Ethics Regulation (JER)", dated August 30, 1993.

4.9 The Contractor's employees shall be subject to the same general rules of conduct while on the installation that apply to Government civilian employees. The Government reserves the right to refuse installation access to any Contractor employee if the Contracting Officer determines it to be in the best interests of the Government.

4.10 The Contractor will be required to respond within two (2) calendar days from the time contacted by the Contracting Officer or COR regarding conduct of Contractor employees.

4.11 TIER 1 Subcontractors. The Contractor is responsible for subcontracting architectural and engineering services, when required by the task order statement of work, for preparing construction documents to include, but not limited to, reports, plans, and specifications. All construction documents and inspection and testing services for acceptance of work must be completed by firms appropriately licensed or certified and shall be financially independent of the installer, unless the installer is the Contractor self-performing the work.

5. Training, Physical Requirements, or Other Expertise Required: The Contractor shall ensure all employees are certified or licensed in the specific areas required for each TO. The Contractor shall ensure all required documentation of certification or licensure for Contractor personnel are filed with the COR/ACOR within thirty (30) calendar days prior to employees commencing performance or as directed by the COR/ACOR.

6. Organizational Conflict of Interest (OCI):

6.1 Purpose. To aid in ensuring that:

6.1.1 The Contractor does not obtain an unfair competitive advantage by establishing the ground rules for a future competition.

6.1.2 The Contractor's objectivity and judgment are not biased because of its present or future interests (financial, contractual, organizational, or otherwise) which relate to work performed under this contract; and

6.1.3 The Contractor does not obtain an unfair competitive advantage by virtue of its access to non-public or proprietary information belonging to others.

6.2 Definitions.

6.2.1 The term “Contractor” herein used in section 1.5., OCI, means: (a) the organization (hereinafter referred to as "it" or "its") entering into this agreement with the Government; (b) all business organizations with which it may merge, join or affiliate now or in the future and in any manner whatsoever, or which hold or may obtain, by purchase or otherwise, direct or indirect control of it; (c) it’s parent organization, if any and any of its present or future subsidiaries, associates, affiliates, or holding companies, and; (d) any organization or enterprise over which it has direct or indirect control now or in the future.

6.2.2 The term "proprietary information" for purposes of section 1.5., OCI, means any information considered so valuable by its owners that it is held secret by them and their licensees. Information furnished voluntarily by the owner without limitations on its use, or which is available without restrictions from other sources, is not considered proprietary.

6.3 OCI Examples. The following examples illustrate situations in which OCIs may arise. These examples are not all inclusive.

6.3.1 Biased Ground Rules. This type of conflict may arise in situations where a company sets the ground rules

Statement of Work – National Capital Region Indefinite Delivery-Indefinite quantity Multiple Award Task for a future competition. For example, when a Contractor develops requirements then competes to provide products or services to satisfy those requirements, thus obtaining a competitive advantage.

6.3.2 Impaired Objectivity. This type of conflict may exist where a Contractor’s obligations under a contract require objectivity, but another role of the Contractor casts doubt on its ability to be truly objective. An example of this type of conflict is where a Contractor’s work under one contract entails evaluating itself, its affiliates, or its competitors under a separate contract.

6.3.3 Unequal Access to Information. This type of conflict may arise when a Contractor has access to nonpublic or proprietary information as part of its performance under a contract that gives it an unfair advantage in a competition for a later contract.

6.3.4 General Constraints. The provisions of FAR Subpart 9.5, Organizational and Consultant Conflicts of Interest, concerning organizational conflicts of interest govern this contract. Potential conflicts may exist in accordance with FAR 9.505-1, Providing Systems Engineering and Technical Direction, through 9.505-4, Obtaining Access to Proprietary Information. In this regard, the Contractor is responsible for identifying any actual or potential organizational conflicts of interest to the Contracting Officer that arise as the result of performance under this contract. To avoid or mitigate a potential conflict related to performance under this contract, the Contracting Officer will impose appropriate constraints such as the constraints discussed below. Since it is impossible to foresee all of the circumstances that might give rise to organizational conflicts of interest, the constraints discussed below are not all inclusive and the Contracting Officer may impose constraints other than, or in addition to, the constraints listed below.

6.3.5 The Contractor agrees that if it provides, under a contract or task order or delivery order, systems engineering and technical guidance for systems and programs, but does not have overall contractual responsibility, it will not be allowed to be awarded a contract or task or delivery order to supply the system or any of its major components or be a subcontractor or consultant to a supplier of the system or any of its major components (FAR 9.505-1).

6.3.6 The Contractor agrees that if it prepares complete specifications for non-developmental items or assists in the preparation of work statements for a system or services under a contract or task order or delivery order, it will not be allowed to furnish these items, either as a prime Contractor, a subcontractor or as a consultant (FAR 9.505-2).

6.3.7 The Contractor agrees that it will neither evaluate nor advise the Government with regard to its own products or activities. The Contractor will objectively evaluate or advise the Government concerning products or activities of any prospective competitors (FAR 9.505-3).

6.3.8 The Contractor agrees that if it gains access to proprietary information of other companies, it will exercise diligent effort to protect such proprietary information from unauthorized use or disclosure (FAR 9.505-4). In addition, the Contractor agrees to protect the proprietary information of other organizations disclosed to the Contractor during performance of this contract with the same caution that a reasonably prudent Contractor would use to safeguard highly valuable property. The Contractor also agrees that if it gains access to the proprietary information of other companies it will enter into written agreements with the other companies to protect their information from unauthorized use or disclosure for as long as it remains proprietary and to refrain from using the information for any purpose other than that for which it was furnished. The Contractor shall provide copies of such agreements to the Contracting Officer.

6.3.9 If the Contractor, in the performance of this contract, obtains access to plans, policies, reports, studies, financial plans, data or other information of any nature which has not been released or otherwise made available to the public, the Contractor agrees that without prior written approval of the Contracting Officer, it shall not: (a) use such information for any private purpose unless the information has been released or otherwise made available to the public, or (b) release such information unless release is otherwise authorized under the contract or such information has previously been released or otherwise made available to the public by the Government.

6.3.10 Non-Disclosure Agreements. The Contractor shall obtain from each employee who has access to proprietary information under this contract, a written agreement which shall in substance provide that such employee shall not, Statement of Work – National Capital Region Indefinite Delivery-Indefinite quantity Multiple Award Task during his/her employment by the Contractor or thereafter, disclose to others or use for their benefit, proprietary information received in connection with the work under this contract. The Contractor will educate its employees regarding the restrictions imposed by FAR 9.505-4, so that they will not use or disclose proprietary information or data generated or acquired in the performance of this contract, except as provided herein.

6.3.11 Training. The Contractor shall effectively educate its employees, through formal training, company policy, information directives and procedures, in an awareness of the legal provisions of FAR Subpart 9.5 and its underlying policy and principles, so that each employee will know and understand the provisions of that Subpart and the absolute necessity of safeguarding information from anyone other than the Contractor's employees who have a need to know, and the U.S. Government.

6.3.12 Subcontracts. The Contractor agrees that it will include the provisions in paragraphs 1.5.4., 1.5.5., and 1.5.6.

above and this paragraph in consulting agreements, teaming agreements, and subcontracts of all tiers, which involve access to information or the performance of services described in paragraph 1.5.4. above. The use of section 1.5., in such agreements, shall be read by substituting the word "consultant" or "subcontractor" for the word "Contractor" whenever the latter appears.

6.3.13 Additional Constraints. If this contract provides for the issuance of task or delivery orders, such orders may impose additional requirements and/or restrictions relating to 1.5., to include the requirement for the Contractor and its subcontractors and employees to furnish the Government with written non-disclosure agreements or statements of no conflict of interest. With regard to any proposal submitted by the Contractor, in response to a Request for Task Order Proposal (RTOP), by submitting its proposal the Contractor represents that it has disclosed to the Contracting Officer, prior to the issuance of the task or delivery order, all facts relevant to the existence or potential existence of organizational conflict of interest as that term is used in FAR Subpart 9.5.

6.3.14 Conflicts Involving Future Procurements. The award of this contract, and all task or delivery orders issued under this contract, government taskings or acquiescence in the Contractor’s performance of services hereunder shall not constitute or be interpreted as a determination that the Contractor is eligible to participate in future procurements, developmental efforts, implementation efforts, or related activities. Only the Contracting Officer for such efforts, applying the rules, principles, and procedures of FAR Subpart 9.5, have the authority to determine whether a conflict exists, in connection with such procurements.

6.3.15 Representations and Disclosures.

6.3.15.1 The Contractor represents that it has disclosed to the Contracting Officer, prior to award of this contract, all facts relevant to the existence or potential existence of organizational conflict of interest as that term is used in FAR Subpart 9.5.

6.3.15.2 The Contractor represents that if it discovers an organizational conflict of interest or potential conflict of interest after award of this contract, a prompt and full disclosure shall be made in writing to the Contracting Officer.

This disclosure shall include a description of the action the Contractor has taken or proposes to take in order to avoid or mitigate such conflict.

6.3.16 Remedies and Waiver.

6.3.16.1 For breach of any of the above restrictions or for non-disclosure or misrepresentation of any relevant facts required to be disclosed concerning this contract, the Government may terminate this contract for default, disqualify the contractor for subsequent related contractual efforts, and pursue such other remedies as may be permitted by law or this contract. If, however, in compliance with section 1.19., the Contractor discovers and promptly reports an organizational conflict of interest (or the potential thereof) subsequent to contract award, the Contracting Officer may terminate this contract, or any task or delivery order issued under this contract for convenience, if such termination is deemed to be in the best interest of the Government.

6.3.16.2 The parties recognize that this clause has potential effects, which will survive the performance of this contract, and that it is impossible to foresee each circumstance to which it might be applied in the future.

Statement of Work – National Capital Region Indefinite Delivery-Indefinite quantity Multiple Award Task

Accordingly, the Contractor may at any time seek a waiver from the cognizant Contracting Officer by submitting a full written description of the requested waiver and the reasons in support thereof (FAR 9.503).

PART 2 WORK RESONSIBILITY

The Contractor shall perform minor construction as defined in each TO SOW. Individual SOWs will vary in size and complexity depending on the nature of the work. The Contracting Officer will issue a Request for Task Order Proposal (ROTP) detailing the task to be accomplished. The Contractor shall estimate the level of effort required to perform the requested work and shall submit a detailed proposal of items required to accomplish the work within the time frame stated in the ROTP. The proposal shall be detailed and broken out so the Government can readily identify the material, quantities of labor hours and skill sets being utilized for that task order. The Contractor shall furnish all management, supervision, labor, materials, equipment, and incidentals required for a broad range of restoration and minor construction work on various facilities at installations covered under this contract.

The Contracting Officer will identify any security training required before the start of work. The Contractor’s key personnel shall train all Contractor personnel at the Contractor's own expense.

1. Contractor Responsibility

1.1 General Responsibilities: The Contractor shall assume full responsibility and liability for non-compliance with all Federal, State, and local laws, regulations, codes, policies, and directives pertaining to the health and safety of personnel during the execution of work and shall hold the Government harmless. The Contractor shall perform all related Contractor administrative services, planning, programming, and management necessary to perform the work, to include but not limited to maintenance of accurate and complete records, files, and libraries of documents on a Government provided system (e.g., MS Teams, SharePoint, etc.).

At the TO level, the Contractor shall provide related services to include, but not limited to, pre-award project development, project management, QC, and submission of required deliverables necessary to satisfy requirements specified under this contract and individual TOs. The Contractor shall visit and inspect the job site prior to the start of any work. The Contractor shall document (with photos) any damaged areas and promptly turn them into the Installation-ACOR associated with the TO, so as to preclude any responsibility for damages present that are not a result of the performance of work required in the TO. In the absence of the COR, the Contractor will report to the Alternate COR (ACOR).

1.2 Dig Permit: Any work involving disturbance of earth will require a Dig Permit. The Dig Permit shall be submitted at least 30 calendar days prior to digging. The Contractor will be required to resubmit the Dig Permit every thirty (30) calendar days to ensure all agencies remain aware of the ongoing work and so that other agencies can notify the Contractor of any changes to the project site that may have occurred. Each subsequent Dig Permit shall be provided to the project inspector no later than the termination of the previous 30-day period.

1.3 Electrical Service and Communications Facilities: The Contractor shall not disturb electrical or communications facilities and wiring not discussed in the SOW or drawings. Where such facilities require removal for accomplishment of the project work, the Contractor shall notify the Contracting Officer in coordination with the DPW in writing at least seven (7) calendar days in advance of the requirement, for the accomplishment of such removal work by the Government. The Contractor shall allow the utility owner to remove the systems required. If the lines are damaged by the Contractor’s construction activities, the Contractor shall restore service within twenty-four (24) hours with no cost to the Government.

1.4 Disruptions: The Contractor shall perform work in a manner that will minimize disruptions to normal base operations. The Contractor shall notify the Contracting Officer if there are disruptions to sprinkler or alarm systems requiring either the evacuation of the building or a fire watch provided by the Contractor. Any disruptions to Fire Protection systems will be coordinated with DPW and the respective Fire Marshal/Fire Department.

Statement of Work – National Capital Region Indefinite Delivery-Indefinite quantity Multiple Award Task

1.5 Route: Only routes designated by the Contracting Officer for each TO shall be utilized by the Contractor for access to the work site. The use of an existing elevator shall be approved by the Contracting Officer prior to use.

Such use will be of an intermittent and temporary nature. The Contractor shall protect the elevator against damage due to their use. In no case shall the load exceed the rated capacity of the elevator.

1.6 Contractor Vehicles: The company name shall be prominently displayed on all Contractor vehicles operated on Army installations and the ANC. The Contractor may obtain entry passes at the Visitors Center for vehicles needed to transport materials and equipment. The Contractor will be required to present proof of insurance, driver’s license, vehicle registration, and other documentation as needed to obtain vehicle entry pass. Entry to restricted areas of an installation will require a vehicle pass and additional clearances. All commercial vehicles requiring installation access will require inspection through the respective gate (see site specific requirements).

1.7 Contractor Storage/Laydown Yard: There is no designated Contractor Storage/Laydown Yard provided. The Contractor is encouraged to use the TO job site for staging materials. The Contractor is advised that an off-base storage/staging area may be useful for execution of some TOs. Security shall be the responsibility of the Contractor in all cases. The Government has no liability for materials or equipment which become lost or damaged.

1.8 TO Coordination: The contracts team will verify licenses and bonding prior to issuing a Notice to Proceed.

Prior to scheduling work for a TO, the Contractor shall coordinate with the Installation-ACOR associated with the TO to agree on a sequence of procedure, means of access to premises/building, space for storage of materials and equipment, delivery of materials, and use of corridors, stairways, elevators, eating spaces, and restrooms for Contractor personnel.

1.8.1 On-Site Staff: The Contractor shall provide to the Contracting Officer, an employee roster identifying the Contractor’s on-site project staff prior to the TO performance. The roster shall include the individual’s name and job title.