About this file

This is a bid specification document from the Consolidated School District of New Britain for painting services at New Britain High School's auto shop facility located at 110 Mill Street, New Britain, Connecticut 06051. The project scope includes painting the ceiling with two coats of PPG 6-725xi Speed Hide Acrylic Dry Fall black paint, painting walls and room structures with two coats of PPG 16-1510 PPG Pitt-Glaze WB water-based epoxy, painting a chain link fence black, and applying a DuraFlex Hibriflex floor coating system with solid color to be determined. The work also encompasses comprehensive preparation activities including masking, protecting equipment and doorways, and final cleanup. A mandatory walkthrough is scheduled for November 3, 2025 at 9:00 a.m., with all interested contractors required to attend to qualify for the bidding process. Written inquiries or questions must be submitted to Robert Smedley at Smedley@csdnb.org by November 10, 2025. Sealed bids are due November 14, 2025 at 10:00 a.m. at 250 John Downey Drive, New Britain, Connecticut 06051. The work is scheduled to commence December 15, 2025 and must be substantially completed by January 6, 2026, with no work permitted on December 24, 25, 26, or January 1, 2026. Work hours are Monday through Friday 7:00 a.m. to 10:00 p.m. and Saturday 7:00 a.m. to 3:00 p.m.

The district will award the contract to the lowest responsible bidder in its best interest, considering factors including contractor qualifications and experience with public school projects, ability to meet the project schedule, and total project cost. Proposals must remain valid for 60 days following the bid opening. A $500 per calendar day penalty applies for each day beyond the January 6, 2026 substantial completion date. The successful bidder must provide comprehensive insurance coverage including general liability of $1,000,000 per occurrence with $2,000,000 general aggregate, auto liability of $1,000,000 combined single limit, professional liability of $1,000,000 per occurrence and aggregate, and umbrella coverage of $1,000,000 per occurrence and aggregate. Workers' compensation insurance must comply with statutory limits. The contractor must comply with prevailing wage requirements (Federal Davis-Bacon wages) if the project exceeds $100,000. Contractors must demonstrate compliance with immigration laws, non-discrimination requirements, and Connecticut General Statutes Section 4a-60a regarding equal employment opportunities and affirmative action. Payment and performance bonds are required under Connecticut's Little Miller Act for public works projects exceeding $100,000. The district is exempt from federal excise taxes and Connecticut sales and use taxes, and the successful bidder must provide a completed W-9 form prior to contract execution.

View the file

Other files

File Type Posted
33259_Jan_27_26_solicitation_doc.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Consolidated School District of New Britain New Britain High School Auto Shop Painting

Bid Specification

New Britain High School- 110 Mill Street, New Britain, CT 06051

Mandatory walkthrough - November 3, 2025 @ 9am

Inquiries or Questions Due by November 10, 2025 to Smedley@csdnb.org

Sealed Bids Due November 14, 2025 at 10am at 250 John Downey Drive, New Britain, CT 06051

Start of Work: Completion by: January 6, 2026 Dec 15, 2025

1.0 GENERAL INFORMATION:

A walk through will be held at New Britain School and will be held on November 3, 2025 at 9am. All interested contractors or vendors need to attend this walk through to qualify for the bid process.

No alleged "verbal interpretation" shall be held valid. No oral interpretations shall be made to any respondent as to the meaning of any of these documents or to be effective to modify and of the provisions of this request. Every request for an interpretation shall be made in writing via e-mail to Robert Smedley Smedley@csdnb.org by November 10, 2025.

All questions received as above provided, and the decision regarding each, will be arranged as addenda.

Any related addenda will be published on www.csdnb.org/bids and emailed to vendors, and shall become part of the contract. Prospective respondents may obtain a copy of the addenda, if any, via e-mail and/or online at the District's website at http://www.csdnb.org/bids

Non-receipt of said addenda shall not excuse compliance with said addenda. It is the responsibility of each respondent to determine whether any addenda have been issued and if so, whether the respondent has received a copy of each. Addenda issued during the bidding period shall supersede any previous information.

Each bidder is considered to have examined the work to fully acquaint themselves with the exact existing conditions relating to the work and has fully informed himself as to the work involved and the difficulties and restrictions attending the performance of this bid. The submission of a bid will be considered as conclusive evidence that the bidder has made such an examination.

Each bidder contemplating the use of any subcontractor shall submit a list of subcontractors. The apparent low bidder shall file with CSDNB within five (5) days after the date of bid opening, a complete list of the names and addresses of competent, responsible and qualified subcontractors who are actually to perform major portions of the work. This in no way restricts or limits the requirement that all subcontractors must be approved by CSDNB. Subcontractors listed on the Bid Form or those previously approved may not be changed without the approval of CSDNB.

1.0 General Information Continued:

Inasmuch as this work concerns a needed public improvement, the provisions of this bid relating to the time of delivery, performance and completion of the work are of the essence of this bid. Accordingly, the successful bidder shall commence work upon receipt of the signed Purchase Order unless CSDNB shall authorize or direct a further delay. Time of delivery shall be stated as the number of calendar days following receipt of the Purchase Order by the Bidder to receipt of the goods or services by Consolidated

School District of New Britain. Prices quoted must include delivery to the Consolidated School District of

New Britain as specified on the Purchase Order. No charges will be allowed for parking, crating, freight, express or cartage unless specifically stated and included in this bid.

Time of delivery and completion of the project will be considered in the award. Please refer to the schedule of work attached.

1.1 SCOPE OF WORK - PROPOSAL OVERVIEW

The Consolidated School District of New Britain seeks to have a qualified contractor paint the ceiling, walls and floor of the NBHS Auto Shop.

Work conducted for this project shall follow trade standards for professional commercial style painting and in general shall be conducted consistent with trade standards as defined in local or state building codes.

A. Preparation Work

a. Mask ceiling and wall mounted devices, lights, alarms and clocks.

b. Protect walls, floors and ceilings where necessary from overspray.

c. Protect doorways into the classroom and hallway to prevent dust/overspray.

d. Protect all equipment permanently mounted in the room.

i. Car lifts, compressors, automotive machines

e. Clean and prep floor for application of floor coating system according to floor coating system specifications.

B. Paint Ceiling

a. Materials: PPG 6-725xi Speed Hide Acrylic Dry Fall

b. Apply two coats of black paint to all ceiling areas extending down 6 coarse of block on walls to meet drop ceiling in teaching area. (see photo attached.)

i. Existing ceiling is coated with Acrylic Dryfall

c. Follow all manufacture application guidelines

C. Paint walls and room structures

a. PPG 16-1510 PPG Pitt-Glaze WB 1 Single component Water Base Epoxy

b. Apply two coats of paint to all walls and columns. Color to match the existing newly painted area.

c. Follow all manufacturer application guidelines

d. Paint chain link fence. Color: Black

D. Floor Coating

a. Apply DuraFlex ⅛ inch Hibriflex system to the floor. Solid Color TBD.

1.2 SPECIAL INSTRUCTIONS

Vendors responding to this RFQ must have sufficient staff to assure timely project completion. A penalty in the amount of $500 per calendar day will be applied as a back charge to the vendor for failure to meet the substantial construction completion date of January 6, 2026. The awarded vendor will be charged

$500 per day for each day beyond January 6, 2026 for work not completed.

The bidders Project Manager must be experienced in educational facilities work and the public bidding environment, with emphasis on public school projects. Key consultants must also assign licensed, certified and experienced personnel who are knowledgeable in this type of project.

Respondents are hereby notified that all proposal submittals and information contained therein are attached thereto shall become public information upon selection of the successful bidder.

Comprehensive responses to the RFQ are expected. Additional information, not specifically requested, will be considered if provided.

The District reserves the right to reject any or all proposals for any reason it determines to be in its best interest or, in the alternative, to abandon the selection process in whole or in part. The district is not obligated to select the lowest priced vendor or lowest price submission. The District reserves the right to request additional information from any vendor at any time after proposals are submitted or opened.

No fee or mark-up may be charged for reimbursable expenses. Expenses of outside printing, copying and reproducible drawings shall be reimbursed at the vendors direct cost.

Please be advised that the person signing the formal proposal must be authorized by your organization to contractually bind your firm with regard to prices and related contractual obligations for the request.

1.3 SCOPE OF SERVICES

Services to be provided will include, but may not necessarily be limited to the following:

1. Owner walkthrough to finalize project expectations

2. Schedule of work showing start date, progress dates and project completion date.

3. Schedule of Values at request of owner for all materials

4. Regular meetings with the owner's representative to provide project progress updates.

5. Preparation of area of reclamation and preparation of areas to be paved.

6. Signage to be posted in the immediate area of the project to ensure public/ student/ staff pedestrian and vehicle safety.

7. Provision of proper refuse removal containers or dumpsters. Onsite school dumpsters are not to be used.

8. Provision of waste manifests if applicable to project and materials

9. Final clean of project area to include “Broom Clean.”

The vendor is responsible for all site preparations to ensure that proper installation or demolition and application of all materials is compliant with local building code standards and to the manufacturer specific standards.

The vendor will be responsible for “Call Before You Dig” services if necessary.

The vendor is responsible for all permits necessary to complete the specified work.

Working hours will be Monday Through Friday 7am - 10pm and all equipment, tools & machinery must be secured at the end of each day. Saturday work is permitted from 7am -3pm.

These objectives are an example of the items that shall be addressed, but are in no way limited in scope to these alone.

1.4 PROPOSAL SUBMISSION GUIDELINES AND FORMAT

All submissions shall be provided in sealed big packages to Robert Smedley: 250 John Downey Dr. New

Britain, CT 06052. Please label your envelope “NBHS Autoshop Painting” Sealed bid packages are

DUE November 14, 2025 at 10am.

All blank spaces for proposal prices must be completed in ink or be typewritten; proposal prices must be stated in both words and figures. The person signing the Proposal Form must initial any errors, alterations or corrections on that form. Ditto marks or words such as "SAME" shall not be used in the

Proposal Form.

Proposals may be withdrawn personally or in writing provided that the Board of Education receives the withdrawal prior to the time and date the proposals are scheduled to be opened. Proposals are considered valid, and may not be withdrawn, canceled or modified, for sixty (60) days after the opening date, to give the District sufficient time to review the proposals, investigate the proposers' qualifications, secure any required municipal approvals, and execute a binding contract with the successful proposer.

Upon award of the RFP, the winning respondent shall be bound by the proposal price throughout the contract period. An authorized person representing the legal entity of the proposer must sign the

Proposal Form and all other forms included in this RFP.

All proposals will be publicly opened and received on the date, at the time, and at the place identified in this RFP. Proposers may be present at the opening. The District reserves the right to correct, after proposer verification, any mistake in a proposal that is a clerical error, such as a price extension, decimal point error or FOB terms. If an error exists in an extension of prices, the unit price shall prevail. In the event of a discrepancy between the price quoted in words and in figures, the words shall control.

The District reserves the rights to accept all or any part of a proposal, reject all proposals, and waive any informalities or non-material deficiencies in a proposal. The District also reserves the right, if applicable, to award the purchase of individual items under this RFQ to any combination of separate proposals or proposers.

The District will accept the proposal that, all things considered, the District determines is in its best interests. Although price will be an important factor in most RFPs, it will not be the only basis for award.

Due consideration may also be given to a proposer's experience, references, service, ability to respond promptly to requests, past performance, and other criteria relevant to the District's interests, including compliance with the procedural requirements stated in this RFP. The District will not award the proposal to any business that or person who is in arrears or in default to the District with regard to any tax, debt, contract, security, or any other obligation.

The award may be subject to further discussions with the proposer. The making of a preliminary award to a proposer does not provide the proposer with any rights and does not impose upon the District any obligations. The District is free to withdraw a preliminary award at any time and for any reason. A proposer has rights, and the Board has obligations, only if and when a Contract is executed by the

District and the proposer.

The Consolidated School District of New Britain and the City of New Britain are not responsible for any costs incurred by any Responder in connection with this RFP. The expenses incurred by any Responder in the presentation, submission, and presentation of their proposal are the sole responsibility of the

Responder and shall not be charged to the Board of Education, the City of New Britain.

Each proposer is responsible for having read and understood each document in this RFP and any addenda issued. A proposer's failure to have reviewed all information that is part of or applicable to this

RFQ, including but not only any addenda posted on the District's website, shall in no way relieve it from any aspect of its proposal or the obligations related thereto. Each proposer is deemed to be familiar with and is required to comply with all federal, state, and local laws, regulations, ordinances, codes and orders that in any manner related to this RFP or the performance of the work described herein.

By submitting a proposal, each proposer represents that it has thoroughly examined and become familiar with the scope of work outlined in this RFQ, and it is capable of performing the work to achieve the District's objectives. If applicable, each proposer shall visit the site, examine the areas and thoroughly familiarize themself with all conditions of the property before preparing its proposal.

The District reserves the right, either before or after the opening of proposals, to ask any proposer to clarify its proposal or to submit additional information that the District in its sole discretion deems desirable.

1.5 Wages and Salaries

A. Attention of bidders is particularly called to the requirements concerning the payment of not less than the prevailing wage (Federal Davis Bacon wages) and salary rates specified in the

Contract Documents and the conditions of employment with respect to certain categories and classifications of employees; if the total amount of project is more than $100,000 . (This is not state wages.) Please visit the the site listed here for information:

(dol.gov/agencies/whd/forms/wh347)

B. The rates of pay set forth within the Contract Documents are the minimum to be paid during the life of the contract. It is therefore the responsibility of bidders to inform themselves as to local labor conditions, such as the length of work day and work week, overtime compensation, health and welfare contributions, labor supply and prospective changes or adjustments of rates.

C. The bidder is advised of the requirement under this contract for compliance with the Federal

Labor Standards Provisions including the “Anti-Kickback Act” and Labor Standards for Ratios of

Apprentices and Trainee to Journeymen (Exhibit B)

1.6 GENERAL CONDITIONS

A. Non-Discrimination and Affirmative Action - Respondent, in performing under this contract shall not discriminate against any worker, employee or applicant, or any member of the public, because of race, creed, color, age, marital status, sexual orientation, national origin, ancestry, sex, mental retardation or physical disability, including but not limited to blindness, unless it is shown by the Respondent that such disability prevents performance of the work involved in any manner prohibited by the laws of the United States of the State of Connecticut, nor otherwise commit an unfair employment practice. Respondent further agrees that this article, (and any additional provisions required by law), will be incorporated by Respondent in all contracts entered into in connection with this contract. Every contract to which the State is party must contain the nondiscrimination and affirmative action provisions provided by the Connecticut

General Statutes Section 4a-60a.

B. Each proposer must submit a completed Proposer's Certification Concerning Equal Employment

Opportunities and Affirmative Action Policy form included with this RFP. Proposers with fewer than ten (10) employees should indicate that fact on the form and return the form with their proposals.

C. Executive Orders - The contract is subject to the provisions of Executive Order No. Three of

Governor Thomas J. Meskill, promulgated June 16, 1971, concerning labor employment practices, Executive Order No. Seventeen of Governor Thomas J. Meskill promulgated February

15, 1973, concerning the listing of employment openings and Executive Order No. Sixteen of

Governor John G. Rowland promulgated August 4, 1999, concerning violence in the workplace, all of which are incorporated into and are made part of the contract as if they had been fully set forth in it. The contract may also be subject to Executive ORder NO. 7C of Governor M. Jodi Rell, promulgated July 13, 2006, concerning contracting reforms and Executive Order No. 14 of

Governor M. Jodi Rell, promulgated April 17, 2006, concerning procurement of cleaning products and services, in accordance with their respective terms and conditions.

D. Compliance with Immigration Laws - By submitting a proposal, each proposer confirms that it has complied, and during the term of the Contract will comply, with the Immigration Reform and

Control Act ("IRCA") and that each person it provides under the Contract will at all times be authorized for employment in the United States of America. Each proposer confirms that it has a properly completed Employment Eligibility Verification, Form 1-9 for each person who will be assigned under the Contract. The successful proposer shall defend, indemnify, and hold harmless the Consolidated School District of New Britain, its employees, officers, officials, agents, volunteers and independent contractors, including any of the foregoing sued as individuals

(collectively, the "Town Indemnified Parties"), against any and all proceedings, suits, actions, claims, damages, injuries, awards, judgements, losses or expenses, including fines, penalties, punitive damages, attorney's fees and costs, brought or assessed against, or incurred by, the

District indemnified Parties related to or arising from the obligations under IRCA imposed upon the successful proposer or its subcontractor. The successful proposer shall also be required to pay any and all attorney's fees and costs incurred by the District's Indemnified Parties in enforcing any of the successful proposer's obligations under this provision, whether or not a lawsuit or other proceeding is commenced, which obligations shall survive the termination or expiration of the Contract.

E. Payment Bond/Performance Bond State Law Requirements - Conn. Gen. Stat. Sec. 49-41, known as the Little Miller Act, requires that the District ensure that payment bonds a/k/a labor and materials bond in the amount of the contract are provided for public works projects over

$100,000. When a contract for construction, alteration, remodeling, repair or demolition of any public building is estimated to cost more than $500,000 additional laws/requirements apply. The contractor should familiarize themselves with all aspects of state law and any applicable regulations pertaining to these requirements in order to ensure full compliance.

F. Equal Employment Opportunity (EEO) - Minority Business Enterprises (MBE). If a project is funded in whole or in part by state or federal funds, there may be a requirement that the contractor comply with Conn. Gen. Stat. Sec. 4a-60 and applicable State regulations. On these projects it will depend upon which set-aside requirements are imposed by the funding agency. If no set-aside requirement is imposed, a statement that the contractor is required to undertake good faith efforts to include subcontractors and suppliers who are minority business enterprises will suffice and shall be deemed to be incorporated into the Contract with the District. If there is a set-aside goal, the District and contractor shall comply with the Small Contractors Set-Aside

Program and the hiring goals identified by the State Commission on Human Rights and

Opportunities (CHRO).

G. Tax Exemptions - The District is exempt from the payment of federal excise taxes and

Connecticut sales and use taxes. The District is exempt from State sales tax.

H. Assigning, Transferring of Agreement - The successful Respondent is prohibited from assigning, transferring, converting, subletting or otherwise disposing of this agreement, its rights, title or interest therein or its power to execute such agreement by any other person, company, or corporation without the prior consent and approval in writing by the Town.

I. Advertising - The successful proposer shall not name the District in its advertising, news releases, or promotional efforts without the District's prior written approval. If it chooses, the successful proposer may list the District in a Statement of References or similar document required as part of its response to a public procurement. The District's permission to the successful proposer to do so is not a statement about the quality of the successful proposer's work or the District's endorsement of the successful proposer.

J. W-9 Form - The successful proposer must provide the District with a completed W-9 form before

Contract execution.

K. Non-Employment Relationship - The District and successful proposer are independent parties.

Nothing contained in the Contract shall create, or be construed or deemed as creating, the relationships of principal and agent, partnership, joint venture, employer and employee, and/or any relationship other than that of independent parties contracting with each other solely for the purpose of carrying out the terms and conditions of the Contract. The successful proposer understands and agrees that it is not entitled to employee benefits, including but not limited to worker's compensation and employment insurance coverage, and disability. The successful proposer shall be solely responsible for any applicable taxes.

L. Amendment/Termination - The District may, before and after proposal opening and in its sole discretion, clarify, modify, amend or terminate this RFP if the District determines it is in the

District's best interest. Any such action shall be effected by a posting on the District website, www.csdnb.org. under "Departments", "Finance and Contracted Services". Each proposer is responsible for checking the District website to determine if the District has issued any addenda and, if so, to complete its proposal in accordance with the RFP as modified by the addenda.

M. Penalties- The District may apply penalties to the contract for any extensive delay in delivery of materials or construction and services as required in this bid and subsequent contract in the amount of $500 per day per instance until materials or services are delivered. Stop work, abandonment or termination of the contract by contractor is also subject to penalties of $500 per day including termination of contract by the Consolidated School District of New Britain and any associated legal or court fees necessary to settle any dispute.

1.7 CRITERIA FOR EVALUATING PROPOSAL SUBMISSIONS

A. The Facilities Department will evaluate the proposals and establish a shortlist of finalists based on the lowest responsible bid in the best interest of CSDNB. The shortlisted vendors will be evaluated and one will be considered based on:

1. The firm's qualifications, experience and demonstrated familiarity with Public School projects in general and specifically renovation projects of similar size, scope and nature and

2. The ability to meet the schedule of work and

3. Total cost of project.

B. The Committee's recommendation for the most responsive and responsible respondent shall be presented to the Board of Education for approval and for final negotiations to finalize the contract(s) in conformance with the District requirements and subject to BOE approvals and possible review by the District attorney. The contract will not be deemed to be awarded until a written contract, in a form acceptable to the District, has been fully executed by both parties.

C. The factors listed below will be considered as stated in section A. This list is not necessarily exclusive.

a. The key personnel assigned to the project and their present workload.

b. The project team's experience with projects of similar nature and scope.

c. The firm's qualifications, experience and demonstrated familiarity with Public School

Building projects in general and specifically renovation projects of a similar size, scope and nature.

d. Previous design and oversight experience in projects involving alterations and renovations to similar facilities, equipment and services.

e. The proposed project approach and how staff and consultants will be organized and utilized both during design and construction administration phases.

f. Extent of services offered and depth and extent of overall resources that can be put to use to ensure the success of the project.

g. Availability and continuity of staff during the course of the agreement, if selected.

h. Identification of critical issues that could affect a successful outcome.

i. Detailed work experience on similar projects during the last 5 years.

j. A detailed statement including the organizational structure under which the firm proposed to conduct business.

Although price will be an important factor in most RFPs, it will not be the only basis for award. Due consideration may also be given to a proposer's experience, references, service, ability to respond promptly to requests, past performance, and other criteria relevant to the District's interests, including compliance with the procedural requirements and schedule stated in the RFP.

The District Selection Committee may choose finalists to interview.

1.8 INSURANCE REQUIREMENTS

The Contractor shall provide and maintain insurance coverage related to its services in connection with the Project in compliance with the following requirements.

The insurance required shall be written for not less than the scope and limits of insurance specified hereunder, or required by applicable federal, state and/or municipal law, regulation or requirement, whichever coverage requirement is greater. It is agreed and understood that the scope and limits of insurance specified hereunder are minimum requirements and shall in no way limit or preclude the

District from requiring additional limits and coverage to be provided under the Contractor's policies.

Minimum Scope of Limits of Insurance

The Contractor awarded shall agree to maintain in force at all times during the contract the following minimum coverages and shall name “The City of New Britain and the Consolidated School District of New

Britain” as an Additional Insured on a primary and noncontributory basis to all policies, except Workers

Compensation. All policies should also include a Waiver of Subrogation. Insurance shall be written with

Carriers approved in the State of Connecticut and with a minimum AM Best's rating of "A-"VIII.

General Liability (Minimum Limits)

Each Occurrence $1,000,000

General Aggregate $2,000,000

Products/Completed Operations Aggregate $2,000,000

Auto Liability

Combined Single Limit Including Hired $1,000,000

/Non Owned Auto Liability

Professional Liability

Each Claim or Each Occurrence $1,000,000

Aggregate $1,000,000

Umbrella

Each Occurrence $1,000,000

(Excess Liability)

Aggregate $1,000,000

If any policy is written on a "Claims Made" basis, the policy must be continually renewed for a minimum of two (2) years from the completion date of this contract. If the policy is replaced and/or the retroactive date is changed, then the expiring policy must be endorsed to extend the reporting period for claims for the policy in effect during the contract for two (2) years from the completion date.

Workers' Compensation and employers' Liability WC Statutory Limits

EL Each Accident $1,000,000

EL Disease Each Employee $1,000,000

EL Disease Policy Limit $1,000,000

The Contractor must provide a current Certificate of Insurance to the Consolidated School District of

New Britain prior to commencement of work. The Contractor agrees to provide replacement/renewal certificates at least 30 days prior to the expiration date of the policies. Should any of the above described policies be canceled, limits reduced or coverage altered, 30 days written notice must be given to the

Consolidated School District of New Britain.

Subcontractors

The Contractor shall require all subcontractors to provide the same "minimum scope and limits of insurance" as required herein, with the exception of Errors and Omissions/Professional Liability insurance, unless Errors and Omissions/Professional Liability insurance is applicable to the Work performed by the subcontractors. All Certificates of Insurance shall be provided to the Consolidated

School District of New Britain as required herein.

Aggregate Limits

Any aggregate limits must be declared to and be approved by the Consolidated School District of New

Britain. It is agreed that the Contractor shall notify the Consolidated School District of New Britain whenever fifty percent (50%) of the aggregate limits are eroded during the required coverage period. If the aggregate limit is eroded for the full limit, the Contractor agrees to reinstate or purchase additional limits to meet the minimum limit requirements stated herein.

Any premium for such shall be paid by the Contractor.

Deductibles and Self-Insured Retentions

Any deductible or self-insured retention must be declared to and approved by the Consolidated School

District of New Britain. All deductibles or self-insured retentions are the sole responsibility of the

Contractor to pay and/or to indemnify.

Waiver of Governmental Immunity

Unless requested otherwise by the Consolidated School District of New Britain, the Contractor and its insurer shall waive governmental immunity as defense and shall not use the defense of governmental immunity in the adjustment of claims or in the defense of any suit brought against the Consolidated

School District of New Britain.

1.9 BID PROTEST PROCEDURES

CONSOLIDATED SCHOOL DISTRICT OF NEW BRITAIN PROTEST PROCEDURE

A. Submission of Protest

1. In the event a bidder wishes to protest the award of a bid, the protesting party may submit a protest to the Chief Operations Officer within five (5) business days after the delivery of bid results, in writing, setting forth the basis on which the protesting party challenges a contract awarded by the selection committee.

2. A protest must be submitted to the Chief Operations Officer at the address provided in the RFP and include the following:

a. Name, address, e-mail address and telephone number of the protesting party.

b. Bid, proposal, or contract number.

c. Detailed statement of the legal and factual grounds for the protest, including a description of resulting prejudice to the protesting party.

d. Copies of all relevant documents.

e. Request for a determination by the Chief Operations Officer.

f. Statement of the relief requested.

g. Information establishing that the protest was timely filed in accordance with this protest procedure.

3. The successful bidder may, but is not required to, file an answer to the protest with the Chief

Operations Officer. Any answer by the successful bidder must be postmarked no later than ten (10) business days after the successful bidder's receipt of the protest.

4. Any untimely protest will not be considered and will be returned to the protesting party.

B. Review of Protest and Determination:

1. Upon receipt of the protest, the Chief Operations Officer shall review the protest, supporting documents, and any other documents, including an answer by the successful bidder, if any, and issue a written determination within forty-five (45) business days after receipt of the protest.

The protest office may take any action or make any requests he or she deems necessary to investigate the protest, including extending the time to issue a decision to obtain all evidence and other pertinent information.

2. A conference with respect to the protest shall be scheduled by the Chief Operations Officer and shall be attended by their designee and such other persons as the Chief Operations Officers shall require to attend. The subject matter of the conference shall be limited to the reasons for the protest specified in the written request for the conference. The conference shall also include a discussion of the notice of determination with the reason(s) upon which it is based. The protesting party shall be advised their right to appeal an unfavorable determination.

C. Appeals

1. The determination rendered by the Chief Operations Officer to resolve the protest shall be the conclusive and final determination of the protest, unless, within ten (10) business days after the protest conference, an appeal is postmarked by the protesting party or successful bidder. The appeal shall be in writing and sent to the appeals officer at the address provided for in the bid or proposal, or as provided at the protest conference. The successful bidder may, but is not required to, submit an answer or further documentation in opposition to an appeal filed by the protesting party.

2. The appeals officer will consider all information relevant to the protest, and may, at its discretion, suspend, modify, or cancel the disputed procurement action prior to issuance of a formal dispute decision.

3. No evidence or information may be introduced or relied upon in the appeal that has not been presented to the Assistant Director of Finance. The appeals officer shall review the appeal and supportive documents. The appeals officer will issue a written decision within ten (10) business days of receipt of the appeal. The appeals officer may take any action or make any requests he or she deems necessary including extending the time to issue a written determination. A copy of the written determination, stating the reason(s) upon which it is based shall be sent to the protesting party and the successful bidder by mail. The determination of the appeals officer shall be the District's conclusive and final determination of the protest.

Pursuant to and in compliance with the proposed Contract Documents prepared by OWNER the undersigned, having become thoroughly familiar with the terms and conditions of the Contract Documents and with local conditions affecting performance and costs of the work at the place where the work is to be completed, hereby proposes and agrees to furnish all labor and materials required to perform the work within the time stated, in strict accordance with the proposed Contract Documents for the prices specified below:

A. Base Bid: (Typical Description below)

1. Painting of Automotive Shop area to include ceiling, walls and floor.

(Amount written in words)

Start of Work: December 15, 2025 - Completion of Work: January 6, 2026

The above price totals will remain valid for 90 days from the signed date below.

Vendor: ________________________________________________________________________

Signed: __________________________________________

Date:______________________

Printed Name: ____________________________________

Phone: ____________________

Bid Process Schedule:

Bid Posted: October 28, 2025

Walkthrough: November 3, 2025 @ 9am at 183 Steele Street, New Britain, CT 06052

Bids Due: November 14, 2025 at 10am @ 250 John Downey Drive. New Britain, CT 06052

Schedule of Work:

Start of Work: Completion by: January 6, 2026 Dec 15, 2025

- No work on Dec 24, 25, 26 and January 1, 2026

- Work can be done on first and second shift

- Saturday work is permitted (must pre schedule)

Vendor Acknowledgement of Schedule of Work Dates:

Vendor: ________________________________________________________________________

Signed: __________________________________________ Date:______________________

Printed Name: ____________________________________ Phone: ____________________

Notice of Subcontractor Assignment

Name of Subcontractor firm 1:

Address of firm:

Phone Number of Primary / Lead:

Work to be performed by Subcontractor:

Date of work assignment:

Expected completion of work by subcontractor:

Name of Subcontractor firm 2:

Name of Subcontractor firm 3:

File details come from the government source that posted it. Updated .