Statement of Work Summary

This Statement of Work (SOW) specifies Construction Quality Assurance (QA) and Coordination services for NASA's Goddard Space Flight Center (GSFC) Greenbelt campus in Maryland and Wallops Flight Facility (WFF) in Virginia. The contract covers quality assurance, inspection, documentation, and coordination services for construction projects categorized as Center-Funded (CF), Construction of Facilities (CoF), or Customer Funded (Cust). Services encompass monitoring OSHA safety compliance, performing independent construction inspections, reviewing design and construction documents, conducting inspections of civil, architectural, structural, mechanical, electrical, and specialty systems work, coordinating day-to-day construction activities with facility occupants and contractors, processing invoices, managing project closeouts and punch list resolution, and preparing daily reports. The QA Contractor will employ on-site personnel within the GSFC Facilities Management Division Engineering Branch (Code 224 for Greenbelt, Code 228 for WFF) and maintain a distributed skill mix across construction disciplines.

The contract requires QA staff to maintain specific qualifications depending on their level. QA Level 5 (Site Manager) requires a high school diploma minimum, 20 years construction industry experience, 10 years QA experience, and 3 years managing a QA team. QA Level 4 Inspectors require a high school diploma, 15 years construction experience, and 10 years QA experience, plus current certifications in Construction Quality Management for Contractors and OSHA 30-hour Construction Safety Course. All QA staff must obtain GSFC security badges and maintain flexible work schedules to support construction activities occurring after hours and weekends while maintaining a 40-hour work week. Optional services available via task order include Commissioning Authority (CxA) services requiring personnel with specific certifications (BCxA CCP, ACG CxA, or ASHRAE BCxP), minimum 5 years commissioning experience, 10 years HVAC/controls systems experience, and preferably a bachelor's degree in mechanical or electrical engineering with a PE license. The Government provides office space, computers, software (Trimble Prolog, Microsoft Office), phones, vehicles with fuel, and communications radios, while the Contractor supplies inspection tools, personal protective equipment, cell phones, and mobile devices with construction management software.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

FOR THE

NASA GODDARD SPACE FLIGHT CENTER

GREENBELT AND WALLOPS FLIGHT FACILITY

CONSTRUCTION QUALITY ASSURANCE AND

COORDINATION SERVICES

JANUARY 14, 2026

TABLE OF CONTENTS

1.0 Overview

1.1 Hours of Operation

1.2 Qualifications of QA Staff

1.4 Resources Provided by the Government

1.5 Resources Provided by the Contractor

2.0 Services Provided by the QA Contractor for Quality Assurance

2.1 Monitor for OSHA Safety Compliance

2.2 Construction Inspection

2.2.1 General

2.2.2 Types of Work

2.3 Construction Coordination

2.4 Invoice processing

2.5 Close-Out Management

2.6 Punch List Resolution

2.7 O&M Manuals

2.8 As-Built Accuracy Review

2.9 Meetings

2.9.1 Pre-Construction Meetings

2.9.2 Progress Meetings

2.9.3 Weekly General Construction Meetings

2.9.4 Resolution Meetings

2.9.5 CQC Meetings

2.10. Deliverables for QA Services

2.10.1 Daily Reports

2.10.2 Design Document Review

2.10.3 Construction Document Review

2.10.4 Construction Contract Modifications

2.10.5 Test Logs

2.10.6 Discrepancy Logs

2.10.7 Independent Testing (If requested via Task Order)

2.11 Commissioning Services (If requested via Task Order)

2.11.1 CxA Tasks

2.11.2 Qualifications of Commissioning Personnel

3.0 Document Control Services (If requested via Task Order)

4.0 Contract Level Provisions

4.1 Conducting Operations at GSFC

4.2 Submittals

4.2.1 Quality Assurance Plan

4.3 Safety and Environmental References

5.0 Definitions/Acronyms

6.0 Travel Requirements

1.0 Overview

This contract provides Construction Quality Assurance (QA) and Coordination services for construction work performed by NASA/Goddard Space Flight Center (GSFC), Greenbelt, MD campus and Wallops Flight Facility (WFF) Wallops Island, VA. Construction categories are defined as: 1) Center-Funded (CF), 2) Construction of Facilities (CoF), and 3) Customer Funded (Cust), and will be recognized in the task scopes. Large discrete CoF projects and other projects not fitting these three categories shall be tasked separately.

The Greenbelt campus is approximately 1,100 acres with 36 major buildings, two central power plants and electrical substations, several outlying sites and numerous smaller outlying buildings, and associated infrastructure of roadways and underground utilities. It has more than 3,000,000

sq. ft of research, development and office space. GSFC/Greenbelt is unique in that these facilities provide for the construction and development of spacecraft software, scientific instruments and satellites, information processing centers for satellites, and research and development of programs pertaining to the planet. WFF is a multi-user/multi-tenant facility supporting satellite command and control, military operations, scientific investigations, technology development, and commercial aerospace. Tenant agencies include U.S. Navy, National Oceanic and Atmospheric Administration (NOAA), and Virginia Commercial Space Flight Authority (VCSFA), also known as Virginia Spaceport Authority.

The QA services required under this contract include but are not limited to: quality assurance, inspection, documentation, document control, coordination of construction with Center operations and construction contractors, review of design drawings, specifications, shop submittals associated with the work, and safety monitoring.

The types of projects include but are not limited to: site work and new building construction, alterations, renovation, and repair of buildings. Types of work include but are not limited to:

underground utilities, roads and parking lots, sidewalks, office buildings and state of the art technical facilities, laboratories, clean rooms, central power plants, and high voltage substations and distribution systems. Typical building systems include: walls and architectural finishes, structural, bathrooms and plumbing systems, central and local mechanical Heating, Ventilation, and Air Conditioning (HVAC) systems, process gas and high purity water distribution systems, electrical distribution, grounding, lightning protection, and lighting.

The contractor employees will be located on-site and within the GSFC Facilities Management Division (FMD) – Engineering Branch (Code 224 for Greenbelt and Code 228 for WFF) organization, which is responsible for the design and construction of facility projects for GSFC.

Construction projects are accomplished via wide range of contract vehicles, including, but not limited to:

1. ROME (Repair, Operations and Maintenance, Engineering);

2. “Invitation for Bid” contracts;

3. TProjects constructed by other GSFC organizations but monitored by FMD; and

4. Construction of Facilities Projects some of which are performed by outside contractors.

1.1 Hours of Operation

The Greenbelt campus and Wallops Flight Facility operate 365 days per year 24 hours per day.

The Greenbelt campus is always accessible via the ICESat Gate on Greenbelt Road. Access to the Wallops Flight Facility is restricted to the WFF Main Gate accessed from Route 798, Mill Dam Road, and via Wallops Island Road, Route 803 to on-site entry gate for the Wallops Island site. However, during severe weather events and other announced emergencies, both sites are closed to all non-essential employees. Safety, security, mission operations, and other specifically designated essential employees will be identified for such events.

Normal business hours for GSFC/Greenbelt and WFF are from 6:00 a.m. to 6:00 p.m. Monday through Friday, except for federal holidays.

The QA Contractor work hours shall be dictated by the variability of the construction work.

Construction contractors work after hours and/or weekends as necessitated by activities that cause disruption to the normal business environment, including noisy work, asbestos abatement, electrical outages, shutdowns of mechanical units, and for expedited schedule purposes.

Generally, the earliest start time is 6:00 a.m. and the latest end time is 6:00 p.m., but hours are often extended, and portions of the work under this contract shall be performed after normal working hours and on weekends.

The QA Contractor’s employees shall be required to support the construction work that occurs after hours and on weekends. The Contractor’s QA employees shall not be required to work matching hours with construction Contractors on after-hours/weekend work, but shall work hours as needed to provide the necessary QA coordination and oversight. The QA Contractor’s employees shall maintain a 40-hour work week to include normal business hours, after hours, and weekend work, by using flexible working schedule and off days.

1.2 Qualifications of QA Staff

The QA Contractor shall ensure that all personnel are qualified on the basis of appropriate education, training, and experience to perform their assigned tasks. The skills of the individuals shall be commensurate with that required for the work. Contractor personnel shall receive adequate annual training to improve and maintain skills required by this contract. At a minimum, training shall cover any changes in the Corps of Engineers Quality Control (QC)-QA program, in the OSHA 1926 regulations, or in the NASA/GSFC safety requirements. There may be opportunities for NASA organized training that the Contractor can take advantage of via System for Administration, Training, and Educational Resources for NASA (SATERN), the Learning Management System (LMS) that provides web-based access to training and career development resources. The Contactor shall coordinate these opportunities with the Contracting Officer (CO)/Contracting Officer’s Representative (COR) at least 10 business days in advance of scheduled training. The QA Contractor shall staff a distributed skill mix to cover construction disciplines, including: civil/structural, architectural, mechanical, electrical, plumbing, and fire protection.

The following qualifications and duties shall be required:

QA Level 5 (Site Manager)

The Site Manager shall be the responsible individual for all Contractor Staff on the contract, and for ensuring the satisfactory performance of all contract requirements. The site manager shall interface with the CO and COR to validate contract compliance, identify and correct deficiencies in personnel, process, and procedures. The site manager shall also provide QA Services for assigned projects.

Education and Experience:

o High School (HS) Diploma;

o A minimum of 20 years of experience in the construction industry;

o A minimum of 10 years of prior quality assurance experience;

o A minimum of 3 years of experience in managing a construction management, quality assurance, or inspection team.

Knowledge, Skills, and Abilities (KSAs):

o Ability to multi-task; ability to manage personnel; ability to develop and present the monthly QA report to the COR.

o All KSAs listed in QA Level 4

QA Level 4

The Level 4 Quality Assurance Inspector shall be primarily responsible for the daily quality assurance and inspection of assigned projects.

Education and Experience:

o High School (HS) Diploma;

o A minimum of 15 years of experience in the construction industry;

o A minimum of 10 years of prior quality assurance experience.

Knowledge, Skills, and Abilities (KSAs):

o Advanced knowledge of the construction industry in applicant’s area of expertise;

o General knowledge of all construction trades and scheduling;

o Competency in OSHA regulations;

o Current certification for Construction Quality Management for Contractors;

o Current certification for OSHA 30-hour Construction Safety Course;

o Working knowledge of GSFC procedures specifically related to construction;

o Ability to read and interpret construction drawings, specifications, and shop drawings;

o Flexibility to work nights and weekends when required;

o Computer skills for MOSI TOMS and MOSI TOSR, MS Office, and MS

Outlook;

o Organizational skills;

o Initiative, responsibility, and flexibility in dealing with construction issues;

o Ability to multi-task and establish priorities;

o Ability to communicate effectively in English, both written and oral;

o Ability to drive a motor vehicle, be mobile on foot in construction sites in fair and inclement weather, access buildings and other improvements under construction, enter and navigate confined spaces, heights, and job conditions including scaffolding, ladders, trenches, etc.;

o Ability to communicate effectively with diverse levels of personnel encountered in the job including construction Contractors, NASA building occupants including scientists, engineers, administrative personnel, operations and maintenance staff, designers, etc.;

o Ability to prepare daily reports, mishap statements, and emails that are concise, factual, and complete;

o Ability to respond to inquiries or complaints from customers, regulatory inspectors, and the general business community at large.

QA Staff shall provide proof indicating they have completed the 30-hour OSHA construction safety program within 60 days of contract award.

QA Staff shall have and maintain a valid certificate of having attended the Construction Quality Management for Contractors, a one day course offered by the Associated General Contractors of America Maryland Chapter (www.marylandagc.org) or the Associated Builders and Contractors Virginia Chapter (www.abcva.org). Certificates are valid for 5 years.

QA Staff shall have the credentials to obtain GSFC Protective Services Office issued badges.

The Contractor shall follow procedures shown in the attachment titled PIV CARD ISSUANCE

PROCEDURES.

1.4 Resources Provided by the Government

The Government will provide:

o Office space and furniture;

o On-site telephone (hard-wired) service;

o Computers and software necessary for the job (Trimble Prolog, office calendaring and email, and Microsoft Office software);

o Communication radios;

o Government owned Motor vehicles with fuel provided by the Government;

o Access to network printers/copiers/fax machines and office supplies.

The QA Contractor personnel shall be responsible for the proper, safe, and controlled use of Government provided equipment. Resources shall only be used for the performance of official duties on Center. All resources remain the property of the Government.

1.5 Resources Provided by the Contractor

The Contractor shall provide:

o Inspection tools such as tapes, levels, circuit testers, etc.;

o Personal Protective Equipment o Cell phones (needed to communicate in the field with construction Contractors that don’t have radios).

o iPads or acceptable alternative mobile devices for field use with construction management software.

2.0 Services Provided by the QA Contractor for Quality Assurance

Construction work is accomplished via a Contractor Quality Control (CQC) system, where the construction Contractor establishes a workforce and procedures to produce quality construction.

Services under this contract shall provide oversight quality assurance of the work performed by construction Contractors. The Contractor shall provide a traditional QA approach to the CQC program. In addition, the QA Contractor also functions as an independent inspector of the construction Contractor’s work on a limited basis. The QA Contractor shall be responsible for inspecting the quality of construction work performed by other Contractors. The QA Contractor shall monitor safety compliance, attend meetings, produce reports, and perform other construction management administrative functions on a daily basis as described in section 2.10.1.

2.1 Monitor for OSHA Safety Compliance

The construction Contractor shall be responsible for safety of their workforce and the worksite as required by OSHA and NASA regulations delineated in the contract.

The QA Contractor shall monitor activities of construction Contractors for compliance with NASA and OSHA safety standards. The QA Contractor shall record the results of their observations in the daily report. Any violation found shall be brought to the attention of the construction Contractor’s superintendent and the Government project manager. If the QA Contractor encounters what is believed to be an imminent life-threatening situation, they shall immediately address the workers involved directly, and then immediately notify the construction Contractor’s superintendent and Government representatives. Examples of life-threatening violations include but are not limited to: violations of lockout/tagout, lack of fall protection, non-compliant trenches and excavations, and confined space violations.

The QA Contractor shall be thoroughly familiar with the construction Contractor’s approved Safety Plan, OSHA requirements, and the GSFC’s Safety Standards.

The QA Contractor shall follow all NASA and OSHA safety standards and requirements in the performance of monitoring the Contractor’s work.

2.2 Construction Inspection

2.2.1 General

The QA Contractor shall inspect the construction work to confirm compliance with the contract plans and specifications, including any approved shop drawings and submittals. Inspection of the work shall be performed independent of and in addition to, the inspection done by the construction Contractor under his CQC program.

The QA inspector shall be familiar with the construction Contractor’s approved Construction Quality Control Plan.

2.2.2 Types of Work

The construction work performed at GSFC involves: civil, architectural, structural, mechanical, and electrical systems. Projects may include demolition (including asbestos removal), earthwork, utilities, pavements, roofing, renovations, finishes, structural steel and concrete, HVAC systems, plumbing, controls systems, fire protection, high and low voltage electrical, and fire alarm work.

Due to the nature of the research and development work done at the GSFC, projects may involve special systems and construction requirements.

2.2.3 Stormwater and Erosion Sediment Control Inspection

At WFF the QA Contractor shall perform Stormwater and Erosion Sediment Control Construction Site Inspections for designated projects upon initial installation of erosion & Sediment Controls; at least once during every two-week period; within 48 hours of any runoff-producing storm event i.e., typically any rain event >1/4” of rain; and upon completion of the project. All WFF QA Inspectors shall maintain current VA Department of Environmental Combined Quality Storm Water Management and Erosion and Sediment Control Inspector certification.

2.3 Construction Coordination

The QA Contractor shall provide assistance to the FMD Project Manager who is the central point of contact for the coordination of construction work among interested parties, including Contractors, customers, building occupants, designers, operations and maintenance personnel, safety personnel, protective service personnel, telecommunications and IT personnel, Building Managers, Facility Operation Managers, Disabilities Coordinator, and GSFC other management.

The QA Contractor shall assist the Project Manager (PM) with coordinating day-to-day activities requiring coordination between the construction Contractor and the Government occupied work area. Coordination includes but is not limited to keeping occupants aware of construction status, being the point of contact for field resolution of construction problems, scheduling of outages, scheduling/coordinating access to the work site, coordinating work with the GSFC Greenbelt freeze schedule, coordinating weekend work with security operations when heavy truck traffic is expected, developing freeze exemption requests, developing hot work/burn permits, coordinating training with O&M department, updating the PM when needed to address issues that cannot be resolved by the QA staff, and similar activities.

While the FMD project manager retains the ultimate responsibility for the project at all times, the QA Contractor shall be the day-to-day point of contact for the construction project.

If tasked through separate task order the QA Contractor’s duties may extend beyond the construction completion to the activation or occupation of the facilities. This includes, but is not limited to, interfacing with and coordinating the telecommunications, security, fire protection, and other logistics functions to ensure that all necessary work is scheduled and implemented in a timely manner to meet the needs of the facility occupants.

The QA Contractor shall work very closely with all parties to coordinate an integrated effort to ensure quality and timely completion of construction projects to meet operational schedules.

2.4 Invoice processing

The QA Contractor shall verify the accuracy of the quantity and quality of work for which the construction Contractor’s progress payment is being requested and make appropriate recommendation to the PM. The review shall be complete within three workdays of the QA receiving the progress report from the PM.

2.5 Close-Out Management

The QA Contractor shall provide project close-out support to the PMs. All facilities equipment scheduled for Operational Readiness Review (ORR) inspections shall be fully operational, tested, adjusted and correctly performing its designed function according to contract requirements PRIOR to scheduling ORRs. This will alleviate any unnecessary delays for the Government’s commissioning O&M personnel. The QA Contractor shall set up and witness the ORR and system commissioning of building systems installed by the construction Contractor in accordance with contract requirements and the NASA Building and Commissioning Guide. All material, equipment, instrumentation, and personnel required for the ORR shall be provided by the construction Contractor. The ORR shall clearly demonstrate that the equipment operates as required by the contract. The ORR shall be done for each equipment/system as required by individual technical sections. Commissioning and ORR results shall be documented in the Daily Reports. The QA Contractor shall witness and document all training sessions on new equipment in their daily reports.

2.6 Punch List Resolution

Near the completion of all work or any increment thereof authorized by the Government, the QA Contractor in conjunction with the Contractor’s Quality Control Manager (CQCM) shall conduct a pre-final review/inspection of the work and develop a pre-punch list of deficiencies which do not conform to the project documents and/or which would otherwise interfere with the ability to conduct a timely and functional final walk-through inspection with the Government. Such list shall be included in the QA daily reports and punch list items shall be recorded in PlanGrid or Trimble Prolog as determined by the Government. A final inspection shall be scheduled by the QA staff only after all known pre-punch list items have been corrected. Focus of such pre-punch lists shall include but not be limited to proper functioning of mechanical and electrical equipment, control systems having been tested and ensured to be working according to specified control sequences, etc.

The QA Contractor shall schedule the final project walk-through inspection with the customer, the construction Contractor, and other project and Government personnel as required, participate in the preparation of punch lists, and follow-up inspections to ensure that punch list items are corrected and closed out in PlanGrid or Trimble Prolog as determined by the Government.

2.7 O&M Manuals

The QA Contractor shall review submittals of O&M manuals for compliance with contract requirements, and notify the PM in writing, if deficiencies exist upon completion of the review.

2.8 As-Built Accuracy Review

The QA Contractor shall verify the accuracy of the construction Contractor’s As-Built drawings.

At a minimum this shall be done once a month before the monthly invoice is processed. As-Built drawings shall be kept in accordance with the requirements of the construction contract. The QA Contractor shall review As-Built data on the record contract drawings, and notify the PM in writing upon detection of discrepancies or any compliance problems.

The QA Contractor shall recommend to the PM, if appropriate, a portion of the payment, including final payment, to be withheld until the As-Built drawings are current.

The QA Contractor shall coordinate the recordation and GPS survey of underground utilities installed by the Contractor with the FMD Configuration Management Program CADD office.

2.9 Meetings

The QA Contractor shall attend all project meetings requested by the PM.

2.9.1 Pre-Construction Meetings

Prior to the beginning of work on any project, the QA Contractor shall be responsible for attending pre-construction meetings. Pre-construction meetings shall include but not be limited to information regarding mobilization, construction site access, safety, special construction constraints, preliminary scheduling issues, and Center Announcement/notifications if necessary, etc.

2.9.2 Progress Meetings

The QA Contractor shall attend all progress meetings scheduled by the construction Contractor or Government for assigned projects.

2.9.3 Weekly General Construction Meetings

The QA Contractor shall attend a weekly construction coordination meeting with construction Contractors and Government personnel. The weekly meeting shall review the status of projects for the entire construction program as well as future planned work. The QA Contractor shall bring forth any quality issue they deem necessary to be escalated to this meeting.

2.9.4 Resolution Meetings

The QA Contractor shall attend and participate as they occur throughout construction to resolve issues.

2.9.5 CQC Meetings

The QA Contractor shall attend and participate in the construction Contractor’s CQC review, 3-phase preparatory, initial, follow-on meetings, and provide clarification of the construction quality requirements as necessary.

2.10. Deliverables for QA Services

2.10.1 Daily Reports

The QA Contractor shall maintain current daily records providing factual evidence that required quality control activities, and/or tests and inspections have been performed. These records shall include all the work performed under the construction contract. The QA Contractor shall prepare a daily report for each project that was observed to have construction activity that day. The QA daily report shall refer to tests and/or CQC activities performed with results and references to specifications/drawings requirements. The quality control phase shall be identified (Preparatory, Initial, Follow-up). The daily report shall include materials received at the site with a statement as to acceptability, storage, and reference to specification/drawings requirements and submittal compliance. The daily report shall include any off-site inspection activities, safety evaluations, and any instructions or directions given to the construction Contractor by the Government. The QA Daily reports shall be recorded in Trimble Prolog by COB the following business day. If the QA Contractor is unable to visit the jobsite on a working day due to an unexpected manpower issue (personnel sick, etc.), other job emergency, or similar type constraint, a daily report shall still be filed indicating why the jobsite could not be visited that day and any other relevant information.

2.10.2 Design Document Review

The QA Contractor shall review the engineering design during the design development process to make recommendations regarding construction approaches, constructability, maintainability, sequencing of work within the project and/or sequencing with other construction work, and the effect of site conditions, and quality control/quality assurance requirements. Review may take place at the 30%, 60%, 90%, and/or other percentage design submission. The Contractor shall participate in design review meetings and provide written comments to the PM within established review period which is typically 10 days but can be shorter at the Government’s discretion. Participation in onboard review meetings may be necessary to discuss or clarify review comments if required by the project.

2.10.3 Construction Document Review

When requested by the PM, the QA Contractor shall review and provide recommendations to the PM on information submitted by the construction Contractor to the Government. Items that shall be reviewed include but are not limited to: product submittals, coordination drawings, CQC plans, safety plans, RFIs, shop drawings, commissioning plans, CQC test reports, schedules, and similar submissions required under the construction contracts.

The QA Contractor shall review the construction Contractor’s monthly progress assessment as shown on the schedule of values (SOV), attached to the Payment Application. The QA shall recommend revised progress percentages as necessary to reflect actual field progress to the PM within 3 working days.

2.10.4 Construction Contract Modifications

The QA Contractor staff shall interface with the PM in the resolution of problems, providing recommendations on changes. Changes may be due to technical inaccuracies in the plans and/or specifications, unforeseen field conditions, changed customer requirements, and material problems. The QA Contractor shall assist the PM in providing an assessment of cost and/or scheduling impacts resulting from such changes.

2.10.5 Test Logs

The QA Contractor shall witness the construction Contractor’s field testing. The results of all tests, both passing and failing, shall be recorded on the daily report. Specification paragraph reference, location where tests were taken, and the sequential control number identifying the test shall be documented. The QA Contractor shall review test results when they are submitted by the construction Contractor and note in the daily report the results of the test and whether or not it complies with the contract. Failure or lack of test results shall be reported when recommending payment for invoiced work. Daily reports shall also document lack of required testing if testing is not performed by the construction Contractor as required.

2.10.6 Discrepancy Logs

The QA Contractor shall maintain a list of non-conformances or deficiencies, whether discovered by the construction Contractor and subcontractors, suppliers, Government representatives or others. The list shall identify what items need to be corrected, the date the item was originally discovered, the date the item will be corrected by, and the date the item was corrected. This documentation shall be entered on an as needed basis in PlanGrid or Trimble Prolog as determined by the Government.

2.10.7 Independent Testing (If requested via Task Order)

The QA Contractor shall provide, on an as-needed basis, incidental services (subcontract) by a qualified testing laboratory (ASTM E 329) to do independent testing of any portion of the construction work. Services may include, but not be limited to work such as testing of soil compaction, concrete testing, weld inspection, and other similar construction related testing.

2.10.8 Factory Test Support (If requested via Task Order)

If tasked with an RFTP, the QA Contractor shall provide a proposal for round trip travel and materials required to attend offsite factory test locations within the continental United States.

Such travel shall be approved by the COR in advance.

2.11 Commissioning Services (If requested via Task Order)

If tasked, the QA Contractor shall provide a proposal for Commissioning Authority (CxA) services for specific projects. In each case, the Government will identify scope of services and systems and equipment to be commissioned. Commissioning services may require any or all of the tasks identified in 2.11.1 based on individual RFTP requirements.

2.11.1 CxA Tasks

The CxA shall be responsible for carrying out the following tasks; however the CxA is free to suggest changes and improvements to the Government for review and approval:

o Coordinate and direct the commissioning activities in a logical, sequential and efficient manner using consistent protocols and forms, centralized documentation, clear and regular communications and consultations with all necessary parties, frequently updated timelines and schedules and technical expertise;

o Coordinate the commissioning work with the design team and general Contractor to ensure that commissioning activities are being incorporated into the general Contractor’s master schedule;

o Develop the Preliminary and Final Commissioning Plans;

o Plan and conduct commissioning meetings as needed and distribute minutes;

o Request and review additional information required to perform commissioning tasks, including O&M materials, Contractor start-up and checkout procedures. Prior to start-up, gather and review the current control sequences and interlocks and work with Contractors and design engineers until sufficient clarity has been obtained, in writing, to be able to write detailed testing procedures;

o Review submittals applicable to systems being commissioned for compliance with commissioning needs, concurrent with the design team and general Contractor reviews;

o Review requests for information and change orders for impact on commissioning and project objectives;

o Review coordination drawings to ensure that trades are making a reasonable effort to coordinate;

o Develop and distribute construction checklists “aka Prefunctional Checklist” for commissioned equipment;

o Develop and distribute Functional Performance Test procedures that demonstrate performance of the equipment or system in all modes of operation for commissioned equipment or systems;

o Develop an enhanced start-up and initial systems checkout plan with Contractors for equipment to be commissioned;

o Perform site visits, as necessary, to observe component and system installations. Attend selected planning and job-site meetings to obtain information on construction progress.

Review construction meeting minutes for revisions/substitutions relating to the commissioning process. Assist in resolving any discrepancies;

o Review HVAC piping pressure and flushing test reports, sufficient to be confident that proper procedures were followed. Include testing documentation in the Commissioning Record;

o Review any ductwork testing and cleaning reports sufficient to be confident that proper procedures were followed. Include documentation in the Commissioning Record;

o Document construction checklist completion by reviewing completed construction checklists and by selected site observation;

o Document systems start-up by reviewing start-up reports and by selected site observation;

o Review Testing, Adjusting, and Balancing (TAB) plans, submittals, reports, participate during TAB Verification process, and review FINAL TAB Reports;

o Attend and provide oversight of functional testing for all commissioned systems and assemblies. Witness and document manual functional performance tests performed by the Construction Contractor for all commissioned systems and assemblies, except: a) some smaller equipment may be sample tested at the Governments discretion, b) electrical equipment testing and regulated testing may be directed and documented by the Construction Contractor with only spot witnessing and report review by the Commissioning Agent. The functional testing shall include operating the system and components through each of the written sequences of operation, and other significant modes and sequences, including start-up, shutdown, unoccupied mode, manual mode, staging, miscellaneous alarms, power failure, security alarm when impacted and interlocks with other systems or equipment. Sensors and actuators shall be calibrated during construction check listing by the installing Contractors, and spot-checked by the commissioning provider during functional testing. Analyze functional performance trend logs and monitoring data to verify performance. Attend and provide oversight of retesting as necessary until satisfactory performance is achieved. Tests on respective HVAC equipment shall be executed, as indicated in the construction specifications, during both the heating and cooling seasons. However, some overwriting of control values to simulate conditions may be allowed, when approved by the Government. Functional testing shall be done using conventional manual methods, control system trend logs, and readouts or standalone data loggers, to provide a high level of confidence in proper system function, as deemed appropriate by the Commissioning Agent and the Government;

o After manual testing and initial trouble shooting is complete, monitor system operation and performance for selected data points for up to two weeks by requesting trend logs from the Construction Contractor from the building automation system. For needed system points not able to be trended by the building automation system, furnish and install temporary portable data loggers that will monitor up to 20 points. Analyze monitored data to verify operation and performance and issue a written report. This time frame and monitoring points may be modified to accurately commission the building;

o The final acceptance tests of all fire protection and life safety systems shall be witnessed by the NASA GSFC Authority Having Jurisdiction (AHJ) or their designated representative. Testing and commissioning for the fire protection and life safety systems shall be per the requirements of those sections of the specifications and the applicable governing codes and standards. No building or portion thereof shall be occupied until the NASA GSFC AHJ has issued a certificate of occupancy. Once the NASA GSFC AHJ has ensured that to the best of their knowledge all the fire protection and life safety systems have been completed, inspected, successfully tested and approved and all outstanding fire and life safety deficiencies have been corrected to afford a reasonable degree of safety to the building occupants from fire and similar emergencies, a certificate of occupancy will be issued; Maintain a master issues log and a separate record of functional testing. Report all issues through the Government and copy the general Contractor as they occur. Provide through the Government and copy the general Contractor written progress reports and test results with recommended actions;

o Review equipment warranties to ensure that Government responsibilities are clearly defined;

o Facilitate, oversee and review the training of NASA GSFC operating personnel. Oversee the videotaping and/or electronic video of this training. Attend and participate in key training sessions;

o Review of the O&M manuals for commissioned equipment;

o Compile a Commissioning Record, which shall include:

A. Brief summary report that includes a list of participants and roles, brief building description, overview of commissioning and testing scope, and a general description of testing and verification methods. For each piece of commissioned equipment, the report shall contain the disposition of the commissioning provider regarding the adequacy of the equipment, documentation and training meeting the contract documents in the following areas:

1) Equipment meeting the equipment specifications;

2) Equipment installation;

3) Functional performance and efficiency;

4) Equipment documentation; and

5) Operator training;

B. All outstanding non-compliance items shall be specifically listed. Recommendations for improvement to equipment or operations, future actions, commissioning process changes, etc. shall also be listed. Each noncompliance issue shall be referenced to the specific functional test, inspection, trend log, etc. where the deficiency is documented;

C. The commissioning plan, Owner’s Project Requirements (from NASA GSFC PM), Basis of Design (from A/E), commissioning specifications, design review, submittal review, issues log, construction checklists, CXA site visit and Commissioning Team meeting minutes, O&M review, training documentation, test procedures, warranty review and test data reports;

D. A Recommissioning Management Manual which provides guidance and establishes timelines for recommissioning of building systems and components. The format of the Recommissioning Management Manual shall closely parallel the Commissioning Plan for the facility;

E. Submit 3 bound text copies of the Commissioning Records with 3 CD copies as specified in the task order.

2.11.2 Qualifications of Commissioning Personnel

The Contractor shall at a minimum, satisfy the following requirements:

o Maintain current certification in any of one of the following commissioning certifications; BCxA Building Commissioning Association - Certified Commissioning Professional (CCP), ACG AABC Commissioning Group –Certified Commissioning Authority (CxA), ASHRAE – Building Commissioning Professional Certification (BCxP).

o Membership with the Building Commissioning Association, ASHRAE, or ACG AABC Commissioning Group.

o LEED Accredited Professional certification is preferred o Acted as the principal Commissioning Agent for at least three projects of comparable size, type and scope;

o Have a minimum of 5 full years’ of field experience in this type of work;

o Have at least 10 years’ experience in the operation and troubleshooting of HVAC systems and energy management control systems. This entails being able to identify the cause of equipment not performing in conformance with the control sequence or the manufacturers specifications;

o Knowledge in building operation and maintenance and O&M training;

o Technical training in fire protection engineering, and/ or past commissioning, field experience, and knowledge in national building & fire codes as well as egress systems, water-based fire extinguishing systems, fire detection systems, fire alarm systems, smoke management systems.

o Knowledge in national building & fire codes as well as water-based fire extinguishing systems, detection systems and alarms systems.

o Knowledge in test and balance of both air and water systems.

o Knowledgeable in Leadership in Energy and Environmental Design (LEED) and

Sustainable design criteria.

o Experienced in energy-efficient equipment design and control strategy optimization.

o Specific experience with specialty systems relative to the particular facility type (i.e.

Federal blast and progressive collapse requirements, security systems, etc.)

o Demonstrated experience with total building commissioning approach including building envelope, data and communication systems and other specialty systems o Direct experience in monitoring and analyzing system operation using energy management control system trending and stand-alone data logging equipment.

o Excellent verbal and writing communication skills. Highly organized and able to work with both management and trade Contractors.

o Experience in writing commissioning specifications for at least three prior projects o A bachelor’s degree in mechanical or electrical engineering, and Professional Engineer license; however, other technical training, past commissioning, and field experience will be considered.

o Membership with the US Green Building Council.

o A member of the prime firm shall be the designated Commissioning Agent who is the member of the team that will coordinate the commissioning activities from the technical perspective.

o If the Commissioning Agent or prime firm does not have sufficient skills to commission a specific system, the prime firm shall subcontract with a qualified party to do so.

Subcontractor qualifications shall meet the aforementioned requirement and shall be included and clearly designated in the response to this Statement of Work.

3.0 Document Control Services (If requested via Task Order)

If requested, the QA Contractor shall provide a proposal for on-site contract administration and/or clerical support to be responsible for the day-to-day matters of contract administration including receipt, routing, tracking, scanning, distribution, and filing of construction documents;

inquiry response; attending meetings; taking notes; providing copies, etc. Documents shall be recorded and tracked in Trimble Prolog and other Government databases as required. The QA administrative support shall follow processes and timelines established by the Government.

Contract administration and/or clerical support are not intended to function as QA Level 3, 4, or 5 services, however; past experience in working in the construction industry and/or a construction field office is desirable.

4.0 Contract Level Provisions

4.1 Conducting Operations at GSFC

The QA Contractor comply with and adhere to all standards, requirements, and regulations for working at GSFC and shall conduct themselves in a professional manner. The QA Contractor shall comply with all on-site training (instructor or computer based) as may periodically be required for use of areas such as, but not limited to, Information Technology Security, Ethics Conduct.

4.2 Submittals

4.2.1 Quality Assurance Plan

The QA Contractor shall provide a QA Plan in accordance with the general format indicated in Appendix A of Corps of Engineers document ER 1180-1-6 dated 30 Sept 1995, available at:

http://www.publications.usace.army.mil/Portals/76/Publications/EngineerRegulations/ER_1180- 1-6.pdf

The QA plan shall be due within 30 days after the effective date of the contract and updated as needed. Subset plans shall be required for special tasks.

4.3 Safety and Environmental References

The following regulations shall be adhered to during performance of the contract. The most recent version shall be implemented.

CODE OF FEDERAL REGULATIONS (CFR)

29 CFR 1910, Occupational Safety and Health Standards (General Industry) 29 CFR 1926, Safety and Health Regulations for Construction 40 CFR 260, Hazardous Waste Management System: General 40 CFR 761, PCB Manufacturing, Processing, Distribution in Commerce, and Use Prohibition

CODE OF MARYLAND REGULATION (COMAR)

Title 26, Department of the Environment

NATIONAL AERONAUTICS AND SPACE ADMINISTRATION (NASA)

NASA-STD-8719.11 Rev. A, Safety Standard for Fire Protection NASA-STD-8719.12, Safety Standard for Explosives, Propellants, and Pyrotechnics NASA NPR 8715.1, NASA Safety and Health Programs

GODDARD SPACE FLIGHT CENTER (GSFC)

GSFC GPD 8500.1, Environmental Policy and Program Management GSFC GPD 8715.1, Goddard Space Flight Center Safety Policy GSFC GPR 1700.1, Occupational Safety Program at Goddard Space Flight Center GSFC GPR 1700.5, Control of Hazardous Energy (Lockout/Tagout) GSFC GPR 1700.6, Confined Space Program at the Goddard Space Flight Center GSFC GPR 1700.7, Electrical Safety GSFC GPR 1700.8, GSFC Hazard Communication Program GSFC GPR 1820.1, Hearing Conservation Program GSFC GPR 1820.2, Respiratory Protection GSFC GPR 1840.1, Asbestos Management Program at GSFC GSFC GPR 1840.2, Industrial Hygiene Program GSFC GPR 1860.1, Ionizing Radiation Protection GSFC GPR 1860.2, Laser Radiation Protection GSFC GPR 1860.3, Radio Frequency Radiation Safety GSFC GPR 1860.4, Ultraviolet and High Intensity Light (UV/HIL) Radiation Protection GSFC GPR 7320.1B, Facilities System Safety GSFC GPR 8500.3, Waste Management GSFC GPR 8500.4, Air Quality Management Program GSFC GPR 8500.5, Water Management GSFC GPR 8621.4, GSFC Mishaps Preparedness and Contingency Plan GSFC GPR 8710.2, Goddard Space Flight Center (GSFC) Emergency Management Program Plan (EMP) GSFC GPR 8710.3, Certification and Recertification of Ground-Based Pressure Vessels and Pressurized Systems GSFC GPR 8710.7, Cryogenic Safety GSFC GPR 8710.8, GSFC Safety Program Management GSFC GPR 8715.5, Fire Protection at GSFC/Greenbelt GSFC GPR 8719.1, Certification and Recertification of Lifting Devices and Equipment and its Operators GSFC 8730.6, Electrostatic Discharge (ESD) Control GSFC ICP, GSFC Integrated Contingency Plan GSFC SWPPP, GSFC Storm Water Pollution Prevention Plan

U.S. DEPARTMENT OF LABOR (USDL)

O.M.B. No. 1220-0029 Recordkeeping Guidelines for Occupational Injuries and Illnesses

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 10, Standard for Portable Fire Extinguishers NFPA 13, Installation of Sprinkler Systems NFPA 30, Flammable and Combustible Liquids Code NFPA 70, National Electrical Code NFPA 70E, Standard for Electrical Safety in the Workplace NFPA 101, Life Safety Code NFPA 241, Standard for Safeguarding Construction, Alteration, and Demolition Operations

AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)

ANSI Z136.1, Standard for Safe Use of Lasers ANSI/ASSE Z359.1, Safety Requirements for Personal Fall Arrest Systems, Subsystems, and Components

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

ANSI/IEEE C95.1, Standard for Safety Levels with Respect to Human Exposure to Radio Frequency Electromagnetic Fields, 3 kHz to 300 GHz

5.0 Definitions/Acronyms

AHJ – Authority Having Jurisdiction COR – Contracting Officer’s Representative CQC - Contractor Quality Control CQCM – Contractor’s Quality Control Manager FMD – Facilities Management Division GSFC – Goddard Space Flight Center O&M – Operations and Maintenance ORR - Operational Readiness Review PM – Government Project Manager with overall responsibility for a specific design and/or construction project.

Trimble Prolog – Construction Management Software used extensively at GSFC and WFF QA – Quality Assurance Contractor (or Inspector, Staff, etc.) – Refers to the Contractor personnel performing work under this contract.

QC – Quality Control Inspectors – Refers to a construction Contractor’s personnel responsible for quality control.

WFF – Wallops Flight Facility

6.0 Travel Requirements

Travel required in association with the work shall be included in the Contractors proposed task plans. Travel will be approved by the Contractor Officer when the task order is executed.

End of Statement of Work