RFC-002 Response.docx

DOCX document 24 KB Posted

Attached to
UPS BATTERY REPLACEMENT NORFOLK VA
Solicitation number
N7027224Q0029
Issued by

About this file

This document is a Request for Clarification (RFC) related to the UPS Batteries Replacement Solicitation N7027224Q0029 at the MB100 facility in Norfolk, VA. The key details are:

The solicitation is seeking to replace Eaton UPS batteries at the facility. The RFC asks for clarification on several items, including the battery cabinet model, whether equivalent battery products would be acceptable, and applicable Buy American Act/Trade Agreements Act requirements. It also requests details on the delivery process, such as availability of a loading dock, storage capacity, freight elevator access, and logistics for transporting the batteries to the UPS room. Additionally, the RFC inquires about site restrictions, delivery hours, and removal of existing batteries and equipment. The answers provided indicate that a battery monitoring system is in place and provide some high-level logistical details for the delivery.

View the file

Other files

File Type Posted
RFC-001 Response.docx DOCX document
ANNEX A PWS.docx DOCX document
ANNEX B EVAL FACTORS.docx DOCX document
24Q0029 RFQ.docx DOCX document
24Q0029 BNLS REDACTED.pdf PDF
ANNEX C PRICE BREAKDOWN.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N7027224Q0029

UPS BATTERIES REPLACEMENT AT MB100 NORFOLK VA

REQUEST FOR SPECIFICATION CLARIFICATION

RFC -002

NAME OF CONTRACTOR: _______________________________________________

SPECIFICATION ITEM NO.: _ SAM.GOV Notice ID: N7027224Q0029.

PARAGRAPH / SECTION NO: _VARIOUS_

TITLE: UPS BATTERIES

QUESTIONS:

1. Can you share the battery cabinet make & model please. A picture of the cabinet nameplate would be best if possible.

2. Equivalent Products; The RFQ identifies Deka Unigy HR7500ETUB batteries for replacement. Will equivalent or brand-name-or-equal batteries meeting the same specifications be acceptable?

3. Buy American Act / Trade Agreements Act; Can you confirm whether the Buy American Act (BAA) or Trade Agreements Act (TAA) is applicable to this procurement? If either applies, please provide clarification on the necessary compliance requirements.

4. Delivery, Handling and Storage; Could you provide more details about the delivery process at the project site assuming approximately 30 pallets of the batteries being delivered?

5. Is there a loading dock available for the delivery?

6. Are there any specific site restrictions or guidelines we should be aware of for receiving and handling large shipments of this kind?

7. Does the site have short term storage capacity for the ~30 pallets?

8. Is there is a loading dock available?

9. What are the logistics from the dock/off loading area to the ups room?

10. Is this project being done on a first floor or second?

11. If second floor, is there a freight elevator available for use?

12. Do you have a staging area (somewhere to hold the batteries, we’re looking at 16 pallets).

13. Is the area an air controlled-environment where we would be staging the batteries?

14. What are the delivery hours?

15. Is there a loading dock?

16. Would we need to provide a truck that has a lift-gate?

17. How wide are the doors to the room? Is it a single standard door or a double that we can open wide for access?

18. How many doors do we have to go through to get the room?

19. Is the flooring carpet/tile/etc. where we would need to lay down protection?

20. Are there any staircases/steps that would prevent a pallet jack from going through the door?

21. Lift gate: Is a lift gate required for the delivery or removal?

22. If yes, what type of truck is needed?

23. Forklift/Pallet Jack:

24. Is a forklift or pallet jack available on site?

25. Step end Route: Are there any steps or obstacles that need to be navigated to reach the delivery or removal location?

26. Dock: Is a dock available for loading/unloading?

27. If yes, is a dock plate required?

28. Dock Height:

29. What is the height of the dock?

30. Floor Protection: Is floor protection required during the delivery or removal process?

31. Freight Elevator:

32. Is a freight elevator available on site?

33. If yes, what is its capacity in pounds?

34. Can it accommodate passengers?

35. Distance Measurements:

36. What is the distance from the battery room to the elevator?

37. What is the distance from the dock to the elevator?

38. What is the distance from the dock to the battery room?

39. Equipment Removal:

40. Are battery/UPS racks required to be removed?

41. Are battery/UPS cabinets required to be removed?

42. What type of batteries are being removed?

43. How many jars and racks need to be removed?

44. BMS (Battery Monitoring System):Is a battery monitoring system in place?

ANSWERS:

1. Model – UBC75 Battery Cabinet Model Number – 400-1805143

2. Brand Name

3. Yes; Reference clauses DFARS 252.225-7001 and 252.225-7002.

4. Can be stored in a lay down area inside the building compound or maybe room in the warehouse

5. Yes

6. Warehouse notification

7. Yes

8. Yes

9. 3 or 4 rooms away from unloading area

10. First Floor

11. NA

12. Yes

13. Can be stored in a lay down area inside the building compound or maybe room in the warehouse

14. 0600 – 1500

15. Yes but will not be necessary

16. No

17. Roll up door for building entry doors large enough for pallet jack

18. Up to 4 or 5 rooms that are accessible from each other

19. Coated concrete floor

20. No

21. No

22. NA

23. NA

24. Yes

25. NO

26. Yes

27. No

28. Hydraulically raised

29. NA

30. No

31. Yes but not necessary UPS is on first floor

32. NA

33. NA

34. NA

35. NA

36. NA

37. NA

38. Up to 4 or 5 rooms that are accessible from each other from loading area

39. No

40. Remove and replace batteries

41. No

42. Deka Unigy HR7500ETUB

43. 420

44. Yes CellWatch