Attachment 1
| Attachment 1 |
| Exhibit Line Item Numbers |
Contract Line Item Number (CLIN) 0001 - General Requirements
| Year 1 | | | | |
| Exhibit Line Item Number (ELIN) | Item/NSN | Offeror's Unit Price | | |
| ($/MM BTU) | Estimated Quantity | | | | |
| (MM BTU) | Extended Price ($) | | | | |
| A001AA | Liquefied Natural Gas (LNG) 6830-01-672-6379 | $0.00 | 898,506 | $0.00 |
| Year 2 | | | | |
| Exhibit Line Item Number (ELIN) | Item/NSN | Offeror's Unit Price | | |
| ($/MM BTU) | Estimated Quantity | | | | |
| (MM BTU) | Extended Price ($) | | | | |
| A001AB | Liquefied Natural Gas (LNG) 6830-01-672-6379 | $0.00 | 898,506 | $0.00 |
| Year 3 | | | | |
| Exhibit Line Item Number (ELIN) | Item/NSN | Offeror's Unit Price | | |
| ($/MM BTU) | Estimated Quantity | | | | |
| (MM BTU) | Extended Price ($) | | | | |
| A001AC | Liquefied Natural Gas (LNG) 6830-01-672-6379 | $0.00 | 898,506 | $0.00 |
| Year 4 | | | | |
| Exhibit Line Item Number (ELIN) | Item/NSN | Unit Price ($/MM BTU | Estimated Quantity (MM BTU) | Extended Price ($) |
| A001AD | Liquefied Natural Gas (LNG) 6830-01-672-6379 | $0.00 | 898,506 | $0.00 |
| Year 5 | | | | |
| Exhibit Line Item Number (ELIN) | Item/NSN | Offeror's Unit Price | | |
| ($/MM BTU) | Estimated Quantity | | | | |
| (MM BTU) | Extended Price ($) | | | | |
| A001AD | Liquefied Natural Gas (LNG) 6830-01-672-6379 | $0.00 | 898,506 | $0.00 |
| Total Cost: Years 1 thru 5 | | | |
| The total of ELINs A001AA through A001AD (above) will be the amount you should enter in CLIN 0001. | | | |
| Contract Line Number (CLIN) | Item/NSN | Estimated Quantity | |
| (MM BTU) | Extended Price ($) | | | |
| 0001 | Liquefied Natural Gas (LNG) 6830-01-672-6379 | 4,492,530 | $0.00 |
CLIN 0002 - Cool-Down & Commissioning
| Contract Line Number | Item/NSN | Price $/day | Extended Price ($) |
| 0002 | Cost per day of Ship berthing at Pier Charlie | $0.00 | $0.00 |
| Total Proposed Price |
| $0.00 |