N6945022Q0002_GPI_Responses_0001.pdf
PDF 325 KB Posted
- Solicitation number
- 69450
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N6945022Q0002_SectionC_PWS_0001.pdf | ||
| N6945022Q0002_SectionJ_Technical Attachments_0001.pdf | ||
| N6945022Q0002_Amendment_0001.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N69450-22-Q-0002
Gulfport ISWM
GOVERNMENT PRE AWARD INQUIRY FORM
Page Section Para.
1 1/25/22 36 Sec C 3.2
Currently, there is only one disposal location for MSW and C&D in the area (with scales), which is owned by
Waste Management. They have a recent history of changing their contracts midterm and raising tipping fees over 50% with little to no notice. If this happens during the contract can the contractor request equitable adjustment to the contract to account for the raise in fees?
All associated cost and/or projected cost required for completion of the scope of work in the RFP should be included in the offeror's original bid proposal. Any adjustments to the contract price would be handled on a case-by-case basis after award.
2 1/25/22 37 Sec C 3.2.2
Many of the current FEL recycling containers are contaminated to the point where they cannot be recycled. Who pays the disposal fees if they are contaminated since the contractor has no control over what goes into the FEL containers?
The contractor is responsible for paying all fees associated with disposal. Spec Item 3.2.2 has been revised via Amendment 0001 to state that, "The contractor keeps proceeds from recycling and pays all disposal fees including those for contaminated loads."
3 1/25/22 37 Sec C 3.2.2
Who pays for the disposal if the recycling roll-offs are contaminated? Currently the contractor keeps the proceeds and the contamination potential/fees are offset by keeping the proceeds. Would the Government please consider letting the contractor keep the proceeds?
Otherwise how does the contractor recoup disposal from contamination on a FFP bid?
See Government Response to GPI #2.
4 1/25/22 37 Sec C 3.2.2
If the above is "no", How does the contractor return the money to the Government, i.e what is the process?
What recyclables generate money? Who is responsible for marketing, transferring money to the Government, educating the public etc.?
N/A, see Government Response to GPI #2.
5 1/25/22 N/A Attachment J-
1503030-05-02
Recycled Waste
(tab)
Will the Government please specify what type of recycling material goes into each container?
In accordance with Spec Item 3.1.2.2, all containers are mixed recycling stream. Recycling stream consists of white/mixed paper, cardboard, aluminum and plastic.
6 1/25/22 N/A Attachment J-
1503030-05-02
Recycled Waste
(tab)
Currently there are some containers that have concrete in them and are very heavy. Who pays for those disposal fees?
Construction training is part of the Installation mission and the resulting construction debris is part of the contract and the responsibility of the contractor to dispose. The contractor is responsible to dispose of all material placed in ‘on call’ roll offs, to include concrete and construction debris. The Government may also order additional containers via the non-recurring work
ELINS to dispose of concrete and construction debris for tenant commands and for quantities in excess of those specified in Section J Attachment J-1503030-05.
Amend No.
REFERENCEQuestion
No.
QUESTION GOVERNMENT RESPONSE
Date
Received
SOURCE SELECTION INFORMATION - SEE FAR 2.101 AND 3.104
N69450-22-Q-0002
Gulfport ISWM
GOVERNMENT PRE AWARD INQUIRY FORM
Page Section Para.
Amend No.
Question
No.
QUESTION GOVERNMENT RESPONSE
Date
Received
7 1/25/22 N/A N/A N/A Will the Government please confirm that you cannot park or store vehicles/equipment on the Base?
This is to confirm that the contractor cannot park or store vehicles/equipment on the Base.
8 1/25/22
Sec C and
Sec J
Sec C and Sec J
SEC C 3.1.2.2 SEC
J Attachment J-
1503030-03
Common Output
Level Standards for
Solid and
Recyclable Waste
Sec C 3.1.2.2 says "Type of recyclable waste includes white/mixed paper, plastics, aluminum cans, and cardboard." Sec J says Note 1: "The Contractor shall collect and process only white paper and cardboard products. General and Recyclable waste collection points are listed in J-1503030-05" Which COL Level are we in? Please confirm what we are supposed to recycle?
Spec Item 3 has been updated via Amendment 0001 to clarifiy which COL level applies, specifically COL 3 with additional measures Level 3. In addition, Note 2 in Attachment J-1503030-03 has been revised to clarify that recyclables for COL3 Additional Measures Level 3 include white/mixed paper, cardboard, aluminum and plastic.
9 1/25/22 Sec J 36
Attachment J-
1503030-05
General and
Recyclable Waste
Collection Points and Historical Data
The Government lists 20, 30 and 40 CY annual hauls as
8, 250 and 100 respectively, and there are also more roll offs required from previous ISWM bids on this contract. This number doesn’t include recycling and needs to be increased. Can the Government please correct?
Attachment J-1503030-05 has been updated via
Amendment 0001 to correct the quantities of annual pulls, which are as follows: 50 hauls of 20CY roll offs, 200 hauls of 30CY roll offs, and 150 hauls of 40CY roll offs. This does not include recycling.
SOURCE SELECTION INFORMATION - SEE FAR 2.101 AND 3.104
File details come from the government source that posted it. Updated .