Hydraulic Actuator Flow Test Stand (HAFTS) - SOW.docx

DOCX document 83 KB Posted

Attached to
Hydraulic Actuator Flow Test Stand
Solicitation number
N68520-27-RFPREQ-KN00000-0075
Issued by

About this file

This is a Statement of Work (SOW) for the procurement and installation of a Hydraulic Actuator Flow Test Stand (HAFTS) at Naval Air Station North Island, California, specifically for Fleet Readiness Center Southwest (FRCSW) in Building 472. The HAFTS is a turn-key operation that will replace an existing Dayton T. Brown test stand and will be used to test various hydraulic actuators and servo cylinders used on the E-2C/E-2D Platform aircraft. The contractor must provide all parts, labor, materials, installation, start-up, commissioning, validation, calibration, and training. The test stand must be manually controlled with a 60-gallon minimum hydraulic fluid tank using MIL-PRF-832820 fluid, maintain oil temperatures between 75-100 degrees Fahrenheit with an automatic shutoff at 125 degrees, and include a motor and pump system capable of 0-5000 PSI pressure and 0-30 GPM flow ratings. The testing area must be enclosed and accommodate actuators up to 31.25 inches in length with expansion and retraction capability, include minimum two pressure and two return ports, a selector/switch valve, a manual hand pump (0-10,000 PSI), and a sump tank with filtration system. The electrical system must conform to 480-volt, 3-phase, 60 Hertz facility power with appropriate transformers, include emergency stop switches with red push-button actuation, and comply with NFPA, NEMA, ISO 4413, and ISO 4414 standards for hydraulic and pneumatic systems.

The contractor is responsible for complete installation including shipping, uncrating, floor securing, leveling, utility connections, waste disposal, and all calibration and testing. The government will provide utilities within 20 feet of the test stand and existing chilled water systems (45-65 degrees Fahrenheit) which the contractor may connect to but not modify. The contractor must provide technical data (3 hard copies and 1 electronic copy via DOD Safe), a Plan of Action and Milestones within 30 days of contract award, preliminary and critical design reviews, Instrument Calibration Procedures Source Data, an Acceptance Test Plan, printed training aids, and test/inspection reports. Training deliverables include operator training for up to 10 personnel (40 hours minimum) and maintenance training for 5 personnel each in mechanical and electronic/electrical systems (40 hours minimum), both conducted at the government facility during normal business hours (Monday-Friday, 0600-1430 hours Pacific Time). All inspection and acceptance testing occurs in two phases: Origin Inspection/Test at the contractor's facility and Final Inspection/Acceptance Test at the destination after installation, with the government withholding DD250 signature until all requirements are satisfied. The contractor must comply with security requirements including SECNAV Form 5512/1 completion for NBC access, FRCSW Form 5512/5 for site access, DBIDS card requirements, visitor badge protocols, photo/video restrictions, and CMMC Level 2 or above cybersecurity compliance per DFARS 252.204-7021. Equipment must include an hour meter displaying 0-99,999.9 hours, nameplate with manufacturer information and contract number, and Item Unique Identification Marking (IUID) per MIL-STD-130N with both machine-readable and human-readable information.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

HYDRAULIC ACTUATOR FLOW TEST STAND

1. SCOPE:

1.1. This statement of work (SOW) describes the minimum specifications and requirements necessary to purchase one (1) new Hydraulic Actuator Flow Test Stand (HAFTS) for the E2-C/E2-D Platform. The new test stand will replace an existing test stand manufactured by Dayton T. Brown. No building modifications or alterations are prescribed for this project or within this SOW.

1.2. DESCRIPTION:

The purpose of this SOW is to provide details for a Turn-Key operation for an Offeror to provide parts, labor, and materials delineated by contract scope specified by the SOW, to include but not limited to; installation, start-up, commissioning, validation, calibration, and training for HAFTS located at Naval Air Station (NAS) North Island, CA, Fleet Readiness Center Southwest (FRCSW), in Building 472 Hydraulic Shop. The quality, size, and capacity shall be no less than the minimum specification outlined in Section 4 of this SOW.

2. APPLICABLE DOCUMENTS AND REFERENCES

2.1. Government Documents:

Specifications, Standards, and Handbooks. The following specifications, standards, and handbooks are a part of this requirement. to the extent specified herein. Unless otherwise specified, the issues of these documents are those listed in the latest issue of the Department of Defense Index of Specifications and Standards (DoDISS) and supplement thereto.

2.1.1. Federal Documents:

2.1.1.1. FED-STD-H28B - Screw Thread Standards for Federal Services (1994 edition).

2.1.1.2. FED-STD-313F – Material Safety Data, Transportation Data and Disposal Data for Hazardous Materials Furnished to Government Activities

2.1.1.3. MIL-STD-130N – Identification Marking of U.S. Military Property (2007 edition)

2.1.1.4. MIL-PRF-81836B – Filter and Disposable Element, Fluid Pressure (1998 edition)

2.1.1.5. MIL-S-8512D – Support Equipment, General Specification for Design (2002 edition) (Copies of Federal and military specifications, standards, and handbooks are available from the Superintendent of Documents, U.S. Government Printing Office, Washington, DC 20402-0001)

2.1.2. Environmental Protection Agency (EPA)

2.1.2.1. 40 CFR 82: Protection of Stratospheric Ozone

2.1.2.2. 40 CFR 761: Polychlorinated Biphenyls (PCBs) Manufacturing, Processing, Distribution in Commerce, and Use Prohibitions (Application for copies should be addressed to the EPA Ariel Rios Building 1200 Pennsylvania Avenue, N.W. Washington, DC 20460)

2.1.3. Government Documents, Drawings, and Publications

2.1.3.1. FY21 NAVAIR METCAL scheduling letter

2.1.3.2. Courtesy Layout Drawing – FRCSW Building layout of physical location with electrical and water connections (when applicable) Distribution Statement A: Approved for public release. Distribution is unlimited.

Drawing release number: 26-0027

2.1.3.3. NPSL-BP-01, Metrology Engineering FST, NAVAIR ISSC North Island, NAVY Primary Standards Lab North Island, (01 September 2020)

2.1.3.4. MIL-STD-130N w/Change 1 - Identification Marking of U.S. Military Property (2012 Ed.) Item Unique Identification Marking (IUID)

(Application for copies should be addressed to Air Force Product Data Systems Modernization Standards (TMSS) Office, 554 ELSG/SBP, 4375 Chidlaw Road, Bldg. 262, Room S008, Wright-Patterson AFB, OH 45433-5006, Phone (937) 257-0870 or 0853 or https://quicksearch.dla.mil/qsSearch.aspx)

The following documents are under Distribution Statement D [Distribution authorized to the Department of Defense and U.S. DoD contractors only (critical technology) (1 May 2019). Other requests shall be referred to Program Executive Officer Tactical (PEO(T)), PMA−231, 47123 Buse Rd., RADM William A Moffett Building, Patuxent River, MD 20670−1547

WARNING - These document(s) contain technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Section 2751 et seq.) or the Export Administration Act of 1979 (Title 50, U.S.C., App 2401 et seq.) as amended Title 50, U.S.C., App. 2401 et. seq. Violation of these export laws is subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25.

2.1.3.5. NAVAIR 03-5CGU-12 – Depot Maintenance Instructions for the Outboard Rudder Tandem Servo Actuator

2.1.3.6. NAVAIR 03-5CGU-14 – Depot Maintenance Instructions for the Inboard Rudder Tandem Servo Actuator

2.1.3.7. NAVAIR 03-5CGU-16 – Depot Maintenance Instructions for the Elevator Tandem Servo Actuator

2.1.3.8. NAVAIR 03-5CGU-18 – Depot Maintenance Instructions for the Port Aileron Tandem Integrated Servo Actuator

2.1.3.9. NAVAIR 03-5CGU-20 – Depot Maintenance Instructions for the Electrohydraulic Autopilot Servo Actuator

2.1.3.10. NAVAIR 03-25GR-35 – Depot Maintenance Instructions for the Main Gear Actuating Cylinder Assemblies

2.1.3.11. NAVAIR 03-30GA-50 – Depot Maintenance Instructions for the Wing Fold Actuating Cylinder Assemblies

2.2. Non-Government Documents:

The following documents form a part of this document to the extent specified herein. Unless otherwise specified, the issues of these documents are those cited in the solicitation or contract. The product offered shall comply with the following codes and specifications where applicable. Unless a date or version is specified, the latest edition of the referenced publications in effect at the time of the bid shall govern. In case of a conflict between the requirements in this specification and those listed in the references, the supplier shall notify the Technical Point of Contact (TPOC).

2.2.1. National Institute of Standards and Technology (NIST), 2013 Edition. Traceable Standard/Calibration NIST 2013 edition can be found at: http://nvlpubs.nist.gov/nistpubs/ir/2013/NIST.IR.7298r2.pdf, and http://www.nist.gov/calibrations/sp250_series.cfm)

(Application for copies should be addressed to: https://www.asme.org/products/codes-standards/b894103602-2008-acceptance-test-reverification or http://www.ansi.org/ )

2.2.2. American National Standards Institute, Inc. (ANSI)

B11/STD B11: General Safety Requirements Common to ANSI B1 Machines (Address application for copies to the American National Standards Institute, 11 West 42nd Street, New York, NY 10036)

2.2.3. American Society of Mechanical Engineers (ASME) Y14.100: Engineering Drawing Practices (Applications for copies should be addressed to ASME International Three Park Avenue New York, NY 10016-5990 or www.asme.org)

2.2.4. International Organization for Standardization (ISO)

2.2.4.1. ISO 4413: Hydraulic fluid power-General rules and safety requirements for systems and their components

2.2.4.2. ISO 4414: Pneumatic Power-General rules and safety requirements for systems and their components

2.2.4.3. ISO 4406: Hydraulic fluid power-Fluids-Method for coding the level of contamination by solid particles (1999 edition)

2.2.4.4. ISO 7500: Calibration and Verification of Static Uniaxial Testing Machines (2018 edition) (Application for copies should be addressed to the International Organization for Standardization (ISO) 1 rue de Varembe, Casepostale56, CH211Geneva 20, Switzerland)

2.2.5. National Electrical Manufacturers Association (NEMA)

2.2.5.1. NEMA ICS 6: Industrial Control and Systems: Enclosures (2016 Rev.)

2.2.5.2. NEMA MG-1 Industrial Control and Systems: Motors and Generators (2018 Ed.)

2.2.5.3. NEMA 250: Enclosures for Electrical Equipment (1000 V Maximum) (2020 Ed.)

2.2.5.4. NEMA ICS 1: Industrial Control and Systems General Requirements (2000 Ed. 2015R)

2.2.5.5. NEMA Z535.4: Product Safety Signs and Labels (2011 Ed.) (2017 Rev.)

(Application for copies should be addressed to the National Electrical Manufacturers Association, 1300 N 17th Street, Rosslyn, VA 22209)

2.2.6. National Fire Protection Association (NFPA)

2.2.6.1. NFPA 70: National Electrical Code

2.2.6.2. NFPA 79: Electrical Standard for Industrial Machinery (Applications for copies should be addressed to the National Fire Protection Association, ATTN: Support Services, 11 Tracy Drive, Avon, MA 02322)

2.3. Order of Precedence. In the event of a conflict between the text of this document and the references cited herein, the text of this document takes precedence. Nothing in this document, however, supersedes applicable laws and regulations unless a specific exemption has been obtained.

3. REQUIREMENTS

This describes the minimum requirements for the procurement, design, and at the site installation of a HAFTS at FRCSW North Island, Building 472. The Contractor shall make all the adjustments, replacements, modifications, upgrade, and pass all the environmental, safety, and fire regulations according to the technical requirements included in this SOW in Section 2 and subsequent SOW sections. Specifications and requirements are as follows:

3.1. Design. The HAFTS equipment shall be manufactured of parts that are new, without defects, and free of repairs. The structure shall withstand all forces encountered during operation of the HAFTS to its maximum rating and capacity without distortion. The HAFTS shall include all components, parts, and features necessary to meet the performance requirements specified herein. All parts subject to wear, breakage or distortion shall be accessible for adjustment, replacement, and repair.

3.1.1. Measuring and Indicating Device Graduations. All measuring and indicating devices on the HAFTS shall be graduated in the inch/pound units of measurement.

3.1.2. Controls. All electrical, mechanical, hydraulic, and pneumatic operating controls shall be located convenient to the operator's workstation(s).

3.2. Safety and Health Requirements. All HAFTS parts, components, mechanisms, and assemblies furnished on the HAFTS, whether or not specifically required herein, shall comply with all of the requirements of ISO/EN/DIN/JIS standards referenced in Sections 3.2.1, 3.2.2. and 3.2.3.

3.2.1. Safety Guarding. Covers, guards, or other safety devices shall be provided by the Contractor per ANSI B11 or equivalent ISO standards, Section 2.2.2 & 2.2.5. The safety devices shall not interfere with the operation of the HAFTS. The safety devices shall prevent unintentional contact with the guarded part, and shall be easily removed to facilitate inspection, maintenance, and repair of the parts.

3.2.2. Hazardous Material Exclusions. Supplies or materials being provided as part of the equipment shall be free of known hazardous materials. These materials shall not be brought on site without prior approval of the Government. Radioactive materials or instruments capable of producing ionizing radiation as well as materials which contain asbestos, mercury, lithium, methylene chloride, lead (= or >0.06%), or polychlorinated biphenyls (PCB’s) are prohibited. Definitions of hazardous materials are specified in the latest version, including revisions adopted during the term of the contract, of FED-STD-313F Section 2.1.1. Nickel Metal Hydride and lithium batteries are permissible for memory backup. Class I Ozone Depleting Substances as defined in 40 CFR 82 shall not be used in the performance of this contract or be provided as part of the equipment. Exceptions to the prohibition of these materials must be referred to the Procuring Contracting Officer (PCO) in writing, for consideration, not later than 60 calendar days after effective date of contract and prior to any work being performed.

3.2.3. Environmental Protection and Safety Requirements: During the operation of the equipment at their final location after the installation is complete, all equipment shall comply with all applicable EPA and OSHA regulations in effect on the date of contract regulating the emission of material hazardous to the environment. The Contractor shall coordinate with FRCSW regarding site approvals and environmental permits required by Federal, State, Country, and Local Laws. For additional information, the Contractor is instructed to contact the TPOC.

3.2.4. The Contractor shall provide a Facilities Requirements Document (FRD). The FRD shall provide the make, model, capacity, footprint, mechanical, and electrical requirements of the equipment.

3.2.5. Lubrication. Means shall be provided to ensure adequate lubrication for all moving parts. Recirculating lubrication systems shall include filters that are cleanable or replaceable according to Section 2.1.1.4. Each lubricant reservoir shall have a minimum of twenty-four (24) hour capacity. Means shall be provided to indicate low oil condition. Should low oil condition occur; the machine shall enter an emergency stop condition upon completion of the current operation. All oil holes, grease fittings, and filler caps shall be accessible.

3.2.6. Interchangeability: Replacement parts shall be interchangeable without requiring modification. Replacement parts are those that are subject to wear or failure such as gears, bearings, shafts, feed screws, drive belts, pumps, and seals. Electrical replacement parts shall include but not be limited to, motors, relays, fuses, switches, magnetics, pushbuttons, light bulbs, braking mechanisms, and solid-state devices. Tooling and accessories normally supplied as standard items shall also be considered replacement parts. Foreign-sourced replacement parts shall be interchangeable with domestically supplied components or be readily available from a domestic source.

4. DETAILED TASKS:

4.1. Castings and Forgings. All castings and forgings shall be free of defects, scale, and mismatching. No processes such as welding, peening, plugging, filling with solder or paste shall be used for reclaiming any defective part.

4.2. Fastening Devices. All screws, pins, bolts, and other fasteners shall be installed to prevent unintentional loosening. Fastening devices subject to removal or adjustment shall not be permanently installed.

4.3. Threads. All threaded parts used on the HAFTS and its related attachments and accessories shall conform to FED-STD-H28B Section 2.1 and the applicable Detailed Standard section referenced therein or equivalent ISO/EN/DIN/JIS standards.

4.4. Surfaces. All surfaces shall be clean and free of harmful or extraneous materials. All edges shall be either rounded or beveled unless sharpness is required to perform a necessary function. The condition and finish of all surfaces shall be in accordance with the manufacturer's commercial practice.

4.5. Welding, Brazing, or Soldering. Welding, brazing, or soldering shall be employed only where specified in the original design. None of these operations shall be employed as a repair measure for any defective part.

4.6. Coating. The HAFTS shall be coated with the proper material in accordance with the manufacturer’s commercial practice. All coatings shall be of the lead-free type.

4.7. Workmanship. Workmanship of the HAFTS shall meet all requirements specified herein and shall be of a quality equal to that prevailing among manufacturers producing equipment of the type covered by this purchase description.

4.8. Maintainability: The equipment shall be designed and manufactured to permit maintenance personnel to easily service the equipment using a minimal number of tools. All parts subject to wear, breakage, or distortion shall be accessible for adjustment, replacement or repair. Consistent with required maintenance and design of the equipment, the Contractor shall provide any special tools required to service the Test Stand. The equipment shall be equipped with access covers to facilitate inspection, cleaning, and repair, or replacement of parts.

4.9. HAFTS shall integrate mechanical and electrical components to deliver the functional capabilities specified below, in accordance with MIL-S-8512D, Section 2.1.1.5. For any testing requirements for the Units Under Test (UUT) that are not specified below, the contractor shall comply with the Technical Publications listed in Sections 2.1.3.5 through 2.1.3.11.

Units Under Test:

The following table (Table 1) is a list of current UUT’s to be tested on the new test stand. During the testing phase of this contract, the contractor may not receive all the listed components for testing at their facility, depending on UUT availability. This test stand may also be used to test UUT’s not listed in Table 1. The technical publications for the UUT’s are listed under 2.1.3.5-2.1.3.11.

TABLE 1 (UUT)Comment by Anderson, Michael A CIV USN FRCSW (USA): @Pinterich, Jason W CIV USN (USA)The NIINs in red are missing from the GFP Attachment. They need to be added.
FIC
Part Number
NIIN
Component
WAD1
3136-17
014370498
Elevator Servo Actuator
AHQB
3137-13
001068507
Aileron Actuator
3137-15
013586812
Tandem Servo Actuator
JXYB
3241-11
009300219
Electro-Hyd. Autopilot Servo
JYK1
3136-13
001068508
Elevator Tandem Actuator
JTH6
123H10065-502
000245282
Wing Fold Cylinder RH
JTH5
123H10065-501
000252475
Wing Fold Cylinder LH
ZDPN
127400-11
011915741
Servo cylinder
127400-13
013752510
Rudder Actuator Assembly
ZDPJ
127400-12
011915742
Servo Actuator RH
127400-14
013752511
Outboard Rudder Actuator
AJLB
123H10088-502
001597785
Actuating MLG Cylinder
123H10088-501
001597782
Actuating MLG Cylinder
YYZW
123SCH144-6
006788990
Actuator Rudder Inboard
123SCH144-8
006888477
Actuator Rudder Inboard
1273-10
009624351
Rudder Servo Cylinder
123SCH144-12
013848665
Servo cylinder
A21B
893V0200
011515805
Valve Assembly

Note: * Part 3241-9 uses same

4.10. Test Stand:

4.10.1. The operation of the stand shall be manually controlled (i.e manual valves and controls) for all pressure and flow going into the unit(s).

4.10.2. The test stand shall have one (1) built in tank using MIL-PRF-832820 Hydraulic Fluid.

4.10.2.1. The tank shall hold a minimum of 60 gallons of the above fluid.

4.10.2.2. A visible level gauge shall be installed on the tank to show fluid level.

4.10.2.3. The tank shall have a drain port to allow for easy fluid removal and use a manual shutoff valve to open/close the line.

4.10.2.4. The inlet line(s) to the testing will have two (2) hydraulic filters with a minimum of 10-micron and 5-micron ratings.

4.10.3. The temperature of the oil during testing shall be maintained at 75-100℉. The test stand shall have an automatic shutoff if the main reservoir fluid temperature exceeds 125℉.

4.10.4. The main reservoir tank may use water heat exchangers, using an existing chilled water system ranging from 45-65℉.

4.10.5. The contractor shall not modify the chilled water system. The contractor is permitted to modify only the chilled water lines in the testing area when connecting to the test stand during installation.

4.10.6. The test stand shall have a built-in motor and pump system to apply the necessary pressure(s) and flow(s) for testing.

4.10.6.1. Pressure rating of 0-5000 PSI (Pounds per Square Inch)

4.10.6.2. Flow rating of 0-30 GPM (Gallons per Minute)

4.10.7. The testing area for the UUT’s shall be enclosed. The doors shall not have electronic safety sensors due to secondary equipment connected from outside of the bench.

4.10.8. The test area shall utilize existing holding fixture(s), which the vendor does not have to manufacture.

4.10.9. The test area shall accommodate the various lengths with additional space (around 6 inches to 1 ft) on both sides of the UUT. The UUT’s will extend and retract during testing with the longest length being ~31.25 inch.

4.10.10. The test area shall have at minimum two (2) pressure ports and two (2) return ports.

4.10.11. A Selector/Switch valve shall be used on the pressure inlet.

4.10.12. The test area shall have a manual hand pump that is connected to the main reservoir that ranges from 0-10000 PSI.

4.10.13. The test area shall have a sump tank for the runoff fluid during and after testing with a pump and filter system that feeds back into the main reservoir.

4.10.14. The test stand shall have a built-in power supply that can provide 0-120VAC/3ph./400Hz power and 0-40VDC Power.

4.11. Emergency Stop Switches. The HAFTS shall include emergency stop switches that shall be large, red, and push-style. Actuation of the emergency stop switch shall remove all electrical control power from the system to shut down the hydraulic electrical utilities to a safe condition and show an Emergency Shutdown display on the test stand monitor.

4.12. Pneumatic System. The HAFTS system shall conform to ISO 4414, Section 2.2.5.2. The system shall be complete, including all pumps, valves, piping, cylinders, and pressure controls.

4.13. Electrical System. The HAFTS shall conform to NFPA and NEMA standards, Section 2.2.6 & 2.2.7, or current equivalent ISO/EN/DIN/JIS/IEC standards. The existing source power available at the facility is 480 volt, 3-phase, 60 Hertz (Hz). The electrical system shall be complete, including any electrical transformer(s) that may be required to modify the existing source voltage to the proper operating voltage of the equipment. A properly rated, and fused, single disconnect device shall be utilized on the HAFTS with means of lockout in the off position only.

4.13.1. Electrical Enclosures. Construction of the electrical enclosures shall be in accordance with NEMA 250 type 12 or current equivalent ISO/EN/DIN/JIS/IEC standards and shall provide for ventilation of components and shall be designed for an indoor non-hazardous location. All electrical components shall conform to NFPA 79 or equivalent ISO/EN/DIN/JIS standards. The HAFTS shall be provided with interlocks on its electronic cabinet that shall instantly remove power from the equipment when the door is opened in accordance with NFPA 79 or current equivalent ISO/EN/DIN/JIS/IEC standards.

4.13.2. Arc Flash Protection. The HAFTS enclosures shall be marked for arc flash in accordance with NFPA 79 Paragraph 16.2.3 Safety Signs for Electrical Enclosures or current equivalent ISO/EN/DIN/JIS/IEC standards for arc flash safety.

4.13.3. Solid-State Components. Electrical devices used to power electrical servo motors of control voltage delivered to solid-state electrical components shall be solid-state devices. Such devices shall be equipped to handle the electrical load imposed by operation of the HAFTS to its maximum potential. The use of selenium in solid-state components shall be restricted to those devices that protect other solid-state components from voltage surge.

4.13.4. Electronic System Architecture. The electronics system architecture shall have the capability for background monitoring of any measurable parameter with programmed responses as necessary. This monitoring process shall be performed at the application level while essential system wide parameters monitor at the main menu.

4.14. Motors. Motors shall be rated for continuous duty. Alternating-current (AC) motors shall be designed to operate on 60-Hz and each motor enclosure shall meet the requirements for a drip-proof enclosure. All motors shall meet the requirements of NEMA MG-1 or current equivalent ISO/EN/DIN/JIS/IEC standards. Each motor shall have a name plate in accordance with paragraph 4.19 to identify manufacturer, model number, serial number, voltage, amperage, horsepower, phase, frequency, and frame number. Motor horsepower shall be the manufacturer’s standard or standard optional horsepower as indicated on the manufacturer's design and construction drawing(s).

4.15. Facility Connections. Electrical connections made to the facility electrical system shall conform to NFPA 70.

4.16. Hour Meter. The HAFTS shall be equipped with a non-resetting type, hour meter to display accumulated operating time of the drive motor(s), mounted on the main electrical panel visible from the outside, sealed to prevent the entrance of dust and moisture, and shall be mounted to withstand shock and vibration generated by the HAFTS. The meter shall have a range of 0 to 99,999.9 hours in increments of one (1) tenth of one (1) hour. A Programmable Logic Controller (PLC) that tracks and displays total HAFTS on time (a non-resetting type), controller on, program runtime, and run time of the servo motor(s) shall be considered to meet this requirement. The meter shall be sealed to prevent the entrance of dust and moisture and shall be mounted to withstand shock and vibration generated by the HAFTS.

4.17. Standard Tooling and Equipment. The Contractor shall provide all standard tooling and equipment required for proper operation and maintenance of the HAFTS. A list of these items shall be furnished at time of proposal.

4.18. Marking on Instruments, Control Panels, and Plates. All words on plates shall be in the English language. Characters shall be engraved, etched, embossed, or stamped in boldface on a contrasting background. All plates shall be corrosion resistant.

4.19. Lubrication Plate. A lubrication plate shall be permanently and securely attached to the HAFTS. The plate shall contain the following information:

4.19.1. Points of Lubricant Application

4.19.2. Servicing Interval

4.19.3. Type of Lubricant

4.19.4. Viscosity

4.19.5. Military or Federal Specification for Each Lubricant (If available)

4.19.6. Size and Type of Each Lubricant Filter

4.20. Nameplate. A nameplate shall be permanently and securely attached to the HAFTS. The nameplate shall contain the information listed below. If the HAFTS is a special model, the model designation shall include the model number of the basic standard machine and a suffix identified in the manufacturer's permanent records.

4.20.1. Nomenclature

4.20.1.1. Manufacturer’s Name

4.20.1.2. Manufacturer’s Model Designation

4.20.1.3. Manufacturer’s Serial Number

4.20.1.4. Power Input (Volts, Total Amps, Phase, Frequency)

4.20.1.5. Contract Number

4.20.1.6. Date of Manufacture

4.21. Identification Marking of Military Property. An Item Unique Identification Marking (IUID) shall be provided in accordance with MIL-STD-130N Section 2.1.1 and all applicable documents within the standard with Machine Readable Information (MRI) for item identification marking and automatic data capture. The application of Human Readable Information (HRI) shall be used in combination with MRI and free text. At a minimum this tag shall contain the information listed in paragraph 4.19 Nameplate.

4.22. Technical Data (CDRL A001). Three (3) hard copies and one (1) electronic copy of the technical data shall be provided via DOD Safe with the test stand. Technical data shall contain specifications, instructions for the operation, maintenance of the HAFTS and recommended spare parts list. All copies of technical data shall be legible and written in the English language. Technical Data shall include the following:

4.22.1. All engineering drawings shall be in accordance with ASME Y14.100, Section 2.2.3. Technical data shall contain technical information, specifications, instructions for the operation, maintenance of the HAFTS, consumables and expendables information (such as oils, fluids, grease, filters), and recommended spare parts list.

4.22.2. Factory service and operator manuals for the HAFTS system.

4.22.3. Diagnostic procedures for isolating and correcting faults. Procedures shall be included in the service manuals for recalibrating and performing operational checks to ensure proper operation of any replaced parts, as required.

4.22.4. Preventative and predictive maintenance tasks, including oil and vibration analysis, and show recommended intervals of tasks.

4.22.5. Software manuals and registration keys/codes shall be provided, along with original software installation disks.

4.23. Plan of Action and Milestones (POA&M) (CDRL A002). The contractor shall provide a POA&M to identify contractor performance dates of all major events from contract award to completion of all contract requirements. The initial POA&M shall be delivered thirty (30) calendar days After Contract Award (ACA). The milestones shall be prepared using a recognized project management technique (preferably Microsoft Project). The Government and the contractor shall review the report on a monthly basis. The contractor shall notify the Government prior to making any changes to the POA&M. All changes to the POA&M shall be approved in advance by the Government. The POA&M shall detail such items as engineering, procurement of major hardware, assembly, operational debug, factory acceptance, shipment, installation, training, and final acceptance test.

4.24. Preliminary Design Review (CDRL A003). The Contractor shall provide a preliminary design review for the design of the test stand for review by the Government, to show the end users how the stand will look and if possible be reconfigured.

4.25. Critical Design Review (CDRL A003). Once the preliminary design review has been completed, the Contractor shall provide the final design to the Government, to finalize the test stand before factory acceptance.

4.26. Instrument Calibration Procedures Source (ICPS) Data (CDRL A004). The Contractor shall provide ICP source data: system/subsystem specifications, functional specifications, manufacturer’s catalogs or data sheets, user’s manuals, engineering drawings and associated technical data including all versions of relevant software (which impact calibration) for all Test, Measurement and Diagnostic Equipment (TMDE) and calibration equipment/standards that do not have US Navy-approved ICPs. The Contractor shall submit specific recommendations and data using any Contractor’s Technical Report process. The contractor shall provide the calibration procedure in accordance with NAVAIR METCAL and NPSL-BP-01, Section 2.1.3. Vendor prepared ICPs must have Government approval for Navy use.

4.27. Acceptance Test Plan (ATP) (CDRL A005). The Contractor shall prepare an Acceptance Test Plan (ATP). The ATP shall be a step-by-step written instruction on how to verify compliance during Origin Inspection/Test and Final Inspection/Acceptance Test specified in Sections 5.3 and 5.5. The Contractor shall develop and provide how the UUT’s will be tested as specified in Paragraph 5.7.1. The Manufacture’s standard testing procedures shall be included in the ATP. Any procedures necessary for compliance with Section 5, which are not covered by the Manufacturer’s standard testing procedures, shall be identified and included in the ATP. The initial ATP shall be submitted thirty (30) calendar days ACA for Government review and approval. The accepted test procedures shall become part of this contract and property of the Government.

4.28. Installation. The contractor shall be responsible for the complete installation of the HAFTS. FRCSW will only be responsible to drill the anchor bolt holes per contractor’s specifications. The contractor shall provide the Government with the anchor bolt layout, anchor bolt sizes and all information regarding the hardware to be used. The contractor shall verify that the holes are correct before installation. Installation shall include shipping, rigging, uncrating, securing the HAFTS to the floor, leveling of the HAFTS, calibration of the HAFTS, connecting to the existing utilities and conducting the tests listed in section 5.7. The contractor shall not exceed the equipment installation dimensions that are provided in the FRCSW North Island Building 472 Clean Room Layout Drawing. Installation shall also include the following:

4.28.1. Waste Disposal: The contractor shall be responsible for waste disposal generated from the installation process of the HAFTS. Disposal of nonhazardous solid waste shall be the responsibility of the Contractor.

4.28.2. Disposal of Existing Equipment. FRCSW will be responsible for the disposal of the existing piece of equipment.

4.28.3. Facility Connections. Electrical connections made to the facility electrical system shall conform to NFPA 70. The Government will provide all utilities needed within 20 feet of the HAFTS.

4.28.4. Work Stoppage. For unforeseen issues that are found during installation of the foundation, the contractor shall notify the TPOC and PCO immediately to determine further course of action.

4.29. Training. After satisfactory completion of acceptance testing of the system, the contractor shall provide specialized training to familiarize Government personnel with the equipment and to help ensure reliable performance and maximum service life, during normal usage. The course shall utilize as-built drawings and manuals provided under this contract and shall include both classroom and hands on portions. All printed training aids shall be supplied for the course, be in the English language, and become the property of the Government.

4.29.1. Operator Training. Operator training shall be provided at FRCSW. Training shall be provided for a maximum of ten (10) operators. Training shall not be less than five (5) consecutive eight (8) hour workdays, between 6:00 am and 2:30 pm excluding weekends and federal holidays, totaling at least 40 hours of training. Training shall include preparation of equipment for safe operation and proper isolation of equipment procedures. The operator shall be provided instruction for the care, use and operation of all attachments and accessories. Training manuals shall be provided for each operator. Comment by Taylor, Amanda J CIV USN COMFLTREADCEN PAX (USA): @Anderson, Michael A CIV USN FRCSW (USA) @Pinterich, Jason W CIV USN (USA) What if training doesn’t take this long? Do you really want to specify the number of days? Or, is the description good enough for the vendor to determine the time it will take to train them? Comment by Pinterich, Jason W CIV USN (USA): Good question, this used to be how long we did it for the other benches. It seems like the maintenance department wants almost a couple of days training on top of operator training, which i try to give the operators 3-4 days Comment by Anderson, Michael A CIV USN FRCSW (USA): @Pinterich, Jason W CIV USN (USA)State exactly how many days/hours are need for operator training in section 4.29.1. If it’s five days/40 hours, reply that 40 hours are required then resolve thread.

4.29.2. Maintenance Training. Mechanical and Electronic/Electrical maintenance training shall be provided for five (5) maintenance personnel each. Training shall be performed at the Government facility and shall not be less than five (5) consecutive eight (8) hour workdays each, between 6:00 am and 2:30 PM excluding weekends and federal holidays, totaling at least 40 hours of training. Comment by Taylor, Amanda J CIV USN COMFLTREADCEN PAX (USA): Same question Comment by Anderson, Michael A CIV USN FRCSW (USA): @Pinterich, Jason W CIV USN (USA) State exactly how many days/hours are need for maintenance training in section 4.29.2. If it’s five days/40 hours, reply that 40 hours are required then resolve thread.

4.29.3. Training Manuals (CDRL A006). Training manuals shall be provided for each student. The maintenance course shall cover at a minimum:

a. Review of systems drawings and schematics

b. Component location and function

c. Trouble shooting procedures and techniques

d. Repair procedures including disassembly and assembly

e. System maintenance and servicing

f. Set-up, adjustments, and calibration (how, when, and where)

g. Preventative Maintenance procedure

h. Procedures for proper isolation

4.30. Weight Handling Requirements. All weight handling of equipment and any deliverables related to such must adhere to NAVFAC P-307 (June 2016) Weight Handling Program Management. Applicable sections from P-307 include Section 11, 14 and Appendix P. The contractor shall prepare the Certificate of Compliance and the Contractor Crane or Rigging Operation Checklist in Appendix B. Prior to the installation of the HAFTS, a Lift Plan shall be provided by the contractor and approved by the Weight Handling Team. The Lift Plan shall meet all requirements as listed in P-307 Section 11 Part G.

4.31. FRCSW normal business hours of Monday through Friday 0600 to 1430 hours Pacific Standard Time (local time), respecting federal holidays, furloughs, base closures, and other dates that the base might not be operational.

5. INSPECTION AND ACCEPTANCE.

5.1. Responsibility for Inspection. The contractor shall be responsible for the performance of all inspection requirements specified herein. Except as otherwise specified in the contract or purchase order, the contractor may use his own facility for the performance of the inspection requirements specified herein, unless disapproved by the Government. The Government reserves the right to witness any inspections set forth in the purchase description where such inspections are deemed necessary to assure supplies and services conform to prescribed requirements.

5.1.1. Responsibility for Compliance. All items must meet all requirements of sections 3 and 4.

5.1.2. Classification of Inspections. The inspection requirements specified herein are classified as follows:

5.1.2.1. Origin Inspection/Test (see 5.3).

5.1.2.2. Final Inspection/Acceptance test (Destination) (see 5.5).

5.2. Inspection Conditions. All inspections, tests, and examinations shall be performed in an indoor facility with ambient temperature conditions in the range of 55 degrees F to 100 degrees F and 10% to 95% relative humidity.

5.3. Origin Inspection/Test. Origin inspection and origin test shall be conducted at the contractor’s facility prior to being offered for acceptance under the contract. The HAFTS and all peripheral equipment added to the HAFTS shall be fully assembled and perform all functions in accordance with this SOW. Origin inspection and origin test shall consist of the examination in 5.6 and the tests in 5.5.2. and 5.5.2.1. The HAFTS shall pass the examination, all tests, and inspection to be acceptable for shipment. If the HAFTS does not pass origin test, it does not ship until Contractor meets all requirements for origin test. Comment by Taylor, Amanda J CIV USN COMFLTREADCEN PAX (USA): @Anderson, Michael A CIV USN FRCSW (USA) @Pinterich, Jason W CIV USN (USA) What is passing? What if it doesn’t? Comment by Anderson, Michael A CIV USN FRCSW (USA): Passing is defined in Section 5.5.2. & 5.5.2.1. If the HAFTS does not pass origin test, it does not ship until Contractor meets all requirements for origin test.

5.4. UUT’s (Origin). The Government will provide and ship all the UUT’s listed in section 4.9, TABLE I for the performance test at origin. The Contractor shall cover the cost and ship all UUTs in Section 4.9 back to FRCSW in the same condition received for Final Inspection/Acceptance Test.

5.5. Final Inspection/Acceptance Test (Destination). Final Inspection and acceptance test shall be performed on the HAFTS to ensure conformance with SOW description. The acceptance test shall be performed only after the HAFTS is installed at its final location. The acceptance test shall consist of the examination in Section 5.5.1. and all tests in Section 5.5.2. and 5.5.2.1. The HAFTS shall pass the examination and all tests to be accepted. FRCSW will NOT sign the DD250 until the HAFTS passes Section 5.5 and associated subsections. Comment by Taylor, Amanda J CIV USN COMFLTREADCEN PAX (USA): @Anderson, Michael A CIV USN FRCSW (USA) @Pinterich, Jason W CIV USN (USA) what happens if it doesn’t? Comment by Anderson, Michael A CIV USN FRCSW (USA): FRCSW will NOT sign the DD250 until the HAFTS passes Section 5.5 and associated subsections.

5.5.1. Examination. The equipment shall be examined for design, dimensions, construction, materials, components, electrical equipment and workmanship to determine compliance with the requirements listed in Sections 4 and 5 of this SOW. Comment by Taylor, Amanda J CIV USN COMFLTREADCEN PAX (USA): Should it be examined before you test it? What if it passes the test but not the examination? Comment by Anderson, Michael A CIV USN FRCSW (USA): Examination and test can run concurrently. FRCSW will not decide whether test or inspection occurs first. This is at the Contractors discretion.

If either the test or the examination fail, the Contractor shall fix any discrepancies for the HAFTS to be accepted by FRCSW/sign the DD250.

5.5.2. Tests. Unless otherwise specified within this SOW, all programs, instruments, materials, material handling equipment, and tools required to perform and evaluate the tests shall be furnished by the contractor. All measurement tools and indicating devices shall be calibrated in accordance with National Institute of Standards and Technology (NIST) Section 2.2.1. If a malfunction occurs during the test, the test shall be restarted each time until all tests under section 5.7 are completed without a malfunction. Three (3) consecutive failures without completion of the test may be considered cause for rejection of the system. For the purpose of this test, a failure is defined as any equipment malfunction which requires remedial action to restore the system to full operation in accordance with this specification. Comment by Taylor, Amanda J CIV USN COMFLTREADCEN PAX (USA): @Anderson, Michael A CIV USN FRCSW (USA) @Pinterich, Jason W CIV USN (USA) answers the above. Put it where it makes sense. Comment by Anderson, Michael A CIV USN FRCSW (USA): Corrected

5.5.2.1. Performance Test. The test stand shall satisfactorily and accurately test each UUT in accordance with the parameters defined in the NAVAIR manuals listed in TABLE 1 of this SOW. After completion of this test, the contractor shall provide the Government a copy of all test results completed. (CDRL A007). The government will provide the UUTs for the performance test.

6. WARRANTY:

6.1. The equipment furnished under this contract shall be covered by the most favorable commercial warranties the Contractor gives to any customer for such equipment.

7. DELIVERABLES

7.1. Contract Data Requirements List (CDRL). The following items that have been listed in this specification are deliverables that the contractor shall provide:

7.1.1. Technical Data (A001)

7.1.2. Plan Of Actions and Milestones (A002)

7.1.3. Preliminary/Critical Design Review (A003)

7.1.4. Instrument Calibration Procedures Source Data (A004)

7.1.5. Acceptance Test Plan (A005)

7.1.6. Printed Training Aids (A006)

7.1.7. Test/Inspection Report (A007)

8. SECURITY REQUIREMENTS

8.1. Naval Base Coronado (NBC) Access

8.1.1. Security Forms. The Contractor shall coordinate with the TPOC to obtain SECNAV Form(s) 5512/1. The Contractor shall complete one SECNAV Form(s) 5512/1 for each of the Contractor’s personnel requiring access to NBC. Form 5512/1 requires the following information for each contractor personnel working on-site:

8.1.1.1. Full name (first, middle and last)

8.1.1.2. Date of birth and place of birth

8.1.1.3. Citizenship (contractors must be a US citizen)

8.1.1.4. Full social security number

8.1.2. The Contractor shall submit SECNAV Form(s) 5512/1 to the TPOC at least ten (10) business days in advance of the scheduled site visit.

8.1.3. Upon arrival, Contractor personnel shall report to the Visitor Control Center (VCC) Bldg. 680, which is located near the Main Gate to Naval Base Coronado, NAS North Island, San Diego, CA. Contractor personnel shall check in and request a Defense Biometric Identification System (DBIDS) card. Only personnel in compliance with Sections9.1.1. and 9.1.2. will receive a DBIDS. Contractor personnel that do not possess a DBIDS will be refused entry to NBC.

8.2. FRCSW Access

8.2.1. Security Forms. The Contractor shall coordinate with the TPOC to obtain FRCSW Form 5512/5. The Contractor shall complete one FRCSW Form 5512/5 listing all Contractor personnel. The Contractor shall submit FRCSW Form 5512/5 to the TPOC at least ten (10) business days in advance of the scheduled site visit.

8.2.2. Contractor personnel shall coordinate with the TPOC to obtain Visitor Badges through the FRCSW Quarterdeck, located in Building 94. Only personnel in compliance with Section 9.2.1. will receive a Visitor Badge. Contractor personnel shall submit a federally issued identification card to obtain a Visitor badge.

8.2.3. Contractor personnel shall report to FRCSW Quarterdeck at Building 94 before start of daily work to obtain visitor badges. Visitor badges shall be worn and visible at all times while on FRCSW work site.

8.2.4. After completion of daily work Contractor personnel shall return visitor badges to FRCSW Quarterdeck at Building 94.

8.3. Photo/Video Compliance:

8.3.1. The Contractor shall not take any photographs or videos onsite. The Contractor shall submit a request to the TPOC for any required photographs or videos.

8.4. Cybersecurity Compliance:

8.4.1. The contractor shall achieve and maintain CMMC Level 2 or above in accordance with DFARS 252.204-7021 for each Contractor information system that will process, store, or transmit Federal Contract Information (FCI) used in performance of the contract.

File details come from the government source that posted it. Updated .