This document appears to be a questions and answers (Q&A) document for a facilities relocation project involving multiple buildings (B678, B150, and B5). The document details specific furniture and equipment moving requirements for different rooms across these locations.

Key details include: For B678, the Contractor is required to move Bench Units to rooms S159 and S144 in Hangar 1 ALOFT, specifically breaking a 6-top unit into a 4-top and 2-top configuration. In B150, the Contractor must move a standing desk and executive office desk from Room 231 to the outside office area and dispose of the old desks. For B5, ports along the eastern wall in Room 208 will be left open as they are compatible with the proposed configuration. The document references an attachment "A-1-Benching Removal from B678 to Hangar 1" for detailed layout diagrams, and most non-replaced furniture will be moved by Government personnel prior to the Period of Performance start date.

View the file

Other files

File Type Posted
Attachment 002 - Price Sheet v2.xlsx XLSX spreadsheet
Attachment 001 - Statement of Work_redlined.pdf PDF
CDRLs.pdf PDF
N6833525Q0357.pdf PDF
Attachment 001 - Statement of Work.docx DOCX document
Attachment 002 - Price Sheet.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

B678

1. There are filing cabinets and an additional cabinet present in one of the installation areas that need to be moved. Will the contractor be responsible for moving these?

a. The cabinets will be moved by Government personnel prior to the Period of Performance start date.

2. The Bench Units currently in the area are to be moved to Hangar 1 ALOFT. Is there a specific room these units are to be moved to?

a. The Contractor shall be responsible for moving the Bench Units to rooms S159 and S144 in Hangar 1 ALOFT. The Contractor will need to break up the 6-top unit into a 4-top and 2-top and relocate it into S159. The remaining benches will be relocated to S144. Please refer to the attachment “A-1-Benching Removal from B678 to Hangar 1” for a diagram of the current setup in B678 and rooms S159 and S144 as well as what the new layouts of rooms S159 and S144 will be.

B150

1. In Room 231, there is a file cabinet, bookcase, and couch that are not being replaced. Will that furniture be moved prior to the Period of Performance starts date?

a. That furniture will remain in the office.

2. In Room 231, will the standing desk and executive office desk be moved to the office area outside of the room?

a. The Contractor shall be responsible for moving the standing desk and executive office desk currently in Room 231 to the office area outside the room and disposing of the old desks.

B5

1. Will the furniture in Room 203 not being replaced be moved prior to the Period of Performance start date?

a. These items will be moved by Government personnel before the Period of Performance start date.

2. There are ports present along the eastern wall in Room 208. Will these be left open?

a. These ports will be left open as they work with the proposed configuration.