QA2.pdf
PDF 228 KB Posted
- Solicitation number
- N6833524R0497
About this file
This document appears to be a Question and Answer (Q&A) related to a federal contract opportunity. The key details are:
The contract opportunity is for the procurement, assembly, and installation of furniture in support of the NAWCAD LKE Building 678 SEAMLESS Work Area Build, as outlined in the attached Statement of Work (SOW). The contract will be a Firm-Fixed-Price with a Period of Performance of 90 days. A site visit is required for award, and interested offerors must confirm attendance no later than 48 hours prior to the visit on 5 June 2024. The Q&A provides clarification on the required CAT6 data cabling, confirms the location of the termination point, and indicates that all available drawings have been distributed to site visit attendees. Requests for the SOW diagram must be submitted by 12 June 2024. The contracting agency is the Department of the Navy Naval Air Systems Command Naval Air Warfare Center.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site Visit QA.pdf | ||
| Attachment 002 - Price Sheet (6-6).xlsx | XLSX spreadsheet | |
| Attachment 002 - Price Sheet.xlsx | XLSX spreadsheet | |
| Attachment 001 - Statement of Work.pdf | ||
| N6833524R0497.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Q1a. Please confirm what type of cable is required for NMCI & RDT&E loca ons (Category 6 data cable?
Or something else?)
A1a. A er reviewing the Statement of Work (SOW) Sec on 5, the NMCI Cable Installa on Standards paragraph 2.1 Inside Plant and the UFC Telecommunica ons Interior Infrastructure Planning and Design, Change 1 Sec on 2-6, please u lize CAT6 data cabling with 8-posi on (RJ45) jacks. See NMCI Cable Installa on Standards paragraph 2.1 for required color coding.
Q1b. Will these cables all be pulled to the same network room, but on different patch panels? Or are they going to a different loca on.
A1b. All the data and telephone cables will be pulled to the designated "COMM" Room shown on the Statement of Work (SOW) - Diagram. It is located just above the electrical room on the diagram and has the door which swings opens into the Hallway. Within that same COMM Room, one exis ng rack is designated for NMCI, one exis ng rack is designated for RDT&E and the exis ng telephone block is mounted on the plywood.
Q2. Are there any previous as-built drawings available that we can review to confirm what is exis ng currently in the space? If not, is there anyway to confirm what is exis ng in the space?
A2. All available drawings have been distributed via DoD SAFE to all site visit a endees. If you a ended the site visit and did not receive the drawings, please check your spam folder or contact mark.a.schni man.civ@us.navy.mil.
Q3. Please confirm the loca on of the MDF/IDF on the plans provided. If not shown on any plans, please confirm how far away it is in rela on to the renovated area.
A3. For this Statement of Work (SOW), the contractor is only required to comply with Sec on 5.0 Cabling and add the required cabling from the termina on site to the respec ve COMM Room rack either in the exis ng patch panel or a new patch panel provided by this contractor, if needed.