This document is a Specifications for Work to Be Accomplished for the USS Lewis B Puller (ESB 3), a Naval Expeditionary Support Vessel. The specification number is NAPL-008-27, and it includes all changes through November 18, 2026.
The specification establishes work requirements across multiple categories of tasks. Category I contains 36 FY-27 Standard Items that apply directly to this job order, including general criteria, environmental compliance, quality management, confined space entry, fire protection, asbestos control, government property management, and ship stability maintenance. Notable items include temporary access requirements, electrical cable procedures, occupational safety and health planning, and various testing and certification protocols. Category II identifies three additional standard items that may be invoked as needed: insulation and lagging, weld/fabricate/inspect operations, and cleaning and painting requirements (updated June 6, 2025). The specification also defines six specific work items: installation of three Twenty-Foot Equivalent Reefer Units (TEU) with 460-volt or 230-volt electrical requirements; replacement of two walk-in cooler/freezer doors in designated storerooms; replacement of two Aircraft Electrical Service Stations (AESS) on the Flight Deck; replacement of one modular dishwasher in the Scullery requiring OEM service provider support; removal and replacement of four 4-drawer file safes in communications and training spaces; and provision of steel tube and clamp scaffolding at the Aft House to reach antenna equipment, capable of sustaining 750-pound working loads with daily safety certification requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 4.02a J-1 Price Breakdown.xlsx | XLSX spreadsheet | |
| 4.02d J-4. Contract Qualification TIP Example.pdf | ||
| 4.02e S-1. Non-Disclosure Agreement.pdf | ||
| 4.02 N6817127QN013.pdf | ||
| 4.02c J-3. Contract Qualification Checklist.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE NAVY
FDRMC NAPLES
FPO, AE
USS LEWIS B PULLER (ESB 3)
SPECIFICATIONS FOR WORK TO BE ACCOMPLISHED
SPECIFICATION NUMBER: NAPL-008-27
INCLUDES ALL CHANGES THROUGH 11/18/2026
INDEX
SHIP: USS LEWIS B PULLER (ESB 3) NAPL-008-27
ITEMS THAT ARE STRUCK OUT IN THIS INDEX DO NOT APPLY TO THIS CONTRACT.
CATEGORY I. FY-27 STANDARD ITEMS APPLICABLE TO THIS JOB ORDER WITHOUT FURTHER REFERENCE.
ITEM_NO. TITLE CHANGE DATE CHANGE
009-001 General Criteria; accomplish 10/01/2024 Original
009-002 Environmental Compliance Report for Material Usage; accomplish 10/01/2024 Original
009-003 Toxic and Hazardous Substance; control 10/01/2024 Original
009-004 Quality Management System; provide 10/01/2024 Original
009-005 Temporary Access; accomplish 11/18/2024 CH-1
009-006 Maintaining Protection and Cleanliness from Non-Radioactive Operations;
accomplish
10/01/2024 Original
009-007 Confined Space Entry, and Certification; accomplish 10/01/2024 Original
009-008 Shipboard Fire Protection and Fire Prevention; accomplish 10/01/2024 Original
009-010 Asbestos-Containing Material (ACM); control 10/01/2024 Original
009-018 Mine Warfare Ships Magnetic Material; control 10/01/2024 Original
009-019 Provisioning Technical Documentation (PTD); provide 10/01/2024 Original
009-020 Government Property; control 10/01/2024 Original
009-021 Alteration Verification, Logistic and Technical Data; provide 10/01/2024 Original
009-023 Interference; remove and install 11/18/2024 CH-1
009-024 Authorization, Control, Isolation, Blanking, Tagging, and Cleanliness; accomplish 10/01/2024 Original
009-034 Fire Protection of Unmanned Vessel at Contractor Facility; accomplish 10/01/2024 Original
009-039 Technical Manual Contract Requirement (TMCR) for a New Technical Manual for
Commercial Equipment/Component; accomplish
10/01/2024 Original
009-040 Contractor Crane, Multi-Purpose Machine and Material Handling Equipment at a
Naval Facility; provide
10/01/2024 Original
009-060 Schedule and Associated Report for CNO Availability; provide and manage 10/01/2024 Original
009-061 Shipboard Use of Fluorocarbons; control 10/01/2024 Original
009-067 Integrated Total Ship Testing; manage 10/01/2024 Original
009-068 Availability Work Certification (AWC) Data for Chief of Naval Operations (CNO)
Availabilities; provide
10/01/2024 Original
009-069 Heavy Weather/Mooring Plan; provide 10/01/2024 Original
009-070 Confined Space Entry, Certification, Fire Protection, Fire Prevention and
Housekeeping for Unmanned Vessels; accomplish
10/01/2024 Original
009-072 Physical Security at a Private Contractor Facility; accomplish 10/01/2024 Original
009-073 Shipboard Electrical/Electronic Cable Procedure; inspect, test, install, remove, and repair
10/01/2024 Original
009-074 Occupational, Safety and Health Plan; accomplish 10/01/2024 Original
009-080 Ship Facility; maintain 10/01/2024 Original
009-081 Compartment Closeout; accomplish 10/01/2024 Original
009-082 Installation of Equal Component Vice Specified Component; report 10/01/2024 Original
009-084 Threaded Fastener Requirement; accomplish 10/01/2024 Original
009-088 Collection, Holding and Transfer (CHT) and Motor Gasoline (MOGAS) Tank, Space, and Piping, including Sewage or MOGAS-Contaminated Tank, Space, and Piping; certify
10/01/2024 Original
009-093 Emergency Planning and Community Right-to-Know Act (EPCRA) and Pollution
Prevention Act (PPA) Information; provide
10/01/2024 Original
Page 1 of 4 PLANNED WORK
ITEM_NO. TITLE CHANGE DATE CHANGE
009-099 Ship Departure Report; provide 10/01/2024 Original
009-100 Ship's Stability; maintain 10/01/2024 Original
009-101 Ship Transit and Berthing; accomplish 10/01/2024 Original
009-106 Work Authorization Form Coordinator (WAFCOR); provide 10/01/2024 Original
009-109 Non-SUBSAFE Work on SUBSAFE-Certified Vessel; accomplish 10/01/2024 Original
009-110 Non-Nuclear Work on a Nuclear Vessel; accomplish 10/01/2024 Original
009-111 Schedule and Associated Report for Non-CNO Availability; provide and manage 10/01/2024 Original
009-117 Combat Systems, Light-Off Suport; provide 10/01/2024 Original
009-118 CG Deck Loading; accomplish 10/01/2024 Original
009-120 Fact Finding and Critique of Unplanned Event; manage 10/01/2024 Original
009-122 Temporary Padeye; install and remove 11/18/2024 CH-1
009-125 Boat 65 Feet (20meters) Long and Less; accomplish 11/18/2024 CH-1
009-126 Schedule Model Review (SMR); accomplish 10/01/2024 Original
Page 2 of 4 PLANNED WORK
CATEGORY II. FY-27 STANDARD ITEMS WHICH MAY BE INVOKED IN THE WORK ITEMS OF THIS JOB ORDER.
TITLE CHANGE DATEITEM NO. CHANGE
009-011 Insulation and Lagging; accomplish 10/01/2024 Original
009-012 Weld, Fabricate, and Inspect; accomplish 10/01/2024 Original
009-032 Cleaning and Painting Requirements; accomplish 06/06/2025 CH-2
Page 3 of 4 PLANNED WORK
ITEM NO. TITLE
Twenty-Foot Equivalent Reefer Unit (TEU) Install; accomplish516-10-001
Walk-In Reefer Door Replacement; accomplish516-10-002
Aircraft Electrical Service Station (AESS) Replacement; accomplish631-13-001
Dishwasher Replacement; accomplish651-11-001
Safes, Remove and Replace; accomplish671-00-001
Scaffolding for Ship's Force Use; provide991-12-001
Page 4 of 4 PLANNED WORK
SHIP: USS LEWIS B PULLER (ESB 3) ITEM NO: 516-10-001
COAR: 26 PCN: SERV-L189
CMP: NONE
PLANNER: KRIEGER, DANIEL
STAPLES,
MICHAEL.FDRMC
SSP: NAPL-008-27 1 of 2 ITEM NO: 516-10-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Twenty-Foot Equivalent Reefer Unit (TEU) Install; accomplish
1.2 Location of Work:
1.2.1 A1 Level, Mission Deck (FWD)
1.3 Identification:
1.3.1 Quantity (3 EA), Seabox 8140.6, 20-foot Refrigerated Storage Container, Carrier Model No. MTWC-50/50-SP, Refrigerant: (R-513a)
2. REFERENCES:
2.1 NAVSEA Standard Items, (FY27 CH-2)
2.2 S0400-AD-URM-010 Rev 8, Tag-out Users Manual
2.3 801-8389193, General Arrangement
3. REQUIREMENTS:
3.1 Install new the equipment listed 1.3 and located in 1.2, using 2.2 and 2.3 for guidance. See Note 4.2.
3.1.1 Provide crane lifts and riggers to support loading new
equipment from the pier and as directed by the SUPERVISOR.
(V)(G) "OPERATIONAL TEST"
3.2 Test newly installed Reefer Unit TEUs under systems normal operating pressure and temperature. Allowable leakage or malfunction: None.
(V)(G) "COMPARTMENT CLOSEOUT"
3.3 Accomplish a joint inspection with the SUPERVISOR and the Commanding Officer's designated representative upon completion, inspection, and acceptance, by the contractor, of work within each compartment. Ensure Attachment A, Work Completion Certification, is completed in accordance with 009 004 of 2.1.
4. NOTES:
4.1 Standard Items are available at:
https://www.navsea.navy.mil/Home/RMC/CNRMC/Our-Programs/SSRAC/.
4.2 TEU's have been ordered and will be provided by the ship. 8’6” x 20’ Reefer Container, EZ-open 1/3-2/3 door, easy access "butcher" door, LED lighting, panic alarm, air curtains, inside safety release, and flat flooring, Electrical Requirements: 460 volt, 3-phase, 30 amps or 230 volt, 3-phase, 60 amps.
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
SHIP: USS LEWIS B PULLER (ESB 3)
SSP: NAPL-008-27 2 of 2 ITEM NO: 516-10-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
TOTAL
QUANTITY
PROVIDED NAME Of PART
PIECE
NO.
REF
NO.
NATIONAL
STOCK
NO.
REQ
PARA NO.
1. 3 EA
20' X 8'6" Reefer Container
SB8140.6
Q 2.2 N/A 3.1
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
1. None.
SHIP: USS LEWIS B PULLER (ESB 3) ITEM NO: 516-10-002
COAR: 26 PCN: EE02-0717
EA01-0754
CMP: NONE
PLANNER: KRIEGER, DANIEL
SSP: NAPL-008-27 1 of 2 ITEM NO: 516-10-002
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Walk-In Reefer Door Replacement; accomplish
1.2 Location of Work:
1.2.1 Chilled Food Storeroom (A4-93-1)
1.2.2 Freezer Storeroom (A4-94-1)
1.3 Identification:
1.3.1 Quantity (2 EA), Walk-in Cooler/Freezer, MFR: Arctic
Industries Inc., MFR DWG: 81726, MFR ID: F-8478, Type: Walk-in Cooler/Freezer MLP-RPA-01-01.008
2. REFERENCES:
2.1 NAVSEA Standard Items, (FY27 CH-2)
2.2 516-8468139 Rev C, Refrigeration System Diagram
2.3 T6161-LN-FSE-010, Ship Service Refrigeration Plant 1 & 2, MODEL 90TG41RBJ6BA6K9B; Chill Room, Dairy Room, Frozen Room Unit Coolers, MODELS AA36-145B-FS, AA26-115B-FS, AE64-215B-FS FOR USNS MONTFORD POINT
2.4 605-2540769 Rev D, Label Plate Standards
3. REQUIREMENTS:
3.1 Remove existing and install new material provided in 5.2, and located in 1.2, using 2.2 and 2.3 for guidance.
3.1.1 Restore each mating surface exposed by door removal. Repair by removing each high spot, burr, abrasion and foreign matter, where removal can be accomplished by hand tool.
3.1.2 Chase and tap each exposed threaded area.
(Q)(G) "OPERATIONAL TEST"
3.2 Accomplish an operational test of the door in accordance with 2.3.
Cycle each door from full closed to full open to full closed 4 times.
Allowable binding or sticking: None.
3.3 Install each new label plate in accordance with 2.4, using 2.2 for guidance.
(V)(G) "COMPARTMENT CLOSEOUT"
3.4 Accomplish a joint inspection with the SUPERVISOR and the Commanding Officer's designated representative upon completion, inspection, and acceptance, by the contractor, of work within each compartment. Ensure Attachment A, Work Completion Certification, is completed in accordance with 009 004 of 2.1.
4. NOTES:
SSP: NAPL-008-27 2 of 2 ITEM NO: 516-10-002
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
4.1 None.
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
TOTAL
QUANTITY
PROVIDED NAME Of PART
PIECE
NO.
REF
NO.
NATIONAL
STOCK
NO.
REQ
PARA NO.
1. 2 EA
Door, Walk-in Refrigerator 2.1 3.1
SHIP: USS LEWIS B PULLER (ESB 3) ITEM NO: 631-13-001
COAR: 26 PCN: EE02-L032
EE02-L031
CMP: NONE
PLANNER: KRIEGER, DANIEL
STAPLES,
MICHAEL.FDRMC
SSP: NAPL-008-27 1 of 2 ITEM NO: 631-13-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Aircraft Electrical Service Station (AESS) Replacement;
accomplish
1.2 Location of Work:
1.2.1 Flight Deck, A5 Level
1.2.1.1 A5-78-2-WD, AESS No. 2
1.2.1.2 A5-58-2-WD, AESS No. 4
1.3 Identification:
1.3.1 Quantity (2 EA) Quantity Aircraft Electrical Service Station (AESS), MFR-ID-MODEL 60SE230, MFR Part No. 500038-001; APL: 11A150020
2. REFERENCES:
2.1 NAVSEA Standard Items, (FY27 CH-2)
2.2 801-8389193, General Arrangement
2.3 588-8393781 Rev H, Aviation Facilities Strategy Sketch
2.4 S9086-VD-STM-010/CH-631 Rev 3, ACN 1/R4 Preservation of Ships in Service – General
2.5 TE010-BP-MMC-010, 400 Hz Ground Power Unit Model 45SE230
3. REQUIREMENTS:
3.1 Provide the service of an authorized original equipment manufacturer (OEM) service provider for removal, inspection, repair, installation, testing and provide each special tool and drawing for each equipment listed in 1.3 and located in 1.2.
3.2 Disconnect and remove the equipment listed in 1.3 and located in 1.2 such that each mounting bracket and deck plating are accessible for inspection.
(V)(G) "VISUAL INSPECTION"
3.3 Accomplish a visual inspection of each area exposed by equipment removals for structural integrity, deterioration, pitting, cracks, and areas of damage or distortion in each location listed in 1.2 using 2.2 through 2.4 for guidance.
3.3.1 Submit one legible copy, in an approved transferrable media, of a report listing results of the requirements of 3.3 to the
SUPERVISOR.
3.4 Provide and replace each new equipment listed in 1.3 and located in
SSP: NAPL-008-27 2 of 2 ITEM NO: 631-13-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1.2 using 2.2, 2.3 and 2.5 for guidance.
(V)(G) "AESS POWER-UP TEST"
3.5 Accomplish a power-on test of each AESS unit to verify proper input power in accordance with shipboard operating procedure, using Chapter 1, Section 4 and Table 1-4-3 of 2.5 for guidance. CAUTION: DO NOT TEST
OUTPUT POWER.
(V)(G) "LOAD BANK TEST"
3.6 Accomplish load bank test of each new equipment listed in 1.3 and located in 1.2 using 2.5 for guidance.
3.7 Accomplish the requirements of 009-032 of 2.1 for each new and disturbed surface.
(V)(G) "COMPARTMENT CLOSEOUT"
3.8 Accomplish a joint inspection with the SUPERVISOR and the Commanding Officer's designated representative upon completion, inspection, and acceptance, by the contractor, of work within each compartment. Ensure Attachment A, Work Completion Certification, is completed in accordance with 009 004 of 2.1.
4. NOTES:
4.1 Known possible source for qualified Technical Representative:
SIDUS 7352 Trade St. San Diego CA 92121 USA www.sidus-solutions.com
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
SHIP: USS LEWIS B PULLER (ESB 3) ITEM NO: 651-11-001
COAR: 26 PCN: EA01-0733
CMP: NONE
PLANNER: KRIEGER, DANIEL
STAPLES,
MICHAEL.FDRMC
SSP: NAPL-008-27 1 of 9 ITEM NO: 651-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Dishwasher Replacement; accomplish
1.2 Location of Work:
1.2.1 Scullery (A4-92-2-E)
1.3 Identification:
1.3.1 Quantity (One EA), Modular Dishwasher, Mfr: Insinger Machine Co., Sheet 10 of 14 of 2.5, APL: 43A070052.
2. REFERENCES:
2.1 NAVSEA Standard Items, (FY27 CH-2)
2.2 S6163-CD-MMO-010 Rev 1, Installation, Operation, and Maintenance Insinger Dishwasher, Galleymaster Series
2.3 S0400-AD-URM-010/TUM Rev 8, Tag-out Users Manual
2.4 651-8614511 Rev A, Galley & Messroom Arrgt & Detail
2.5 533-8886051, Ships Service Hot and Cold Potable Water System Diagram
2.6 505-8468249 Rev A, Booklet of System Diagram
2.7 MIL-STD-2003B (NAVY), Electric Plant Installation Standard Methods for Surface Ships and Submarines
2.8 MIL-STD-1310H (NAVY), Shipboard Bonding, Grounding and Other Techniques for Electromagnetic Compatibility, Electromagnetic Pulse (EMP) Mitigation, and Safety
2.9 S9086-KC-STM-010/300V1, Electric Plant - General
2.10 635-8614804 Rev D, Insulation Schedule Pipe and Vent
3. REQUIREMENTS:
3.1 Provide the service of an authorized original equipment manufacturer (OEM) service provider for removal, inspection, repair, installation, testing and provide each special tool and drawing for each equipment listed in 1.3, and located in 1.2. See Note 4.2.
3.1.1 Submit one legible copy, in English, in approved transferrable media, of the name and each qualification of the Technical Representative to the SUPERVISOR for approval a minimum of 15 days prior to commencement of work.
(V)(G) "RECEIPT INSPECTION"
3.2 Accomplish material receipt inspection for GFM. Verify exact quantity, material batch/lot, shelf life, and condition of material packaging. Allowable damage or deviation: None.
(V)(G) "TAG-OUT VERIFICATION"
SSP: NAPL-008-27 2 of 9 ITEM NO: 651-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
3.3 Prior to commencement of work, contractor shall obtain Ship's Force signature as verification of tag out and record tagout serial number using 2.3 for guidance. Acceptance Criteria: Equipment/System De-energized: No Deviation.
3.4 Provide rigging services with certified rigging tools and chain falls to support rigging of equipment listed in 1.3.1. and located in 1.2.
3.4.1 Submit one legible copy, in hard copy or approved
transferrable media, of a report to the SUPERVISOR that all lifting and handling materials have been inspected, tested, and are safe for use.
3.5 Disconnect mechanically and electrically, and remove each equipment listed in 1.3 and located in 1.2 using 2.2 for guidance. Retain electrical hook up data and installation hardware for reuse.
3.5.1 Dispose each equipment in accordance with local environmental and waste management practices as directed by the SUPERVISOR.
(V)(G) "VISUAL INSPECTION"
3.5.2 Accomplish a visual inspection of each exposed foundation surface for equipment removed in 3.5, for structural integrity, deterioration, pitting, cracks, and areas of damage or distortion.
Document results on Enclosure (One).
3.5.2.1 Submit one legible copy, in hard copy or transferrable media, of a report listing results of the requirements of 3.5.2 to the SUPERVISOR. Document results on Enclosure (One).
3.5.3 Restore each mating surface exposed by removal. Repair by removing each high spot, burr, abrasion, and foreign matter, where removal can be accomplished by a hand tool.
3.5.4 Chase and tap each exposed threaded area.
3.6 Install new equipment provided in 5.1.1 and inspected in 3.2 in the location listed in 1.2 in accordance with 2.2 using 2.4 through 2.9 for guidance.
3.6.1 Mechanically clean each exposed mating flange assembly free of contamination.
3.6.2 Clean exposed parts free of oil and foreign matter, leaving no residue or injurious effects.
3.6.3 Chip and grind surfaces flush in way of repairs.
(I)(G) "NDT INSPECTION"
3.7 Accomplish the requirements of 009-012 of 2.1 Table 2, Column D, Lines One through 6 for the equipment listed is 1.3 located in 1.2 using 2.2, 2.4 through 2.6 for guidance.
(I)(G) "FINAL VISUAL INSPECTION"
3.8 Conduct visual inspection of areas welded in 3.7 in accordance with 009-012 Table 2, Column D, Line 7.
SSP: NAPL-008-27 3 of 9 ITEM NO: 651-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
3.9 Install electrical equipment and cabling using hook-up data retained in 3.5 using 2.7 for guidance.
(V)(G) "INSULATION RESISTANCE TEST"
3.9.1 Accomplish an insulation resistance test of each cable using the appropriate direct current megger using Table 300-3-4 of 2.9 for guidance.
3.9.1.1 Submit one legible copy, in English, in hard copy or
approved transferrable media, a report in English, listing results of the requirements of 3.9.1 to the SUPERVISOR within 24 hours of testing. Document results on Enclosure (One)
3.9.2 Accomplish bonding and grounding of the equipment in
accordance with 2.8.
(V)(G) "OPERATIONAL TEST"
3.10 Accomplish an operational test of each new dishwasher under normal operating conditions, in accordance with 2.2 and technical representative. Acceptable Criteria: Equipment operating at 20 PSIG and final rinse is heated at 180 Degrees Fahrenheit. Document results on Enclosure (One).
3.10.1 Upon satisfactorily completion of operational tests, turn over all manuals, guides, and warranties of new equipment to the Ship's Force via SUPERVISOR.
(V)(G) "TIGHTNESS TEST"
3.11 Accomplish tightness test for each new and disturbed mechanical joint at nominal operating pressure and temperature. Allowable leakage:
None.
3.12 Accomplish the requirements of 009-011 of 2.1 for disturbed and damaged potable water piping lagging using 2.10 for guidance.
3.13 Accomplish the requirements of 009-032 of 2.1 for each new and disturbed surface.
(V)(G) "COMPARTMENT CLOSEOUT"
3.14 Accomplish a joint inspection with the SUPERVISOR and the Commanding Officer's designated representative upon completion, inspection, and acceptance, by the contractor, of work within each compartment. Ensure Attachment A, Work Completion Certification, is completed in accordance with 009 004 of 2.1.
4. NOTES:
4.1 NAVSEA Standard Items are available at:
https://www.navsea.navy.mil/Home/RMC/CNRMC/Our-Programs/SSRAC/
4.2 Known OEM:
Dennis Boyd
D. W. Boyd Corporation
4003 Colley Ave.
SSP: NAPL-008-27 4 of 9 ITEM NO: 651-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
Norfolk, VA 23508
Phone: 757.423.2268
Facsimile: 757.423.1868
Mobile: 757.201.4837 www.dwboyd.com
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
TOTAL
QUANTITY
PROVIDED NAME Of PART
PIECE
NO.
REF
NO.
NATIONAL
STOCK
NO.
REQ
PARA NO.
1. 1 EA
Dishwashing Machine 2.1 3.6
5.2 PUSH MATERIAL:
1. None.
SSP: NAPL-008-27 5 of 9 ITEM NO: 651-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S. International Traffic in Arms Regulation (ITAR).
This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
Enclosure (One)
TEST AND INSPECTION VERIFICATION SHEET (TIVS)
REV/
PARA
REQUIREMENTS / COMPONENT
IDENTIFICATION RESULTS ACTIVITY SIGNATURE/PRINTED NAME
KTR
3.1.1.1 Submit Welding Intended for use
Submitted:
YES / NO:
DATE/TIME: ______________ SRF
KTR
3.1.2.1 Submit welder performance qualification to the
proposed WPS.
Submitted:
YES / NO:
DATE/TIME: ______________ SRF
KTR
3.2
(V)(G) "RESTRICTION SHEET BRIEFING"
Contractor must attend a briefing on WPS and NDT restriction sheets as directed by the Marine
Surveyor and must have in their possession copies of the restriction sheets for use at the jobsite.
Acceptance Criteria:
Contractor has been Brief and in position of copies of WPS and NDT restriction sheets.
YES/NO: _______
DATE/TIME: ______________
SRF
3.4
(V)(G) "RECEIPT INSPECTION"
Accomplish material receipt inspection for GFM.
Verify exact quantity, material batch/lot, shelf life, and condition of material packaging.
Acceptance Criteria:
Allowable damage or deviation: None.
YES/NO: _______
DATE/TIME: ______________
KTR
SSP: NAPL-008-27 6 of 9 ITEM NO: 651-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S. International Traffic in Arms Regulation (ITAR).
This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
SRF
KTR
3.4.1
REPORTS
Submit one legible copy, in approved transferrable media, of a status report listing Contractor
Furnished Material (CFM) required to accomplish this work to the Supervisor not later than 30 days after Job Order award, or 2 days after availability start date, whichever occurs first.
The report to contain the following for SUPERVISOR approval prior to use: Description of material, quantity ordered, receipt date, and a summary listing any procurement problems.
Submitted:
YES / NO:
DATE/TIME: ______________
SRF
S/F
KTR
3.5
(V)(G) "TAG-OUT VERIFICATION"
Prior to commencement of work, contractor shall obtain Ship's Force signature on Enclosure (One) as verification of tag out and record tag-out serial number using 2.3 for guidance.
Tag-out S/N:________
Acceptance Criteria:
Equipment/System De-energized: No Deviation.
YES/NO: _______
DATE/TIME: ______________
SRF
3.6
(V)(G) "VERIFY CLEANLINESS"
Verify cleanliness Level II is maintained in the work location identified in 1.2 throughout the performance of this work item. Cleanliness Level II: Surface shall be visually free of grease, oil, flux, scale, dirt, loose particles and any other contamination foreign to the base metal. Tap water residues on all surfaces, caused by short time exposure to the atmosphere, are permitted. Light dust on cleaned surfaces is not objectionable, provided that the quantity and size of the particles does not adversely affect system
Acceptance Criteria:
SAT/UNSAT
YES/NO: _______
KTR
SSP: NAPL-008-27 7 of 9 ITEM NO: 651-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S. International Traffic in Arms Regulation (ITAR).
This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
operations.
SRF
KTR
3.7
Obtain Hot Work authorization Form from the Ship Force Fire Marshall before commencement of hot work. Post the approved hot work authorization form conspicuously at the entrance to each area where hot work is being formed.
Acceptance Criteria:
YES/NO: _______
SRF
KTR
3.8.1
REPORTS
Submit one legible copy, in hard copy or approved transferrable media, of a report to the SUPERVISOR that all lifting and handling materials have been inspected, tested, and are safe for use.
Submitted:
YES / NO:
DATE/TIME: ______________ SRF
KTR
3.9.2
(V)(G) "VISUAL INSPECTION"
Accomplish a visual inspection of each exposed foundation surface for equipment removed in 3.9, for structural integrity, deterioration, pitting, cracks, and areas of damage or distortion.
Acceptance Criteria:
SAT/UNSAT
YES/NO: _______
DATE/TIME: ______________
SRF
KTR
3.9.2.1
REPORTS
Submit one legible copy, in hard copy or transferrable media, of a report listing results of the requirements of 3.9.2 to the SUPERVISOR
Submitted:
YES / NO:
DATE/TIME: ______________ SRF
SSP: NAPL-008-27 8 of 9 ITEM NO: 651-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S. International Traffic in Arms Regulation (ITAR).
This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
KTR
3.13
(V)(G) “FINAL VISUAL INSPECTION”
Conduct visual inspection of areas welded in 3.12.
Weld(s) must be complete and free of cracks.
Acceptance Criteria: Weld is complete and free of cracks
SAT/UNSAT: _______
DATE/TIME: ______________ SRF
KTR
3.14.1
(V)(G) "INSULATION RESISTANCE TEST"
Accomplish an insulation resistance test of each cable using the appropriate direct current megger using Table 300-3-4 of 2.11 for guidance.
Acceptance Criteria: In accordance Table 300-3-4 of
2.11
SAT/UNSAT: _______
DATE/TIME: ______________ SRF
KTR
3.14.1.1
REPORTS
Submit one legible copy, in hard copy or approved transferrable media, of a report listing results of the requirements of 3.13.1 to the SUPERVISOR within 24 hours of testing.
Submitted:
YES / NO:
DATE/TIME: ______________ SRF
KTR
3.14.2.1
REPORTS
Submit one legible copy, in hard copy or approved transferrable media, of a report listing results of the requirements of 3.13.2 to the SUPERVISOR.
Submitted:
YES / NO:
DATE/TIME: ______________ SRF
3.15
(V)(G) "OPERATIONAL TEST"
Accomplish an operational test of each new dishwasher under normal operating conditions, in accordance with 2.2 and technical representative.
Acceptable Criteria: Equipment operating at 20
Acceptable Criteria:
Equipment operating at 20 PSIG and final rinse is heated at 180 Degrees
Fahrenheit.
S/F
SSP: NAPL-008-27 9 of 9 ITEM NO: 651-11-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S. International Traffic in Arms Regulation (ITAR).
This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
Work Completed:
Sign: _______________________Print:___________________Date:________________________
PROJECT MANAGER
KTR
PSIG and final rinse is heated at 180 Degrees Fahrenheit
SAT/UNSAT: _______
DATE/TIME: ______________
SRF
KTR
3.16
(V)(G) "TIGHTNESS TEST"
Accomplish tightness test for each new and disturbed mechanical joint at nominal operating pressure and temperature.
Acceptance Criteria:
Allowable leakage: None.
SAT/UNSAT: _______
DATE/TIME: ______________ SRF
S/F
KTR
3.19
(V)(G) "COMPARTMENT CLOSEOUT"
Accomplish a joint inspection with the SUPERVISOR upon completion, inspection, and acceptance, by the contractor, of work within each compartment.
Acceptance criteria is completion of all contractor work within the compartment inclusive of associated Work Items, and settled changes to associated Work Items
Acceptance Criteria:
SAT /UNSAT
SAT/UNSAT: _______
SRF
SHIP: USS LEWIS B PULLER (ESB 3) ITEM NO: 671-00-001
COAR: 26 PCN: CC01-0403
CC01-0355
CC02-0472
CC01-0402
CMP: NONE
PLANNER: KRIEGER, DANIEL
STAPLES,
MICHAEL.FDRMC
SSP: NAPL-008-27 1 of 2 ITEM NO: 671-00-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Safes, Remove and Replace; accomplish
1.2 Location of Work:
1.2.1 Communication Center (A8-94-0)
1.2.2 A8 Training Room (A8-90-2)
1.2.3 A8 Training Room (A8-89-2)
1.2.4 TACAIR / Ops Center (A8-91-0)
1.3 Identification:
1.3.1 Quantity (4 EA), Cabinet Safe, File, 4 Drawer, Steel, NSN:
7110-00-920-9343
2. REFERENCES:
2.1 NAVSEA Standard Items, (FY27 CH-2)
3. REQUIREMENTS:
3.1 Remove existing, fit and install each new safe listed in 1.3, provided in 5.1 and located in 1.2.
3.1.1 Restore each mating surface exposed by removal. Repair by removing each high spot, burr, abrasion, and foreign matter where removal can be accomplished by a hand tool.
3.1.2 Modify existing foundations to suit new safes.
(I)(G) "NDT INSPECTION"
3.2 Accomplish the requirements of 009-012, including Table 2, Column A, Lines One through 6.
(I)(G) "NDT - VT"
3.3 Accomplish the requirements of 009-012, including Table 2, Column A, Line 7.
(V)(G) "OPERATIONAL TEST"
3.4 Accomplish an operational test of each new file cabinet installed in
3.1. Open and close each drawer through 4 complete cycles. Allowable sticking or binding: None.
3.4.1 Accomplish adjustments and alignment to correct each
discrepancy resulting from 3.4.
(V)(G) "COMPARTMENT CLOSEOUT"
SSP: NAPL-008-27 2 of 2 ITEM NO: 671-00-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
3.5 Accomplish a joint inspection with the SUPERVISOR and the Commanding Officer's designated representative upon completion, inspection, and acceptance, by the contractor, of work within each compartment. Ensure Attachment A, Work Completion Certification, is completed in accordance with 009 004 of 2.1.
4. NOTES:
4.1 None
5. GOVERNMENT FURNISHED MATERIAL (GFM):
5.1 LLTM:
TOTAL
QUANTITY
PROVIDED NAME Of PART
PIECE
NO.
REF
NO.
NATIONAL
STOCK
NO.
REQ
PARA NO.
1. 4 EA 4 drawer safe 7110-00- 920-9343
5.2 PUSH MATERIAL:
1. None.
SHIP: USS LEWIS B PULLER (ESB 3) ITEM NO: 991-12-001
COAR: 26 PCN: SERV-L188
CMP: NONE
PLANNER: KRIEGER, DANIEL
JONES, DOUGLAS
SSP: NAPL-008-27 1 of 2 ITEM NO: 991-12-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
1. SCOPE:
1.1 Title: Scaffolding for Ship's Force Use; provide
1.2 Location of Work:
1.2.1 Weather Deck E-Level, Aft House, Frame 55, Centerline
1.3 Identification:
1.3.1 Quantity (One Set), Steel tube and clamp type scaffolding built at Aft Deck House frame 55, E-Level, above Bridge to reach (Vista ASR Antenna). Approximate height 20 ft by width of 10 ft, with access to multiple level platforms.
2. REFERENCES:
2.1 NAVSEA Standard Items, (FY27 CH-2)
2.2 29 CFR Part 1915, Occupational Safety and Health Standards for Shipyard Employment
2.3 OSHA, Safe Work Practices for Marine Hanging Staging
2.4 801-8389193, General Arrangement
3. REQUIREMENTS:
3.1 Notify the Ship's Duty Officer, via the SUPERVISOR, in writing, 24-hours in advance of intention to send personnel aloft to accomplish work required by this Work Item.
3.1.1 No scaffold shall be erected, moved, dismantled or altered except under the supervision of a competent person.
3.2 Install steel tube and clamp type scaffold in accordance with 2.2 and 2.3 in each location listed in 1.2, as identified in 1.3.1, as designated by the SUPERVISOR, with sufficient levels and projections to safely reach and perform inspection and repair to equipment listed in
1.3.2 for the entire contract period for use by Ship's Force (SF).
3.2.1 Ensure scaffold is capable of sustaining a working load of 750 pounds at any point or level on each working surface.
3.2.2 Ensure each end of tubing resting on deck structure and transmitting weight of the scaffold shall terminate on framing immediately below and utilize a steel sole plate of at least 300 MM x 300 MM x 6 MM (12 INCH x 12 INCH x 1/4 INCH) to stabilize and distribute the weight of the scaffold.
3.2.3 Ensure planking is secured (cleated) to preclude shifting or coming loose during high winds.
3.2.3.1 Planking and wood shall be fire retardant.
3.2.3.2 Ensure Toe Boards are installed in accordance with
reference 2.3
SSP: NAPL-008-27 2 of 2 ITEM NO: 991-12-001
EXPORT CONTROLLED DATA: This document contains technical information whose export is governed by U.S.
International Traffic in Arms Regulation (ITAR). This information must not be transferred to a foreign person/entity without proper authorization of the U.S. Government. Violations may result in administrative, civil, or criminal penalties.
3.2.4 Ensure scaffold is tagged to inform workers of the status and condition of the staging in a manner similar to Appendix C of 2.3.
3.2.5 Scaffolding shall be inspected daily and certified safe for use.
3.3 Conduct safety inspection with the Ship's designated safety inspector, Contractor Safety inspector, and the SUPERVISOR. Do not install scaffolding in a manner that blocks or inhibits the use of ship's fire stations or emergency egresses.
3.4 Disassemble and remove staging when directed by the SUPERVISOR.
(V)(G) "COMPARTMENT CLOSEOUT"
3.5 Accomplish a joint inspection with the SUPERVISOR and the Commanding Officer's designated representative upon completion, inspection, and acceptance, by the contractor, of work within each compartment. Ensure Attachment A, Work Completion Certification, is completed in accordance with 009 004 of 2.1.
4. NOTES:
4.1 OSHA information is on the website:
https://www.osha.gov/etools/shipyard/general-requirements/scaffolds/hanging-staging/use-of
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.