Request for Quotations (RFQ) Summary

This is a Request for Quotations (RFQ) for commercial construction services issued by Naval Undersea Warfare Center Division Newport (NUWCDIVNPT) under solicitation number N66604-27-Q-0033. The procurement is for the B68 Renovation Project at NUWCDIVNPT, with a mandatory site visit on December 2, 2026 at 10:00 AM EST and quotation due date of December 18, 2026 at 2:00 PM EST. The contract will be firm fixed price on a completion basis with 120 days to complete all work after contract award, anticipated in December 2026. The estimated contract value is between $100,000 and $250,000. This is a Total Small Business set-aside with NAICS code 236220 (small business size standard 45M). The government intends to award to the responsible offeror offering the lowest price that is technically acceptable (LPTA). Two CLINs are included: CLIN 0001 for the B68 Renovation Project requiring all personnel, equipment, tools, materials, supervision, quality control, and transportation for construction services per specifications and drawings; and CLIN 0002 for construction submittals not separately priced and to be included in CLIN 0001 pricing.

Offerors must be registered in SAM with active certification of CMMC Level 1 (or higher) status and possess a current NIST SP 800-171 DoD Assessment score posted in SPRS (completed within three years). A bid guarantee of 20 percent of bid price is required, and performance and payment bonds must be furnished within 10 days of award. The evaluation is based on three factors: Factor 1 (Technical Capability—20 pages maximum) covering technical approach/quality control, project schedule, and management/staffing/key personnel; Factor 2 (Past Performance & Safety—8 pages maximum) covering three project references and corporate safety records including EMR and DART rates; and Factor 3 (Price—no page limit). Work must comply with U.S. Army Corps of Engineers EM 385-1-1 and OSHA standards, Davis Bacon wage rates apply, and the contract is DO-C2 rated under DPAS. Electronic payment via WAWF will be used.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PLEASE READ THIS ENTIRE NOTICE CAREFULLY AS IT CONSTITUES THE ONLY

NOTICE THAT WILL BE ISSUED.

Solicitation Number: N66604-27-Q-0033

Project Title: B68 Renovation Project

Location of Work: Naval Undersea Warfare Center Division Newport (NUWCDIVNPT)

Site Visit Date/Time: December 2, 2026 @ 10:00 am EST

Response Due Date/Time: December 18, 2026 @ 2:00pm EST

This is a Request for Quotations (RFQ) for commercial construction services at NUWCDIVNPT, prepared in accordance with the format in FAR Overhaul Part 12 (Acquisition of Commercial Products and Commercial Services), as supplemented with simplified acquisition procedures in FAR Overhaul Part

13, and incorporating the construction principles of FAR Overhaul Part 36. This announcement constitutes the only solicitation; quotations are being requested and a separate written solicitation will not be issued.

This is a completion effort with a Construction completion date of 120 Days after Date of Contract

Award.

The associated North American Industrial Classification System (NAICS) code for this procurement is

236220 with a small business size standard of 45M.

This procurement is a Total Small business set-aside.

NUWCDIVNPT intends to award a Firm Fixed Price Type purchase order to the responsible offeror whose conforming quotation represents the Lowest Price Technically Acceptable (LPTA) to the

Government.

Please provide NUWCDIVNPT Code 02 Contracting office with a quotation on a Firm Fixed Price, Completion basis prior to December 18, 2026 at 2:00PM EST for the following:

CLIN 0001: B68 Renovation Project; The contractor shall provide all personnel, equipment, tools, materials, supervision, quality control, and transportation necessary to perform construction services as described in the attached Specification and Drawings.

CLIN 0002: Construction Submittals in support of CLIN 0001; (NOT SEPERATELY PRICED

Provide pricing for CLIN 0002 within CLIN 0001

INSTRUCTIONS TO OFFERORS

General Notes:

Note 1: For pricing purposes, the anticipated award date is December 2026.

Note 2: The Product Service Code for this requirement is Z2AZ.

Note 3: Work shall be conducted in accordance with U.S. Army Corps of Engineers EM 385-1-1 and

OSHA standards.

Note 4: Magnitude: Between $100,000 and $250,000.

Note 5: To be eligible and considered for contract award, the Offeror MUST possess:

• An active registration in the System for Award Management (SAM);

• An active, certified Cybersecurity Maturity Model Certification (CMMC) Level 1 (or higher) status; and

• A current NIST SP 800-171 DoD Assessment score (completed within the last 3 years) posted in the Supplier Performance Risk System (SPRS)."

Note 6: A Bid Guarantee is required, See 52.228-1 below.

Note 7: Offerors shall provide fill-in information for all clauses/provisions that require it.

Note 8: Davis Bacon Wage Determination for Rhode Island dated 1 October 2026 is attached

(Attachment 3).

Note 9: Any contract awarded as a result of this solicitation will be a DO-C2 rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and

Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation.

Note 10: Method of Payment: Electronic Payment through Wide Area Workflow (WAWF) will be used.

Note 11: The contractor shall furnish any required Performance and Payment Bonds within 10 Days of award.

Note 12: This is a new requirement.

Note 13: Offerors are hereby notified that, from time to time, the Government may post additional information to the SAM.gov web site relating to this RFQ (e.g., responses to questions, amendments, etc.). It is the Offeror’s responsibility to check the web site for any such information.

Note 14: A site visit will be held on December 2, 2026 @ 10:00 AM (EST). Please see attached site visit instructions for complete details on base access.

The Government intends to evaluate quotes and award a contract without discussions with offerors.

Therefore, the offeror’s initial quote should contain the offeror’s best terms from a price and technical standpoint.

SECTION L – INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS

1.0 GENERAL INSTRUCTIONS

1.1 Solicitation Posting & Amendments

1. Offerors are responsible for monitoring SAM.gov periodically for any amendments, clarifications, or updates to this solicitation.

2. The Government assumes no responsibility for any oral representations, explanations, or interpretations made by Government personnel prior to award, except as confirmed by formal written solicitation amendment.

1.2 Inquiries and Questions

All questions concerning this Request for Proposal, whether technical, legal, or contractual, must be submitted in writing via email no later than 10 calendar Days prior to the solicitation closing date and time.

• Direct discussions between prospective offerors and Government technical representatives are strictly prohibited.

• Questions shall be directed to the following designated points of contact:

Primary Point of Contact:

• Name: Michael Ouellette

• Title: Contracting Officer, NUWCDIVNPT

• Email: Michael.N.Ouellette.civ@us.navy.mil

Alternate Point of Contact:

• Name: Amy Prisco

• Title: Contract Specialist, NUWCDIVNPT

• Email: Amy.K.Prisco.civ@us.navy.mil

2.0 PROPOSAL PREPARATION AND SUBMISSION

2.1 Submission Guidelines

Offerors shall submit all proposal volumes electronically to the designated points of contact no later than the date and time specified above and posted on SAM.gov Contract Opportunities.

1. File Format: Files must be submitted in formats fully readable by Microsoft Office (Word, Excel) or Adobe Acrobat PDF. Offerors must ensure submission files are uncorrupted, virus-free, and not password-protected. Offerors are cautioned that compressed files (zip) or macro-enabled files may be rejected by Department of Defense email security gateways. Offerors shall name all files with the Offeror’s name and volume designator.

2. Compliance: Proposals must strictly comply with solicitation instructions set forth herein.

Proposals that fail to conform to these instructions may be deemed non-compliant and rejected without further evaluation.

2.2 Proposal Structure and Page Limitations

The proposal shall be segregated into distinct volumes as indicated below:

Volume Factor / Content Page Limits

Cover

Page

Transmittal Data and Signed

Proposal Cover Page Excluded from page limits

Volume I

Factor 1: Technical Capability

• Subfactor (a): Technical Approach &

Quality Control

• Subfactor (b): Project Schedule

• Subfactor (c): Management, Staffing

& Key Personnel

Max (20) Pages

(Resumes and certifications excluded from page count)

Volume

II

Factor 2: Past Performance & Safety

• Past Performance Project References

• Past Safety Performance &

Compliance

Max three (3) project references; max (8) pages total.

Safety records, OSHA logs, and EMR certifications are excluded from page limits.

Volume

III

Factor 3: Price

• Supporting Price Schedule No page limit

2.3 Cover Page

Offerors must include a Proposal Cover Page positioned directly before Volume I. The Proposal Cover

Page shall contain the following Transmittal data elements:

1. Solicitation Details: Solicitation number, project title, and acknowledgment of all solicitation amendments to include the number and date of each.

2. Offeror Entity Information:

Full legal corporate/business name, DBA (if applicable), physical corporate headquarters address, local branch office address, company website, telephone number, and state of incorporation.

3. Entity Identification & SAM Standing:

Commercial and Government Entity (CAGE) Code, SAM Unique Entity Identifier (UEI), and

Taxpayer Identification Number (TIN).

4. Cybersecurity & CMMC Reporting (Verification Prior to Award):

The Offeror shall provide the CMMC UIDs issued by the Supplier Performance Risk system

(SPRS), in accordance with DFARS 252.204-7025(d), for each contractor information system that will process, store, or transmit Federal Contract Information (FCI) or Controlled Unclassified

Information (CUI) during performance of a contract, task order, or delivery order resulting from this solicitation

5. Points of Contact & Signatory Authority:

Name, title, telephone number, and valid email address of primary technical and contractual contacts; and signature of the corporate official authorized to legally bind the company and conduct negotiations.

3.0 VOLUME I – FACTOR 1: TECHNICAL CAPABILITY

The Offeror shall submit a comprehensive technical volume demonstrating its technical execution methodology, scheduling logic, and project management structure to accomplish all work detailed in the project Specifications and Drawings.

3.1 Subfactor (a): Technical Approach & Quality Control

The Offeror shall provide a detailed narrative describing its technical approach. This narrative must demonstrate a thorough understanding of the project requirements and present a logical, comprehensive plan for construction. At a minimum, the narrative must include:

• Understanding of Requirements & Technical Solution: A clear description of the construction methodology, sequence of operations, site logistics, and specialized technical work. Offerors must address specific constraints evident from site conditions (e.g., security restrictions at

NUWCDIVNPT, working in occupied or operational facilities, environmental/tidal constraints).

• Quality Management Strategy: A detailed overview of quality control methodologies, inspection schedules, testing protocols, and non-conformance tracking procedures.

3.2 Subfactor (b): Project Schedule

The Offeror shall submit a comprehensive project schedule in Gantt chart format (e.g., Microsoft Project, Primavera, or equivalent) demonstrating completion within the required Period of Performance (PoP).

The schedule shall clearly depict:

• Major mobilization milestones, work breakdown phasing, and operational sequence;

• Submittal preparation, Government review periods, and procurement lead times for long-lead materials and equipment;

• Critical Government inspection gates, base access coordination, and planned utility outages; and

• Final punch-list walkthroughs, commissioning, testing, and physical turnover.

3.3 Subfactor (c): Management, Staffing & Key Personnel

The Offeror shall submit a comprehensive management and staffing plan demonstrating that it possesses governance, supervisory leadership, and personnel resources to successfully execute the project. The plan must include:

Management Structure & Subcontractor Oversight: An organizational chart and narrative detailing the Offeror's project governance structure, clear lines of supervisory authority, on-site decision-making escalation paths, and procedures for coordinating and overseeing specialized trade subcontractors.

Staffing Availability & On-Site Dedication: Affirmation that Key Personnel will be dedicated full-time on-site to this project at the NUWCDIVNPT worksite by the required mobilization date. If any proposed

Key Personnel are currently assigned to active ongoing construction projects, the Offeror must provide an explicit transition and release plan detailing anticipated release dates from existing commitments.

Concurrent full-time commitments are permissible only during the pre-construction administrative submittal phase and must terminate no later than the date of physical site mobilization or thirty (30) calendar days from contract award, whichever occurs first. From the start of physical field work through final inspection, 100% dedicated on-site presence at NUWCDIVNPT is strictly required.

Key Personnel Qualifications:

The Offeror shall submit resumes, proof of active registrations, licensures, and required certifications for the three key personnel positions identified below:

1. Site Superintendent

• Experience: Minimum of ten (10) years of general construction experience, with at least five (5) of those years serving as a primary construction superintendent on projects of similar size, scope, and technical complexity.

• Safety & Regulatory Competency: Demonstrated familiarity with USACE Safety and Health

Requirements Manual (EM 385-1-1), job hazard analyses (JHAs), and Federal OSHA regulations.

• Technical Proficiency: Demonstrated capability in reading, interpreting, and managing CPM schedules, architectural drawings, and civil/structural engineering specifications.

2. Quality Control Manager (QCM)

• Experience: Minimum of five (5) years of combined experience as a superintendent, inspector, QCM, project manager, or construction manager on projects of similar magnitude involving the major trades associated with this requirement.

• Mandatory Certification: Successful completion of the USACE/NAVFAC course Construction

Quality Management for Contractors (CQM-C) with a valid certificate.

• Safety Knowledge: Familiarity with EM 385-1-1 requirements and proactive quality inspection phases (preparatory, initial, and follow-up).

3. Site Safety and Health Officer (SSHO)

• Experience & Certifications: The SSHO must meet the training, credentialing, and experience standards specified in EM 385-1-1, Section 02-03, for a Level 2 SSHO.

• Safety Knowledge: Provide documented evidence of completion of the OSHA 30-Hour Construction

Safety course (within the last 5 years) and required annual safety continuing education (minimum 8 hours annually).

Multi-Role Staffing:

Concurrent multi-role staffing—whether dual-hatting (e.g., Site Superintendent or QCM serving concurrently as SSHO) or triple-hatting (a single qualified individual serving concurrently as Site

Superintendent, Quality Control Manager, and Site Safety and Health Officer)—is permissible only if the candidate fully satisfies all individual experience, licensing, credentialing, and certification requirements for every assigned position. The Offeror must provide a detailed resource allocation plan demonstrating how operational supervision, quality control enforcement, and jobsite safety oversight will remain uncompromised and fully executed.

4.0 VOLUME II – FACTOR 2: PAST PERFORMANCE & SAFETY

Offerors shall submit documentation demonstrating both project past performance history and corporate safety performance.

4.1 Construction Project References

The Offeror shall submit a maximum of three (3) past performance references reflecting recent and relevant performance as a Prime Contractor (or as a major subcontractor where the Offeror performed at least 30% of the field work).

1. Recency: A reference is considered recent if physical work was performed within three (3) years prior to the closing date of this solicitation.

2. Relevancy: A reference is considered relevant if it is of similar scope, dollar value, and technical complexity to the requirements identified in this solicitation.

For each submitted project reference, the Offeror shall provide:

• Contract and Task Order Number (if applicable).

• Contract Type (e.g., Firm-Fixed-Price, Cost-Plus, IDIQ Delivery Order).

• Total Award Value and Final Completed Contract Value (with an explanation of any significant delta).

• Detailed Narrative Description of the work performed, explicitly detailing how the project aligns with the technical complexity and scope of this NUWCDIVNPT requirement.

• Client Contact Information: Complete name, official title, current valid email address, and active telephone number for the Contracting Officer, Contracting Officer’s Representative (COR), and/or Program/Project Manager.

4.2 Past Safety Performance & Compliance

The Offeror shall submit corporate safety records demonstrating its historical commitment to jobsite safety, risk mitigation, and regulatory compliance. Safety documentation is excluded from all proposal page limitations.

4.2.1 Experience Modification Rate (EMR)

• Required Documentation: The Offeror shall provide official documentation from its workers' compensation insurance carrier or state rating bureau (e.g., NCCI) certifying its interstate and intrastate Workers' Compensation EMR for the past three (3) calendar years.

• Elevated EMR Explanations: If the Offeror's EMR for any of the past three (3) years is 1.0 or higher, the Offeror must submit a detailed explanatory narrative. The narrative must describe:

1. The specific incidents or claims that contributed to the elevated rate;

2. Immediate corrective measures implemented to mitigate jobsite hazards; and

3. Corporate safety program improvements instituted to prevent recurrence.

4.2.2 OSHA Days Away, Restricted Duty, or Job Transfer (DART) Rate & OSHA Logs

• Required Documentation: The Offeror shall provide copies of its OSHA Form 300A (Summary of Work-Related Injuries and Illnesses) for the three (3) most recent calendar years.

• Redacted Logs: The Offeror shall provide copies of OSHA Form 300 (Log of Work-Related

Injuries and Illnesses) for the preceding calendar year and the current year to date, with all

Personally Identifiable Information (PII) redacted.

• DART Calculation: The Offeror shall calculate and report its annual DART rate for each of the three (3) calendar years using the standard OSHA formula:

DART Rate = (Total DART Cases × 200,000) / Total Employee Hours Worked

• Elevated DART Explanations: If any calculated annual DART rate is 3.4 or higher (the current national Bureau of Labor Statistics average for NAICS 236220 / construction trades), the Offeror must provide a comprehensive explanation of the circumstances and documented corrective actions implemented to improve jobsite safety.

4.2.3 Exemptions and Neutral Ratings

To ensure fair competition and prevent undue restrictions on small entities, Offerors qualifying for statutory recordkeeping exemptions under federal law (29 CFR 1904.1) by employing ten (10) or fewer personnel across the preceding calendar year are exempt from submitting OSHA Forms 300 and 300A and shall instead provide a signed certification of exempt status on corporate letterhead. Additionally, small or newly established Offerors lacking an official NCCI or state-promulgated EMR due to low premium volume or business tenure may submit a written verification letter from their insurance carrier or agent in lieu of an EMR history; Offerors submitting valid exemption statements under this provision will not be penalized or found non-compliant and will be evaluated under the neutral rating procedures outlined below.

An Offeror lacking a record of recent and relevant project past performance, or a newly formed entity/joint venture lacking a historical safety record (EMR/DART logs), shall submit a statement certifying that it possesses no relevant past performance or historical safety records.

Offerors with no recent and relevant past performance or historical safety data will receive an Acceptable

(Neutral) rating under Factor 2 and will not be evaluated favorably or unfavorably.

Note: The Government reserves the right to contact any points of contact provided, review the Contractor

Performance Assessment Reporting System (CPARS), and consider information obtained from other available Government sources.

5.0 VOLUME III – FACTOR 3: PRICE PROPOSAL

5.1 Pricing Basis

Offerors shall provide a single, all-inclusive firm-fixed-price for CLIN 0001 by submitting:

1. Solicitation Pricing Schedule: Fully completed unit price and extended lump-sum amount for

CLIN 0001.

2. Proposal Cover Page / Offer Transmittal: Executed by an authorized corporate representative possessing binding legal authority.

Note on Deliverables (CLIN 0002): All administrative, management, and technical efforts required under

CLIN 0002 (Construction Submittals, Quality Control Plans, Safety Plans, Environmental Protection

Plans, and As-Built Drawings) are Not Separately Priced (NSP) and must be fully absorbed into the total lump-sum firm-fixed-price proposed for CLIN 0001.

SECTION M – EVALUATION FACTORS FOR AWARD

1.0 GENERAL EVALUATION PROVISIONS

1.1 Basis for Award (Lowest Price Technically Acceptable - LPTA)

The Government intends to award a firm-fixed-price contract to the responsible Offeror submitting the lowest evaluated price proposal that is rated "Acceptable" for all non-price evaluation factors, in accordance with FAR Overhaul 15.103-2 and DFARS 215.103-72.

The Government intends to evaluate proposals and award without discussions but reserves the right to conduct discussions if determined to be in the Government's best interest.

1.2 Evaluation Factors and Subfactors

Proposals will be evaluated based on the following volumes:

Volume Factor / Content Page Limits

Cover

Page

Transmittal Data and Signed

Proposal Cover Page Excluded from page limits

Volume I

Factor 1: Technical Capability

• Subfactor (a): Technical Approach &

Quality Control

• Subfactor (b): Project Schedule

• Subfactor (c): Management, Staffing

& Key Personnel

Max (20) Pages

(Resumes and certifications excluded from page count)

Volume

II

Factor 2: Past Performance & Safety

• Past Performance Project References

• Past Safety Performance &

Compliance

Max three (3) project references; max (8) pages total.

Safety records, OSHA logs, and EMR certifications are excluded from page limits.

Volume

III

Factor 3: Price

• Supporting Price Schedule No page limit

1.3 Evaluation of Cover Page

Prior to technical evaluation, the Government will review the Proposal Cover Page for completeness, statutory and regulatory compliance, and pre-award responsibility factors. This review is conducted on a

Pass / Fail basis:

Administrative

Review Item "Pass" Evaluation Standard "Fail" / Non-Responsive Condition

Proposal Cover Page

& Signatory

Authority

The Offeror submitted a completed

Proposal Cover Page signed by an authorized corporate official possessing binding legal authority. All solicitation amendments (if applicable) are acknowledged.

The cover page is missing, unsigned by an authorized corporate official possessing binding legal authority, or fails to acknowledge material solicitation amendments.

SAM Registration

The Offeror has an Active registration status in SAM.gov under NAICS

236220 at the time of award evaluation.

The Offeror is not registered in SAM, registration has expired, or is active but carries an active exclusion/debarment

CMMC Level 1

Compliance (DFARS

252.204-7025 / 7021)

The Offeror provides verification of active, current CMMC Level 1 (or higher) compliance status.

The Offeror fails to demonstrate active

CMMC Level 1 status, or the certification is expired/invalid.

NIST SP 800-171

DoD Assessment

(DFARS 252.204-

7019)

The Offeror has a current NIST SP 800-

171 DoD Assessment summary-level score (Basic, Medium, or High) posted in SPRS that is not more than three (3) years old

The Offeror has no assessment score posted in SPRS, or the posted assessment is older than three (3) years

1.4 Adjectival Rating Standards (Non-Price Factors)

The Government will evaluate Technical Capability and Past Performance, on an Acceptable /

Unacceptable basis using the following standards:

Rating Definition

ACCEPTABLE The proposal meets the minimum requirements of the solicitation.

UNACCEPTABLE The proposal fails to meet the minimum requirements of the solicitation.

Note: In accordance with RFO FAR 15.202(c), an Offeror lacking a record of recent and relevant past performance will not be evaluated favorably or unfavorably and will be assigned an "Acceptable

(Neutral)" rating.

2.0 NON-PRICE EVALUATION FACTORS AND CRITERIA

2.1 FACTOR 1: TECHNICAL CAPABILITY

To be eligible for award, the Offeror must achieve a rating of "Acceptable" under each of the three subfactors. A rating of "Unacceptable" under any single subfactor will render the entire technical proposal

"Unacceptable."

2.1.1 Subfactor (a): Technical Approach & Quality Control

The Government will evaluate the extent to which Offeror's narrative demonstrates a clear understanding of the project's technical scope, operational sequence, environmental and site constraints (including naval installation security protocols, operating within occupied research facilities, and utility outage coordination). The Government will evaluate the extent to which the proposal provides a feasible technical execution methodology and an objective quality management strategy.

Examples of an unacceptable proposal include, but are not limited to, a narrative that:

• Merely restates or paraphrases the Statement of Work or specifications without demonstrating comprehension or practical execution methods;

• Fails to address critical site constraints (e.g., naval facility access, utility outages, tidal/waterfront conditions);

• Omits or provides an unfeasible Quality Management Strategy lacking inspection schedules, testing protocols, or non-conformance tracking.

2.1.2 Subfactor (b): Project Schedule

The Government will evaluate the extent to which the proposal includes a logical, credible, and feasible project schedule in Gantt chart format demonstrating project completion within the required Period of

Performance (PoP), complete with all major mobilization milestones, phasing, submittal timelines, and long-lead procurement lead times.

Examples of an unacceptable proposal include, but are not limited to:

• The project schedule is missing or fails to demonstrate completion within the required PoP; OR

• The schedule is so lacking in detail that operational feasibility and construction sequencing cannot be determined.

• A schedule that meets the overall Period of Performance but omits critical elements (such as

Government review periods, long-lead procurement, base access coordination, utility outages, or key inspection gates).

2.1.3 Subfactor (c): Management, Staffing & Key Personnel

The Government will evaluate the extent to which the Offeror’s proposed organizational chart and narrative establishes project governance structure, clear lines of supervisory authority and effective subcontractor oversight. The Government will evaluate the extent to which the proposal demonstrates how designated Key Personnel will be dedicated full-time on-site at the NUWCDIVNPT worksite by the required mobilization date. If proposed Key Personnel are committed to active projects, the Government will evaluate the extent to which a credible transition plan with firm release/mobilization dates is provided; the extent to which any transition period is clearly defined and limited so that concurrent full-time commitments occur only during the pre-construction administrative submittal phase and terminate no later than the date of physical site mobilization or thirty (30) calendar days from contract award, whichever occurs first.

The Government will evaluate the extent to which key personnel resumes demonstrate required experience, and valid licenses, and active certifications are provided for all three (3) designated key personnel:

• Site Superintendent: Minimum 10 years general construction experience (5 years as primary superintendent on comparable projects) and demonstrated EM 385-1-1/OSHA competency.

• Quality Control Manager (QCM): Minimum 5 years relevant experience and a current

USACE/NAVFAC Construction Quality Management for Contractors (CQM-C) certificate.

• Site Safety and Health Officer (SSHO): Satisfies EM 385-1-1 Section 02-03 credentials, OSHA

30-Hour Construction Safety certification (within past 5 years), and verified annual continuing education. If dual-hatting or triple-hatting is proposed, the proposed candidate(s) must fully satisfy all credentialing, certification, and divisibility prerequisites for each assigned position, and the staffing structure must be explicitly authorized by the solicitation.

Examples of an unacceptable proposal include, but are not limited to:

• Resumes, licenses, or mandatory certifications are omitted, invalid, or expired for any proposed key personnel;

• A proposed candidate fails to meet the minimum experience thresholds;

• The proposal omits an organizational chart, fails to define clear lines of supervisory accountability, or fails to demonstrate that Key Personnel will be available on-site;

• Proposed Key Personnel are committed to overlapping projects without a credible release and mobilization plan ensuring full-time on-site dedication to NUWCDIVNPT by the required mobilization date, or the proposed transition creates an unmitigated risk of divided attention or delayed mobilization; OR

• Unauthorized or unworkable dual-hatting or triple-hatting is proposed that violates solicitation safety stipulations or where the candidate fails to meet the individual qualifications for all assigned roles.

• Failure to provide a valid, unexpired USACE/NAVFAC CQM-C certificate or OSHA 30-Hour

Construction Safety certificate (issued within the past five years) for the proposed QCM or

SSHO, as applicable.

(Note on Corporate Capacity vs. Technical Evaluation: Overall corporate financial liquidity and general capacity are evaluated under pre-award responsibility determinations pursuant to FAR Part 9. An

Offeror will not be evaluated as technically Unacceptable under this subfactor solely based on general corporate capacity; evaluation is strictly confined to whether the proposed staffing and key personnel meet solicitation requirements).

2.2 FACTOR 2: PAST PERFORMANCE & SAFETY

To be rated "Acceptable," the Offeror’s record of past performance and corporate safety must demonstrate a reasonable expectation that the Offeror will successfully and safely perform the required effort demonstrating:

• A record of recent (within 3 years of solicitation closing date) and relevant (similar scope, complexity, and magnitude to the requirements identified in this solicitation) as the prime contractor.

• Documented Workers' Compensation Experience Modification Rate (EMR) for the past three (3) calendar years, and OSHA Days Away, Restricted, or Transferred (DART) rates below the national BLS industry average (3.4). If an Offeror's EMR is 1.0 or higher, or annual DART rate is

3.4 or higher, the Offeror must provide a credible, detailed written explanation of the circumstances and documented corrective actions demonstrating that jobsite safety has been institutionalized.

An Offeror will be rated "Unacceptable" under this factor if (unless exempt pursuant to Section L §4.2.3 or 29 CFR 1904.1)

• Past performance history reflects persistent, uncorrected deficiencies in quality of work, schedule compliance, cost control, or subcontract management;

• The Offeror has an EMR of 1.0 or higher or DART rates above 3.4 and fails to provide a sufficient, credible explanation of root causes and corrective actions;

• The record creates significant doubt that the Offeror can execute the project safely and effectively; OR

• The Offeror fails to provide required OSHA Form 300A logs, OSHA 300 summaries, or EMR verification from an authorized bureau/carrier, unless the Offeror qualifies for and submits a valid statutory exemption certification pursuant to Section L §4.2.3 or 29 CFR 1904.1.

In accordance with FAR Overhaul 15.202(c), an Offeror lacking a record of recent and relevant project past performance or historical safety ratings (e.g., a newly formed joint venture or small business exempt under 29 CFR 1904.1) will receive an Acceptable (Neutral) rating and will not be evaluated favorably or unfavorably.

The Government may also evaluate the past performance of an Offeror’s proposed subcontractors. In the evaluation of an Offeror’s past performance, the Government reserves the right to contact former customers, Government agencies and other private and public sources of information.

3.0 FACTOR 3: PRICE EVALUATION

The Government will evaluate the price proposal of all technically acceptable Offerors to determine completeness and price reasonableness in accordance with FAR 15.404-1.

3.1 No Adjectival Rating: Price will not receive an adjectival rating.

3.2 Completeness:

The Government will verify that the Offeror has submitted a fully completed Solicitation Pricing

Schedule for CLIN 0001. The proposed lump sum price must reflect complete coverage of all construction requirements, drawings, specifications, and non-separately priced administrative deliverables under CLIN 0002.

3.3 Price Reasonableness:

The Government will evaluate the total proposed firm-fixed-price for CLIN 0001 for reasonableness primarily through price analysis techniques pursuant to FAR Overhaul 15.404-1(b).

4.0 AWARD DETERMINATION

Award will be made to the responsible Offeror submitting the lowest evaluated fair and reasonable price found Technically Acceptable across all non-price factors.

CLAUSES INCORPORATED BY REFERENCE

52.203-13 Contractor Code of Business Ethics and Conduct (Nov 2021)

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan

2017)

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020)

52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab Covered Entities (Dec 2023)

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance

Services or Equipment. (Nov 2021)

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (Jan 2025)

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015)

52.219-6 Notice of Total Small Business Set-Aside (Nov 2020)

52.219-8 Utilization of Small Business Concerns (Jan 2025)

52.222-3 Convict Labor (Jun 2003)

52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011

52.222-6 Construction Wage Rate Requirements

52.222-7 Withholding of Funds

52.222-8 Payrolls and Basic Records

52.222-9 Apprentices and Trainees

52.222-10 Compliance with Copeland Act Requirements

52.222-11 Subcontracts (Labor Standards)

52.222-90 Addressing DEI Discrimination by Federal Contractors

52.223-90 Instructions to Contractor's Environmental Representatives

52.225-9 (Buy American - Construction Materials).

52.228-13 Alternative Payment Protections.

52.228-15 Performance and Payment Bonds-Construction.

52.232-33 Payment by Electronic Funds Transfer-System for Award Management (Oct2018)

52.232-40 Providing Accelerated Payments to Small Business Subcontractors (Mar 2023)

52.233-3 Protest After Award (Aug 1996)

52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004)

52.236-2 Differing Site Conditions APR 1984

52.236-3 Site Investigation and Conditions Affecting the Work APR 1984

52.236-5 Material and Workmanship.

52.236-6 Superintendence by the Contractor.

52.236-7 Permits and Responsibilities NOV 1991

52.236-8 Other Contracts.

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.

52.236-10 Operations and Storage Areas.

52.236-12 Cleaning Up.

52.236-13 Accident Prevention NOV 1991

52.236-14 Availability and Use of Utility Services.

52.236-16 Quantity Surveys.

52.236-17 Layout of Work.

52.236-21 Specifications and Drawings for Construction (Feb 1997)

52.237-1 Site Visit.

52.237-2 Protection of Government Buildings, Equipment, and Vegetation APR 1984

52.243-5 Changes and Changed Conditions (Apr 1984)

52.245-1 Government Property SEP 2021

52.204-7 System for Award Management OCT 2018

52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014

52.232-39 Unenforceability of Unauthorized Obligations JUN 2013

52.249-1 Termination for Convenience of the Government (Fixed-Price) (Short Form) (Apr 1984)

52.249-10 Default (Fixed-Price Construction) (Apr 1984)

252.204-7012 Safeguarding Covered Defense Info and Cyber Incident Reporting (JAN 2023)

252.204-7020 NIST SP 800-171 DoD Assessment Requirements (MAR 2024)

252.204-7021 Cybersecurity Maturity Model Certification Requirements.

252.204-7025 Compliance with Safeguarding Covered Defense Information Controls (Notice).

252.223-7008 Prohibition of Hexavalent Chromium (Jun 2013)

252.232-7003 Electronic Submission of Payment Requests and Receiving Reports DEC 2018

252.232-7006 Wide Area WorkFlow Payment Instructions (DEC 2018)

252.211-7003 Item Identification and Valuation

252.213-7000 Notice to Prospective Suppliers on Use of Supplier Performance Risk System in Past

Performance Evaluations

252.215-7013 Supplies and Services Provided by Nontraditional Defense Contractors

252.236-7001 Contract Drawings and Specifications (Aug 2000)

252.246-7008 Sources of Electronic Parts

CLAUSES INCORPORATED BY FULL TEXT

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

https://www.acquisition.gov

C-223-W002 ON-SITE SAFETY REQUIREMENTS (NAVSEA) (OCT 2018)

(a) The contractor shall ensure that each contractor employee reads any necessary safety documents within 30 days of commencing performance at any Government facility. Required safety documents can be obtained from the respective safety office. Contractors shall notify the Safety office points of contact below to report completion of the required training via email. The email shall include the contractor employee’s name, work site, and contract number.

(b) It is expected that contractor employees will have received training from their employer on hazards associated with the areas in which they will be working and know what to do in order to protect themselves. Contractors are required to adhere to the requirements of 29 CFR 1910, 29 CFR 1926 and applicable state and local requirements while in Government spaces. The contractor shall ensure that all on-site contractor work at the Government facility is in accordance with any local safety instructions as provided via the COR. The contractor shall report all work-related injuries/illnesses that occurred while working at the Government site to the COR.

(c) Contractors whose employees perform work within Government spaces in excess of 1000 hours per calendar quarter during a calendar year shall submit the data elements on OSHA Form 300A, Summary of Work-Related Injuries and Illnesses, for those employees to the safety office, via the

COR by 15 January for the previous calendar year, even if no work-related injuries or illnesses occurred. If a contractor’s injury/illness rates are above the Bureau of Labor Statistics industry standards, a safety assessment may be performed by the Safety Office to determine if any administrative or engineering controls can be utilized to prevent further injuries/illnesses, or if any additional Personal Protective Equipment or training will be required.

(d) Any contractor employee exhibiting unsafe behavior may be removed from the Government site.

Such removal shall not relieve the contractor from meeting its contractual obligations and shall not be considered an excusable delay as defined in FAR 52.249-14.

(e) The Safety Office points of contact are as follows: TO BE PROVIDED AT AWARD

C-228-H002 MINIMUM INSURANCE REQUIREMENTS (NAVSEA) (JAN 2019)

(a) In accordance with the clause(s) of this contract entitled "Insurance--Work On a Government

Installation" (FAR 52.228-5) and “Liability and Insurance” (DFARS 252.217-7012), as https://www.acquisition.gov/ applicable, the Contractor shall procure and maintain insurance, of at least the kinds and minimum amounts set forth below:

(i) Workers' compensation and employer’s liability coverage shall be at least $100,000, except as provided in FAR 28.307-2(a), if applicable

(ii) Bodily injury liability insurance coverage shall be written on the comprehensive form of policy of at least $500,000 per occurrence.

(iii) Automobile liability policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.

(b) To be approved by the Contracting Officer, insurance certificates must include the following cancellation policy statement: Prior to cancellation or material change in coverage, the contractor shall give 30 days written notice to the Contracting Officer.

(c) Physical work cannot begin until the insurance certificate has been approved by the Contracting

Officer. Failure to provide an acceptable insurance certificate will not remove the contractor’s responsibility to meet the delivery requirements outlined in Section F and FAR 52.211-11, Liquidated Damages – Supplies, Services, or Research and Development, if applicable.

52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the

Contractor shall pay liquidated damages to the Government in the amount of $200 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY

PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)

Any contract awarded as a result of this solicitation will be ☐DX rated order; ☒ DO rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and

Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation.

(End of provision)

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of provision)

CONTRACTOR REQUIREMENTS FOR PERFORMANCE ON A GOVERNMENT SITE (APR

2018)

(a) Control of Contractor Personnel

The contractor shall comply with the requirements of NUWCDIVNPTINST 5500.4C regarding performance at Government facilities. All persons engaged in work while on Government property shall be subject to search of their persons and vehicles at any time by the Government and shall report any known or suspected security violations to the Security Department of the contracting activity.

Assignment, transfer, and reassignment of contractor personnel shall be at the discretion of the contractor.

However, the contractor shall remove from contract performance any person who endangers life, property, or national security through improper conduct. Such removal shall not relieve the contractor from meeting its contractual obligations and shall not be considered an excusable delay as defined in FAR

52.249-14.

(b) Contract Personnel Administration

The contractor is responsible for managing its employees and guarding against any actions that are of the nature of personal services or give the perception that personal services are being provided. If the contractor feels that any actions constitute, or are perceived to constitute personal services, it is the contractor's responsibility to notify the PCO immediately in accordance with the clause FAR 52.243-7.

When on-site in Government office spaces, laboratories, test facilities, or ship assets, Contractor employees shall be clearly identified as a Contractor (e.g. utilizing Common Access Cards (CACs) and sign identifications in office spaces). In addition, Contractor employees shall identify themselves as

Contractor personnel when answering telephones and sending emails. Contractor personnel cannot lead/manage/supervise Government personnel. Contractor program /project managers/Senior Technical

Representative (STR) shall be clearly identified and known as such by Government employees. As circumstances permit, periodic meetings shall be conducted between the COR and the Contractor organization program manager/project manager.

(c) Early Dismissal and Closure of Government Facilities

When a Government facility is closed or Federal employees are dismissed early (due to severe weather, security threat, security exercise, or a facility related problem) that prevents personnel from working, onsite contractor personnel regularly assigned to work at that facility shall follow the same reporting and/or departure directions given to Government personnel. The contractor shall not direct charge to the contract for such time off but shall follow parent company policies regarding taking leave (administrative or other). Non-essential contractor personnel, who are not required to remain at or report to the facility, shall follow their parent company policy regarding whether they should go/stay home or report to another company facility. Subsequent to an early dismissal and during periods of inclement weather, onsite contractors should monitor radio and television announcements before departing for work to determine if the facility is closed or operating on a delayed arrival basis.

When Federal employees are excused from work due to a holiday or a special event (that is unrelated to severe weather, a security threat, or a facility related problem), on site contractors shall continue working established work hours or take leave in accordance with parent company policy. Those contractor employees who take leave shall not direct charge the non- working hours to the contract. Contractors are responsible for predetermining and disclosing their accounting standards, and company policy.

Contractors shall follow their disclosed charging practices during the contract period of performance and shall not follow any verbal directions to the contrary. The Contracting Officer will make the determination of cost allowability for time lost due to facility closure in accordance with FAR, applicable

Cost Accounting Standards, and the Contractor's established accounting policy.

(d) Training Requirements

(A) The contractor shall ensure that each contractor employee performing work at any NUWC Division

Newport site take the following actions:

• Complete all required trainings as indicated on the following website:

https://newportalv3.nwpt.nuwc.navy.mil/10/101/Training/SitePages/TrainingWelcome.aspx

• Read the documents titled “Occupational Safety and Health Information for Contractors” and “NUWC

Division Newport Environmental Policy”, available at the following website, prior to performing any work:

http://www.navsea.navy.mil/Home/WarfareCenters/NUWCNewport/ContactUs/VisitorInformation.aspx

• Complete Environmental Awareness training, available at the following website, within 30 days of commencing performance:

http://www.navsea.navy.mil/Home/WarfareCenters/NUWCNewport/ContactUs/VisitorInformation.aspx

(2) The contractor shall email the following web address indicating completion of items (B) and (C) above upon completion of both: NWPT.NUWC_NPT_1023_Training@navy.mil

(e) Safety Requirements

(1) Prior to commencing any work that falls under the following areas, the contractor shall provide a complete listing of all qualified and trained employees who will perform the work on company letterhead http://www.navsea.navy.mil/Home/WarfareCenters/NUWCNewport/ContactUs/VisitorInformation.aspx mailto:NWPT.NUWC_NPT_1023_Training@navy.mil to the Contracting Officer’s Representative, or, if no COR is assigned, to the NUWC Division Newport

Safety Office:

(A) Permit required Confined Space Program

(B) Control of Hazardous Energy (Lock out / Tag out)

(C) Respiratory Protection

(D) Walking-Working Surfaces, Fall Protection Program and Scaffolding

(2) The contractor shall follow the posted provisions of the building’s Emergency Action Plan (EAP) for any mishap, incident, or emergency situation.

(3) The contractor shall report unsafe work conditions, safety hazards, and any mishaps (injury/property damage) to their supervisor, the COR, and the NUWC Division Newport Safety Office.

In order to comply with Division Newport’s Minor Source Air permit and EPA’s Emergency Planning and Community Right-to Know Act (EPCRA), the contractor must provide usage reports for all air quality and EPCRA regulated activities. This includes reporting all hazardous materials brought onsite, a copy of the corresponding Safety Data Sheets, and the total volume or weight of each product used monthly. The contractor shall complete the provided Hazardous Materials Inventory Log and submit it to

Environmental, no later than the 10th day of the following month. In addition, the contractor shall comply with the state air quality regulations cited in this form. If any portable generators are used at the facility, the contractor shall complete the Generator Fuel Tracking Form and submit it to Environmental, no later than the 10th day of the following month. Please submit to Environmental using the following email address. TO BE PROVIDED AT AWARD.

End of text

LIST OF ATTACHMENTS:

Attachment 1: Specification

Attachment 2: Drawings # 25-031

Attachment 3: Davis Bacon Wage…