Summary of Federal Solicitation N66604-26-Q-0338

This is a combined synopsis and solicitation for interior renovation construction services issued by the Naval Undersea Warfare Center Division Newport (NUWCDIVNPT). The procurement is a firm fixed-price, total small business set-aside with NAICS code 236220 and a 45-million-dollar size standard. Quotations are due by July 28, 2026 at 2:00 PM EST, with an anticipated contract award date in August 2026. The contractor must complete all construction services within 90 days after contract award. The work involves interior window and wall renovations at a facility in Williamsburg, Virginia, including demolition, wall reconstruction with ICD-705 security compliance, acoustic treatment, RF shielding, window replacement, and painting. All work must comply with Davis Bacon wage requirements (WD #VA20260157), U.S. Army Corps of Engineers EM 385-1-1 standards, and OSHA regulations. A 20-percent bid guarantee is required per FAR 52.228-1.

Offerors must submit a technical proposal addressing understanding of requirements and technical solution methodology, including a detailed project schedule and quality control processes, plus up to three relevant past performance references from work completed within three years. The proposal must also include pricing for CLIN 0001 (Interior Renovation Services) with construction submittals (CLIN 0002) costs incorporated into the total price. Evaluation criteria include technical capability and past performance rated as acceptable or unacceptable, with award to the lowest-priced technically acceptable proposal. Mandatory requirements include SAM registration, approved insurance certificates (workers' compensation minimum $100,000, bodily injury minimum $500,000, automobile coverage $200,000 per person), compliance with NUWC contractor requirements including security clearances and facility training, and DPAS DO-rated priority for national defense use. A pre-bid site visit was held July 13, 2026, with a second site visit available July 17, 2026.

View the file

Other files

File Type Posted
RFQ Amendment 0003.pdf PDF
Davis Bacon WD VA Building.pdf PDF
RFQ Amendment 0002.pdf PDF
SECNAV 5512 Fillable printable version.pdf PDF
RFQ Amendment 0001.pdf PDF
II.F. Wage Determination 6 3 2026.pdf PDF
Request for Quote.docx DOCX document
II.F. CDRL - Update to Facility Windows.docx DOCX document
Statement of Work -Window Infill Final.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PLEASE READ THIS ENTIRE NOTICE CAREFULLY AS IT CONSTITUES THE ONLY NOTICE

THAT WILL BE ISSUED.

N66604-26-Q-0338 Amendment 0004:

The purpose of this amendment is to:

1. Provide corrected Davis Bacon Wage Determination VA20260157.

ALL OTHER SOLICITAION TERMS AND CONDITIONS REMAIN UNCHANGED

N66604-26-Q-0338 Amendment 0003:

2. Provide answers to RFIs Below

RFI

1. Bid Guarantee: The solicitation states that a bid guarantee is required, but we did not identify the required percentage/penal amount or the applicable bid-guarantee provision. Please kindly advise.

Answer: 20 Percent. See 52.228-1 BID GUARANTEE (SEP 1996) below.

2. Wage Determination: The attached VA20260001 document is identified as Heavy construction and contains dredging classifications. It does not appear to include the building-trade classifications applicable to this interior window/wall renovation. Please confirm the correct wage determination or provide instructions for the applicable classifications and rates.

Answer: Corrected Wage Determination is attached. VA20260159

3. Completion Requirement: The solicitation narrative states completion within 90 days after contract award, while the CLIN 0001 description states 30 Days ARO. Please confirm the controlling period of performance.

Answer: 90 Days ARO, CLIN 0001 revised.

N66604-26-Q-0338 Amendment 0002:

1. Answer below RFIs 1-24

2. Extend Solicitation until 7/28/2026 at 2:00PM EST

3. A second Site Visit will be held Friday 7/17 at 10:00AM EST

RFI No. 1 – ICD-705 Wall Assembly Requirements

Please confirm whether the wall detail shown in Appendix A is the governing construction requirement or whether full ICD-705 compliance beyond the illustrated assembly is required.

Please identify any approved manufacturers or products.

A. Appendix A is the governing construction requirement. Allowable products/manufacturers are at the discretion of the installer as long as it meets fit, form, and function of Appendix A and the SOW.

RFI No. 2 – RF Shielding Requirements

Please clarify whether foil-backed gypsum board, RF membranes, RF shielding materials, or only

RF-blocking sealants are required. Identify approved manufacturers and whether post-installation RF testing will be performed.

A. RF shielding materials as outlined in Appendix A is appropriate (e.g., foil backed

OSB or equivalent). TEMPEST attenuation testing will not be performed post installation.

RFI No. 3 – Acoustic Wall Requirements

Please provide the required insulation type, density, thickness, stud gauge, stud spacing, gypsum thickness, and number of gypsum layers required on each side of the wall.

A. Thickness of insulation shall be at a minimum of 3-1/2” and meet the intent of SF-50 decibel requirements. Walls shall be constructed to the guidelines provided in

Appendix A (e.g., 2 layers of 5/8” gypsum wall board on 3-5/8” 16-gauge metal framing or 2x4” studs at 16” o.c., minimum 3-1/2” of sound attenuating insulation, 5/8” Gypsum wall board or OSB, all joints to be sealed with RF-blocking caulk)

RFI No. 4 – Existing Window Construction

Please provide available information regarding the existing window manufacturer, frame type, attachment method, flashing, sealants, and glazing type.

A. Above information is not attainable without partial de-construction of existing lab walls. Drawings are not attainable. Information must be gathered via site survey.

RFI No. 5 – Existing Wall Construction

Please provide available drawings showing existing wall thickness, framing, insulation, vapor barrier, exterior panel attachment, and interior finishes.

RFI No. 6 – Exterior Metal Panels

Please provide the manufacturer, panel profile, gauge, finish, color designation, and trim profiles. If exact replacements are unavailable, please confirm acceptable substitute materials.

RFI No. 7 – Painting Requirements

Please clarify whether painting is limited to repaired areas or entire walls, whether primer is required, the number of finish coats, and the paint manufacturer, finish, and color specifications.

A. Painting is to occur on the entirety of the walls that will be disturbed. Primer is recommended on bare sheetrock, minimum of 2 finish coats. Preferred manufacturer is Sherwin Williams. Stain finish is preferred. Color swatches are available at request

RFI No. 8 – Temporary Weather Protection

Please confirm acceptable methods for overnight weather protection and temporary security of wall openings.

A. Per the SOW, requested temporary protection is ¾” plywood .

RFI No. 9 – Hazardous Materials

Please confirm whether surveys for asbestos, lead-based paint, or other hazardous materials have been completed and provide copies if available.

A. Building was erected in 1991. Not asbestos, lead-based paint, or other hazardous materials are present.

RFI No. 10 – Lift Access

Please identify lift access restrictions, working heights, floor loading limitations, staging areas, and any access constraints.

A. Lift access will be required on exterior portions of the build only. Supporting substrate is grass at grade. Contractor will be provided laydown area for equipment and materials in our parking lot (approx.. 20’ x 20’) if more is required, we can discuss.

RFI No. 11 – Existing Utilities

Please identify any electrical, communications, alarm, or security systems that may require protection or relocation.

Electrical outlets are along the walls to be worked. IT systems and furniture will be moved prior to contractor beginning work.

RFI No. 12 – Inspection Requirements

Please identify all Government, NAVFAC, security, acoustic, and final acceptance inspections required.

A. Visual inspection shall be completed by government personnel prior to drywall installation and after finish work is completed.

RFI No. 13 – Security Certification

Please clarify whether post-installation certification of ICD-705 compliance is required and identify the responsible party.

A. ICD-705 certification is not required (space is already accredited), BUT if the installer can provide a written statement that they completed to work IAW Appendix

A of the SOW, that will satiate our security personnel.

RFI No. 14 – Temporary Glazing / Building Closure

Please clarify whether temporary glazing systems or additional weather barriers are required during construction.

A. Beyond the plywood required to secure openings at the end of the day, no further barriers are required during construction. Request that contractors conduct “good industry standards” to protect the worksite.

RFI No. 15 – Existing Window Glazing

Please confirm whether the existing glazing contains ballistic, blast-resistant, RF-shielded, laminated, security-film, or other specialty coatings. If glazing is to remain elsewhere, please clarify whether any coating, film, or RF treatment is required under this contract.

A. Existing glazing does not contain specialized treatments.

RFI No. 16 – Material Submittals

Please provide all required shop drawing, product data, certification, testing, and closeout documentation requirements.

RFI No. 17 – Existing Conditions Verification

Please advise whether a pre-bid site visit will be held and whether limited destructive investigation is permitted before bid submission.

A.Pre-bid site visit was held (7/13/26). Limited destructive investigation is not permitted.

RFI No. 18 – Independent Government Estimate (IGE)

Please advise whether the Government has established an Independent Government Estimate

(IGE) or anticipated budget range that may be shared with offerors.

A. Local government rep has received a quote for the work but does not have an official

IGE. Recommend not sharing the budget to not skew their bids.

RFI No. 19 - Who will move furniture and IT equipment in work areas?

A. The team on-site will move the furniture and IT equipment.

RFI No. 20- Will we bid to paint the interior and exterior of the spaces?

A. Paint to match entirety of interior walls and displaced / new siding on the exterior.

RFI No. 21- We have confirmed that all first-floor windows have existing steel framed expanded metal security screens. These security window screens are not identified in the scope of work for removal. Please confirm that we are to remove all security window screens.

A. Confirmed, steel security screens will need to be removed.

RFI No. 22- Paragraph 4.0.1, 2 Wall Construction, Wall Type A -Wall Type A shows a 3-5/8” metal stud framing. We confirmed during the site visit that the existing exterior wall thickness is

12” plus. We suggest that a double 3-5/8” metal stud wall be installed. One at the exterior side and one at the interior side. Please confirm if our recommendation is acceptable.

A. 3-5/8” stud size is the minimum stud size. Recommendation is acceptable.

RFI No. 23- We have confirmed that all windows have exiting 1” window blinds and curtains.

Please confirm that we will be required to remove all window treatments as part of the demolition scope of work.

A. Removal of window blinds and curtains will be removed by the team one-site prior to work start.

RFI No. 24- We have confirmed that the interior wall in the breakroom has 12” wide metal wall panels on the interior side of the wall. Please confirm that we are to patch the interior side of the wall with 12” Metal Wall Panels to match the existing.

A. Confirmed. Request that wall restoration in the break room contain 12” metal wall panels to match existing interior wall.

6/25/2026

N66604-26-Q-0338 Amendment 0001:

4. Update Site Visit to 13 July 2026 at 10:00am EST

Solicitation Number: N66604-26-Q-0338

Project Title: Williamsburg INTERIOR RENOVATIONS

Location of Work: Williamsburg, VA 23185

Response Due Date/Time: 28 July 2026 @ 2:00pm EST

This is a combined synopsis and solicitation for commercial items prepared in accordance with the format in FAR Subpart 12.6-Streamlined Procedures for Evaluation and Solicitation for Commercial Items, as supplemented with additional information included in this notice. This announcement constitutes the only solicitation; quotations are being requested and a written solicitation will not be issued.

The Naval Undersea Warfare Center Division Newport (NUWCDIVNPT) has a requirement for

INTERIOR RENOVATIONS.

This is a completion effort with a Construction completion date of 90 Days after Date of Contract

Award.

The associated North American Industrial Classification System (NAICS) code for this procurement is

236220 with a small business size standard of 45M.

This procurement is a Total Small business set-aside.

The Naval Undersea Warfare Center Division Newport (NUWCDIVNPT) intends to award a Firm Fixed

Price Type purchase order for this requirement. Please provide NUWCDIVNPT code 02 Contracting office with a quotation on a Firm Fixed Price, Completion basis prior to 28 July 2026 at 2:00PM EST for the following:

CLIN 0001: Interior Renovation Services IAW SOW. 90 Days ARO. The contractor shall provide all personnel, equipment, tools, materials, supervision, quality control, and transportation necessary to perform construction services as described in the attached Statement of Work

CLIN 0002: Construction Submittals and Contract Data Requirements Lists (CDRLs) in support of CLIN

0001(NOT SEPERATELY PRICED Provide pricing for CLIN 0002 within CLIN 0001

General Notes:

Note 1: For pricing purposes, the anticipated award date is August 2026

Note 2: The Product Service Code for this requirement is Z1AZ.

Note 3: Work shall be conducted in accordance with U.S. Army Corps of Engineers EM 385-

1-1and OSHA standards.

Note 4: Offeror MUST be registered in the System for Award Management (SAM) to be considered for award. Bid Guarantee is also required to be considered for award.

Note 5: Offerors shall provide fill-in information for all clauses/provisions that require it.

Note 6: Davis Bacon Wage Determination WD # VA20260001 is attached.

Note 7: Any contract awarded as a result of this solicitation will be a DO rated order certified for national defense, emergency preparedness, and energy program use under the Defense

Priorities and Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation.

Note 8: Method of Payment: Electronic Payment through Wide Area Workflow (WAWF) will be used.

Note 9: This is a new requirement.

Note 10: Offerors are hereby notified that, from time to time, the Government may post additional information to the SAM.gov web site relating to this RFQ (e.g., responses to questions, amendments, etc.). It is the Offeror’s responsibility to check the web site for any such information.

Note 11: Site Visits available upon request

All questions concerning this procurement, either technical or contractual, must be submitted via email by 20 July 2026. No direct discussion between the technical representative and prospective Offeror will be conducted. Questions shall be submitted to the following points of contact:

PRIMARY: Meaghan DeMarco; meaghan.d.demarco.civ@us.navy.mil

ALTERNATE: Michael Ouellette; Email: michael.n.ouellette.civ@us.navy.mil

The Government intends to evaluate quotes and award a contract without discussions with offerors. Therefore, the offeror’s initial quote should contain the offeror’s best terms from a price and technical standpoint.

The RFP will be made available only through the Government Point of Entry, also known as

Contract Opportunities (formerly FBO) at: http://www.sam.gov

PROPOSALS

Offerors shall submit proposals by electronic means. All electronic submissions shall be sent to meaghan.d.demarco.civ@us.navy.mil and michael.n.ouellette.civ@us.navy.mil .

Submissions must be received by the closing date and time identified above.

(A) Proposal Format. Proposal attachments must be in formats readable by Microsoft Office or Adobe

PDF. Offerors shall comply with the detailed instructions for the format and content of the proposals;

proposals that do not comply may be considered unacceptable and may render the Offeror ineligible for award.

(B) Organization. In the Technical Proposal, the Offeror shall provide information and documentation to clearly and concisely identify the Offeror’s overall ability to meet the requirements of the so solicitation.

The Offeror shall divide the Technical Proposal into the following factors in the order listed below:

TECHNICAL PROPOSAL

Factor 1: Technical Approach

Offeror shall provide a narrative detailing their technical approach to accomplishing the work identified in the Specification and Drawings. The narrative shall be divided into the following two subfactors:

Subfactor (a): Understanding of the Requirements:

Offeror shall provide 1) A step-by-step description of the Offeror's plan for executing the work, from pre-construction through project closeout. This should go beyond simply restating the specifications and should detail the Offeror's specific methods and sequencing for major features of work.

Subfactor (b): Technical Solution to Complete Project:

The offeror shall provide a detailed, step-by-step methodology for completing the project. This shall include a project schedule demonstrating completion within the required timeframe, a description of the quality control processes to be used, and a staffing plan identifying key personnel and their roles.

Factor 2: Past Performance

The Offeror shall provide a maximum of three (3) past performance references that reflect recent and relevant experience. A reference is considered recent if the work was performed within three (3) years of this solicitation's closing date. A reference is considered relevant if it is of a similar size, scope, and complexity to the work required by this solicitation.

For each reference, the Offeror shall provide:

mailto:michael.n.ouellette.civ@us.navy.mil http://www.sam.gov/ mailto:meaghan.d.demarco.civ@us.navy.mil mailto:michael.n.ouellette.civ@us.navy.mil

• Contract/Task Order Number

• Contract/Task Order Type (Firm-Fixed-Price, T&M, etc.)

• Total Contract/Task Order Value

• A brief description of the work performed, including a discussion of how the project is relevant to the work being proposed.

• Contact information for the client's primary technical and contracting points of contact (e.g., Contracting Officer, COR, Program Manager).

Factor 3: PRICE

Offerors shall provide an all-inclusive firm-fixed-price for CLIN 0001. The work and/or deliverables required under CLIN 0002, which are Construction submittals, are not separately priced. The Offeror shall include all costs associated with the performance of CLIN 0002 within the total price proposed for

CLIN 0001.

EVALUATION OF OFFERS

The Government intends to award a firm-fixed-price contract to the responsible Offeror submitting the lowest evaluated price proposal that is rated "Acceptable" for all non-price evaluation factors. The

Government intends to award without discussions but reserves the right to conduct discussions if determined to be in the Government's best interest.

Factors

Proposals will be evaluated based on the following three (3) factors.

FACTORS SUBFACTORS

1.0 Technical Capability (a) Understanding of the Requirements.

(b) Technical Solution to Complete Project

2.0 Past Performance None

3.0 Price None

The Government will evaluate Technical Capability and Past Performance using the following adjectival ratings:

TECHNICAL CAPABILITY

SUBFACTORS

ACCEPTABLE UNACCEPTABLE

Technical Capability-Subfactor

(a) Understanding of the

Requirements.

The Offeror's narrative must demonstrate a clear understanding of the project's objectives, challenges, and key performance parameters.

A proposal will be rated

"Unacceptable" under this subfactor if the narrative fails to demonstrate a clear understanding of the requirements. Examples of an unacceptable proposal include, but are not limited to, a narrative

Technical Capability- Subfactor

(b) Technical Solution to

Complete Project

The Offeror's narrative must provide a logical and feasible step-by-step methodology for completing the project. The proposal must include a project schedule demonstrating completion within the required timeframe, a description of the quality control processes to be used, and a staffing plan identifying key personnel and their roles.

that: Merely restates or paraphrases the requirements from the solicitation without providing any unique insight or demonstrating comprehension.

Fails to identify or address significant challenges that are evident from the solicitation documents (e.g., working in an occupied facility, specific environmental constraints, etc.).

Demonstrates a fundamental misunderstanding of the project's primary objectives.

A proposal will be rated

"Unacceptable" under this subfactor if it fails to meet one or more of the minimum requirements stated above. For example, a proposal will be rated Unacceptable if: The proposed methodology is illogical, unfeasible, or omits major required steps detailed in the solicitation; OR The project schedule is missing, exceeds the required period of performance, or is so lacking in detail that its feasibility cannot be determined;

OR The description of quality control processes is omitted or is so generic that it fails to describe how the Offeror will ensure compliance with the solicitation's specifications; OR

The staffing plan is omitted or fails to identify the key personnel required by the solicitation.

PAST PERFORMANCE* ACCEPTABLE UNACCEPTABLE

To be rated "Acceptable," the

Offeror's past performance must demonstrate a history of successful contract performance, and the Government must have a reasonable expectation that the

An Offeror will be rated

"Unacceptable" if their past performance record indicates performance that was unsuccessful or of a quality that creates significant doubt that the

Offeror will successfully perform the required effort.

Offeror will successfully perform the required effort.

*Review of past performance will be based on available information in the Contractor Performance

Assessment Reporting System (CPARS), Federal Awardee Performance and Integrity Information

System (FAPIIS) and information in provided references. The Government reserves the right to contact any individuals identified by the offeror as part of their submitted references.

The Government will evaluate the price proposal of all technically acceptable Offerors for completeness and reasonableness. Price will not be adjectivally rated. The evaluated price of all technically acceptable proposals will be ranked from lowest to highest to determine the awardee.

CLAUSES INCORPORATED BY REFERENCE

52.203-13 Contractor Code of Business Ethics and Conduct (Nov 2021)

52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (Jan 2017)

52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (Jun 2020) 52.204-23

Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky

Lab Covered Entities (Dec 2023)

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (Nov 2021)

52.209-6 Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (Jan 2025)

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015)

52.212-1 Instructions to Offerors—Commercial Products and Commercial Services SEP 2023 52.212-2

Evaluation—Commercial Products and Commercial Services (Nov 2021).

52.212-3 Offeror Representations and Certifications—Commercial Products and Commercial Services

DEC 2022

52.212-4 Contract Terms and Conditions—Commercial Products and Commercial Services DEC 2022

52.219-6, Notice of Total Small Business Set-Aside (Nov 2020)

52.219-8, Utilization of Small Business Concerns (Jan 2025)

52.222-3, Convict Labor (Jun 2003)

52.223-5 Pollution Prevention and Right-to-Know Information MAY 2011

52.232-33 Payment by Electronic Funds Transfer-System for Award Management (Oct2018) 52.232-40

Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) 52.233-3 Protest After

Award (Aug 1996)

52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004)

52.236-2 Differing Site Conditions APR 1984

52.236-3 Site Investigation and Conditions Affecting the Work APR 1984

52.236-5 Material and Workmanship.

52.236-6 Superintendence by the Contractor.

52.236-7 Permits and Responsibilities NOV 1991

52.236-8 Other Contracts.

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.

52.236-10 Operations and Storage Areas.

52.236-12 Cleaning Up.

52.236-13 Accident Prevention NOV 1991

52.236-14 Availability and Use of Utility Services.

52.236-16 Quantity Surveys.

52.236-17 Layout of Work.

52.237-2 Protection of Government Buildings, Equipment, and Vegetation APR 1984

52.245-1 Government Property SEP 2021

52.204-7 System for Award Management OCT 2018

52.232-5 Payments under Fixed-Price Construction Contracts MAY 2014

52.232-39 Unenforceability of Unauthorized Obligations JUN 2013

252.204-7012 Safeguarding Covered Defense Info and Cyber Incident Reporting (JAN 2023) 252.204-

7020 NIST SP 800-171 DoD Assessment Requirements (MAR 2024)

252.225-7001 Buy American and Balance of Payments Program (MAR 2024)

252.232-7003 Electronic Submission of Payment Requests and Receiving ReportsDEC 2018 252.232-

7006 Wide Area WorkFlow Payment Instructions (DEC 2018)

252.211-7003 Item Identification and Valuation

252.213-7000 Notice to Prospective Suppliers on Use of Supplier Performance Risk System in Past

Performance Evaluations

252.215-7013 Supplies and Services Provided by Nontraditional Defense Contractors

252.246-7008 Sources of Electronic Parts

CLAUSES INCORPORATED BY FULL TEXT

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): https://www.acquisition.gov

C-223-W002 ON-SITE SAFETY REQUIREMENTS (NAVSEA) (OCT 2018)

(a) The contractor shall ensure that each contractor employee reads any necessary safety documents within 30 days of commencing performance at any Government facility. Required safety documents can be obtained from the respective safety office. Contractors shall notify the Safety office points of contact below to report completion of the required training via email. The email shall include the contractor employee’s name, work site, and contract number.

(b) It is expected that contractor employees will have received training from their employer on hazards associated with the areas in which they will be working and know what to do in order to protect themselves. Contractors are required to adhere to the requirements of 29 CFR 1910, 29 CFR 1926 and applicable state and local requirements while in Government spaces.

The contractor shall ensure that all on-site contractor work at the Government facility is in accordance with any local safety instructions as provided via the COR. The contractor shall report all work- related injuries/illnesses that occurred while working at the Government site to the COR.

(c) Contractors whose employees perform work within Government spaces in excess of 1000 hours per calendar quarter during a calendar year shall submit the data elements on OSHA Form 300A, Summary of

Work Related Injuries and Illnesses, for those employees to the safety office, via the COR by 15 January for the previous calendar year, even if no work related injuries or illnesses occurred. If a contractor’s injury/illness rates are above the Bureau of Labor Statistics industry standards, a safety assessment may be performed by the Safety Office to determine if any administrative or engineering controls can be utilized to prevent further injuries/illnesses, or if any additional Personal Protective Equipment or training will be required.

https://www.acquisition.gov/

(d) Any contractor employee exhibiting unsafe behavior may be removed from the Government site. Such removal shall not relieve the contractor from meeting its contractual obligations and shall not be considered an excusable delay as defined in FAR 52.249-14.

(e) The Safety Office points of contacts are as follows: TO BE PROVIDED AT AWARD

C-228-H002 MINIMUM INSURANCE REQUIREMENTS (NAVSEA) (JAN 2019)

(a) In accordance with the clause(s) of this contract entitled "Insurance--Work On a Government

Installation" (FAR 52.228-5) and “Liability and Insurance” (DFARS 252.217- 7012), as applicable, the

Contractor shall procure and maintain insurance, of at least the kinds and minimum amounts set forth below:

(i) Workers' compensation and employer’s liability coverage shall be at least $100,000, except as provided in FAR 28.307-2(a), if applicable

(ii) Bodily injury liability insurance coverage shall be written on the comprehensive form of policy of at least $500,000 per occurrence.

(iii) Automobile liability policies covering automobiles operated in the United States shall provide coverage of at least $200,000 per person and $500,000 per occurrence for bodily injury and $20,000 per occurrence for property damage. The amount of liability coverage on other policies shall be commensurate with any legal requirements of the locality and sufficient to meet normal and customary claims.

(b) To be approved by the Contracting Officer, insurance certificates must include the following cancellation policy statement: Prior to cancellation or material change in coverage, the contractor shall give 30 days written notice to the Contracting Officer.

(c) Physical work cannot begin until the insurance certificate has been approved by the Contracting

Officer. Failure to provide an acceptable insurance certificate will not remove the contractor’s responsibility to meet the delivery requirements outlined in Section F and FAR 52.211-11, Liquidated

Damages – Supplies, Services, or Research and Development, if applicable.

52.211-14 NOTICE OF PRIORITY RATING FOR NATIONAL DEFENSE, EMERGENCY

PREPAREDNESS, AND ENERGY PROGRAM USE (APR 2008)

Any contract awarded as a result of this solicitation will be DX rated order; X DO rated order certified for national defense, emergency preparedness, and energy program use under the Defense Priorities and

Allocations System (DPAS) (15 CFR 700), and the Contractor will be required to follow all of the requirements of this regulation.

(End of provision)

CONTRACTOR REQUIREMENTS FOR PERFORMANCE ON A GOVERNMENT SITE (APR

2018)

(a) Control of Contractor Personnel

The contractor shall comply with the requirements of NUWCDIVNPTINST 5500.4C regarding performance at Government facilities. All persons engaged in work while on Government property shall be subject to search of their persons and vehicles at any time by the Government, and shall report any known or suspected security violations to the Security Department of the contracting activity. Assignment, transfer, and reassignment of contractor personnel shall be at the discretion of the contractor. However, the contractor shall remove from contract performance any person who endangers life, property, or national security through improper conduct. Such removal shall not relieve the contractor from meeting its contractual obligations and shall not be considered an excusable delay as defined in FAR 52.249-14.

(b) Contract Personnel Administration

The contractor is responsible for managing its employees and guarding against any actions that are of the nature of personal services or give the perception that personal services are being provided. If the contractor feels that any actions constitute, or are perceived to constitute personal services, it is the contractor's responsibility to notify the PCO immediately in accordance with the clause FAR 52.243-

7. When on-site in Government office spaces, laboratories, test facilities, or ship assets, Contractor employees shall be clearly identified as a Contractor (e.g. utilizing Common Access Cards (CACs) and sign identifications in office spaces). In addition, Contractor employees shall identify themselves as Contractor personnel when answering telephones and sending emails. Contractor personnel cannot lead/manage/supervise Government personnel. Contractor program /project managers/Senior

Technical Representative (STR) shall be clearly identified and known as such by Government employees. As circumstances permit, periodic meetings shall be conducted between the COR and the

Contractor organization program manager/project manager.

(c) Early Dismissal and Closure of Government Facilities

When a Government facility is closed or Federal employees are dismissed early (due to severe weather, security threat, security exercise, or a facility related problem) that prevents personnel from working, onsite contractor personnel regularly assigned to work at that facility shall follow the same reporting and/or departure directions given to Government personnel. The contractor shall not direct charge to the contract for such time off, but shall follow parent company policies regarding taking leave (administrative or other). Non-essential contractor personnel, who are not required to remain at or report to the facility, shall follow their parent company policy regarding whether they should go/stay home or report to another company facility. Subsequent to an early dismissal and during periods of inclement weather, onsite contractors should monitor radio and television announcements before departing for work to determine if the facility is closed or operating on a delayed arrival basis.

When Federal employees are excused from work due to a holiday or a special event (that is unrelated to severe weather, a security threat, or a facility related problem), on site contractors shall continue working established work hours or take leave in accordance with parent company policy. Those contractor employees who take leave shall not direct charge the non- working hours to the contract.

Contractors are responsible for predetermining and disclosing their accounting standards, and company policy. Contractors shall follow their disclosed charging practices during the contract period of performance, and shall not follow any verbal directions to the contrary. The Contracting Officer will make the determination of cost allowability for time lost due to facility closure in accordance with FAR, applicable Cost Accounting Standards, and the Contractor's established accounting policy.

(d) Training Requirements

(A) The contractor shall ensure that each contractor employee performing work at any NUWC

Division Newport site take the following actions:

• Complete all required trainings as indicated on the following website:

https://newportalv3.nwpt.nuwc.navy.mil/10/101/Training/SitePages/TrainingWelcome.as px • Read the documents titled “Occupational Safety and Health Information for Contractors” and “NUWC

Division Newport Environmental Policy”, available at the following website, prior to performing any work:

http://www.navsea.navy.mil/Home/WarfareCenters/NUWCNewport/ContactUs/VisitorInformation.as px

• Complete Environmental Awareness training, available at the following website, within 30 days of commencing performance:

http://www.navsea.navy.mil/Home/WarfareCenters/NUWCNewport/ContactUs/VisitorInformation.as px

(2) The contractor shall email the following web address indicating completion of items (B) and (C) above upon completion of both: NWPT.NUWC_NPT_1023_Training@navy.mil

(e) Safety Requirements

(1) Prior to commencing any work that falls under the following areas, the contractor shall provide a complete listing of all qualified and trained employees who will perform the work on company letterhead to the Contracting Officer’s Representative, or, if no COR is assigned, to the NUWC

Division Newport Safety Office:

(A) Permit required Confined Space Program

(B) Control of Hazardous Energy (Lock out / Tag out)

(C) Respiratory Protection

(D) Walking-Working Surfaces, Fall Protection Program and Scaffolding

(2) The contractor shall follow the posted provisions of the building’s Emergency Action Plan (EAP) for any mishap, incident, or emergency situation.

(3) The contractor shall report unsafe work conditions, safety hazards, and any mishaps

(injury/property damage) to their supervisor, the COR, and the NUWC Division Newport Safety

Office. In order to comply with Division Newport’s Minor Source Air permit and EPA’s Emergency

Planning and Community Right-to Know Act (EPCRA), the contractor must provide usage reports for all air quality and EPCRA regulated activities. This includes reporting all hazardous materials brought onsite, a copy of the corresponding Safety Data Sheets, and the total volume or weight of each product used monthly. The contractor shall complete the provided Hazardous Materials

Inventory Log and submit it to Environmental, no later than the 10th day of the following month. In addition, the contractor shall comply with the state air quality regulations cited in this form. If any portable generators are used at the facility, the contractor shall complete the Generator Fuel Tracking

Form and submit it to Environmental, no later than the 10th day of the following month. Please submit to Environmental using the following email address. TO BE PROVIDED AT AWARD

End of text

52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and http://www.navsea.navy.mil/Home/WarfareCenters/NUWCNewport/ContactUs/VisitorInformation.aspx http://www.navsea.navy.mil/Home/WarfareCenters/NUWCNewport/ContactUs/VisitorInformation.aspx http://www.navsea.navy.mil/Home/WarfareCenters/NUWCNewport/ContactUs/VisitorInformation.aspx http://www.navsea.navy.mil/Home/WarfareCenters/NUWCNewport/ContactUs/VisitorInformation.aspx mailto:NWPT.NUWC_NPT_1023_Training@navy.mil sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United

States.

The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-

(c) The amount of the bid guarantee shall be 20 percent of the bid price.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of provision)

LIST OF ATTACHMENTS:

Attachment 1: Statement of Work

Attachment 2: Davis Bacon Wage Determination VA20260157

Attachment 3: CDRLs