This document is Amendment 0004 to Solicitation N6660424R0251 for Construction - B1302 Second Floor Renovation. The amendment provides answers to Request for Information (RFI) 0003 submitted by potential offerors. The key details are:
- The requirement to recycle demolished carpet cushion and ceiling tile will not be enforced.
- Acoustical ceiling tile and grid will need reconfiguration at the location of the new stick built walls as well as any incidental work, beyond just adding one 2-foot tee and one 2x2 ceiling tile.
- The SSPC QP 1 Certification requirement for the painting subcontractor will not be enforced.
All other solicitation terms and conditions remain unchanged.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N6660424R0251 Amendment 0005.pdf | ||
| N6660424R0251 Amendment 0003.pdf | ||
| N6660424R0251 Amendment 0002.pdf | ||
| N6660424R0251Amendment0001.pdf | ||
| N6660424R0251.pdf | ||
| Attachment_3_Davis Bacon Wage Determination 3_8_2024.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1301136959
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
See Page 2.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 10-Apr-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N6660424R0251
X 9B. DATED (SEE ITEM 11)
15-Mar-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
10-Apr-2024
CODE
NAVAL UNDERSEA WARFARE CENTER
MICHAEL NORMAN OUELLETTE , CODE 0221
CONTRACTS DEPARTMENT
1176 HOWELL STREET, BLDG. 1258
NEWPORT RI 02841-1708
N66604 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6660424R0251
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The following have been modified:
GENERAL INFORMATION
Distribution: TBD NUWCDIVNPT Requisition Number: 1301136959 NUWCDIVNPT PID Number: N66604-24-RFPREQ-NPT-10-0176 NUWCDIVNPT POC: Michael Ouellette; Email: Michael.n.ouellette.civ@us.navy.mil
AMENDMENT 0004:
The purpose of this amendment is to:
1. Provide answers to RFI 0003 as seen below:
RFI 0003
1.Specification Section 02 41 00 Demolition and Deconstruction; para 3.1.1 and 3.1.2 state that the demolished carpet and cushion and acoustical ceiling tile is to be recycled. Past experience has shown that recycling small amounts of carpet and/or acoustical ceiling tile is not cost effective, nor time conducive. Due to the limited amount of demolished carpet and acoustical tile, will this requirement be enforced?
1. The requirement to recycle demolished carpet cushion and ceiling tile will not be enforced.
2.Scope for acoustical ceiling tile and grid appear to only include adding one (1) two foot tee and one (1) 2x2 ceiling tile at locations where 4’ lights are replaced with 2’ lights. Please confirm that no other grid or tile work is to be included under this contract.
2. Acoustical ceiling tile and grid will need reconfiguration at the location of the new stick built walls as well as any incidental work.
3.Specification Section 09 90 00; para 1.6.3 states that SSPC QP 1 Certification is required for the painting subcontractor. This certification is held by large companies only, and typically
N6660424R0251 cannot be competitive on smaller projects, such as this renovation. Please confirm if this requirement will be enforced during the submittal process.
3. SSPC QP 1 Certification for the painting subcontractor will not be enforced.
All other solicitation terms and conditions remain unchanged.